5th ADB BUSINESSOPPORTUNITIES FAIR
East Asia Department Transport and Communications Division
(EATC)
13 March 2014
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
2/14
East Asia Department
Country Coverage
ADB Assistance to PRC and Mongolia Transport Sector Strategy in the PRC Transport Sector Strategy in Mongolia Business Opportunities
Consulting Services Under Approved and Proposed TAsand Loans
Civil Works Under Approved Loans Equipment Under Approved Loans
Transport and Communications SectorOUTLINE
2
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
3/14
EARD Countries
The Peoples Republic of China (PRC)
Mongolia
3
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
4/14
ADB Assistance to PRC and MongoliasTransport and Communication Sectors
(as of 5 March 2014)
Country Start YearLoan
Amount($ million)
TA Amount
($ million)
PRC 1986 13,843.00 70.45
Mongolia 1991 324.53 15.2
4
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
5/14
Transport Sector Strategy in the PRCCountry Partnership Strategy
Accessible, affordable, environment-friendly and safe transport system Road network rehabilitation, rural roads, more effective road
maintenance systems, and road safety
Efficient and safe railways with strong regional dimensions and
facilitation of containerization Urban transport , non-motorized transport, multimodal passenger
hubs, and traffic demand management
Inland waterways and inland ports
Multimodal logistics centers, logistics services, and intelligenttransport systems
Key policy reforms including asset management and roadmaintenance, efficiency and safety of transport services, and effectiveurban transport planning
5
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
6/14
Transport Sector Strategy in MongoliaCountry Partnership Strategy
Regional and international transport corridors toreduce transport and logistics costs for trade and fosterregional cooperation
Urban transport infrastructure and services to enhanceurban efficiency
Transport efficiency and safety through public-privatepartnership (PPP )
Harmonization of cross-border transpor t procedures andtransport regulations
Sector institutions, financial management, and humancapacity development
6
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
7/14
Business Opportunities(2014-2018)
Type No. of TAProjectsNo. of Loan
ProjectsTotal Value($ million) Timeline
i. ConsultingServices 17 6 25.07 2014-2015
ii. Civil Works 0 8 841.32 2014-2018iii. Equipment 0 4 112.06 2014-2017
7
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
8/14
Consulting Services Under Approved TAs
TA No. Indicative Project Name TA Amount($)TA
TypeIndicative Yearof Opportunity
8465-MON Connectivity for Future Growth 500,000 PATA 2014-2015
8212-MON Ulaanbaatar Urban Transport CapacityDevelopment 1,000,000 CDTA 2014
8476-PRC Strategy for Restructuring IWT/MultimodalLogistics in Chongqing Region 400,000 PATA 2014-2015
8440-PRC Shaanxi Trunk Roads Improvement 700,000 PPTA 2014
7164-PRC Chongqing Guiyang Railway Development 1,220,000 PPTA 2014
8464-PRC Railway Container Transport Development 450,000 CDTA 2014-2015
7692-PRC Capacity Development for Railway TrackMaintenance 400,000 CDTA 2014
7975-PRC Yuxi-Mohan Subregional Railway Link 800,000 PPTA 2014-2015
7925-PRC Developing Multimodal Passenger TransportHubs 500,000 PATA 2014
7988-PRC Anhui Intermodal Sustainable TransportDevelopment 1,000,000 PPTA 2014
8482-PRCFormulation of Northeast Asia LogisticsInformation Sharing Network DevelopmentProgram and Organizational Mechanism
400,000 PATA 2014-2015
8
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
9/14
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
10/14
Consulting Services Under Approved Loans
Loan No. Project Name Required Field of Service Cost Estimates($ million) IndicativeTiming
2962-PRC Hunan Xiangjiang InlandWaterway Transport Institutional strengthening 0.60 2014
2915-PRCJiangxi Fuzhou UrbanIntegrated InfrastructureImprovement Project
Institutional strengthening andenvironmental and socialmonitoring
1.44 2014
2934/2935-MON
Ulaanbaatar UrbanTransport DevelopmentInvestment Program
Detailed design for rapid bustransit infrastructure, bridgeexpansion and roadimprovement, and intelligenttransport system; constructionsupervision; and projectmanagement support
4.10 2014
3042-PRC Inner Mongolia RoadDevelopment Project
Environmental conservation andecotourism development, projectmanagement, environmentalmonitoring, and tourismdevelopment
1.50 2014
3074-PRC Yunnan Sustainable RoadMaintenance Sector Project Project management and training 2.66 2014
10
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
11/14
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
12/14
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
13/14
Equipment Under Approved Loans
Loan No. Project Name Type of Equipment Cost Estimates($ million) IndicativeTiming
2962-PRCHunan XiangjiangInland Waterway
Transport
Turbine generator and auxiliaryequipment, metal structure of powerplant and sluice structure, metalstructure of ship lock, hydraulic hoist ofdial gates and ship lock, dam crestgantry crane, tailwater gantry crane,
overhead crane, sewage crane powersupply and distribution system andauxiliary equipment for ship lock, powersupply and distribution system andauxiliary equipment for sluice structure
59.6 2014-2017
3042-PRC Inner Mongolia RoadDevelopment ProjectRoad maintenance and safetyequipment 5.62 2014-2017
3014-PRC
Hubei-Yichang
Sustainable UrbanTransport
Traffic aids, vehicle operation system,
ticketing systems and screen doorsystem 31.15 2014-2017
2915-PRC
Jiangxi FuzhouUrban IntegratedInfrastructureImprovement Project
BRT station ticketing system, ITS,dispatching system and trafficengineering, BRT buses, equipment forbus maintenance
15.69 2014-2016
13
8/12/2019 4 Transport ICT EARD by KJKim 05Mar2014
14/14
Thank you
For more information:
Ki-Joon KimSenior Transport Specialist, EATC
kjkim@adb.org
14