Fort Lauderdale – Hollywood International AirportAirport Expansion Program

American Society of Civil EngineersSouth Florida Chapter

May 3, 2013

3.   South Runway Expansion Update

Board Update Agenda

2.   Terminal 4 Gate Replacement Update

1.   Terminal Modernization Update

Airport Expansion Program and Terminal Modernizations

Terminal 4 Gate Expansion 

South Runway Expansion

Terminal Modernizations

Terminal 1Concourse A

Terminal Modernizations – Terminal 1

Terminal Modernizations – Terminal 1

Existing

Ticket LobbyCurbside Canopy

Airline Ticketing OfficesTerminal Roof

Baggage Level

Concourse Level

Ticketing Level

Building Cross Section

Terminal Modernizations – Terminal 1

Existing

Ticket LobbyCurbside Canopy

Airline Ticketing OfficesTerminal Roof

Baggage Level

Concourse Level

Ticketing Level

Building Cross SectionProposed

Baggage Level

Concourse Level

Ticketing Level

Ticket LobbyCurbside Canopy

Airline Ticketing Offices Beyond New Concessions Hall

Building Addition

Mezzanine

Terminal Modernizations – Terminal 1

Central Airside Concessions Hall

Terminal Modernizations – Terminal 1

Terminal Modernizations – Terminal 2

Larger Roof Expansion ‐ Consistent w/ GS&P Interview Presentation

T2 – Alternate 3 –Infill w/ Mezzanine & Clerestory

Terminal Modernizations – Terminal 2

T2 – Alternate 3 –Infill w/ Mezzanine & Clerestory

Terminal Modernizations – Terminal 2

T2 – Alternate 3 –Infill w/ Mezzanine & Clerestory

Terminal Modernizations – Terminal 3

TERM

INAL

 3TERM

INAL

 3

Terminal Modernizations – Terminal 3

T3 –Ticketing Detail 9A – Angled Counter

Terminal Modernizations – Terminal 3

T3 –Ticketing Detail 9B – V‐shaped Counter

Terminal 4 Gate Expansion Update

Western Expansion Eastern Expansion

Terminal 4 Gate Expansion Update

TSA setting up Equipment (SSCP)

Ceiling Grid Installation (SSCP)

Installing Ceiling Lights in the Grid (SSCP)

Installing ProVision ATD (SSCP)

Terminal 4 Gate Expansion Update

Temporary SSCP opened April 17, 2013

Terminal 4 Gate Expansion Update

FLL Airport Expansion Program

“Third World Design”

FLL Airport Expansion Program

South Runway Expansion Update

Sep. Oct. Nov. Dec. Jan.Sep. Oct. Nov. Dec. Jan. Feb.Feb. Mar.Mar.

South Runway Expansion Update

Runway Structure Piles

Runway Structures Bents (Walls)

Runway Structure Piles, Utilities and Earthwork

South Runway Expansion Update