Federal Department of the Environment, Transport, Energy and Communications

Federal Office of Transport

FINANCING AND MANAGEMENT OF THE GOTTHARD BASE TUNNEL

Dr. Rudolf SperlichSwiss Federal Office of TransportNETLIPSE Network Meeting, October 20th 2008

2 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Introduction

• Traffic policy CH • Financing:

Public transport fund• New Rail Link through the Alps (NRLA)

Focus: Gotthard axis• Supervision • Conclusion

3 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

The Alps

A barrier for transportation

4 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Rail

Road

Mio. Net Tonnes / year

Status: 2008

Transalpine Swiss freight traffic:subdivision and modal split

71.6

6.1

11.5

36.125.2

12.9

5 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Swiss Traffic evolution until 2030

0

10

20

30

40

50

2005 2010 2015 2020 2025 2030

Personenverkehr Güterverkehr

+ 54%

+ 24%

6 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Elements of the Swiss transport policy

Railway reformRailway reformHeavy vehicle

feeHeavy vehicle

fee

Shift from road to railShift from road to rail

Modernization of railway

Modernization of railway

AgreementSwitzerland-EU

AgreementSwitzerland-EU

Large railway infrastructure projects:Large railway infrastructure projects:

NRLA (NEAT)NRLA (NEAT)

High Speed LinksHigh Speed Links

Railway 2000 Railway 2000

Noise abatementNoise abatementFDR (ZEB)FDR (ZEB)

Agglo-projectsAgglo-projects

7 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

0

1000

2000

3000

4000

5000

1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005

Expenses for infrastructureExpenses for infrastructure

Road

Rail

Mio

. sF

r.

8 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Improvement of the railway network (large-scale projects until 2030)

Public

Transport

Fund (FinöV)

Ordinary Budget2007-2010

Infrastructure Fund forAgglomeration Projects

9 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

HighSpeedLinks

RAIL 2000

NRLA(NEAT)

Noiseabatement

Vote on public transport funding

Popular vote on financingof public transport

29.11.199829.11.1998

10 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Public transport fund (cross financing)

Noise Abatement

0,8 bn €

High speedLinks

0,6 bn €

RAIL 2000 and FDR6 bn €

NEAT(Alp Transit) 12,3 bn. €

VAT (0,1 %)

Mineral Oil Tax(25% for NRLA)

2/3 of Heavy Vehicle Fee

Public Transport

Fund19,7 bn €

Advances(max. 5,4 bn €)

11 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Public Transport Fund

advance / debt redemption

payments earmarked revenues

0.5 Mrd

1.0 Mrd

1.5 Mrd

2.0 Mrd

2.5 Mrd

0.0 Mrd

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

system change

12 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

NRLA: The AlpTransit tunnels

Lötschberg -Base Tunnel

Gotthard - Base Tunnel

Ceneri -Base Tunnel

Bern

Basel

Lausanne

Genf

Steg

Brig

Frutigen

Erstfeld

Biasca

Lugano

Chiasso

Arth-Goldau

Zürich

St. Gallen

Luzern

Zimmerberg - Base Tunnel

13 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Overview Lötschberg base tunnel

Existing conventional Railway linesLötschberg base tunnelService tunnel/lateral aditlUnequiped single-tracktunnel

Frutigen

Mitholz

Steg

Ferden

Raron

14 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Lötschberg base tunnel

• Beginning of construction: 2000

• Opening: December 9, 2007

• Trustworthiness of tunnel installations > 99,8%

• Costs: 4,3 billion € (+ 0.6 billlion price increase)

• Beginning of construction: 2000

• Opening: December 9, 2007

• Trustworthiness of tunnel installations > 99,8%

• Costs: 4,3 billion € (+ 0.6 billlion price increase)

15 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Profile of the Gotthard axis

.

gradient 26 0/00

gradient max. 8 0/00

SN

susp

ended

susp

ended

16 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Gotthard base tunnel

17 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Gotthard base tunnel: features

• Tunnel length: 57.0 km

• Two single track tubes

• Tunnel profile: EBV IV

• Connecting galleries all 300m

• Max. speed for passenger trains: 250 km/h

• Max. speed for freight trains: 160 km/h

• Culmination point: 550 m

• Maximum overlay: 2,300 m

• Cost of the Gotthard base tunnel: approx. CHF 9,7 bn / € 6,0 bn (1998)

18 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Gotthard base tunnel Umgehungsstollen Bodio

Bodio

Faido

ZugangsstollenFaido

MultifunktionsstelleFaidoBetriebszentraleFaido

MultifunktionsstelleSedrun

Sedrun

Schacht II

EntlüftungsstollenZugangs-stollen

Kabelstollen Amsteg

Amsteg

ZugangsstollenAmstegE rstf eld

Schacht I

BetriebszentraleSedrun

Oströ

hreWe

ströh

re

• tunneling in progres

• excavated

• interior completed

Tunnelling completed: 30 June 2008: 113,2 km (73,8 %) of 153 kmTunnelling completed: 30 June 2008: 113,2 km (73,8 %) of 153 km

19 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Gotthard base tunnel – scheme of tunnel system

20 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Sedrun - emergency stationSedrun - emergency station

21 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

© AlpTransit Gotthard AG

Sedrun - elevator

22 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Bodio south portal: construction site

23 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Ceneri Base Tunnel

Portal Veziakünftig

e Fo

rtsetz

ung S

ÜD

Zwischenangriff Sigirino

FensterstollenErkundungsstollenSigirino

Oströ

hre

Westr

öhre

Portal Vigana(Camorino)

Tunnel length: 15.4 kmTwo single track tubesTunnel profile: EBV IVConnecting galleries all 300mMax. speed for passenger trains: 250 km/hMax. speed for freight trains: 160 km/hOpening: 2019

At the end of 2009, the tunneling in the main tubes will begin out of the intermediate access.

24 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Geological challenges

Deformation of steel arches at the tunnel basein easily deformable rock formations and due to mountain overlay of more than 2000m.

25 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Gotthard base tunnel – geological section

not excavated

26 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

safety and technology progress

improvements for environment

and people

awarding

final costs: 11,874 bn SFR

additional costs +4,158 bn SFR

Gotthard axis: additional costs

cost reference base 1998: 7,716 bn SFR

geology

politically related delays

27 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

0

1.000

2.000

3.000

4.000

5.000

6.000

7.000

8.000

9.000

10.000

11.000

12.000

13.000

14.000

SBII/2000

SBI/2001

SBII/2001

SBI/2002

SBII/2002

SBI/2003

SBII/2003

SBI/2004

SBII/2004

SBI/2005

SBII/2005

SBI/2006

SBII/2006

SBI/2007

SBII/2007

SBI/2008

SBII/2008

Stand-berichte

Mill

ion

en

Fra

nk

en

Rechnungen ([KS14]-[KS15]-[KS17]) Vergaben [KS09] mutmassliche Endkosten ([KP08]-[KS15])

paid

awarded

probable final costs (price rises incl.)

bn SFR

Gotthard axis: cost development

28 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Credit situation NEAT

In the first years, NEAT was knowingly underfinanced.

On 16.9.2008, Parliament authorized the new NEAT global credit.

For the first time in its history, NEAT is fully financed (12 billion €)!

29 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

KommissionenKommissionen

Gotthard axis: Organisation

Federal Council

contractor

Parliament

contractorcontractor

contractor

SBB(operator)

Commissions

Fed. Office of Transport (FOT)

= monitoring and audit

Departement

NEAT Supervision Delegation

AlpTransit Gotthard Ltd (ATG)(constructor)

Financial Control

Experts

30 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

The operator is not the constructor

The organizational separation has

advantages: 1) cost cutting through contradictory interests

constructor --> low investment costsoperator --> high investment costs

(lower costs for renewal and maintenance)2) In case of problems, the autority can take a decision.

inconveniences: 1) supplementary interfaces 2) risk that project elements are „forgotten“

Important:

Strong and „in time“ collaboration between constructor and operator

31 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Management requires:

Objective agreement on project requirements

Procedure referential bases

Control periodical comparisons between reality and forecasts Instruments modification reports, risk management,

reports, controls, etc.

Principles of project management

Instruments

32 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Constructors

Standard - Reporting

NEAT Controlling Directive

auditing

FOT

Levels of project supervision

33 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Conclusion

• Ensured financing = determining factor

• Organization model operator < > constructor

• Supervision functions require clear repartition of roles

• Establishing good control system

• Foreseeing costs for adaptation to technological progress

34 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

The Alps - not only an obstacle!

35 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

36 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Organisation: Fed. Office of Transport

37 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Entwicklung der mutmasslichen Endkosten (Preisstand 1998, [KP11])

18,518,418,4

16,916,716,616,416,315,915,714,814,514,314,2

13,413,9

12,812,212,2

0

2

4

6

8

10

12

14

16

18

20

SBI/1999

SBII/1999

SBI/2000

SBII/2000

SBI/2001

SBII/2001

SBI/2002

SBII/2002

SBI/2003

SBII/2003

SBI/2004

SBII/2004

SBI/2005

SBII/2005

SBI/2006

SBII/2006

SBI/2007

SBII/2007

SBI/2008

SBII/2008

Standberichte

Mil

liard

en

Fra

nke

nNEAT: Development of final costs(price level 1998, without risk share)

Mrd

. sF

r.

11,6 bn €

8,0 bn €

1999 2008

38 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

safety and technology progress

improvements for environment

and people

awarding

final costs: 12,4 bn € (estimation FOT,incl. risk share)

additional costs +4,4 bn €

NEAT - additional costs (estimation)

cost reference base 1998: 8,0 bn €

project extensions

geology

politically related delays

39 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Time frame

19

95

20

00

20

05

20

10

20

15

20

20

20

25

19

90

NEAT (AlpTransit)

FDR II ?

Noise Abatement

High Speed Links

RAIL 2000/1

Future Development of the Railway Infrastructure FDR

40 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Ceneri base tunnelCeneri base tunnel

41 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Gotthard base tunnel: bore width

8.60 – 8.80m 9.20 – 13.08 m

solid rock pressing rock

42 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Vorgehen

Halbjährlicher Zyklus

Daten, Berichte, Anträge Ersteller

Analyse und Risikobeurteilung

Wichtige Steuerungsmöglichkeiten

Verfahren und Zulassungen

Prüfungen, Empfehlungen

Änderungswesen, Kompensationen

Reservenmanagement

Finanz- und Fondsmanagement

Management and controlling through the FOT

43 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Objectives of the Neat Controlling DirectiveTransparency in project management

implementation of agreed objectives

riks /reserves

Early warning system

The autorities have all the necessary information.

The necessary measures can be taken in time.

44 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

.

Bern -

Milano

With LBT

Berne -

Sion

With LBT

3h 16‘

0 1 2 3

2h 42‘ (- 38 Min.)

2h 23‘

1h 45‘ (-34 Min.)

Lötschberg axis: travel times

45 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Public Transport Fund: estimate of expenses

~ 10 CHF(~ 6.3 €)

31.4 CHF(~ 19.7 €)

~ 7 CHF (~ 4.4 €)

Investitionsvolumen real

Teuerung, MWST

Zinsen

Investments

price rises

interests

46 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Financing (1)

Federal budgetFederal budgetAim: Maintain performanceAim: Maintain performance

Regional transport Freight transportInfrastructure

47 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Financing (2)

Public Transport Fund

Public Transport Fund Aim:

Improve performance Aim:Improve performance

Lötschberg Gotthard Mattstetten-Rothrist

48 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Infrastructure fund: financing

Mineral Oil TaxMineral Oil Tax

HighwayvignetteHighwayvignette

Completion of national road network (8.5 billion)Completion of national

road network (8.5 billion)

Suppression of congestionnat. road network (5.5 billion)Suppression of congestion

nat. road network (5.5 billion)

Substance maintenance in per. regions (0.8 billion)Substance maintenance in per. regions (0.8 billion)

Agglomeration traffic (6 billion)Agglomeration traffic (6 billion)

One-time payment 2.6 bil. Fr.One-time payment 2.6 bil. Fr.

I-Fonds

Investment volume 20.8 billion (2005)

49 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Lötschberg south portal: Rhone bridges

50 Dr. R. Sperlich / NETLIPSE Network Meeting 20th October 2008

Construction site for rail technology