Caterina Bertone - 2/10/2012
Dismantling of shielding wall in PSB injection zone
Preliminary concerns
Caterina Bertone - 2/10/2012
To be accessed from PSB or from PS
Caterina Bertone - 2/10/2012
Quantities and weight
• 300 concrete blocks with max weight of 1250kg
• 30 steel beams (1,6mx200x200), with max weith 500kg
• 635 concrete bricks of 18 kg each• Hundreds of steel bricks to close the open
whole
Caterina Bertone - 2/10/2012
Pure dismantling
• Mounting technique and tools no longer authorised: needs for studies and tooling: 50kCHF
• Consider 1 month for wall removal + time needed to mount and dismount lines to arrive to the wall: ~50kCHF for manpower
Caterina Bertone - 2/10/2012
From PS
All you see in the phots needs to be removed
Caterina Bertone - 2/10/2012
From PSWay to go: all to be dismantled
Caterina Bertone - 2/10/2012
From PS: machines in and blocks out
Caterina Bertone - 2/10/2012
Summary of evacuation by this way• Dismantling of the whole zone + up to PS machine• Dismantling of 1-2 PS unit to pass into the inside of the
ring and a part of LBS line• Reinforcement of slab under the PS units and along the
path (to be checked) to pass with heavy machines+blocks• Full reinforcement of the slab from evacuation door and
inner side of PS ring at this position• Unknowns about ground situation• Extra long patch and need for handling means (loco +
trailer+forklifts etc)
Caterina Bertone - 2/10/2012
From PSBAll you see in the phots needs to be removed
Caterina Bertone - 2/10/2012
From PSB open spaceSlab to be reinforced
Caterina Bertone - 2/10/2012
From shielding to tremie
Evacuation lane
Cable trays + line toBe removed
Caterina Bertone - 2/10/2012
And away…
Caterina Bertone - 2/10/2012
Summary of evacuation by this way
• Dismantling of the whole line up to PBS machine
• Reinforcement of slab under along the path (10 m?) to pass with heavy machines+blocks
• Short patch and limited need for handling means
• More activated zone?
Caterina Bertone - 2/10/2012
Open questions and short conclusions
• Activation of blocks?• Permanence of operators in ‘hot zones’ like PSB injection
region?• Reinstallation of the wall after CE? • Sol 1 prevent future exchange of magnets in the zone (no
more transport zone), Sol 2 and seem difficult to realise to lift the dump up and keep in place. Sol 4 needs installation of a crane in the vault up to the zone to allow future handling of the 2 lines (from where do we insert the dump?)
Evacuation from PSB side is clearly the preferred choise It is possible and we are waiting more infos from your side