Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
1/46
CSSFMP
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
Document
Title Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
Client Transport for NSW
Client reference no. SLR-MC-01
Laing O’Rourke contract no. G79
Revisions
Date Copy Number Description Prepared by Approved by Signed
V0.00 Issue to TfNSW L.L/BR R Rubalcaba
V0.01 Issue to TfNSW L.L/BR R Rubalcaba
V0.02 Issue to DPE L.L/BR R Rubalcaba
V0.03 Address NOW and DPE comments L.L R Rubalcaba
Management Reviews
Review Date Details Reviewed By
Controlled: NO Copy no.: Uncontrolled: YES
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
2/46
CSSFMP
Terms and definitions
The following terms, abbreviations and definitions are used in this plan.
Terms Explanation
ANZECC Australia New Zealand Environment and Conservation Council
ASS Acid Sulfate Soil
CAR Corrective Action Register
CCOS Council of City of Sydney
CEMP Construction Environmental Management Plan
CoA Conditions of Approval
Blue Book Managing Urban Stormwater: Soils and Construction, published by Landcom in 2004.
CSELR CBD and South East Light Rail
DPE Department of Planning & Environment
EIS Environmental Impact Statement (TfNSW November 2013)
EPA Environment Protection Authority
EPL Environment Protection Licence
ER Environmental Representative
ERAP Environmental Risk Action Plan
ERSED Erosion & Sedimentation
HSEQ Health, Safety, Environment and Quality
JSEA Job Safety Environmental Analysis
Laing O’Rourke Laing O’Rourke Australia Construction Pty Limited
MC Managing Contractor – Laing O’Rourke’s contract with TfNSW to deliver enabling works for the CSELR to facilitate PPP main works.
NTU Nephelometric Turbidity Unit – field test for construction water
OEH Office of Environment and Heritage
OpCo The Operating Company (for the CSELR Project – company yet to be determined)
PASS Potential Acid Sulfate Soil
PEM Project Environmental Manager
POEO Act Protection of the Environment Operations Act 1997
PPP Public-Private Partnership
RCC Randwick City Council
RCC Randwick City Council
SDS Safety Data Sheet
CSSFMP Construction Soil, Stormwater and Flooding Management Plan
TfNSW Transport for NSW
TSS Total Suspended Solids
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
3/46
CSSFMP
0. Compliance Matrix (Minister’s Conditions of Approval (CoA))
Obligation Document Reference
B66 A Soil, Stormwater and Flooding Management Plan(s) shall be prepared in consultation with the EPA, NOW and relevant Councils during detailed design of the SSI and prior to construction.
This Plan Section 1.4 Consultation
The Plan shall identify actions to ensure that the SSI addresses the management of soil and existing flooding characteristics within the vicinity of the SSI for a full range of flood sizes up to and including the probable maximum flood. The Plan(s) shall be prepared by appropriately qualified person(s) and facilitate a holistic approach to detailed hydrologic assessment and stormwater management, which gives consideration to the cumulative impacts of the SSI associated with its construction and operation, and shall include but not be limited to:
This Plan Section 5.0 - Management Measures
a) Soil and water management measures that are consistent with the guideline Managing urban stormwater: soils and construction (including Volume 1 - Blue Book and Volume 2 - lnstallation of Services);
Section 2.3 Guideline Section 5.0 Management Measures
(b) the design of temporary works, compensatory and management measures that would be implemented during construction to not worsen (as defined in condition B65) existing and known future flooding characteristics;
Section 3.4- Flood Conditions Section 5.8 -Drainage/ Flooding Design and Construction
(c) the identification of flood risks to the SSI and adjoining areas, including the consideration of local and regional drainage catchment assessments, strategies and guidelines; and climate change implications on rainfall and drainage characteristics;
Section 3.3- Flood Conditions Section 5.8 -Drainage/ Flooding Design and Construction
(d) the design and layout of each stop precinct and light rail infrastructure to not worsen (as defined in condition B65), existing and known future flooding characteristics;
N/A to MC Works – applies to light rail infrastructure and stop precincts
(e) Identification of design and mitigation measures that would be implemented to protect proposed construction and operational activities and not worsen existing flooding characteristics, including soil erosion and scouring. Design of mitigation measures should consider more frequent floods besides flood of design; and
Section 3.4- Flood Conditions Section 5.8 -Drainage/ Flooding Design and Construction
(f) Identification of flood risk, potential for inflows, potential consequences and required mitigation measures for each tunnel entrance.
N/A to MC Works – applies to Moore Park tunnel
For surface components of the SSI located on floodplains, flood impacts shall be confirmed in accordance with the Floodplain Development Manual (2005), and other relevant NSW Government Guidelines.
N/A to MC Works – as discussed in Section 3.4.1 of this Plan
B64 Except as may be expressly provided by an Environment Protection Licence for the SSI, the Applicant shall comply with section 120 of the Protection of the Environment Operations Act 1997, which prohibits the pollution of waters.
Section 1.3- Objectives and Targets Section 2.1- Legislation Section 5.7.1- Criteria for Discharge to Water
B65 The Applicant shall design and construct the SSI, to the extent that is reasonable and feasible, to not worsen existing flood characteristics on the vicinity of the SSI. Not worsen is defined as: (a) A maximum increase flood levels of 10 mm in a 100 year average recurrence interval (ARI) flood event; and (b) A maximum increase in time of inundation of one hour in a 100 year ARI flood event; and (c) any increase in high hazard flooding as defined in Appendix L of the NSW Government's Floodplain Development Manual (2005).
Section 3.4- Flood Conditions Section 5.8 -Drainage/ Flooding Design and Construction
B67 The Applicant shall design and construct the SSI in a manner that ensures no more than minimal harm to overall groundwater hydrology including capture, drawdown, flow and quality.
This Plan – Section 3.5.1
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
4/46
CSSFMP
Contents
0. Compliance Matrix (Minister’s Conditions of Approval (CoA)) .......................................... 3
1. Introduction .............................................................................................................................. 6
1.1 Purpose and Application ........................................................................................................ 6
1.2 Background ............................................................................................................................ 6
1.2.1 CSELR Overview .......................................................................................................... 6
1.2.2 CSELR Moore Park Works Overview ........................................................................... 6
1.2.3 Environmental Planning Approval ................................................................................ 6
1.2.4 CSELR Moore Park Works Approval Pathway ............................................................ 7
1.2.5 Project-Specific Environmental Management System ................................................. 7
1.3 Objectives and Targets .......................................................................................................... 7
1.4 Consultation ........................................................................................................................... 8
2. Legal and Other Requirements .............................................................................................. 9
2.1 Legislation .............................................................................................................................. 9
2.2 Project Approval Conditions .................................................................................................. 9
2.3 Guidelines .............................................................................................................................. 9
3. Existing Environment ............................................................................................................ 10
3.1 Soils ..................................................................................................................................... 10
3.1.1 Moore Park Works Local Conditions .......................................................................... 10
3.2 Contamination ...................................................................................................................... 10
3.2.1 Moore Park Works Local Contamination Risks .......................................................... 10
3.3 Water Quality ....................................................................................................................... 10
3.3.1 Moore Park Works Local Water Quality Conditions ................................................... 10
3.4 Flood Conditions .................................................................................................................. 10
3.4.1 Moore Park Works Local Flood Conditions ................................................................ 10
3.5 Groundwater ........................................................................................................................ 11
3.5.1 Moore Park Works Conditions .................................................................................... 11
4. Aspects, Impacts & Risks ..................................................................................................... 12
5. Management Measures ......................................................................................................... 13
5.1 Key Soil, Stormwater and Flooding Management Tools .................................................... 13
5.2 Principles of Soil, Stormwater and Flooding Management ................................................. 13
5.3 Permanent Controls ............................................................................................................. 14
5.3.1 Vegetation ................................................................................................................... 14
5.3.2 Drainage ...................................................................................................................... 14
5.4 Temporary Controls ............................................................................................................. 14
5.4.1 Erosion and Sediment Control Plans .......................................................................... 14
5.4.2 Batter Protection.......................................................................................................... 14
5.4.3 Sediment Fences ........................................................................................................ 14
5.4.4 Sandbags and Sediment Socks ................................................................................. 15
5.4.5 Dust Control ................................................................................................................ 15
5.4.6 Stockpiles .................................................................................................................... 15
5.4.7 Site Access .................................................................................................................. 15
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
5/46
CSSFMP
5.5 Operation and Maintenance of Site Controls ...................................................................... 15
5.6 Site Wastewater Controls .................................................................................................... 16
5.6.1 Waste Water ............................................................................................................... 16
5.6.2 Concrete Washout ...................................................................................................... 16
5.6.3 Paint Washout ............................................................................................................ 16
5.7 Water Discharge Requirements .......................................................................................... 16
5.7.1 Criteria for Discharge to Water ................................................................................... 16
5.7.2 Discharge to Land ....................................................................................................... 17
5.7.3 Reuse on Site .............................................................................................................. 17
5.8 Drainage/Flooding Design and Construction ...................................................................... 17
5.9 Incident Management .......................................................................................................... 18
6. Soil, Stormwater and Flooding Risk Training .................................................................... 19
7. Monitoring of Controls .......................................................................................................... 20
Appendix A – Stakeholder Consultation Feedback .................................................................. 21
Appendix B – Mitigation Measures Action Plan ........................................................................ 23
Appendix C – Moore Park Works Primary Erosion and Sedimentation Control Plan .......... 27
Appendix D – Landcom “Blue Book” Standard Drawings ...................................................... 31
Appendix E – Laing O’Rourke Monitoring/Inspections Forms ............................................... 40
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
6/46
CSSFMP
1. Introduction
1.1 Purpose and Application
This Construction Soil, Stormwater and Flooding Management Plan (CSSFMP) describes how the Laing O’Rourke team will ensure all risks associated with erosion and sediment control, surface water quality, site wastewater, potential water contamination, groundwater and flooding issues are considered and managed effectively during the design and construction stages of the Moore Park Works as part of the Managing Contractor early works for the CBD and South East Light Rail (CSELR) Project (the Project).
This CSSFMP addresses the relevant requirements of the Project Approval (EIS, Submissions Report and Minister’s Conditions of Approval (CoA)) the Project Contract (with TfNSW) and all applicable guidelines and standards.
Section 0.0 (Page 3) of this CSSFMP includes a table demonstrating the Plan’s compliance against the requirements of the CoA including CoA 66 (which requires the Plan to be prepared, consulted and approved).
1.2 Background
1.2.1 CSELR Overview
The Project incorporates the new light rail network, a 12 km route integrating major interchanges with other transport modes at Circular Quay, Wynyard, Town Hall, Central, Randwick and Kingsford, which will transform Sydney and support the city’s growing economy and population. The expanding light rail network will connect people to jobs, homes, entertainment precincts and form part of an integrated public transport solution to ease congestion and improve services.
The new light rail network will be delivered in two stages, as follows:
Stage 1 – CSELR Early Works Managing Contractor - critical and long lead enabling works being undertaken by Laing O’Rourke (appointed by Transport for NSW (TfNSW)).
Stage 2 – CSELR Main Construction Works – to be delivered under a Public–Private Partnership (PPP) contract (to be appointed by TfNSW).
1.2.2 CSELR Moore Park Works Overview
The Moore Park Works scope includes:
Moore Park Tennis Centre – Reconfiguration of the existing car park and access driveway at the Tennis Centre as well as construction of a replacement amenities block prior to demolition of the existing amenities block for the Moore Park Tennis Centre.
Tramway Oval Eastern Extension - An extension of the turfed surround of the current Tramway Oval Field by 5 metres to the east, to create provision for a subsequent relocation of the oval by the Public Private Partnership (PPP) Contractor.
Moore Park Bus Loop – Construction of a temporary bus turnaround to run event buses in both directions on the events bus loop located to the east of Tramway Oval during construction of the CSELR project.
Moore Park Construction Compound – Establishment of a construction compound to support the works within Moore Park.
Further details are provided in Section 2 of the Moore Park Works CEMP.
1.2.3 Environmental Planning Approval
The Project has been assessed by TfNSW under Part 5.1 of the Environmental Planning and Assessment Act 1979 (EP&A Act) as State Significant Infrastructure (SSI). The Project, its impacts, consultation and mitigation were documented in the following suite of documents:
SSl Application SSI 6042;
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
7/46
CSSFMP
CBD and South East Light Rail Project, Environmental Impact Statement, TfNSW November 2013; and
CBD and South East Light Rail Project, Submissions Report (incorporating Preferred Infrastructure Report), TfNSW March 2014.
The Minister for Planning granted Approval for the Project in the Minister’s Conditions of Approval (CoA, 4 June 2014 (ref SSI-6042)).
1.2.4 CSELR Moore Park Works Approval Pathway
In accordance with Condition of Approval (CoA) A7 of the Planning Approval, the Project is able to be constructed in stages provided that those stages are undertaken consistently with the Conditions of Approval.
Due to a key Project’s priority to commence (and therefore complete) an initial package of early works in advance of the main early works by the Managing Contractor (MC) for the Project, TfNSW has requested a Staged Approval to permit the priority works to be commenced in advance of the main MC works.
A Staging Report has been submitted to DPE which reflects the proposed first stage of MC works, referred to as the Moore Park Works. Subsequent Stages will be described and approved through subsequent submissions of the required Plans such as this CSSFMP.
1.2.5 Project-Specific Environmental Management System
The Moore Park Works Construction Environmental Management Plan (CEMP) is the head EMS document for the delivery of the Moore Park Works and this Plan is one of the suite of Aspect-Specific support Plans and Environment Procedures to the CEMP. In summary, these documents include: Moore Park Works Construction Environmental Management Plan (Moore Park Works CEMP) Moore Park Works Construction Noise and Vibration Management Plan (CoA B89 (b)) Moore Park Works Construction Traffic, Transport and Access Management Plan (CoA B89 (c)) Moore Park Works Soil, Stormwater and Flooding Management Plan (CoA B66) – this Plan Moore Park Works Construction Heritage Management Plan (CoA B89 (e)) Moore Park Works Construction Business Management Plan (CoA B89 (f)) Moore Park Works Construction Compound and Ancillary Facility Plan (CoA B88 (a)) Community Communication Strategy (CoA B90)
1.3 Objectives and Targets
Laing O’Rourke project objectives and targets related to Construction Soil, Stormwater and Flooding Management, and which are applicable to the Moore Park Works are as follows:
Minimise erosion on site through implementation and maintenance of appropriate erosion and sediment controls.
o Target - Inspections by ER, TfNSW and regulator resulting in no occurrence of significant issues/non-compliances.
Limit the disturbed area and stabilise as soon as practicable following the completion of works Prevent pollution of surface water to ensure existing water quality of surrounding surface
watercourses is maintained. o Target: no pollution incidents resulting in environmental harm or regulatory action o Target: no written warnings or Penalty Infringement Notices arising from the works
Ensure all discharges from site comply with the objectives of Section 120 of POEO Act. o Target: no non-compliances with s120 PoEO Act – i.e no incidents of “pollution”.
Prevent mud and litter from being deposited on roadways Minimise demand for, and use of, potable water for construction and maximise opportunities for
water re-use from captured stormwater, wastewater and groundwater. Design and construct works to minimise adverse increase in flood impacts to local and regional
catchments.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
8/46
CSSFMP
1.4 Consultation
The Minister’s Condition of Approval requires that the Soil, Stormwater and Flooding Management Plan be prepared in consultation with the Environment Protection Authority (EPA), NSW Office of Water (NOW) and relevant Councils. For the Moore Park Works this plan has been provided, for review and comment, to: NSW Environment Protection Authority (EPA); NSW Office of Water (NOW); Council of City of Sydney (through the Moore Park Works Reference Group); and NSW Department of Planning & Environment (DPE). A draft copy of the Moore Park Works CSSFMP was issued for comment and consultation purposes to the EPA and NOW via e-mail on 4 August 2014. Draft copies of the Moore Park Works CEMP and Sub Plans, including the draft Moore Park Works CSSFMP, were issued for comment and consultation purposes by TfNSW to the Moore Park Works Reference Group on 7 August 2014. Additionally a briefing session was held on the 11 August 2014 in which all members of the Moore Park Works Reference Group were invited to attend. Appendix A provides a summary and evidence of the comments received during this consultation process and Laing O’Rourke’s response. It is noted that these stakeholders will have an ongoing role in the reviewing relevant subsequent Plans and documents relating to the Moore Park Works as required. Draft copies of the Moore Park Works CEMP and Sub Plans, including a draft copy of this Plan, were issued for comment by TfNSW to DPE on 7 August 2014. Final copies of the Moore Park Works CEMP and Sub Plans, including a final copy of this Plan, would be submitted to DPE for approval by the Secretary prior to construction works commencing.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
9/46
CSSFMP
2. Legal and Other Requirements
2.1 Legislation
Key legislation relevant to this Plan includes: Protection of the Environment Operations Act 1997 Environmental Planning and Assessment Act 1979 Contaminated Land Management Act, 1997 Fisheries Management Act 1994 Water Management Act, 2000. A full description of each legal instrument is included in the Moore Park Works CEMP. A key legislative requirement applicable to construction water management is Section 120 of the Protection of the Environment Operations Act 1997 which relates to pollution of waters and the need to implement all reasonable and feasible measures to minimise the risk of pollution of waters. Part 5.7 of the Act requires that a pollution incident causing or threatening material harm to the environment to be notified to EPA and other relevant authorities as outlined in the Moore Park Works CEMP. Material harm constitutes actual or potential harm to the health or safety of humans and/or ecosystems that is not trivial, or results in actual or potential loss or property damage of amounts in excess of $10,000 in total. Incidents triggering this threshold must be reported to EPA and other relevant authorities as outlined in the Moore Park Works CEMP.
2.2 Project Approval Conditions
The Minister’s Conditions of Approval (MCoA) relevant to soil and water management have been addressed in this Plan in the following sections: Section 0 - Compliance Matrix (Minister’s Conditions of Approval (CoA)) - details where each
related element of CoA is addressed in the Plan. Section 5/Appendix B (Mitigation Measures) – details the applicable Revised Environmental
Mitigation Measures (REMMs from Submissions Report) and other requirements and how they will be addressed during the Project.
2.3 Guidelines
Additional guidelines and standards relating to the management of soil, stormwater and flooding include:
NSW Landcom publication Managing Urban Stormwater - Soils and Construction Edition 4 March 2004 (Blue Book)
Managing Urban Stormwater: Soils and Construction - Volume 2A: Installation of services (DECC 2008)
Guidelines on the Duty to Report Contamination under the Contaminated Land Management Act 1997 (DECC 2009)
Australian and New Zealand Guidelines for Fresh and Marine Water Quality (ANZECC 2000) NSW EPA (1997), Managing Urban Stormwater – Treatment Techniques TfNSW Water Discharge and Reuse Guideline - 7TP-ST-146 ASSMAC (1998). Acid Sulfate Soil Manual. Acid Sulfate Soil Management Advisory Committee,
NSW Floodplain Development Manual (2005) Australian Rainfall and Runoff – Volume 1 (2001), Engineers Australia.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
10/46
CSSFMP
3. Existing Environment
3.1 Soils
3.1.1 Moore Park Works Local Conditions
The Moore Park, Kensington/Kingsford and Randwick precincts are underlain by Quaternary age unconsolidated sands known as Botany Sands. The Botany Sands comprise medium to fine grained marine sand with podsols.
ASS are known to occur in low-lying coastal floodplain areas. The ASS risk map is provided in Figure 10.4 of the EIS, indicates the overall risk of disturbing ASS in the Moore Park sections of the CSELR alignment is considered to be low and no known occurrences of ASS have previously been identified.
3.2 Contamination
3.2.1 Moore Park Works Local Contamination Risks
According to the EIS, historical land use surveys indicate that in the area of Moore Park, the key potential contamination risks are:
• bonded asbestos materials
• PAHs
Further, in accordance with MCoA B72, a Stage 2 Contamination Site Investigation report is currently underway regarding risks within the Moore Park Work. If the Stage 2 Contamination Site Investigation identifies contamination to the extent that a Remediation Action Plan (RAP) is required for the site, any specific risks and mitigation measures, beyond measures in the Moore Park Works CEMP and this Plan, are to be included in the Site Auditor endorsed RAP (CoA B72(a)).
3.3 Water Quality
3.3.1 Moore Park Works Local Water Quality Conditions
Kippax Lake is the only water course in proximity to the work and is located approximately 50m to the north of the Tramway Oval site.
During construction site water would drain to the Ponds of Centennial Parklands which form the upper catchment of the Botany wetlands. They act as a detention basin and receive stormwater runoff from surrounding catchments including Randwick. Water quality has been poor in the past and is currently improving due to recent measures put in place to improve it.
The key construction impacts on stormwater quality would be sediment mobilisation and deposition, oil and petrol from construction vehicles and accidental spills of chemicals and other hazardous construction materials.
If uncontrolled, runoff from the worksites could result in discharge of contaminants to receiving waterways, further contributing to the poor water quality in the catchments downstream.
It is also noted that run off from site (if uncontrolled and polluted) to Ponds of Centennial Parkland has potential to cause pollution of the ground water aquifer which is recharged by the ponds.
3.4 Flood Conditions
3.4.1 Moore Park Works Local Flood Conditions
Flood information related to the Moore Park site is presented in Table 3-1 (Locations 2/3 from EIS) and identifies that the area will suffer some degree of flooding following a rainfall event with an ARI of one in five
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
11/46
CSSFMP
years, with some flooding along the southern section of Anzac Parade predicted to occur more frequently during a one in two year ARI event.
Table 3-1 - Existing known flooding issues along CSELR alignment
FLOODING LOCATIONS FLOOD DEPTH (METRES) 1 YEAR ARI 2 YEAR ARI 5 YEAR ARI 10 YEAR ARI 20 YEAR ARI 100 YEAR
ARI PMF
Location 2: Proposed location for the Moore Park tunnel portal entrance
No flooding No flooding No flooding 0.1–0.29 0.1–0.29 0.1–0.29 0.1–0.29
Location 3: Anzac Parade between Lang Road and Dacey Avenue
No data < 0.1 0.2–0.5 0.2–0.5 0.5–1.0 1.0–2.0 1.0–2.0
Note: ARI = Annual recurrence interval; PMF = probable maximum flood
Potential of localised flooding issues during construction caused by surface water entering, or falling directly onto the construction area will be mitigated by implementing site-based management measures including earthen bunds, sediment fences and stormwater inlet protection as detailed in Section 5 and Appendix C and D. With these measures in place, construction phase stormwater flows should not result in additional flow velocities or volumes off site.
Existing stormwater infrastructure will remain in place during the Moore Park construction works, minimising localised flooding potential due to construction activities. All new connections to the existing stormwater system, as part of the construction works, will be approved by an appropriately certified designer to ensure capacity of the system is acceptable. The above measures will minimise impact to the downstream drainage network.
3.5 Groundwater
3.5.1 Moore Park Works Conditions
The major aquifer system in the vicinity of Moore Park is the Botany Sands aquifer, an unconsolidated aquifer that predominantly consists of sand. Groundwater in the shallower beds is unconfined, but in the deeper layers is partially confined. Groundwater flow direction generally is from north to south, partly tending to the north-east to south-west. Potential sensitive receptors include groundwater bores, a stormwater channel on Alison Road and the Alexandra Canal. Recharge mainly occurs via rainfall infiltration. Ponds in Centennial Park receive stormwater, which recharges the aquifer. It is likely that some recharge from leaking pipes also occurs. Groundwater levels fluctuate over time in response to recharge, pumping, and (in locations where the water table is shallow), evapotranspiration. EIS summarises water table levels taken from the NSW Office of Water’s (2013) database which range between 0.5 metres and 7 metres below ground level. Groundwater within the Botany Sands is mostly low in salinity. In 2003, an embargo was implemented under section 113A of the Water Act 1912 in the northern part of the aquifer (where the alignment is located), because available water was depleted by plumes of contamination. The Moore Park Works will comprise surface/shallow excavations; additionally no groundwater was encountered during geotechnical investigations undertaken for the Moore Park Works which were based on the proposed design and construction methodology depths. Therefore works are not anticipated to encounter or impact significant groundwater, with the exception of perched shallow bodies if encountered, and volumes of groundwater to be intercepted and dewatered are expected to be minimal. The key risk associated with the works is from accidental spills or leakage from construction plant which are to be mitigated as per Section 5 of this Plan.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
12/46
CSSFMP
4. Aspects, Impacts & Risks
The key aspects, impacts and risks (semi quantified) in relation to the management of soil, stormwater and flooding for the Moore Park Works are listed in Table 4-1 below.
Table 4-1 Aspects, Impacts And Risks
Activity Aspect/s Impact/s Risk Level* Moore Park Works
Establishment of site and compounds
Surface water run off on disturbed areas resulting in sediment laden runoff.
Sediment laden runoff entering stormwater drains (and receiving waters) causing pollution and degradation of local watercourses.
M-H
Earthworks (excavation and filling)
Material/spoil stockpiling and handling
General earthworks Dust blowing from the site or from vehicles holding spoil/fill
Deposited dust washing into stormwater drains (and receiving waters) causing pollution and degradation of local watercourses.
M
Run-off from contaminated materials
Contaminated water entering stormwater drains (and receiving waters) causing pollution.
L-M
Alteration of landform resulting in changed flow patterns
Changed stormwater runoff resulting in flooding, exceeding drainage capacity or erosion
L-M
Dewatering of excavations due to surface water or groundwater inundation
Untreated sediment laden water discharges
Sediment laden water entering stormwater drains (and receiving waters) causing pollution and degradation of local watercourses.
H
Operation of compounds Sewage overflows from amenities
Contaminated water entering stormwater drains (and receiving waters) causing pollution.
L
Changes to drainage or landform
Site activities (earthworks or drainage) resulting in adverse flood impact on-site or upstream/downstream
Flood inundation of site facilities or neighbouring properties
Sediment laden runoff entering stormwater drains (and receiving waters) causing pollution and degradation of local watercourses.
L
Concreting works / Concrete cutting
Runoff of contaminated water
Contaminated water entering stormwater drains (and receiving waters) causing pollution.
H
Storage and use of hazardous substances/dangerous goods
Spillage of materials to soil/water.
Soil contamination due to spills
Water pollution due pollutants washing into the stormwater drains (and receiving waters) causing pollution.
M
Operational plant & equipment leakage
Note: * Semi Quantified Risk Rating = Low (L), Medium (M) or High (H) – refer complete RA in Moore Park Works CEMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
13/46
CSSFMP
5. Management Measures This Section describes the overall approach and principles associated with managing and mitigating soil, stormwater and flooding risks during the Moore Park Works. Further Appendix B includes Table B1- Mitigation Measures which details specific actions and responsibilities to be implemented during the works. The management measures are based on the mitigation measures compiled from the EIS, Submissions Report (Revised Environmental Mitigation Measures or REMMs) and the Minister’s Conditions of Approval (MCoA), as well as the requirements and standards of TfNSW and Laing O’Rourke.
5.1 Key Soil, Stormwater and Flooding Management Tools
The hierarchy of management documentation used by Laing O’Rourke for the implementation of the mitigation measures on each site are as follows: 1. Construction Soil, Stormwater and Flooding Management Plan (CSSFMP) – key guidance
document from which the practical site-based management tools are developed 2. Environmental Controls Map (ECM) – plan/map based tool specific to site/work area and includes
the location of existing waterways, environmental protection measures, monitoring requirements, conditions of approval and environmentally/community sensitive areas
3. Erosion and Sedimentation Control Plans (ESCPs) - Site-specific ESCPs developed for each of the site to ensure conformance with the Blue Book and POEO Act requirements. Consisting of the initial Primary ESCP for each site prior to construction followed by Progressive ESCPs (PESCPs) to reflect changing nature of the site as works progress. The ESCPs would include the location of existing drainage infrastructure in proximity to the works and associated controls to be installed.
4. Procedures and Protocols - contain detailed measures to mitigate specific risks which are read in conjunction with the tools above, and include Clearing and Grubbing, Topsoil Stripping and Stockpiling, Installation of drainage, Dewatering and discharge of excavations
5. Drainage Design Reports –– Site Drainage System design reports will include hydraulic and flood modelling, consultation with relevant stakeholders (councils, neighbours) and mitigation measures to reduce flood risks.
5.2 Principles of Soil, Stormwater and Flooding Management
The following points have been identified as the key techniques to control water quality on the project. These points collectively fulfil the principles of sound soil conservation practice. In selecting appropriate control structures care must be taken so that their use does not exceed design limitations. Where exceedance of design limitations cannot be avoided detailed design of the structure will be required.
The key measures associated with sediment and erosion control will include:
Check the operation of all project-related sediment and erosion controls at least once per day during operational hours, to help identify potential water pollution risks
Minimising the exposure of fill and excavated material to active work fronts Ensuring stockpiles or other materials are not placed within 15m of drainage lines or water courses
where practical Retention of stabilised areas as much as practical to prevent erosion Diverting stormwater runoff around disturbed areas of the site where practical to prevent
contamination with runoff from the disturbed areas. Where this is not possible, control measures such as diversion drains will be constructed to ensure stormwater runoff does not cause additional erosive impacts
Bunded chemical storage areas will be located within the compound and will have provision for protection from rainfall and will consist of lockable containers. To avoid the cumulative effect of multiple container failure the bund will be sufficient to contain 110% of all liquid materials contained within the bund
Implementing water quality control measures prior to the commencement of construction activities
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
14/46
CSSFMP
Implementation of temporary and permanent erosion and sediment controls to prevent sediment from the construction site from leaving site. The specific measures are outlined below in subsequent sections of this Plan
Laing O’Rourke will monitor temperature, humidity, wind velocity and rainfall at the nearest Australian Bureau of Meteorology weather station or site compound weather station
If high rainfall events are predicted erosion and sediment controls will be inspected to ensure maintenance is not required, Inspection of controls during rainfall event will occur to ensure they are performing.
5.3 Permanent Controls
5.3.1 Vegetation
All disturbed areas are to be stabilised and or revegetated in accordance with the contractual requirements as soon as practical following final land shaping.
5.3.2 Drainage
Appropriate local stormwater and pavement drainage design will be developed for the Tennis Centre car park and the Tramway Oval for the bus turning circle at the Tramway Oval site.
5.4 Temporary Controls
Temporary controls will be documented on Erosion and Sedimentation Control Plans (ESCPs). These will be developed prior to relevant works activities commencing and based on detailed site investigations.
5.4.1 Erosion and Sediment Control Plans
Progressive Erosion and Sediment Control Plans (ESCP) will be prepared for all areas of the work site prior to the commencement of construction. The ESCPs will include landforms and flow paths, existing drainage infrastructure, ERSED controls, stockpile locations and additional actions for management of spoil in accordance with Managing Urban Stormwater: Soils and Construction Volume 1 (Landcom 2006) (the Blue Book”).
5.4.2 Batter Protection
Exposed batters of the site during earthworks represent a significant source of readily erodible material until final stabilisation is achieved. To minimise the potential for the generation of sediment laden water run-off from exposed batters during the works, geotextile fabric will be placed and secured as a temporary erosion control measure where practical.
5.4.3 Sediment Fences
Sediment fences or suitable equivalent operate by slowing the flow of runoff and enabling the coarse suspended solids to settle out and be trapped behind the control structure. Sediment fences will be utilised for stockpiles of spoil and other erodible materials, site perimeter sections and disturbed areas.
Design limitations are:
Drainage area ≤0.6 ha Maximum grade 1V:2H Maximum slope length 60m.
Particular attention must be made to the potential outlet of the sediment fence during high rainfall events and the likely point at which the fence will discharge. To ensure that the fence remains intact during high flow events and runoff discharges to the appropriate areas, a small reinforced weir may need to be constructed in the fence. This will be reviewed daily during construction. Weirs in sediment fences must outlet to stable areas.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
15/46
CSSFMP
Details on location of these structures will be verified on site, and incorporated in the working Erosion and Sediment Control Plans.
5.4.4 Sandbags and Sediment Socks
Sandbags and sediment socks are utilised to create a weir or check dam in table drains to slow the runoff water velocity and enable coarse sediment to settle. They can also be used to create diversion drains or bunds walls to contain liquids, or to supplement existing sediment controls and will be placed around any existing live stormwater pits or drop inlets prior to decommissioning of the structure. Locations will be confirmed on site and included in working sediment and erosion control plans.
Check dams will be carefully constructed where required to allow runoff to exist the sediment control structure via the intended flow path. A specifically constructed low point must be incorporated into the dam to direct runoff and ensure that flow is retained within its intended path.
5.4.5 Dust Control
Water carts fitted with sprays will be used to wet down any unsealed haul roads and fill areas to minimise the amount of dust generated where required. The number and size of the water carts shall be regularly reviewed by the Site Supervisor and the Project Manager to ensure that adequate watering is taking place and dust is kept to a minimum. Care is to be exercised to limit the amount of water used to ensure run-off does not occur and leave the site.
5.4.6 Stockpiles
Temporary stockpiles shall be located more than 15m from drainage lines or water courses where practical. Sediment barriers shall be erected on the down slope side so that any sediment laden runoff from the stockpile is captured and controlled. On the upslope, berms or catch drains shall be installed, if practicable, to divert clean water away from the stockpile.
Stockpiles will be covered or stabilised when not in use to minimise erosion and dust.
5.4.7 Site Access
A stabilised access is to be utilised to reduce the tracking of sediment off-site. A street sweeper will be utilised as required during the construction phase of the project.
5.5 Operation and Maintenance of Site Controls
Construction water quality structures and sediment controls will be implemented and maintained until such times as disturbed areas have been stabilised. The Site Supervisor and Project Environmental Manager will continually inspect the site’s environmental controls during active works and when controls are required to be installed and left on site between track possessions. An inspection of the site will also be undertaken following heavy rainfall events.
The Site Supervisor and Environmental Manager will also inspect the site prior to Rostered Day Off (RDO site shut-down day) weekends or other periods of extended closure.
Permanent and temporary sediment control structures which become blocked or overloaded with sediments will be cleaned out using appropriate methods such as an excavator, backhoe or by manual means. Cleaning shall be performed prior to or when the accumulated sediment has reduced the capacity of the structure to less than 60%, based on a visual assessment.
Silt collected from cleaning temporary and permanent sediment and erosion control measures shall be mixed with dry material and incorporated into the works where deemed able. Detention basins (if used) will be de-silted when the capacity of the sediment storage zone has been reduced to less than 60%.
All temporary erosion and sediment controls will be removed and the areas rehabilitated as per the revegetation and landscaping details.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
16/46
CSSFMP
5.6 Site Wastewater Controls
5.6.1 Waste Water
All site waste water will be directed to existing site sewerage facilities in compliance with the requirements of the Sydney Water Act 1994 or waste from portable toilet facilities will be managed and disposed by a licenced contractor.
5.6.2 Concrete Washout
Where washout of concrete trucks is required on site, the Laing O’Rourke Site Supervisor will locate a designated washout area a minimum of 20m away from any natural watercourses or drainage lines.
An Environmental Risk Action Plan (ERAP) relating to concrete washout has been included in the Moore Park Works CEMP. Concrete Washout areas will be set up in accordance with the intent of the NSW EPA guideline ‘Environmental Best Management Practice Guideline for Concreting Contractors’ (2002) and TfNSW Concrete Washout Guideline – 3TP-SD-112.
5.6.3 Paint Washout
Where wash out of paint is required on site, a paint washout facility will be located in a designated and signposted washout area.
5.7 Water Discharge Requirements
Water discharge and reuse on the Moore Park Works will be in accordance with the TfNSW Standard; Water Discharge and Reuse Guideline - PE-ST-146.
5.7.1 Criteria for Discharge to Water
As an Environment Protection Licence is not going to be held for the CSELR MC Works, the criteria for discharge of site water to stormwater is set by the objective of compliance with Section 120 of the POEO Act. Specifically, Laing O’Rourke would utilise ANZECC (2000) Australian and New Zealand Guidelines for Fresh and Marine Water Quality (utilising ANZECC Protection Level Criteria of 3. Highly Disturbed Systems) to determine these criteria (i.e. a breach of ANZECC Guideline represents a breach of POEO Act). The highly disturbed criteria has been adopted in the case of the Moore Park Works as suitable for the proposed discharge of site water to stormwater and based on the existing local water quality conditions (Section 3.3.1).
Any water discharged from site must be of the same quality, or better, than the “background” water quality of the receiving water bodies.
Prior to, during and after discharge, the quality of the discharge and receiving waters are to be tested and characterised to demonstrate compliance.
As a guide, before water can be discharged to any receiving waters (whether on or off site), it must as a minimum meet the following criteria:
Parameter Criterion Method Time prior to discharge
Oil and grease No visible Visual inspection < 1 hour
pH 6.5-8.5 Probe/meter 1 < 1 hour
Total Suspended Solids (TSS) < 50mg/L 2 Meter/grab sample 3 < 1 hour/< 24 hours 1 litmus paper and pool testing kits are not to be used 2 a more stringent TSS criterion may need to be adopted in certain situations 3 grab samples to be analysed at a NATA accredited laboratory
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
17/46
CSSFMP
The analytical results report will be assessed to confirm water quality meets applicable criteria.
If the criteria above are not met, the water will be treated and retested prior to discharge or disposed offsite.
If all criteria above are met then the water may be authorised for discharge by the PEM by completing the TfNSW Approval to Discharge or Reuse Water form; Approval to Discharge or Reuse Water - 9TP-FT-207.
As per the TfNSW Standard, discharge can use a syphon system or a pump, with a priority on delivering low energy flows to downstream drainage lines, watercourses or land. The flow from the outlet must be directed onto a non-erodible surface or material and, for discharges to waters, sufficient energy must be dissipated before the flow enters the natural watercourse to ensure no erosion shall occur.
The pump inlet must be placed so that it will not disturb or take in any sediment or sediment laden water. The discharge must be monitored throughout to ensure that the water being syphoned or pumped:
complies with the discharge criteria does not come into contact with any soil or exposed surfaces before discharging does not mix with any sediment laden/untested water at either the inlet or outlet.
Water must never be discharged or reused onsite in a manner that exceeds the capacity of sediment controls and/or generates runoff with the potential to discharge from site.
5.7.2 Discharge to Land
The objective of discharging water to land (within the site boundary) is to allow the water to infiltrate into the ground, thus avoiding direct discharge to, or pollution of, waters. Any suspended solids in the water are deposited either on the surface or retained in underlying soil layers, so the TSS criterion does not apply. However, to avoid impacts to vegetation or soil contamination pH testing and a visual inspection for oil or grease must be undertaken.
In addition to criteria for discharges to water:
No surface runoff will be generated from the discharge and there is no potential for discharged water to reach any watercourse (within or outside the site)
No erosion is caused from the discharge and appropriate erosion and sediment control are installed in accordance with the Blue Book
All discharge water can be wholly contained within the site boundary.
5.7.3 Reuse on Site
Water to be reused on site for dust suppression or other uses will not require the TSS criteria as with discharge requirements as the water will not be discharged from the Project site, however pH testing and visual inspection for oil and grease is still to be undertaken. The flowchart from TfNSW Water Discharge and Reuse Guideline Planning & Environment: Standard PE-ST-146 outlines the process for testing water and determining options for reuse, discharge or disposal.
5.8 Drainage/Flooding Design and Construction
The Moore Park construction works and the operational drainage impacts will not significantly change the site levels, drainage configuration or increase the final impermeable area and consequently is not envisaged to have a significant adverse impact on the local flood potential. Approximately 50m of the existing drainage at Tramway Oval will be replaced as part of the eastern extension of the Oval, designed and approved by an appropriately certified designer. The final design of the Moore Park Tennis Centre works, including car park reconfiguration, landscaping and construction of a new amenities building will be designed and approved by an appropriately certified designer
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
18/46
CSSFMP
As documented in the relevant Design Reports, designs for all Moore Park construction works includes local hydraulic and flood modelling taking into account existing stormwater system capacities, local topography, proposed additions to the stormwater system associated with the new amenities building and areas of new pavement. These reports have indicated that the proposed Moore Park works will not increase flooding potential of the local or downstream area and will have negligible impact to the existing stormwater system. Consultation has been undertaken with relevant stakeholders (CMPT, asset owners, and council) in order to ensure that flood risks are considered and mitigated. These Design Reports will meet the requirements of CoA 65 and, as required, be in compliance with the NSW Floodplain Development Manual.
5.9 Incident Management
In the case of an incident resulting in contamination of water (e.g. fuel spill) or contaminated / turbid water being discharged from the site then the incident management procedures located in Moore Park Works CEMP will be implemented.
In all cases, the situation will be assessed and if safe to proceed measures implemented to stop or slow down the released of contaminated material from the site. The Project Construction Manager and Environmental Manager will be informed and all necessary stakeholders informed as per the incident management process in the Moore Park Works CEMP.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
19/46
CSSFMP
6. Soil, Stormwater and Flooding Risk Training
All site personnel shall undergo site specific induction training, which will include environmental awareness. It will also include training in the need for effective sediment and erosion control on site. Toolbox meetings will also be undertaken as and when required; covering specific environmental issues and shall include erosion and sediment control measures.
Personnel directly involved in implementing sediment and erosion control measures on site will be given specific training in the construction, operation and maintenance of the various measures to be implemented.
Personnel conducting sampling, measuring, monitoring and reporting activities are to be suitable trained or experienced in the activity. Records of all training are to be filed in accordance with the project filing system.
It is the Project Environment Manager (and Site Environmental Officers) responsibility to ensure all personnel are appropriately trained as outlined above.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
20/46
CSSFMP
7. Monitoring of Controls
Site inspections and audits will be undertaken in accordance with Section 18 of the Moore Park Works CEMP, and in accordance with this Plan for soil, stormwater and flooding management during construction.
All water quality control and sediment control structures (e.g. sediment fences, drainage protection, temporary check dams/sumps) will be regularly inspected and maintained throughout the project. The Site Construction Manager is responsible for managing the installation of controls and rehabilitation of the sites in accordance with the requirements. The Project Environment Manager (and Environmental Site Officers) are responsible for monitoring the installation and maintenance of controls and providing training.
Daily inspections of controls will be made by Supervisors and maintenance will be recorded in site diaries during active site works.
The Project Environmental Manager will conduct a detailed documented inspection at least once per week during active works and after any heavy rainfall. An inspection of the site will also be undertaken prior to RDO weekends and other times where the site will be closed or inactive for an extended period. The inspections will focus on the integrity, capacity and performance of the site control measures which will include the sediment fences, temporary check dams/sumps, diversion bunds, drain protection and rehab works.
Items that require repair or action will be documented on the site environmental inspection. Items that require specific and detailed action will be recorded on the Project’s Corrective Action Register. The Superintendent will be responsible for providing appropriate resources in terms of labour, plant and equipment to enable the items to be rectified in the nominated timeframes.
If deemed necessary, additional sedimentation control measures will be implemented to ensure that water quality is maintained throughout the works. Improvement requests received from the TfNSW, Environmental Representative or other appropriate agencies shall be assessed and responded to within 24 hours if the issue is not environmentally threatening.
The following forms and check sheets shall be utilised to inspect, monitor and record erosion and sediment controls and water quality on this project and filed in accordance with the project filing system.
Plan Environmental Control Map Plan Erosion and Sediment Control Plan Form F 1227 Weekly Environmental Checklist Form F 1228 Environmental Improvement Request F 1298 Water Sampling Record Form TPD Approval to Discharge or Reuse Water PE-FO-207 Form LOR Water Quality Testing Form Checklist Rainfall Erosion and Sediment Control Inspection Checklist.
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
21/46
CSSFMP
Appendix A – Stakeholder Consultation Feedback
Stakeholder Date/Format Comment Response
EPA 11 August 2014 / E-mail
Section 1.1 Purpose and Application:The first sentence (which refers to the scope and purpose of the Plan) should also refer to groundwater.
Section 1.1
Section 1.3 Objectives and Targets: The fourth dot point (regarding compliance with the Protection of the Environment Operation Act 1997) needs to be reworded. Section 120 of the Act does not contain any criteria that can be exceeded. It is noted that any discharges to water that do not meet the ANZECC (2000) guideline requirements may be considered to constitute a breach of section 120 of the Protection of the Environment Operation Act 1997 unless an exemption is granted by the EPA via an environment protection licence.
Section 1.3 Noted
Section 2.3 Guidelines: This section should also list guidelines of relevance to water quality. The following additional guidelines should also be referenced: Managing Urban Stormwater: Soils and Construction – Volume 2A:
Installation of services (DECC 2008). Guidelines on the Duty to Report Contamination under the
Contaminated Land Management Act 1997 (DECC 2009) Australian and New Zealand Guidelines for Fresh and Marine Water
Quality (ANZECC 2000)
Section 2.3 Section 2.3 Section 2.3
Section 3.1 Soils:This section should also identify any contamination issues and corresponding management requirements.
Section 3.1
Section 5.7.1 Criteria for Discharge to Water:1st sentence - It is noted that that any discharges to water that do not meet the ANZECC (2000) guideline requirements may be considered to constitute a breach of section 120 of the Protection of the Environment Operation Act 1997 unless an exemption is granted by the EPA via an environment protection licence. 2nd sentence - This should refer to the “background” water quality of the receiving water bodies rather than the quality of receiving waters at the time of discharge. The water quality objectives for the receiving water bodies and relevant trigger levels/ guidelines should be determined with reference to appropriate current guidelines, including the ANZECC (2000) guidelines. In the event that discharges to waters are to be carried out as part of the works, water quality monitoring will be required both prior to and during construction and must be sufficient to enable identification of project impacts.
Section 5.7.1 Section 5.7.1 Section 5.7.1
NOW 22 August 2014 / letter
It is suggested a table is included in the CSSFMP which summarises who will be involved with implementing the plan, the tasks, roles and responsibilities; the frequency etc. including: who will inspect/monitor/maintain the permanent and temporary
sediment controls and the frequency of when will this occur and identify which position(s) this information will be reported to
who will test the quality of any water to be discharged from the site and the receiving waters
who will undertake training; who will remove the controls and rehabilitate disturbed areas.
Section 5.5 Section 7
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
22/46
CSSFMP
Stakeholder Date/Format Comment Response
1.3 Objectives and Targets:Section 1.3 of the CSSFMP indicates the objectives and targets related to Construction, Soil, Stormwater, and Flooding Management include to maximise opportunities for water re-use from captured groundwater (page 8). The Office of Water requests it is provided with details on the expected groundwater inflows and the volumes of groundwater to be dewatered and re-used as part of the Stage 1A Moore Park MC works.
Section 3.5.1 Additionally a response will be provided to NOW on e-mail
3.2.2 Moore Park Water quality Conditions:The CSSFMP notes that during construction, site water would drain to the Ponds of Centennial Parklands (see Section 3.2.2, page 12). It indicates that if uncontrolled, runoff from the worksites could result in discharge of contaminants to receiving waterways but contaminates could also enter the aquifer, as Table 3.5 indicates the Ponds of Centennial Park receive stormwater which recharges the aquifer (page 14). It is suggested Section 3.2.2 also makes reference to the potential for contaminates to enter the aquifer if runoff is uncontrolled.
Section 3.3.1
3.4.2 Moore Park Conditions:Section 3.4.2 notes the Stage 1A Moore Park works will comprise surface/shallow excavations and are not anticipated to encounter or impact significant groundwater with the exception of perched shallow bodies (page 14). It is noted in Table 3.5 that the Sydney Basin Central Aquifer is approximately 2 to 3 m below ground level within areas traversed by the CSELR alignment and water table levels of the Botany Sands Aquifer range between 0.5 m and 7 m (page 14). The Stage 1A Moore park works as outlined in Section 1.2.2 do not appear to involve significant excavation but it is suggested Section 3.4.2 is amended and it includes specific details, including: the maximum depths of excavations associated with the works, the depth of the shallow perched groundwater expected volumes of groundwater to be intercepted and dewatered.
Section 3.5.1
4. Aspects, Impacts and Risks:It is recommended an air photo and scaled map is included in the CSSFMP which shows the location of the proposed works and the location of all watercourses and drainage lines potentially affected by the works.
Section 3.3.1 Section 3.4.1 Section 5.1
Stockpiles and Concrete washout:Section 5.4.6 of the CSSFMP indicates temporary stockpiles shall be located more than 15 m from drainage lines or watercourses (page 18) and Section 5.6.2 refers to concrete washout areas on site being located a minimum of 20 m away from any natural watercourses or drainage lines (page 19). It is suggested Table B1 in Appendix B, is amended so that SSF 24 and SSF 28 specify the minimum setback distances of 20 m and 15 m respectively.
Table B1
6. Soil, Stormwater and flooding risk training:Section 6 Soil, Stormwater and flooding risk training: It is unclear who will be responsible for undertaking the training and it is suggested the CSSFMP includes this detail.
Section 6
Moore Park Works Reference Group
11 August 2014 / Briefing Session
No comments relevant to soil, stormwater or flooding management for the Moore Park Works
N/A
1
Laura Lynch
From: Neville MoranSent: Monday, 4 August 2014 12:39 PMTo: Wendy Stevenson ; Nicole JonesCc: Laura Lynch; Shannon Blackmore; Ambler, JasonSubject: CBD and South East Light Rail (CSELR) - Moore Park Works - EPAAttachments: SLR MC Stage 1A Moore Park Soil Water (SSFMP) v0-04 August 2014.docx; SLR
MC Stage 1A Moore Park Soil Water (SSFMP) v0-04 August 2014.pdf
Hi Wendy/Nicole, For your review the Soil, Stormwater and Flooding Management Plan for the Moore Park Works attached –Word doc and PDF (with appendices). Cheers Neville
Neville Moran Principal Environmental Consultant KMH Environmental P: +61 2 9468 9300 M: 0409 736 881 F: +61 2 8008 1600 E: Nmoran@kmh.com.au
Suite 902, Level 9, North Tower, 1-5 Railway St, Chatswood NSW 2067 PO Box 5487, West Chatswood NSW 1515 www.kmh.com.au ___________________________________________________________________________ This email and any files transmitted with it are confidential and intended for use by the Addressee only. The confidential nature of the information contained in the email and/or file is not waived, lost or destroyed if it is sent in error to other than the Addressee. Use or dissemination of the information contained in the email and/or files by a recipient other than the Addressee may cause commercial damage to both/either the Sender and/or Addressee. If you are not the Addressee of this email/files, please immediately contact the Sender and delete this email/files. please consider the environment before printing this email ___________________________________________________________________________
From: Wendy Stevenson [mailto:Wendy.Stevenson@epa.nsw.gov.au] Sent: Tuesday, 29 July 2014 9:52 AM To: Neville Moran Cc: Nicole Jones Subject: RE: CBD and South East Light Rail (CSELR) - Moore Park Works - EPA Hi Neville Nicole Jones and I will be available to undertake the reviews. Can you please confirm the required review timeframe. Regards Wendy
2
Wendy Stevenson Senior Operations Officer Environment Protection Authority Level 13, 10 Valentine Ave, Parramatta NSW 2150 : (02) 9995 6866 | : (02) 9995 6900 | : wendy.stevenson@epa.nsw.gov.au In my absence, please contact Nicole Jones 9995 6865 (Mon & Fri) or Mark Hanemann 9995 6845.
From: Neville Moran [mailto:Nmoran@kmh.com.au] Sent: Monday, 28 July 2014 1:59 PM To: Stevenson Wendy; Jones Nicole Cc: Shannon Blackmore; Laura Lynch Subject: CBD and South East Light Rail (CSELR) - Moore Park Works - EPA Hi Wendy, Laing O’Rourke has been engaged by Transport for NSW (TfSNW) as Managing Contractor for the Early Works that will be undertaken to facilitate construction of the CSELR Project. These works will form Stage 1 of the project and a Staging Report is currently being prepared in accordance with condition A7 of the Minister’s Conditions of Approval (MCoA attached) that will be submitted to the Department of Planning and Environment (DPE) shortly. Detailed design, construction and operation of the CSELR Project will be undertaken by a Public Private Partnership as the second stage of the project. The first package of works to be undertaken by Laing O’Rourke as part of Stage 1 will occur entirely within Centennial Park / Moore Park Trust (CPMPT) lands. The works, referred to as the Moore Park Works, will include:
Tramway Oval Eastern Extension - An extension of the turfed surround of the current Tramway Oval Field by 5 metres to the east, to create provision for a subsequent relocation of the oval by the Public Private Partnership Contractor.
Moore Park Tennis Centre – Construction of a replacement amenities block and demolition of the existing amenities block for the Moore Park Tennis Centre.
Moore Park Bus Loop – Construction of a temporary bus turnaround to run event buses in both directions on the events bus loop located to the east of Tramway Oval during construction of the CSELR project.
Moore Park Construction Compound – Establishment of a construction compound to support the works within Moore Park and subsequent packages of works within Surry Hills.
Tramway Oval is used as a training ground for the Sydney Swans AFL team. Works on the oval are time constrained due to the fact the oval needs to be handed back to the Sydney Swans by the end of October 2014. In order for this to occur, the construction works at this location would need to be commenced by approximately the 26th August 2014. As the proposed works are limited to the extent of the CPMPT lands, DPE have agreed to TfNSW submitting CEMP and associated sub-plans for the proposed Moore Park Works in order that the above timeframes can be met. As part of this process EPA need to be consulted on the soil and water management plan and the noise and vibration management plan. It is the intention to submit these plans Monday the 4 August for your review. Could you please confirm your availability to undertake this review and if you would like us to come in and discuss the submission this week we would be happy to do so? Regards Neville Neville Moran Principal Environmental Consultant KMH Environmental P: +61 2 9468 9300 M: 0409 736 881 F: +61 2 8008 1600 E: Nmoran@kmh.com.au
3
Suite 902, Level 9, North Tower, 1-5 Railway St, Chatswood NSW 2067 PO Box 5487, West Chatswood NSW 1515 www.kmh.com.au ___________________________________________________________________________ This email and any files transmitted with it are confidential and intended for use by the Addressee only. The confidential nature of the information contained in the email and/or file is not waived, lost or destroyed if it is sent in error to other than the Addressee. Use or dissemination of the information contained in the email and/or files by a recipient other than the Addressee may cause commercial damage to both/either the Sender and/or Addressee. If you are not the Addressee of this email/files, please immediately contact the Sender and delete this email/files. please consider the environment before printing this email ___________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------------------------------------- This email is intended for the addressee(s) named and may contain confidential and/or privileged information. If you are not the intended recipient, please notify the sender and then delete it immediately. Any views expressed in this email are those of the individual sender except where the sender expressly and with authority states them to be the views of the Environment Protection Authority.
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS EMAIL
1
Laura Lynch
From: Neville MoranSent: Monday, 4 August 2014 12:41 PMTo: Janne.Grose@water.nsw.gov.auCc: Shannon Blackmore; Laura Lynch; Ambler, JasonSubject: CBD and South East Light Rail (CSELR) - Moore Park Works - NoWAttachments: SLR MC Stage 1A Moore Park Soil Water (SSFMP) v0-04 August 2014.docx; SLR
MC Stage 1A Moore Park Soil Water (SSFMP) v0-04 August 2014.pdf
Hi Janne, For your review the Soil, Stormwater and Flooding Management Plan for the Moore Park Works attached –Word doc and PDF (with appendices). Cheers Neville
Neville Moran Principal Environmental Consultant KMH Environmental P: +61 2 9468 9300 M: 0409 736 881 F: +61 2 8008 1600 E: Nmoran@kmh.com.au
Suite 902, Level 9, North Tower, 1-5 Railway St, Chatswood NSW 2067 PO Box 5487, West Chatswood NSW 1515 www.kmh.com.au ___________________________________________________________________________ This email and any files transmitted with it are confidential and intended for use by the Addressee only. The confidential nature of the information contained in the email and/or file is not waived, lost or destroyed if it is sent in error to other than the Addressee. Use or dissemination of the information contained in the email and/or files by a recipient other than the Addressee may cause commercial damage to both/either the Sender and/or Addressee. If you are not the Addressee of this email/files, please immediately contact the Sender and delete this email/files. please consider the environment before printing this email ___________________________________________________________________________
From: Neville Moran Sent: Monday, 28 July 2014 2:03 PM To: 'Janne.Grose@water.nsw.gov.au' Cc: 'Shannon Blackmore'; Laura Lynch Subject: CBD and South East Light Rail (CSELR) - Moore Park Works - NoW Hi Janne, Laing O’Rourke has been engaged by Transport for NSW (TfSNW) as Managing Contractor for the Early Works that will be undertaken to facilitate construction of the CSELR Project. These works will form Stage 1 of the project and a Staging Report is currently being prepared in accordance with condition A7 of the Minister’s Conditions of Approval (MCoA attached) that will be submitted to the Department of Planning and Environment (DPE) shortly. Detailed design, construction and operation of the CSELR Project will be undertaken by a Public Private Partnership as the second stage of the project. The first package of works to be undertaken by Laing O’Rourke as part of Stage 1 will occur entirely within Centennial Park / Moore Park Trust (CPMPT) lands. The works, referred to as the Moore Park Works, will include:
2
Tramway Oval Eastern Extension - An extension of the turfed surround of the current Tramway Oval Field by 5 metres to the east, to create provision for a subsequent relocation of the oval by the Public Private Partnership Contractor.
Moore Park Tennis Centre – Construction of a replacement amenities block and demolition of the existing amenities block for the Moore Park Tennis Centre.
Moore Park Bus Loop – Construction of a temporary bus turnaround to run event buses in both directions on the events bus loop located to the east of Tramway Oval during construction of the CSELR project.
Moore Park Construction Compound – Establishment of a construction compound to support the works within Moore Park and subsequent packages of works within Surry Hills.
Tramway Oval is used as a training ground for the Sydney Swans AFL team. Works on the oval are time constrained due to the fact the oval needs to be handed back to the Sydney Swans by the end of October 2014. In order for this to occur, the construction works at this location would need to be commenced by approximately the 26th August 2014. As the proposed works are limited to the extent of the CPMPT lands, DPE have agreed to TfNSW submitting CEMP and associated sub-plans for the proposed Moore Park Works in order that the above timeframes can be met. As part of this process NoW need to be consulted on the soil and water management plan. It is the intention to submit this plan Monday 4 August for your review. Could you please confirm your availability to undertake this review and if you would like us to come in and discuss the submission this week we would be happy to do so? Regards Neville
1
Laura Lynch
Subject: FW: CBD and South East Light Rail (CSELR) - Moore Park Works - EPA Comments on Construction Soil, Stormwater and Flooding Management Plan
Attachments: image001.png; image001.png
From: "Wendy Stevenson " <Wendy.Stevenson@epa.nsw.gov.au> Date: 11 August 2014 2:50:29 PM AEST To: Shannon Blackmore <Shannon.Blackmore@projects.transport.nsw.gov.au> Cc: Neville Moran <Nmoran@kmh.com.au>, Nicole Jones <Nicole.Jones@epa.nsw.gov.au>, Mark Hanemann <Mark.Hanemann@epa.nsw.gov.au> Subject: CBD and South East Light Rail (CSELR) - Moore Park Works - EPA Comments on Construction Soil, Stormwater and Flooding Management Plan
Hi Shannon The EPA has reviewed Copy No. V0.00 of the Construction Soil, Stormwater and Flooding Management Plan (the Plan) prepared for the Stage 1A Moore Park Managing Contractor (MC) Works, which was provided to the EPA via the email below on 04 August 2014. The scope of the review covered environmental protection issues within the remit of the EPA and focussed on the Plan’s identification of appropriate guidelines and procedures. The review also assumed that the Plan has been prepared by appropriately qualified personnel and that all quantitative values contained within the Plan (such as those relating to sediment fence design and water discharge criteria) have been based on appropriate guidelines or criteria. It is noted that the EPA does not approve or endorse EMPs. The EPA’s comments on the Plan are as follows:
Section 1.1 Purpose and Application: The first sentence (which refers to the scope and purpose of the Plan) should also
refer to groundwater. Section 1.3 Objectives and Targets: The fourth dot point (regarding compliance with the Protection of the Environment
Operation Act 1997) needs to be reworded. Section 120 of the Act does not contain any criteria that can be exceeded.
It is noted that any discharges to water that do not meet the ANZECC (2000)
guideline requirements may be considered to constitute a breach of section 120 of the Protection of the Environment Operation Act 1997 unless an exemption is granted by the EPA via an environment protection licence.
Section 2.3 Guidelines: This section should also list guidelines of relevance to water quality.
The following additional guidelines should also be referenced:
o Managing Urban Stormwater: Soils and Construction – Volume 2A: Installation of services (DECC 2008).
o Guidelines on the Duty to Report Contamination under the Contaminated Land Management Act 1997 (DECC 2009)
o Australian and New Zealand Guidelines for Fresh and Marine Water Quality (ANZECC 2000)
Section 3.1 Soils: This section should also identify any contamination issues and corresponding
management requirements.
2
Section 5.7.1 Criteria for Discharge to Water: 1st sentence - It is noted that that any discharges to water that do not meet the
ANZECC (2000) guideline requirements may be considered to constitute a breach of section 120 of the Protection of the Environment Operation Act 1997 unless an exemption is granted by the EPA via an environment protection licence.
2nd sentence - This should refer to the “background” water quality of the receiving
water bodies rather than the quality of receiving waters at the time of discharge. The water quality objectives for the receiving water bodies and relevant trigger levels/ guidelines should be determined with reference to appropriate current guidelines, including the ANZECC (2000) guidelines.
In the event that discharges to waters are to be carried out as part of the works,
water quality monitoring will be required both prior to and during construction and must be sufficient to enable identification of project impacts.
Please contact me if you would like to discuss any of the issues raised in these comments. Regards Wendy Wendy Stevenson Senior Operations Officer Environment Protection Authority Level 13, 10 Valentine Ave, Parramatta NSW 2150 : (02) 9995 6866 | : (02) 9995 6900 | : wendy.stevenson@epa.nsw.gov.au In my absence, please contact Nicole Jones 9995 6865 (Mon & Fri) or Mark Hanemann 9995 6845.
From: Neville Moran [mailto:Nmoran@kmh.com.au] Sent: Monday, 4 August 2014 12:39 PM To: Stevenson Wendy; Jones Nicole Cc: Laura Lynch; Shannon Blackmore; Ambler, Jason Subject: TRIM: CBD and South East Light Rail (CSELR) - Moore Park Works - EPA Hi Wendy/Nicole, For your review the Soil, Stormwater and Flooding Management Plan for the Moore Park Works attached – Word doc and PDF (with appendices). Cheers Neville Neville Moran Principal Environmental Consultant KMH Environmental P: +61 2 9468 9300 M: 0409 736 881 F: +61 2 8008 1600 E: Nmoran@kmh.com.au
3
Suite 902, Level 9, North Tower, 1-5 Railway St, Chatswood NSW 2067 PO Box 5487, West Chatswood NSW 1515 www.kmh.com.au ___________________________________________________________________________ This email and any files transmitted with it are confidential and intended for use by the Addressee only. The confidential nature of the information contained in the email and/or file is not waived, lost or destroyed if it is sent in error to other than the Addressee. Use or dissemination of the information contained in the email and/or files by a recipient other than the Addressee may cause commercial damage to both/either the Sender and/or Addressee. If you are not the Addressee of this email/files, please immediately contact the Sender and delete this email/files. please consider the environment before printing this email ___________________________________________________________________________
From: Wendy Stevenson [mailto:Wendy.Stevenson@epa.nsw.gov.au] Sent: Tuesday, 29 July 2014 9:52 AM To: Neville Moran Cc: Nicole Jones Subject: RE: CBD and South East Light Rail (CSELR) - Moore Park Works - EPA Hi Neville Nicole Jones and I will be available to undertake the reviews. Can you please confirm the required review timeframe. Regards Wendy Wendy Stevenson Senior Operations Officer Environment Protection Authority Level 13, 10 Valentine Ave, Parramatta NSW 2150 : (02) 9995 6866 | : (02) 9995 6900 | : wendy.stevenson@epa.nsw.gov.au In my absence, please contact Nicole Jones 9995 6865 (Mon & Fri) or Mark Hanemann 9995 6845.
From: Neville Moran [mailto:Nmoran@kmh.com.au] Sent: Monday, 28 July 2014 1:59 PM To: Stevenson Wendy; Jones Nicole Cc: Shannon Blackmore; Laura Lynch Subject: CBD and South East Light Rail (CSELR) - Moore Park Works - EPA Hi Wendy, Laing O’Rourke has been engaged by Transport for NSW (TfSNW) as Managing Contractor for the Early Works that will be undertaken to facilitate construction of the CSELR Project. These works will form Stage 1 of the project and a Staging Report is currently being prepared in accordance with condition A7 of the Minister’s Conditions of Approval (MCoA attached) that will be submitted to the Department of Planning and Environment (DPE) shortly. Detailed design, construction and operation of the CSELR Project will be undertaken by a Public Private Partnership as the second stage of the project. The first package of works to be undertaken by Laing O’Rourke as part of Stage 1 will occur entirely within Centennial Park / Moore Park Trust (CPMPT) lands. The works, referred to as the Moore Park Works, will include:
The linked image cannot be displayed. The file may have been moved, renamed, or deleted. Verify that the link points to the correct file and location.
4
Tramway Oval Eastern Extension - An extension of the turfed surround of the current Tramway Oval Field by 5 metres to the east, to create provision for a subsequent relocation of the oval by the Public Private Partnership Contractor.
Moore Park Tennis Centre – Construction of a replacement amenities block and demolition of the existing amenities block for the Moore Park Tennis Centre.
Moore Park Bus Loop – Construction of a temporary bus turnaround to run event buses in both directions on the events bus loop located to the east of Tramway Oval during construction of the CSELR project.
Moore Park Construction Compound – Establishment of a construction compound to support the works within Moore Park and subsequent packages of works within Surry Hills.
Tramway Oval is used as a training ground for the Sydney Swans AFL team. Works on the oval are time constrained due to the fact the oval needs to be handed back to the Sydney Swans by the end of October 2014. In order for this to occur, the construction works at this location would need to be commenced by approximately the 26th August 2014. As the proposed works are limited to the extent of the CPMPT lands, DPE have agreed to TfNSW submitting CEMP and associated sub-plans for the proposed Moore Park Works in order that the above timeframes can be met. As part of this process EPA need to be consulted on the soil and water management plan and the noise and vibration management plan. It is the intention to submit these plans Monday the 4 August for your review. Could you please confirm your availability to undertake this review and if you would like us to come in and discuss the submission this week we would be happy to do so? Regards Neville Neville Moran Principal Environmental Consultant KMH Environmental P: +61 2 9468 9300 M: 0409 736 881 F: +61 2 8008 1600 E: Nmoran@kmh.com.au
Suite 902, Level 9, North Tower, 1-5 Railway St, Chatswood NSW 2067 PO Box 5487, West Chatswood NSW 1515 www.kmh.com.au ___________________________________________________________________________ This email and any files transmitted with it are confidential and intended for use by the Addressee only. The confidential nature of the information contained in the email and/or file is not waived, lost or destroyed if it is sent in error to other than the Addressee. Use or dissemination of the information contained in the email and/or files by a recipient other than the Addressee may cause commercial damage to both/either the Sender and/or Addressee. If you are not the Addressee of this email/files, please immediately contact the Sender and delete this email/files. please consider the environment before printing this email ___________________________________________________________________________
---------------------------------------------------------------------------------------------------------------------------------------------------------------------- This email is intended for the addressee(s) named and may contain confidential and/or privileged information. If you are not the intended recipient, please notify the sender and then delete it immediately. Any views expressed in this email are those of the individual sender except where the sender expressly and with authority states them to be the views of the Environment Protection Authority.
The linked image cannot be displayed. The file may have been moved, renamed, or deleted. Verify that the link points to the correct file and location.
5
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS EMAIL
---------------------------------------------------------------------------------------------------------------------------------------------------------------------- This email is intended for the addressee(s) named and may contain confidential and/or privileged information. If you are not the intended recipient, please notify the sender and then delete it immediately. Any views expressed in this email are those of the individual sender except where the sender expressly and with authority states them to be the views of the Environment Protection Authority.
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS EMAIL
Level 3, 2-6 Station Street, Penrith 2751 | PO Box 323 Penrith NSW 2750
t (02) 4729 8138 | f (02) 4729 8141 | www.water.nsw.gov.au
Contact Janne Grose
Phone 02 4729 8262
Fax 02 4729 8141
Email janne.grose@water.nsw.gov.au
Our ref ER22439
Your ref
KMH Environmental PO Box 5487 WEST CHATSWOOD NSW 1515 Attention: Neville Moran
Dear Mr Moran
CBD and South East Light Rail – Stage 1A Moore Park MC Works – Construction Soil, Stormwater and Flooding Management Plan
I refer to your emails of 28 July and 4 August 2014 to the NSW Office of Water (Office of Water) requesting comments on the Plan.
The Office of Water comments are provided at Attachment A for consideration.
Should you require further information please contact Janne Grose, Water Regulation Officer on (02) 4729 8262 at the Penrith office.
Yours sincerely
Mitchell Isaacs Manager Strategic Stakeholder Liaison Unit 22 August 2014
ATTACHMENT A
NSW Office of Water | Page 2 of 3
CBD and South East Light Rail –Construction Soil, S tormwater and Flooding Management Plan – Stage 1A Moore Park MC works
The NSW Office of Water (Office of Water) provides the following comments on the Construction Soil, Stormwater and Flooding Management Plan (CSSFMP) for the Stage 1A Moore Park MC works:
It is suggested a table is included in the CSSFMP which summarises who will be involved with implementing the plan, the tasks, roles and responsibilities; the frequency etc including:
• who will inspect/monitor/maintain the permanent and temporary sediment controls and the frequency of when will this occur and identify which position(s) this information will be reported to
• who will test the quality of any water to be discharged from the site and the receiving waters • who will undertake training; • who will remove the controls and rehabilitate disturbed areas.
1.3 Objectives and Targets: Section 1.3 of the CSSFMP indicates the objectives and targets related to Construction, Soil, Stormwater, and Flooding Management include to maximise opportunities for water re-use from captured groundwater (page 8). The Office of Water requests it is provided with details on the expected groundwater inflows and the volumes of groundwater to be dewatered and re-used as part of the Stage 1A Moore Park MC works. 3.2.2 Moore Park Water quality Conditions: The CSSFMP notes that during construction, site water would drain to the Ponds of Centennial Parklands (see Section 3.2.2, page 12). It indicates that if uncontrolled, runoff from the worksites could result in discharge of contaminants to receiving waterways but contaminates could also enter the aquifer, as Table 3.5 indicates the Ponds of Centennial Park receive stormwater which recharges the aquifer (page 14). It is suggested Section 3.2.2 also makes reference to the potential for contaminates to enter the aquifer if runoff is uncontrolled. 3.4.2 Moore Park Conditions: Section 3.4.2 notes the Stage 1A Moore Park works will comprise surface/shallow excavations and are not anticipated to encounter or impact significant groundwater with the exception of perched shallow bodies (page 14). It is noted in Table 3.5 that the Sydney Basin Central Aquifer is approximately 2 to 3 m below ground level within areas traversed by the CSELR alignment and water table levels of the Botany Sands Aquifer range between 0.5 m and 7 m (page 14). The Stage 1A Moore park works as outlined in Section 1.2.2 do not appear to involve significant excavation but it is suggested Section 3.4.2 is amended and it includes specific details, including:
• the maximum depths of excavations associated with the works, • the depth of the shallow perched groundwater • expected volumes of groundwater to be intercepted and dewatered.
4. Aspects, Impacts and Risks It is recommended an air photo and scaled map is included in the CSSFMP which shows the location of the proposed works and the location of all watercourses and drainage lines potentially affected by the works.
NSW Office of Water | Page 3 of 3
Stockpiles and Concrete washout Section 5.4.6 of the CSSFMP indicates temporary stockpiles shall be located more than 15 m from drainage lines or watercourses (page 18) and Section 5.6.2 refers to concrete washout areas on site being located a minimum of 20 m away from any natural watercourses or drainage lines (page 19). It is suggested Table B1 in Appendix B, is amended so that SSF 24 and SSF 28 specify the minimum setback distances of 20 m and 15 m respectively. 6 Soil, Stormwater and flooding risk training:
It is unclear who will be responsible for undertaking the training and it is suggested the CSSFMP includes this detail.
End Attachment A
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
23/46
CSSFMP
Appendix B – Mitigation Measures Action Plan
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
24/46
CSSFMP
Table B1- Construction Soil, Stormwater and Flooding Mitigation Measures
ID Mitigation Measures Reference Resp.
PRE-CONSTRUCTION
SSF 1
Soil, water and flood mitigation measures from this Plan that are specific to the risks on each site to be included in relevant activity or area specific Environmental Controls Maps (ECMs) and site based Work Method Statements (WMS).
Moore Park Works CEMP - Good Practice
PEM / Project Engineer
SSF 2 ECMs and ESCPs to identify site storage and spoil stockpile areas of site to ensure community impacts, visual amenity and risk of dust/polluted runoff is minimised.
Blue Book PEM
SSF 3 Prior to any works on a site, a Primary Erosion and Sediment Control Plan (ESCP) to be prepared and implemented.
Blue Book PEM / Soil Conservationist
SSF 4 All site personnel to undertake site induction on environmental awareness (incorporating soil and water related issues) including their responsibilities under this Plan.
Moore Park Works CEMP - Good Practice
PEM
SSF 5 Provide ERSED training to all relevant site personnel with responsibilities for planning, installing and maintaining ERSED controls.
Moore Park Works CEMP - Good Practice
PEM / Soil Conservationist
CONSTRUCTION
SSF 6 Toolbox talks to be regularly held to detail site specific issues including project-wide/site soils and water risks, inspection outcomes and lessons learnt.
Moore Park Works CEMP/ Good Practice
PEM / Foremen
GENERAL ERSED
SSF 7 Progressive Erosion and Sediment Control Plans (PESCP) to be updated and implemented during works to reflect changed site conditions, landforms and risks.
REMM Y16 - Blue Book
PEM / Soil Conservationist
SSF 8 ERSED controls to be installed as per ESCPs and maintained to prevent migration of sediment and sediment laden water from entering any watercourse, drainage line or drainage inlet.
REMM Y19 Superintendent
SSF 9 Prior to and during inclement or extreme weather works to be ceased or modified and ensure ERSED controls installed and stable.
Good Practice Project Manager
SSF 10 Install up-gradient clean-water diversion devices (bunds, trenches, sandbags) to separate from dirty site water.
Blue Book Superintendent / PEM / Soil Conservationist
SSF 11 ERSED controls are to be kept in place and maintained until areas stabilised post works.
REMM Y22 / Blue Book
Superintendent / PEM / Soil Conservationist
SSF 12
Minimise area of disturbance areas and exposed stockpiles within constraints of the works program - stage clearing, topsoil stripping or grading, cover unconsolidated stockpiles, or apply hydro mulch or other revegetation applicant to stockpiles or surfaces left standing for extended periods.
REMM AC9 Superintendent
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
25/46
CSSFMP
ID Mitigation Measures Reference Resp.
SSF 13 Disturbed areas to be reinstated ASAP after construction, including revegetation or rehabilitation activities.
REMM Y 17 / REMM AC10
Superintendent
SSF 14
Runoff and pollution risks from stockpiled materials to be managed to prevent sediment from entering stormwater system (via bunding/sumps or other ERSED controls). Stockpiles and plant to be placed as far away as practicable from stormwater pits/drain/flow paths.
REMM Y18 Superintendent
SSF 15 If contamination is encountered, material will be managed and disposed of in accordance with EPA requirements and the Contaminated Land Protocol
Good Practice PEM
Spoil Haulage/Traffic
SSF 16 Spoil haulage vehicles entering and/or leaving the premises are to be suitably covered, and loose material removed, to prevent spillage to road and dust.
Good Practice Superintendent
SSF 17 Site haulage roads and site accesses to be controlled to prevent mud tracking onto public roads (rumble grids, stabilised roads with aggregate etc).
Good Practice Project Engineers
SSF 18 Vehicle movements to be modified during wet weather to prevent tracking of mud.
Good Practice Superintendent
SSF 19 Sediment tracked onto public roads from the site to be removed as soon as practical (and at end of day) by sweeper trucks, brooms or other equipment.
Good Practice Superintendent
Construction Water Management
SSF 20
Any water collected from the worksites to be treated and discharged in accordance with POEO Act (refer criteria in This Plan): Water to stormwater (refer POEO Act Criteria) – water to liquid waste facility (ref Waste Guidelines (EPA).
Hold Point - No discharge of site water without PEM approval.
REMM X1 Waste Guidelines (EPA)
PEM / Superintendent
SSF 21
During construction, water pumping facilities will be available at locations where water will pool within construction areas. Temporary drainage pipes or channels will also be provided to drain any open excavation areas. Hold Point - No discharge of site water without PEM approval.
REMM X3 Design Manager / PEM
Drainage and Flooding
SSF 22
Where existing longitudinal pit and pipe drainage exists and needs to be reinstated or repaired, appropriate scour protection measures will be reinstated or improved at outlets to watercourses or drainage lines.
REMM X2 Design Manager / PEM
SSF 23
For flood affected locations, the CSELR drainage systems to be designed to ensure compliance with the NSW Floodplain Development Manual (no increase flood levels above existing levels) .
REMM G1 Design Manager
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
26/46
CSSFMP
ID Mitigation Measures Reference Resp.
Concrete and Wastewater Management
SSF 24 Concrete washout areas and pits will be adequately sized, located a minimum of 20m away from natural watercourses or drainage lines where practicable and maintained regularly.
Good Practice PEM / Superintendent
SSF 25 Where practical, wash out of concrete delivery vehicles is to occur back at the suppliers approved facility and controlled to prevent off-site discharge.
Good Practice Superintendent
SSF 26 Prior to any concrete cutting on paved areas, install drain protection and runoff collection systems.
Good Practice PEM / Superintendent
SSF 27 Check levels of any onsite septic system for pump out, check for spillages from the septic system and locate portable toilets in bunded areas.
Good Practice Superintendent / PEM
SSF 28 Site offices, stockpiles, machinery wash down areas, and plant storage areas to be located as far away as practicable from drainage lines and any environmentally sensitive areas.
Good Practice Project Manager
Dangerous/Hazardous Goods Management
SSF 29
Store liquid/solid materials with pollution potential in roofed and/or bunded facilities as per EPA and WorkCover requirements. To avoid the cumulative effect of multiple container failure the bund will be sufficient to contain 110% of all liquid materials contained within the bund.
Good Practice PEM
SSF 30 Install and maintain suitable spill kits at locations of chemical storage, usage (e.g. refuel cells), main work fronts and provide portable spill kits in Foreman and Leading Hand vehicles.
Good Practice PEM
SSF 31 Provide training to authorised personnel on the use of the spill kits, maintenance of bunds.
Good Practice PEM
Monitoring and Inspections
SSF 32 Monitor weather (daily at least) and communicate/implement preventative measures accordingly to wet and windy conditions.
Good Practice PEM
SSF 33 Inspect ERSED controls daily during rain periods and within 24 hours of ceasing, implement required maintenance activities (clean sediment, repair breaches.)
REMM Y21 PEM
SSF 34 Undertake weekly environmental inspections to check the effectiveness of mitigation measures relating to soil, water and flooding management.
Good Practice PEM
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
27/46
CSSFMP
Appendix C – Moore Park Works Primary Erosion and Sedimentation Control Plan
Figure 2-A Stage 1 Moore Park Works - Moore Park Tennis Centre WorksPrimary Erosion & Sedimentation Control Plan (ESCP) Rev1 15/8/14
ESCP LegendSite Boundary/Sedfence placed at downgradient points
SW Pits (ERSEDprotection installed)
CW Pipes
Site Water Flow
Traffic Route
StabilisedSite Access
SiteCompound
Progressive ESCP NotesNotes: Prior to works: installsed fence/sandbags alongdownslope bdy (bus land).
Install stabilised siteentrance/exit
Id and protect drains (sandbags& geofab)Prep: B.Robilliard (CPESC)
Figure 2-B CSELR Stage 1 Moore Park Works - Tramway Oval Primary Erosion & Sedimentation Control Plan (ESCP) Rev01 15/8/14
ESCP LegendSite Boundary
Sed fence placed atdown gradient points– permitting access
SW Pits (ERSEDprotection installed)
CW Pipes
Site Water Flow
Traffic Route
Compound
ProposedTramway OvalCompound (SeeFig 2 C forDetail)
ProposedTramway OvalWorks Zone
ProposedBus WorksZone
Progressive ESCP NotesNotes: Prior to works: install sedfence/sandbags along downslopebdy (bus lane).Minimise stripped area as practicalInstall stabilised site entrance/exitId and protect drains (sandbags &
geofab)Prep: B.Robilliard (CPESC)
Refer ProposedTramway OvalWorks Area (SeeFig 2 B )
Figure 2-C CSELR Stage 1 Moore Park Works - Tramway Oval Primary Erosion & Sedimentation Control Plan (ESCP) Rev0 15/8/14
ESCP LegendSite Boundary
Sed fence placed at downgradient points – permittingaccess
Site Water Flow
Traffic Route
StabilisedSiteAccesses
Progressive ESCP NotesNotes: Prior to works: install sed fence alongdownslope bdy (Road and oval).
Install stabilised site entrance/exitId and protect drains (sandbags & geofab)
Prep: B.Robilliard (CPESC)
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
31/46
CSSFMP
Appendix D – Landcom “Blue Book” Standard Drawings
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
32/46
CSSFMP
Landcom Standard Drawings
NSW Landcom Standard Drawing SD 4-1 Stockpiles
NSW Landcom Standard Drawing SD 5-5 Earth Bank (Low Flow)
NSW Landcom Standard Drawing SD 6-7 Straw Bale Filter
NSW Landcom Standard Drawing SD 6-8 Sediment Fence
NSW Landcom Standard Drawing SD 6-9 Alternative Sediment Fence
NSW Landcom Standard Drawing SD 6-12 Geotextile Inlet Filter
NSW Landcom Standard Drawing SD 6-14 Stabilised Site Access
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
33/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
34/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
35/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
36/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
37/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
38/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
39/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
40/46
CSSFMP
Appendix E – Laing O’Rourke Monitoring/Inspections Forms
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
41/46
CSSFMP
CL SA40- 900-2 Rainfall Erosion and Sediment Control Inspection Checklist
RAINFALL EROSION AND SEDIMENT CONTROL INSPECTION CHECKLIST
PROJECT: Contract No. Inspected by: Date: Time: ITEM DESCRIPTION NO YES REMARKS
1 Have weather conditions changed since last inspection?
2 Has rainfall occurred? How much? mm
3 Are there any areas where runoff discharges from the site without control measures?
4 If yes, what additional control measures have been implemented? (sediment fences, straw bales, sand bags) List locations and additional control measures:
5 Are sediment basins, erosion devices and catch drains damaged and/or in need of maintenance or desilting?
6 Are all pumps and temporary drainage structures fully operational?
7 If yes, list locations and maintenance measures undertaken: 8 Do the sediment basins need emptying? 9 Is visible oil present in sediment basins?
10 Does the site Erosion and Sediment Control Plan require updating?
If a ‘Tick’ is given in the right hand column for any of the above inspections, details must be provided or referenced in the remarks column. Environmental Manager (or Delegate): ............................................. Date: .................................GENERAL COMMENTS:
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
42/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
43/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
44/46
CSSFMP
Transport for NSW CSELR – Stage 1 Managing Contractor Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing ContractorConstruction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
45/46
CSSFMP
Transport for NSW CSELR – Stage 1 Moore Park Works SLR-MC-01 August 2014
© Laing O’Rourke 2013, all rights reserved
CBD and South East Light Rail Project – Stage 1 Managing Contractor Construction Soil, Stormwater and Flooding Management Plan for the Moore Park Works
46/46
CSSFMP
F 1228 Environmental Improvement Request
ENVIRONMENTAL IMPROVEMENT REQUEST EIR No.:
PROJECT:
Contract No.: Date:
Issued To: Attention:
Details of Environmental Nonconformance:
Item Location Details Rt DateComplete
Signature:
LORAC Environmental Representative Date
Rt – Priority Rating:
1 – High priority, complete immediately 2 – Medium priority, complete within 4 days 3 – Low priority, complete within 1 week
Rectification Completed:
All above items rectified, reinspected and accepted as satisfactory.
Signature:
LORAC Site Manager/Foreman/Engineer Date Signature:
LORAC Environmental Representative Date