Chacha Final Year Project presentation

Post on 15-Apr-2017

366 views 6 download

transcript

FINAL YEAR PROJECT II PRESENTATIONMM 499

PROJECT TITTLE:“ASSESSMENT OF EFFICIENCY OF THE CURRENT MINE DEVELOPMENT CYCLES

AT BULYANHULU UNDERGROUND MINE”

STUDENT NAME: CHACHA, GodsonREGIS. NUMBER: 2010-04-02903PROGRAMME: MINING ENGINEERINGACADEMIC YEAR: 2013/14SUPERVISOR: Dr. MAFWENGA

S.GWAMAKA

BACKGROUND OF THE PROBLEMMine development involves making

excavations necessary to access the orebody and support mining operations.

Excavation dimensions depends on mining method used. It undertaken to minimize amount of waste to be excavated to accommodate equipments/materials and services that go along it

Development of these openings lags behind scheduled targets.

PROBLEM STATEMENT Bulyanhulu gold mine is currently

experiencing problems in mine development progress in which, the designed monthly 530m mine development advance is not being met.

This results into lost future production, which then affects overall profitability of the mine.

This causes longterm impacts on future production of gold.

PROJECT OBJECTIVES

GENERAL OBJECTIVE

To assess the effectiveness of the mine development activities in view of achieving the planned monthly target of horizontal development advance

Cont.….SPECIFIC OBJECTIVES

To assess the activity duration of various mine development cycles.

To identify and quantify the effect of each of activity taking place in mine development area using simulation.

SCOPE OF THE PROJECTThis project based on mine development

sections to determine constraints in development rate and mine cycles and their effects to the monthly plan target

The project concentrated on activities carried on during mine development. (TIME STUDY)

METHODOLOGYAdditional Literature reviewConsultationSite survey and Data collection Data analysis

SITE VISTING AND DATA COLLECTION

The project based on waste development headings , which is in deep levels about 1.2km where excavation size of the headings is 5m width by 5m height.

Data collected in horizontal development headings.

Cont...Time for development activities

Cont…Mucking and haulage time with distance to the

dumping area

DATA ANALYSISSTATISTICAL ANALYSISThe data was analyzed by EASYFIT

SOFTWARE to determine behaviour of each activity duration and it statistic parameters.

GPSS/H SIMULATIONThe cumulative probability function

obtained is used in GPSS/H simulation.

DRILLING

CHARGING

BLASTING

VENTILATION

MUCKING

EXTENSION OF UTILITIES

BOLTING

STATISTICAL PARAMETERS

CUMULATIVE PROBABILITY FUNCTION

GPSS/SIMULATION RESULTSSIMULATIONThe Cumulative probability helps in GPSS/H

Simulation to obtained the monthly Advanced metres

THE INPUT DATACont…

Cont…THE OUTPUT DATA

DISCUSSION OF RESULTSFrom statistical analysis the problem

observed on mucking, drilling, bolting, extension of utilities, and charging time which shown high standard deviation and dispersion.

From Simulation results, monthly planned advance metres obtained is 483m which should a target according to the current activity duration.

Cont....Traffic on ramp (Super-ramp and Ramp

A) and queuing at loading and dumping point (1-3980) leads to increase cycle time of haulage which affect mucking.

Mining delays such as Equipment breakdown, Skilled Labor Shortage, Ventilation, Electric Power, Face not clean, Water and flooding at the faces, materials being far from the face to be charged.

CONCLUSIONAT 3980 LEVEL Queue at tipping point which increase

mucking and haulage duration and leads to affect other activities.

Since there is only one tipping point (1-3980) which create queue during dumping process hence increases the mucking and haulage time.

Cont…BELOW 3980 LEVEL (DEEP LEVELS)Because of Truck system used at

Bulyanhulu, cycle time increase due to equipment breakdown at super-ramp (3800 to 3980 level) which only one truck can pass at a time.

Flooding of underground workings mainly due to the frequent breakdowns of pumps (kombi pumps) which stop of activities.

Cont…Operational and service factors such as

Operator efficiency and experience, Materials storage being far away such as explosives, leaking of vent tubes, Remucks and loading point are far away from the face.

RECOMMENDATIONSTo install conveyor belt at super-ramp

from deep levels to (1-3980).

Perimeter blasting should be introduced to reduce overbreak, minimize ground support requirement and scaling.

Cont…Provide promotion and motivation to the

operators.

To introduce roof bolter this will reduce bolting time to enhance development.

To introduce another tipping point at 1-3980 to reduce queuing at rock breaker.

Cont…Improve ventilation especially at deep

levels of the mine includes replacement of leaking vents to ensure adequate air supply to the working areas.

Adequate training to the operators should be given to make them more efficient to will follow SOPs.

THANK YOU ALL