Final plans for renovations to

Central Campus

5th floor

Board Meeting

January 6, 2015

Career Tech Upgrades

• Security upgrades

• Improved learning environment

• Direct freight elevator access to CT programming

• Opportunities for sharing resources

CT Project Highlights

Des Moines Alternative

Program Upgrades

Project Highlights

Des Moines Alternative

• Improved learning environment

• Multipurpose room

• Space designed for alternative learning

• Increased student support

• Sharing programs

Timeline

• January 6, 2015– Board review and approval of final

plans

• February 3, 2015–Award of bid

• February 16, 2015 – Construction start

• January 30, 2016 – Substantial completion. Work will be

performed in phases so some areas complete earlier.

$6,700,000

Project budget

QUESTIONS AND COMMENTS