Flashcards For Passing the PMf>® and CAPM®Exams Fifth Edition

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 2/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 3/642

© Copyright 2005 Rita Mulcahy, PMP RMC Publications, Inc.All Rights Reserved. No part of this publication may be copied or reproduced inany form whatsoever, stored in a retrieval system, or transmitted in any form without the prior written permission of the author.

ISBN 1-932735-01-1 Library of Congress Control Number: 2005905459 Printed in the U.S.A. For more information see: E-mail: info@rmcproject.com Web: www.rmcprojec

t.com Phone: 952.846.4484

2

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 4/642

WARNING: This is not astand-alone product! You will need other review materials in order to pass the PMP or CAPM exam. We make no warranties or representations that use of these materials will result in passage of either exam. This book is designed to work withthe book PMP Exam Prep 5th Edition by Rita Mulcahy, PMP, available at www.rmcproject.com. If you are studying for the PMP exam, use the chapter references on each Hot Topics flashcard to find further information in the PMP Exam Prep Book.

"PMP", "PMBOK" and "CAPM" are marks of the Project Management Institute, Inc. RMC Project Management, Inc. has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.) RMC Project Management has agreed to abide byPMI-established quality assurance criteria.

3

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 5/642

Table of ContentsIntroduction 3 How To Use This Book 5 6 About Us RMC Products 7 Framework 9 Integration 43 Scope 87 Time 127 Cost 193 Quality 263 353 Human Resources Communications 403 Risk 443 Procurement 517 Professional and Social Responsibility 623

4

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 6/642

How To Use This Book: Thisbook has been updated for the PMBOK® Guide - Third Edition, designed as a portable reference to the Hot Topics on the PMP and CAPM exams, to be used to improve test taking speed and information recall. Note that the Professional and Social Responsibility chapter is not covered in the CAPM exam. Read the front of each page and see if you can recall the items on the back of the page and know what they mean. If studying for the PMP exam, Hot Topics you are unfamiliar with should b

e reviewed in the book PMP Exam Prep, 5th Edition and the PMBOK® Guide. An audio version of Hot Topics is also available on CD-ROM.

5

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 7/642

About UsRita Mulcahy, PMP, is an internationally recognized expert in project management and a sought after speaker, trainer and author. She has six project managementbooks and products to her credit, and was a Contributor and Reviewer to the PMBOK® Guide - Third Edition. Rita has spoken at PMI's annual project management symposium to standing room only crowds and has been asked to present encores for an unheard of four years! RMC Project Management, Inc. provides Tricks of the Trade"

 for project management, PMP exam prep and advanced project management training.See us at www.rmcproject.com.

6

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 8/642

See the rest of our PMP and CAPM Exam Prep products at www.rmcproject.com.The Book PM? Exam Prep, j'h Edition This is the only accelerated guide to the PMP exam, and is currently used in more than 40 countries. This Course in a Book"contains review material, exercises, activities, games, and insider tips, and can decrease study time to only about 120 hours.

7

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 9/642

PM FASTrack® Exam Simulation SoftwareBased on a psychometric review with more than 1,300 questions in six testing modes.

Take A Course: Project Management Tricks of the Trade® - A three-day PM course coveringthe project management process using PMI terminology with real-world application

s.

The PMP Exam Prep CourseThis two-day accelerated learning course is designed to help you prepare for the PMP Exam with the most understanding of project management and the least amount of study! Study less than 40 hours after taking the course! This course includes the PMP Exam Prep System.

8

...

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 10/642

What is the definition of a project?

9

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 11/642

· Temporary · Unique · Progressively elaborated

See the Framework Chapter

10

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 12/642

What is the definition of a program?

11

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 13/642

A group of interrelated projects, managed in a coordinated way

See the Framework Chapter

12

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 14/642

What is a product life cycle?

13

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 15/642

The cycle of a product's life from conception to withdrawal

See the Framework Chapter

14

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 16/642

What is a project life cycle?

15

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 17/642

What you need to do to DO the work It varies by industry and type of project

See the Framework Chapter

16

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 18/642

What is the proj ect management process?

17

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 19/642

What you need to do to MANAGE the work · Initiating · Planning · Executing · Monitoringand controlling · ClosingSee the Framework Chapter

18

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 20/642

What is a proj ect management office?

19

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 21/642

A department that centralizes the management of proj ects The PMO provides templates and guidelines, shares lessons learned between proj ects and is represented on the change control board

See the Framework Chapter

20

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 22/642

-

- - What is a constraint?

21

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 23/642

Anything that limits the team's options These include: · Imposed milestone dates · Cash flow requirements · Resources available

See the Framework Chapter

22

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 24/642

What are the components of the "triple constraint"? What is it used for?

23

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 25/642

· Cost · Time · Scope · Quality · Risk · Customer satisfactionIt is used to help evaluate

competing demandsSee the Framework Chapter

24

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 26/642

Who are stakeholders?

25

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 27/642

Anyone whose interests may be positively or negatively impacted by the proj ect, including: · · · · · · · · · Project manager Customer Sponsor Performing organization Teag sources End user Society PMO

See the Framework Chapter

26

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 28/642

What should we do with stakeholders?

27

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 29/642

· Identify all stakeholders · Determine all of their requirements · Determine all of their expectations · Communicate with them · Manage their influence

See the Framework Chapter

28

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 30/642

-

--

- --- --- -

"'-"

-

-

What are three primary forms of organization?

29

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 31/642

· Functional · Projectized · Matrix

See the Framework Chapter

30

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 32/642

What is a functional organization?

31

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 33/642

The company is grouped by areas of specialization (e.g., accounting, marketing)

See the Framework Chapter

32

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 34/642

-

-

.--..

.--..

.--..

.--..

--- -

What is a proj ectized organization?

33

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 35/642

The company is grouped by project The team has no department to go to at project end The proj ect manager has total control of the resourcesSee the Framework Chapter

34

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 36/642

What is a matrix organization?

35

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 37/642

A blend of functional and projectized organization where the team members have two bosses

See the Framework Chapter

36

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 38/642

------

~

--

-

What is a strong matrix organization?

37

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 39/642

A matrix organization where the balance of power rests with the project managerinstead of the functional manager

See the Framework Chapter

38

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 40/642

What is a weak matrix organization?

39

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 41/642

A matrix organization where the balance of power rests with the functional manager instead of the project manager Project management roles include: · Project expediter · Project coordinatorSee the Framework Chapter

40

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 42/642

What is a balanced matrix organization?

41

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 43/642

An organization where power is equally balanced between project managers and functional managers

This is the preferred form

of matrix

See the Framework Chapter

42

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 44/642

What is the process of integration management?

43

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 45/642

· Develop proj ect charter · Develop preliminary project scope statement · Develop project management plan · Direct and manage project execution · Monitor and control project work · Integrated change control · Close projectSee the Integration Chapter

44

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 46/642

What are the methods to select a project?

45

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 47/642

· Benefit measurement (comparative) · Constrained optimization (mathematical)

See the Integration Chapter

46

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 48/642

What is develop project management plan? What is its output?

47

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 49/642

The process of creating a project management plan that is bought into, approved, realistic and formal Output: The project management plan

See the Integration Chapter

48

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 50/642

What is the preliminary project scope statement?

49

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 51/642

Created with input from the sponsor, it is the first attempt to determine the proj ect scope

What must be done to accomplish the project objectives

See the Integration Chapter

50

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 52/642

What are key outputs of direct and manage proj ect execution?

51

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 53/642

· Deliverables · Requested changes · Implemented change requests, corrective and preventive actions and defect repair

See the Integration Chapter

52

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 54/642

What are key outputs of monitor and control proj ect work?

53

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 55/642

· Recommended corrective actions, preventive actions and defect repair · Requested changes · Forecasts

See the Integration Chapter

54

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 56/642

What are key outputs of integrated change control?

55

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 57/642

· Approved change requests, corrective actions, preventive actions and defect repair · Rejected change requests · Validated defect repair · Deliverables

See the Integration Chapter

56

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 58/642

What are key outputs of close project?

57

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 59/642

· Administrative and contract closure procedures · Final product · Formal acceptance · Project files · Project closure documents · Organizational process assets updates

See the Integration Chapter

58

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 60/642

Explain the project manager's role as integrator.

59

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 61/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 62/642

What are baselines?

61

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 63/642

Parts of project management plan used to measure performance against Includes: · · · · · Schedule baseline Scope baseline Cost baseline Quality baseline Performance measurement baselines

Can change with approved changesSee the Integration Chapter

62

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 64/642

What is the proj ect statement of work?

63

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 65/642

Describes need, product scope and how project fits into the strategic plan

Created by the customer/sponsor prior to the beginning of the project

Is later refined into the preliminary and project scope statementsSee the Integration Chapter

64

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 66/642

What is a work authorization system?

65

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 67/642

A formal procedure for sanctioning project work to ensure work is done at the right time, and in the proper sequence

See the Integration Chapter

66

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 68/642

----- ----What is configuration management?

67

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 69/642

Making sure everyone knows what version of the scope, schedule and other components of the project management plan are the latest versions

See the Integration Chapter

68

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 70/642

-

-

--- -- - - What is a change control system?

69

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 71/642

A system of formal procedures, set up in advance, defining how proj ect deliverables and documentation are controlled, changed and approved

See the Integration Chapter

70

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 72/642

----

------

What are enterprise environmental factors? When are they used?

71

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 73/642

Company culture and existing systems that the project will have to deal with orcan make use of

Used throughout the proj ect management process

See the Integration Chapter

72

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 74/642

What are organizational process assets? When are they used?

73

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 75/642

· Company processes and procedures · Historical information · Lessons learned Used throughout the project management process

See the Integration Chapter

74

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 76/642

What is historical information?

75

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 77/642

Records of past projects used to plan and manage future projects Records of current project to become part of organizational process assets

See the Integration Chapter

76

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 78/642

What is a project management information system?

77

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 79/642

The manual and automated system to submit and track changes, and monitor and control project activities

See the Integration Chapter

78

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 80/642

--

--

-- -- --

- -- - - -

What is a change control board? Who may be on it?

79

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 81/642

A group of people that approves or rejects changesMay include:

· Project manager · Customer · Outside experts · Sponsor · OthersSee the Integration Chapter

80

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 82/642

What are change requests? When are they approved?

81

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 83/642

Fonnal requests to change parts of the project after the project management plan is approved

They are approved in integrated change control

See the Integration Chapter

82

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 84/642

--

---- - -- What are preventive actions?

83

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 85/642

Actions taken to deal with anticipated or possible deviations from the performance baselines

See the Integration Chapter

84

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 86/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 87/642

Actions taken to bring expected future project performance in line with the project management plan

See the Integration Chapter

86

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 88/642

-

--

---- - - -

What is a project charter? How does it help the project?

87

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 89/642

A document issued by the sponsor during proj ect initiating that: · Formally recognizes the existence of the project · Gives the project manager authority · Documents the business need, justification, customer requirements and the product or service to satisfy those requirementsSee the Scope Chapter

88

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 90/642

What is the process of scope management?

89

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 91/642

· Scope planning · Scope definition · Create WBS · Scope verification · Scope control

See the Scope Chapter

90

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 92/642

- -

- -- - --- -....."

- -

What is the key output of scope planning?

91

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 93/642

Project scope management plan

See the Scope Chapter

92

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 94/642

What are the key outputs of scope definition?

93

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 95/642

· Project scope statement · Requested changes

See the Scope Chapter

94

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 96/642

-

-- - ..........

..........

..........

......,

-

What are the key outputs of create WBS?

95

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 97/642

· Workbreakdown structure (WBS) · WBS dictionary · Scope baseline · Requested changes

See the Scope Chapter

96

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 98/642

What are the key outputs of scope verification?

97

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 99/642

· Customer formal acceptance of project deliverables · Requested changes

See the Scope Chapter

98

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 100/642

...........

...........

---

-- ---

What are the key outputs of scope control?

99

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 101/642

· Accepted deliverables · Requested changes · Recommended corrective actions

See the Scope Chapter

100

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 102/642

What is the definition of scope management?

101

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 103/642

· Doing all the work, and only the work, included in the project · Determining if work is included in the project or not

See the Scope Chapter

102

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 104/642

-- - - ---- -What is a scope management plan?

103

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 105/642

Part of the project management plan A plan for how scope will be planned, executed and controlled

See the Scope Chapter

104

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 106/642

What is a proj ect scope statement? What are the key items included?

105

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 107/642

A written description of the project deliverables and the work required to create those deliverablesIt includes:

Project objectives Product scope Project requirements Project boundaries Project deliverables Product acceptance criteria · Project constraints and assumptionsSee the Scope Chapter 106

· · · · · ·

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 108/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 109/642

Stakeholder analysis occurs during the process of scope definition.

See the Scope Chapter

108

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 110/642

Product analysis is part of which scope management process?

109

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 111/642

Product analysis occurs during the process of scope definition.

See the Scope Chapter

110

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 112/642

- --

--

-

- - - - -- --

What is a work breakdown structure (WB S)? What is it used for in planning?

111

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 113/642

Created during proj ect planning by the team and used to define or decompose the proj ect into smaller, more manageable pieces

Used to help determine proj ect staffing, estimating, scheduling and risk management

See the Scope Chapter

112

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 114/642

What do work breakdown structures show?

113

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 115/642

· Hierarchy · Interrelationships · Work packages · Control account · Numbering system

See the Scope Chapter

114

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 116/642

--

---

- -

---

What is scope decomposition?

115

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 117/642

Subdividing the major deliverables into smaller, more manageable components

See the Scope Chapter

116

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 118/642

~

~

........

-

-

........

-

......"

- -

What is a WBS dictionary?

117

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 119/642

A description of the work to be done for each work package

See the Scope Chapter

118

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 120/642

---

-

-

-- - --

How are work packages different from activities?

119

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 121/642

Activities are generated from each work package

Work packages are shown in a WBS

Activities are shown in an activity list and network diagramSee the Scope Chapter

120

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 122/642

-

-- - --What is scope verifi cation? When is it done?

---

121

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 123/642

The process of formalizing acceptance of the proj ect scope by the stakeholders/customerIt is done during proj ect

monitoring and controlling and at the end of each phase of the project life cycle

See the Scope Chapter

122

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 124/642

-

---

- _.

-~

"'--

-

'''--

-

What is the difference between product scope and project scope?

123

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 125/642

Product scope is requirements

Project scope is the project management work needed to accomplish the product scope

See the Scope Chapter

124

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 126/642

........................

 _-'----""--"What makes up the scope baseline?

125

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 127/642

· Scope statement · WBS · WBS dictionary

See the Scope Chapter

126

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 128/642

What is the process of time management?

127

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 129/642

· Schedule management planning · Activity definition · Activity sequencing · Activity resource estimating · Activity duration estimating · Schedule development · Schedule controlSee the Time Chapter

128

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 130/642

What is the key output of schedule management planning?

129

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 131/642

A schedule management plan

See the Time Chapter

130

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 132/642

What is the key output of activity definition?

131

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 133/642

Activity list

See the Time Chapter

132

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 134/642

-

-

-- - --- ....."

What is the key output of activity sequencing?

133

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 135/642

Network diagram

See the Time Chapter

134

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 136/642

-

-- -- -- "'......"

What is the key output of activity resource estimating?

135

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 137/642

Activity resource requirements

See the Time Chapter

136

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 138/642

--

-

-- -----

What is the key output of activity duration estimating?

137

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 139/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 140/642

-

- -

---- - - -

What is schedule development? What are its key outputs?

139

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 141/642

The actions and tools necessary to create a bought into, approved, realistic and formal proj ect schedule Outputs: · Project schedule · Schedule baseline · RequestedchangesSee the Time Chapter

140

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 142/642

---------'----What are key outputs of schedule control?

141

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 143/642

· Schedule updates · Performance measurements · Recommended corrective actions · Requested changes

See the Time Chapter

142

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 144/642

~

-- -- --

-- --

-

--

- --

How is an AOA diagram different from a AON diagram?

143

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 145/642

An AOA diagram has only finish-to-start relationships

An AON diagram can have four relationships between activities

See the Time Chapter

144

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 146/642

-

-

---

-

--- --

~

What are mandatory dependencies and discretionary dependencies?

145

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 147/642

Mandatory: One activity MUST be done after or before another May also be calledhard logic Discretionary: When you PREFER activities to be accomplished in a certain order May also be called: · Preferred · Preferential · Soft logicSee the Time Chapter

146

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 148/642

-

- -- - - --- --- --- --What are external dependencies?

....."

147

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 149/642

Based on the needs of a party OUTSIDE the project

See the Time Chapter

148

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 150/642

What is a resource breakdown structure?

149

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 151/642

A hierarchical list of identified resources by category

See the Time Chapter

150

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 152/642

What is a schedule model? Why is it used?

151

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 153/642

A tool to perform schedule network analysis

See the Time Chapter

152

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 154/642

---------What is the critical path? How does it help the project?

153

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 155/642

The longest path in the network diagram that tells you the shortest time in which the project can be completed Tells the project manager where to focus his time Helps to shorten the length of the projectSee the Time Chapter

154

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 156/642

- - - - - - -What is the near-critical path?

--

--

-

155

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 157/642

The path closest in length to the critical path

See the Time Chapter

156

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 158/642

- -

-

- -

- -

Define lag.

157

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 159/642

Waiting time inserted into the schedule

See the Time Chapter

158

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 160/642

Define total float and the formula for total float.

159

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 161/642

The amount of time an activity can be delayed without delaying the project Formula: Late start - Early start OR Late finish - Early finish

See the Time Chapter

160

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 162/642

Define free float and proj ect float.

161

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 163/642

Free Float: The amount of time an activity can be delayed without delaying the early start date of its successor Proj ect Float: The amount of time the projectcan be delayed without affecting a project's required due date The desired project end date less the actual end date.See the Time Chapter

162

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 164/642

-

--

----

-.-.

......,

......,

What are the methods to compress a schedule?

163

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 165/642

· Crashing · Fast tracking · Re-estimating

See the Time Chapter

164

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 166/642

-

-

""-"

-

""-"

- ""-"

""-"

""-"

What is crashing?

165

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 167/642

Schedule compression through analyzing cost and schedule trade-offs to obtain the greatest compression for the least cost while maintaining scope

See the Time Chapter

166

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 168/642

-

---- - -- -What is fast tracking?

167

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 169/642

Schedule compression by doing more critical path activities in parallel

See the Time Chapter

168

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 170/642

~

~

------What is the critical chain method?

......"

169

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 171/642

A schedule network analysis tool that makes use of buffers

See the Time Chapter

170

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 172/642

""--'"

""--'"

""--'"

""--'"

""--'"

-----

What is re-estimating?

171

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 173/642

Decreasing project and/or activity cost by eliminating the risks in activities

See the Time Chapter

172

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 174/642

- - - -

--

-

-

-

-

What is resource leveling?

173

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 175/642

Keeping the amount of resources used for each time period constant, thus affecting the project duration

See the Time Chapter

174

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 176/642

What is a schedule management plan?

175

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 177/642

Part of the project management plan

A plan for how the schedule will be planned, executed and controlled

See the Time Chapter

176

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 178/642

What is the schedule baseline?

177

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 179/642

Approved schedule with any approved changes, used to measure project schedule performance

See the Time Chapter

178

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 180/642

What are the main tools for displaying a schedule?

179

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 181/642

· Network diagrams · Bar charts · Milestone charts · Flowcharts

See the Time Chapter

180

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 182/642

--

---What do network diagrams show?

.......""

.......""

.......""

-

181

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 183/642

· Interdependencies between activities · How project activities will flow from beginning to end · When estimates are added · May also be used to find the critical path

See the Time Chapter

182

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 184/642

What do simple bar charts show?

183

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 185/642

Project schedule or proj ect status

See the Time Chapter

184

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 186/642

What do milestone charts show?

185

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 187/642

High-level project status

See the Time Chapter

186

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 188/642

What do flowcharts show?

187

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 189/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 190/642

What is a Monte Carlo analysis?

189

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 191/642

A schedule network analysis technique Used to simulate the project to determinehow likely you are to get the project completed by any specific date or for anyspecific cost Also used in quantitative risk analysis to determine an overall level of risk on the projectSee the Time Chapter

190

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 192/642

-

- - - - --- - - --- What are the following rules? 50/50 rule 20/80 rule 0/100 rule

191

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 193/642

Methods of progress reporting 50 percent of the effort is reported complete (20percent or 0 percent) when an activity begins The balance (50 percent, 80 percent or 100 percent) is recorded only when an activity is finishedSee the Time Chapter

192

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 194/642

--'

- -- -

- -

- -

What is the process of cost management?

193

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 195/642

· Cost management planning · Cost estimating · Cost budgeting · Cost control

See the Cost Chapter

194

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 196/642

What is a key output of cost management planning?

195

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 197/642

Cost management plan

See the Cost Chapter

196

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 198/642

What are key outputs of cost estimating?

197

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 199/642

· Activity cost estimates · Requested changes

See the Cost Chapter

198

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 200/642

What are key outputs of cost budgeting?

199

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 201/642

· Cost baseline · Funding requirements· Requested changes

See the Cost Chapter

200

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 202/642

~

~

~

--

-- ---

What are key outputs of cost control?

201

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 203/642

· Requested changes · Performance measurements · Recommended corrective actions · Forecasted completion

See the Cost Chapter

202

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 204/642

N arne some inputs to

estimating.

203

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 205/642

· Project scope statement · Work breakdown structure · Network diagram · Schedule and management plan · Enterprise environmental factors · Organizational process assets · Resource pool · Project management effort · Risk management plan and register · Project objectivesSee the Cost Chapter

204

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 206/642

--

-

-- --

---

....."

....."

What is a cost management plan?

205

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 207/642

Part of the project management plan

How cost will be planned, executed and controlled

See the Cost Chapter

206

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 208/642

What are the main approaches to cost or schedule estimating?

207

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 209/642

· Analogous estimating · Bottom-up estimating (cost only) · Parametric estimating · Three-point estimates · One-time estimates

See the Cost Chapter

208

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 210/642

-

-

-

-------

What is analogous estimating?

209

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 211/642

Top-down estimating that looks at the past to predict the future "The last three projects cost $25,000, or took six months, and so should this one"

See the Cost Chapter

210

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 212/642

-

 _._"--_ What is bottom-up estimating?

..........

 _-

211

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 213/642

Estimating based on the details of the project, e.g., from the bottom of the work breakdown structure

See the Cost Chapter

212

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 214/642

What is parametric estimating?

213

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 215/642

Extrapolating from historical information to estimate costs, e.g., cost per line of code, hours per installation

See the Cost Chapter

214

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 216/642

What is earned value analysis?

215

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 217/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 218/642

What is the range for an order of magnitude estimate?

217

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 219/642

-50 percent to + 100 percent from actual

See the Cost Chapter

218

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 220/642

What is the difference between a cost budget and a cost baseline?

219

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 221/642

Cost budget adds

management reserve tothe cost baseline

See the Cost Chapter

220

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 222/642

What is the formula for cost variance?

221

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 223/642

EY -AC=CY

See the Cost Chapter

222

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 224/642

What is the formula for schedule variance?

223

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 225/642

EV - PV= SV

See the Cost Chapter

224

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 226/642

-- -- --- - -What is the formula for cost performance index?

225

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 227/642

EV / AC

=

CPI

See the Cost Chapter

226

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 228/642

- - - - -

- - - --- -

What is the formula for schedule performance index?

227

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 229/642

EV / PV = SPI

See the Cost Chapter

228

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 230/642

-'-------"What are the formulas for estimate at completion?

229

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 231/642

· BAC / CPI = EAC or · AC + ETC · AC + BAC - EV · AC + (BAC - EV) CPI

See the Cost Chapter

230

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 232/642

-- -- - --What is the formula for estimate to complete?

-....-

...,.

231

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 233/642

EAC -AC

=

ETC

See the Cost Chapter

232

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 234/642

- -

------What is the formula for variance at completion?

......,

233

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 235/642

BAC - EAC

=

VAC

See the Cost Chapter

234

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 236/642

-- -- -

----- --

Define present value.

235

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 237/642

The value today of future cash flows

PV=

FV (1 + r)n

See the Cost Chapter

236

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 238/642

--

-

-- --- --

Define net present value.

237

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 239/642

The value in today's dollars of some future costs and expenses For cost, the lower the number the better For revenue, the higher the number the better

See the Cost Chapter

238... WI' WI' WI' ...

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 240/642

-

---- - --- Define internal rate of return.

239

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 241/642

The rate an investment in the proj ect will return The higher the number the better The rate at which a project's inflows and outflows are equal

See the Cost Chapter

240

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 242/642

---

--- - -- -

Define payback period.

241

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 243/642

The number of time periods to recover the investment

A lower number is better than a higher one

See the Cost Chapter

242

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 244/642

- - -

----

---

Define benefit cost ratio.

243

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 245/642

Benefit Cost

The higher the number the better

See the Cost Chapter

244

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 246/642

--'--'-""'-'-

- - - -

Define opportunity cost.

245

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 247/642

The opportunity given up by selecting one project over another

See the Cost Chapter

246

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 248/642

-

---

-

-- - - -

.....,

-

What are sunk costs?

247

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 249/642

Expended costs

See the Cost Chapter

248

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 250/642

Define the law of diminishing returns.

249

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 251/642

The more you put into the effort, the less you get out of it

See the Cost Chapter

250

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 252/642

---- - -- --Define working capital.

251

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 253/642

Current assets minus current liabilities The amount of funds available to spendon projects

See the Cost Chapter

252

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 254/642

---

-

- - - - - - -- Describe a variable cost and a fixed cost chargeable to the project.

253

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 255/642

Variable Cost: A cost that varies with the amount of work done on the project Fixed Cost: A cost that does not vary with the amount of work done on the project

See the Cost Chapter

254

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 256/642

-

~

~

- -

---

-

---

Describe a direct cost and an indirect cost chargeable to the proj ect.

255

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 257/642

Direct Cost: A cost directly attributable to the project

Indirect Cost: Overhead

See the Cost Chapter

256

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 258/642

--- -- --- - What are different types of depreciation?

257

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 259/642

Straight Line Depreciation: Depreciate same amount each time period AcceleratedDepreciation: Depreciate an amount greater than straight line each time period

See the Cost Chapter

258

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 260/642

---

-- - -- - -

What does life cycle costing mean?

259

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 261/642

Considering the future cost of operating and maintaining the proj ect or deliverable over its life when planning and managing the project

See the Cost Chapter

260

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 262/642

- -

--

--- - --

What is value analysis?

261

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 263/642

Finding a less costly way of doing essentially the same work

See the Cost Chapter

262

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 264/642

---'-------What is the process of quality management?

263

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 265/642

· Quality planning · Quality assurance · Quality control

See the Quality Chapter

264

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 266/642

-

-- -

- -- - -

- --

What are key outputs of quality planning?

265

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 267/642

· Quality management plan · Quality metrics · Quality baseline · Process improvement plan

See the Quality Chapter

266

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 268/642

What are key outputs of perform quality assurance?

267

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 269/642

· Requested changes · Recommended corrective actions

See the Quality Chapter

268

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 270/642

What are key outputs of perform quality control?

269

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 271/642

· Quality control measurements · Validated defect repair · Requested changes · Recommended corrective and preventive actions and defect repair

See the Quality Chapter

270

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 272/642

-.-...

-.-...

-

-- - -- --

What does gold plating mean?

271

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 273/642

Adding extra items and services that do not necessarily contribute added value or quality to customer deliverables

See the Quality Chapter

272

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 274/642

What is marginal analysis?

273

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 275/642

An analysis to determine when optimal quality is reached

An analysis to determine the point where incremental revenue from improvement equals the incremental cost to secure it

See the Quality Chapter

274

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 276/642

----- -What is a quality management plan?

- - -

275

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 277/642

Part of the project management plan

A plan for how the project

management team will implement the performing organization's quality policy

See the Quality Chapter

276

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 278/642

-- ---- -- - What is a process improvement plan?

277

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 279/642

A plan for analyzing processes used on the project to decrease defects, save time and money and increase customer satisfaction

See the Quality Chapter

278

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 280/642

------- - What is the quality baseline? What is it used for?

-

279

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 281/642

The project's quality objectives

One of the baselines used to measure performance against

See the Quality Chapter

280

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 282/642

-_._------....-._---What are quality metrics?

281

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 283/642

Specific measures of quality to be used on the project in quality assurance andquality control

See the Quality Chapter

282

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 284/642

"---------What does continuous improvement mean?

283

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 285/642

The never-ending enhancement of a product/service through small, continuous enhancements

See the Quality Chapter

284

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 286/642

~

--

-- --

---- - -

How much inventory is maintained in a just in time environment? How does this affect attention to quality?

285

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 287/642

Little inventory is maintained

It forces attention to quality

See the Quality Chapter

286

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 288/642

...........

 _----What does ISO 9000 stand for?

-

-..-'

287

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 289/642

One of the International Organization for Standardization (ISO) international quality standards that asks, "Do you have a quality standard, and are you following it?"

See the Quality Chapter

288

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 290/642

--

-- - - - --

-- - -

What is the definition of total quality management?

289

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 291/642

A comprehensive management philosophy of encouraging the finding of ways to continuously improve the quality of business practices, products or services

See the Quality Chapter

290

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 292/642

--- - -

---

-

'-

-

-

What does the phrase prevention over inspection mean?

291

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 293/642

The cost of avoiding or preventing mistakes is always much less than the cost of correcting them

See the Quality Chapter

292

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 294/642

---

- -

- --- - --- -

What does mutually exclusive mean?

293

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 295/642

Two events that cannot occur in a single trial For example, you can't roll a 5 and a 6 on one die

See the Quality Chapter

294

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 296/642

-

- -

--

-

-

-

-

-

What does statistical independence mean?

295

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 297/642

The probability of "B" occurring does not depend on "A" occurring For example, the outcome of a second dice roll is not influenced by (dependent on) the outcome of the first roll

See the Quality Chapter

296

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 298/642

--- - --What is a normal distribution curve?

- - -

297

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 299/642

Symmetric bell-shaped frequency distribution curve

The most common probability distribution

See the Quality Chapter

298

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 300/642

"-

-

-- .-

-------

What do three sigma and six sigma refer to?

299

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 301/642

Often used as quality standards. Three Sigma: +/- Three standard deviations from the distribution mean under which 99.73% of all items are acceptable Six Sigma: +/- Six standard deviations from the mean under which 99.999998% of all items are acceptable A higher quality standard than three sigmaSee the Quality Chapter

300

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 302/642

--- ---

-

- --- - - - - -

What is the difference between a population and a sample?

301

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 303/642

Population: The total number of individual members, items or elements comprising a uniquely defined group For example: All women Sample: A subset of populationmembers For example: Women over the age of 30 in EnglandSee the Quality Chapter

302

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 304/642

"-'"

-- -- -- -- -

-- - -

Who has responsibility for quality on a project?

303

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 305/642

The project manager is ultimately responsible, but the team members must inspect their own work

See the Quality Chapter

304

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 306/642

What are the impacts of poor quality?

305

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 307/642

· Higher costs · Increased rework · Lower morale · Lower customer satisfaction · Increased risk

See the Quality Chapter

306

........................

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 308/642

-

-- ---- --Name costs of conformance and costs of nonconformance. Which costs should be greater? What does cost of nonconformance mean? Provide examples.

307

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 309/642

Costs of conformance: · Quality training · Studies · Surveys The costs of conformanceshould be less than the costs of nonconformance. Costs of nonconformance: · Rework · Scrap · Inventory costs · Warranty costs Costs of nonconformance are associated with poor quality.See the Quality Chapter

308

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 310/642

--- ------What is the purpose of quality planning?

309

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 311/642

· Find existing quality standards and processes · Create additional proj ect specific processes and standards · Determine what work you will do to meet those standards · Determine how you will measure · Create quality planSee the Quality Chapter

310

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 312/642

-- - ------Name some of the tools used in quality planning.

311

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 313/642

· Benchmarking · Cost-benefit analysis · Design of experiments · Cost of quality

See the Quality Chapter

312

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 314/642

--

- - - - - Define benchmarking.

-

-

313

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 315/642

Comparing your company or department's performance to those of other companies

See the Quality Chapter

314

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 316/642

--

-- -Define cost-benefit analysis.

-

-

315

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 317/642

Comparing the costs of an effort to the benefits of that effort

See the Quality Chapter

316

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 318/642

~

-

--

-

-- -- -

-

What is a design of experiments?

317

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 319/642

A statistical method for changing important variables to determine what combination will improve overall quality

See the Quality Chapter

318

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 320/642

What is the purpose of quality assurance?

319

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 321/642

· Making sure all processes are used on the proj ect and performing continuous process improvement · Determine if activities comply with processes · Continuous improvement · Identify improvements the company needs to make · Recommend changesSee the Quality Chapter

320

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 322/642

What are some of the activities in quality assurance?

321

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 323/642

· Process analysis · Quality audits

See the Quality Chapter

322

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 324/642

~

~

~

-- ---~

What are quality audits?

323

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 325/642

Structured reviews of quality activities that identify lessons learned

See the Quality Chapter

324

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 326/642

What is the purpose of quality control?

325

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 327/642

· Measure specific proj ect results against quality standards · Make changes to quality baseline · Identify root causes and quality improvements · Recommend correctiveand preventive actions, changes, and defect repair · Validate deliverablesSee the Quality Chapter

326

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 328/642

Name the quality control tools.

327

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 329/642

· Cause and effect diagram · Flowchart · Histogram · Pareto chart · Run chart · Scatter diram · Control chart

See the Quality Chapter

328

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 330/642

---....

- -- --What is defect repair?

--

....",

329

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 331/642

Rework when a component of the proj ect does not meet specifications

Discovered during quality control, formed into change requests during monitor and control project work, and approved or rejected during integrated change control

See the Quality Chapter

330

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 332/642

-

- -

------

What is a cause and effect (fishbone) diagram? Why is it used?

331

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 333/642

Creative way to look at the causes or potential causes of a problem Used to explore the future or the past Also called a fishbone or Ishikawa diagram Maybe used in quality planning or control

See the Quality Chapter

332

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 334/642

-

-- -- -- -What is a checklist?

-'

333

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 335/642

A list of items to inspect or a picture of an item that is marked to show locations of defects found during inspection

See the Quality Chapter

334

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 336/642

- -- -- -- -- -- -What does a Pareto chart show? Why is it used?

-- -

"-""

335

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 337/642

Graphically prioritizes causes of process problems (by frequency of occurrence)to help focus attention on the most critical issues affecting quality

See the Quality Chapter

336

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 338/642

-

-

-

----

- - -

What is the 80/20 rule?

337

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 339/642

80 percent of process problems are caused by 20 percent of the causes

See the Quality Chapter

338

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 340/642

-

-

- - -

-- ---

What is statistical sampling?

339

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 341/642

Inspecting by choosing only part of a population (a sample) to test

See the Quality Chapter

340

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 342/642

- - - - -

--- --

What is a control chart?

341

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 343/642

Specialized trend chart documenting whether a measured process is in or out of statistical control

See the Quality Chapter

342

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 344/642

.........

.........

-

---- ---

What are control limits?

343

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 345/642

The acceptable range of variation on a control chart

See the Quality Chapter

344

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 346/642

- - - -

---- --

What are the specification limits on a control chart?

345

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 347/642

Customer's measures defining acceptable product/service characteristics and tolerances

See the Quality Chapter

346

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 348/642

-

-

-- - -What does out of control mean?

- -

-

347

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 349/642

The process is performing neither consistently nor predictably, due to the existence of assignable causes

See the Quality Chapter

348

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 350/642

What does the rule of seven mean?

349

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 351/642

Seven consecutive data points appearing on a control chart on one side of the mean, suggesting that the process is out of statistical control

See the Quality Chapter

350

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 352/642

What is a special cause?

351

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 353/642

A data point on a control chart or rule of seven indicating that the measured process is out of statistical control and that the cause(s) of the event must be investigated

See the Quality Chapter

352

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 354/642

- -- --

--

-

- - -- - -

What is the process of human resource management?

353

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 355/642

· Human resource planning · Acquire project team · Develop project team · Manage project team

See the Human Resources Chapter

354

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 356/642

--

-- -- --- --- ---

- -- -

'-'"

What are key outputs of human resource planning?

355

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 357/642

· Roles and responsibilities

· Staffing management plan

· Project organizational chart

See the Human Resources Chapter

356

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 358/642

-

--

--- - - -

----

What are key outputs of acquire project team?

357

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 359/642

· Project staff (team) assignment · Resource availability

See the Human Resources Chapter

358

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 360/642

-

- -

-

- - - - -- --

What is a key output of develop project team?

359

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 361/642

Team performance assessment: Evaluating team effectiveness

See the Human Resources Chapter

360

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 362/642

- - -

- -

-- -- -

What are key outputs of manage project team?

361

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 363/642

· Requested changes · Recommended preventive and corrective actions

See the Human Resources Chapter

362

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 364/642

--

-

-

-

-- - --

Describe the roles and responsibilities of all the people involved in a project.

363

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 365/642

This topic cannot be summarized here, but it is critical to understand who doeswhat on the exam.See the Human Resources Chapter in PMP Exam Prep for more on this topic.

See the Human Resources Chapter

364

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 366/642

- - - - - - - Define sponsor.

-

-

365

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 367/642

· Provides information for preliminary proj ect scope statement · Issues the charter · Provides funding · May dictate dates · Approves proj ect management plan · Agrees tothe change control board · Is involved in riskSee the Human Resources Chapter

366

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 368/642

--

- -- -Describe the team's role.

367

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 369/642

· Create the work breakdown structure and help with project management planning · Estimate activities · Complete activities · Help control and close out the project · Held accountable for assigned activities

See the Human Resources Chapter

368

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 370/642

- -- --

--

-

--

-- -- -- --

Define the role of the stakeholders.

369

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 371/642

They may help: · Plan the project · Approve changes · Identify constraints · Perform the risk management processSee the Human Resources Chapter

370

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 372/642

Define the role of functional managers.

371

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 373/642

Resource managers: · Participate in planning · Approve final project management plan · Approve final schedule · Assist with problems related to team member performance

See the Human Resources Chapter

372

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 374/642

---- ----

------ - What are the key elements in a staffing management plan?

373

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 375/642

When and how human resource requirements will be met · Recognition and rewards · Staff acquisition · Timetable · Release criteria · Training needsSee the Human Resources Chapter

374

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 376/642

What must a proj ect manager do in order to develop the project team?

375

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 377/642

· Hold team building activities throughout the proj ect life· Obtain and provide

training where needed · Establish ground rules · Create and give recognition and rewards · Place team members in the same location (co-location)See the Human Resources Chapter

376

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 378/642

- - -

- -

- -

What must a project manager do to manage a proj ect team?

377

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 379/642

· Observe · Use an issue log · Keep in touch · Complete project performance appraisals · Actively look for and help resolve conflicts that the team cannot resolve on their ownSee the Human Resources Chapter

378

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 380/642

---- -----What is a team performance assessment?

379

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 381/642

An assessment by the project manager of

project teameffectiveness

See the Human Resources Chapter

380

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 382/642

- -

------ -Narne the powers of the project manager.

381

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 383/642

· Formal· Reward · Penalty · Expert · Referent

See the Human Resources Chapter

382

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 384/642

- - -

-- - -

- - -

Narne the different leadership styles a project manager may choose to use.

383

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 385/642

· Directing · Facilitating · Coaching · Supportive · Autocratic · Consultative · ConsensusSee the Human Resources Chapter

384

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 386/642

Name the most common sources of conflict on projects.

385

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 387/642

· Schedules · Priorities · Resources · Technical opinions

NOT personalities

See the Human Resources Chapter

386

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 388/642

-- -- --

- - - - - -- -

N arne conflict resolution techniques.

387

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 389/642

· Problem solving (confronting) · Compromise · Withdrawal (avoidance) · Smoothing · Forcing

See the Human Resources Chapter

388

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 390/642

- - -

-

- -

--

--

Define problem solving. Define compromising.

389

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 391/642

Problem Solving: Solving the real problem (Win-win) Compromising: Making all parties somewhat happy (Lose-lose)

See the Human Resources Chapter

390

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 392/642

- - -

-- - -- --

Define withdrawal. Define smoothing. Define forcing.

391

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 393/642

Withdrawal: Postponing a project decision or avoiding addressing the problem Smoothing: Emphasizing agreement rather than differences of opinion Forcing: Do itmy way

See the Human Resources Chapter

392

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 394/642

-

-

--- --

- -

-

What are the project manager's human resource responsibilities?

393

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 395/642

· Create a team directory · Negotiate for best resources · Create project-related jobdescriptions for team members · Make sure team members obtain needed training · Create reward systems · Create a staffing management plan

See the Human Resources Chapter

394

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 396/642

........

---

........

-----

What is a project performance appraisal?

395

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 397/642

An evaluation of individual team member effectiveness

See the Human Resources Chapter

396

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 398/642

- - -

-

-

--

- - -

What is Maslow's theory?

397

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 399/642

People are motivated according to hierarchy: · Self-actualization · Esteem · Social · Safety · Physiological

See the Human Resources Chapter

398

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 400/642

- - - -- - ---What did McGregor describe?

399

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 401/642

Theory X: Managers who accept this theory believe that people need to be watched every second Theory Y: Managers who accept this theory believe that people want to achieve and can work without supervision

See the Human Resources Chapter

400

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 402/642

-- -What did Herzberg describe?

---

- --

401

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 403/642

· Hygiene factors · Motivating agents

See the Human Resources Chapter

402

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 404/642

- - - - -- - -- - Why is releasing resources the last activity in closure?

-

403

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 405/642

The team and other resources are needed to complete closure

See the Communications Chapter

404

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 406/642

-

- -

- - - - - --- -

What is a kickoff meeting? When does it occur?

405

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 407/642

A meeting of all parties to the project (project stakeholders, sellers, etc.) to make sure everyone is "on the same page"

It is held at the end of the

planning process group.

See the Communications Chapter

406

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 408/642

--

--

- - - - - -- - What is the process of communications management?

407

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 409/642

· Communications planning · Information distribution · Performance reporting · Manage stakeholders

See the Communications Chapter

408

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 410/642

- - - - -

-- --

-

What is the key output of communications planning?

409

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 411/642

Communications management plan

See the Communications Chapter

410

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 412/642

- - -

----- --

What are key outputs of information distribution?

411

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 413/642

· Team and stakeholders have the information they need · Requested changes

See the Communications Chapter

412

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 414/642

- - - - - - - What are key outputs of performance reporting?

--

413

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 415/642

· Stakeholders know how the project is performing · Performance reports · Forecasts · Requested changes · Recommended corrective actions

See the Communications Chapter

414

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 416/642

-----

- - - - -

What are key outputs of manage stakeholders?

415

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 417/642

· Resolved issues · Approved change requests · Approved corrective actions

See the Communications Chapter

416

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 418/642

- - - - - - Define communications planning.

-

- -

417

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 419/642

Determining the information and communication needs of stakeholders

See the Communications Chapter

418

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 420/642

-

-

- - "-

What is a communications management plan?

419

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 421/642

Part of the project management plan A formal plan that describes what will be communicated and received from whom, when, and how often

See the Communications Chapter

420

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 422/642

--- -- ---

'-'"

-

--

......",

-

Describe the information distribution requirements on projects.

421

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 423/642

Implementing the communications management plan Creating reports including: · Lessons learned · Performance reportsSee the Communications Chapter in PMP Exam Prep for more on this topic.

See the Communications Chapter

422

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 424/642

--

-- - -- -- -- -- -Describe the communications model and its components.

-..-'

-..-'

423

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 425/642

Messages are encoded, transmitted and unencoded, and must include attention to: ·Nonverbal communication · Paralingual · Active listening · Effective listening · Feedback

See the Communications Chapter

424

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 426/642

- --

--

-- --

-

-

How much of communication is nonverbal?

425

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 427/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 428/642

- -- -- -

--- --

-

What does paralingual mean?

427

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 429/642

Pitch and tone of voice

See the Communications Chapter

428

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 430/642

~

~

-

~

- -

-

-

-

-

Name communications methods.

429

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 431/642

· Formal · Informal· Written · Verbal

See the Communications Chapter

430

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 432/642

- -

------How much time do proj ect managers spend communicating?

431

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 433/642

90 percent

See the Communications Chapter

432

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 434/642

'-""

-- -- -- -- --

-

--

- -

Name communication blockers.

433

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 435/642

· Noise · Distance · Improper encoding · "That was a bad idea" · Hostility · Language · CueSee the Communications Chapter

434

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 436/642

-------

-- -- -- -- --

Describe the rules for effective meetings.

435

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 437/642

· Set a time limit · Schedule in advance · Create an agenda with team input · Distribute agenda in advance · Lead meeting with a set of rulesSee the Communications Chapter in PMP Exam Prep for more on this topic.

See the Communications Chapter

436

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 438/642

What is the formula for communication channels?

437

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 439/642

[N (N-I)] /2

See the Communications Chapter

438

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 440/642

- --

-- --

---

....."

What is an issue log?

439

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 441/642

Documents project issues, persons responsible for resolving issues and target resolution dates

See the Communications Chapter

440

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 442/642

- -- --

- -

--

- - -- -

What are lessons learned? What do we do with them?

441

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 443/642

What went right, wrong, and could be done differently Used in planning a project and are generated by the proj ect to be used by other projects in the future

See the Communications Chapter

442

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 444/642

- - -

-

--

- -

- -

What is the process of risk management?

443

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 445/642

· Risk management planning · Risk identification · Qualitative risk analysis · Quantitative risk analysis · Risk response planning · Risk monitoring and controlSee the Risk Chapter

444

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 446/642

-

-----

--

------

What is the key output of risk management planning?

445

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 447/642

Risk management plan

See the Risk Chapter

446

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 448/642

- - - - -

---

-

-

--

What are key outputs of risk identification?

447

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 449/642

· Risks · Risk register

See the Risk Chapter

448

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 450/642

- - - -

----

- -

What are key outputs of qualitative risk analysis added to the risk register?

449

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 451/642

· List of risks · Ranked risks by category · Watchlist

See the Risk Chapter

450

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 452/642

-----What are key outputs of quantitative risk analysis added to the risk register?

-

-

-

451

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 453/642

· Probability of achieving the cost and time objectives · Prioritized list of quantified risks

See the Risk Chapter

452

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 454/642

-What are key outputs of risk response planning?

--

453

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 455/642

· · · · · · · · ·

Risk response plans Contingency plans Triggers Reserves for time and cost Fallback plans Contracts Revised project management plan Residual risks Secondary risks

See the Risk Chapter

454

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 456/642

What are key outputs of risk monitoring and control?

455

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 457/642

· Requested changes · Recommended preventive and corrective actions · Updates to the risk register · Risk audits · Periodic risk reviews · Risks closedSee the Risk Chapter

456

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 458/642

--

-- -- -- Define risks.

'-

457

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 459/642

Events that can affect a proj ect for better or worse Threats and opportunities

See the Risk Chapter

458

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 460/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 461/642

· Probability · Impact · Timing · Frequency

See the Risk Chapter

460

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 462/642

-

-

- -

-- -- - -

Someone who is risk averse IS:

461

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 463/642

Unwilling to take risks

See the Risk Chapter

462

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 464/642

- -

-

-

---- --

What is risk tolerance?

463

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 465/642

Amount of risk acceptable

See the Risk Chapter

464

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 466/642

-

-

--

-

----

Narne the inputs to the risk management process.

465

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 467/642

· Organizational process assets · Enterprise environmental factors · Proj ect charter ·Project scope statement · Proj ect scope management plan · Staffing plans · WBS · Network diagram · Cost and time estimatesSee the Risk Chapter

466

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 468/642

-

- -

-

---

- -

What are risk categories?

467

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 469/642

Lists of common sources of risk, including: · Technical · Project management · Schedule · Cost · Others

See the Risk Chapter

468

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 470/642

- -- -- '-- -' -- What are risk identification techniques?

--

--

469

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 471/642

· Documentation reviews · Brainstorming · Delphi Technique · Root cause identification · Interviewing · SWOT · Checklists · Assumptions analysis · Diagramming techniques

See the Risk Chapter

470

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 472/642

--

---

-- --

'-'

--

-

-- -

What are the types of risks?

471

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 473/642

· Business · Pure

See the Risk Chapter

472

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 474/642

--'""-"--------What are risk triggers?

473

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 475/642

Early warning signs that a risk event is about to occur

See the Risk Chapter

474

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 476/642

--

"'--'

-- -- --

--

-

- --

"-"'

What is assumptions analysis? When is it done?

475

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 477/642

Explores the validity of project assumptions to identify new risks in risk identification

See the Risk Chapter

476

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 478/642

-- - --

-

---

- -

-

What is risk data quality assessment? When is it done?

477

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 479/642

· Reviewing how well understood is the risk · A method to test reliability of risk information collected· It is done during

qualitative risk analysis

See the Risk Chapter

478

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 480/642

--

--

--

- -

-- - --

What is a probability and impact matrix?

479

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 481/642

The company's scale to determine which risks continue through the risk management process

See the Risk Chapter

480

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 482/642

- -- -

-

- - -

- -

-

What is the formula for expected monetary value?

481

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 483/642

Probability times impact

See the Risk Chapter

482

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 484/642

-

- -

-- -- -

-

What is a decision tree?

483

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 485/642

A model of a decision to be made which includes the probabilities and impacts of future events to help make a decision today

See the Risk Chapter

484

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 486/642

-

--

- - -

--

Who is a risk response owner?

485

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 487/642

The person assigned to execute risk responses for each critical risk

See the Risk Chapter

486

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 488/642

--- '-- -- -' "--

-

'-'--

-- - -

N arne and define the risk response strategies for threats.

487

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 489/642

Avoid: Eliminate a specific threat by eliminating the cause Mitigate; Reduce the probabIlIty or Impact Accept: PassIve - Do nothing If it happens, it happens. Active - Develop contingency plans Transfer: Make another party responsible for a risk May include: outsourcing, InsuranceJ warranties, bonds ana guaranteesSee the Risk Chapter

488

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 490/642

Narne and define the risk response strategies for opportunities.

489

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 491/642

Exploit: Enhance the opportunity Share: Allocate ownershipto a third party

Enhance: Increase probabIhty or impacts Accept: PassIve - Do nothing If it happens, it happens Active - Develop contingency plansSee the Risk Chapter

490

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 492/642

---

--

-

--- - --

What are residual risks?

491

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 493/642

Risks that remain after risk response planning: · Risks for which contingency andfallback plans have been created · Risks which have been accepted Outputs of riskresponse planningSee the Risk Chapter

492

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 494/642

---

- - -

--- --

What are secondary risks?

493

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 495/642

New risks created by risk response strategies Outputs of risk response planning

See the Risk Chapter

494

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 496/642

--

-- -

- - -

-

-

How does buying insurance relate to risk response planning?

495

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 497/642

It exchanges an unknown

risk for a known risk

It is a method to decrease

project risk

It is an output of risk

response planning

See the Risk Chapter

496

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 498/642

-----What do contracts have to do with risk response planning?

-

497

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 499/642

A contract helps allocate and mitigate risks

A risk analysis is done before a contract is signed

Contracts are outputs of risk response planningSee the Risk Chapter

498

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 500/642

-

- -- - -

--

-

-

What are contingency plans?

499

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 501/642

Planned responses to risks

Outputs of risk response planning

See the Risk Chapter

.............................

500

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 502/642

-

---

-

-- -

- -

What are fallback plans?

501

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 503/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 504/642

-- -- -- -- -- -- -- - - What does a revised project management plan have to dowith risk management?

503

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 505/642

The components of the project management plan will need to be updated based on the results of risk planningIt is an output of risk response planning

See the Risk Chapter

504

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 506/642

What are reserves?

505

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 507/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 508/642

What is a contingency reserve?

507

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 509/642

Time or cost allocated to cover known unknowns

Included in cost baseline

See the Risk Chapter

508

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 510/642

What is a management reserve?

509

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 511/642

Time or cost allocated to cover unknown unknowns

Included in cost budget

See the Risk Chapter

510

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 512/642

---

-- -- -- - -- What are risk reassessments? When do they occur?

--

--

511

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 513/642

Identification of new risks

They occur during risk monitoring and control

See the Risk Chapter

512

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 514/642

-

--- ---

-

--

- -- - -

What is reserve analysis? When is it done?

513

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 515/642

· Determining reserves · Managing the reserves and making sure the amount remainingis adequateIt is done during risk

response planning, monitoring and controlling, activity duration estimating, cost budgeting and cost controlSee the Risk Chapter

514

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 516/642

- -- - - - --- - - - What are risk response audits?

515

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 517/642

Examining and documenting the effectiveness of the risk response and the risk response owner

See the Risk Chapter

516

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 518/642

- - --

--

-

'-'

- -

--

What is the process of procurement management?

517

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 519/642

· Plan purchases and acquisitions · Plan contracting · Request seller responses · Select sellers · Contract administration · Contract closureSee the Procurement Chapter

518

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 520/642

- - -- -- --

-- --

--

-- --

Narne the inputs to the procurement management process.

519

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 521/642

· Enterprise environmental factors · Organizational process assets · WBS · Risk register · Proj ect scope statement · Project schedule · Cost estimate for contracted work · Cost baseline for the projectSee the Procurement Chapter

520

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 522/642

-

------What are key outputs of plan purchases and acquisitions?

521

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 523/642

· Procurement management plan · Contract statement of work · Requested changes

See the Procurement Chapter

522

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 524/642

What are key outputs of plan contracting?

523

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 525/642

· Procurement documents · Evaluation criteria

See the Procurement Chapter

524

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 526/642

What are key outputs of request seller responses?

525

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 527/642

· Procurement documents · Proposals

See the Procurement Chapter

526

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 528/642

"'--"

-- - -- - - - - What are key outputs of select sellers?

527

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 529/642

· Contract signed · Contract management plan · Requested changes

See the Procurement Chapter

528

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 530/642

--

---

-- -- -

- - -

--

What are key outputs of contract administration?

529

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 531/642

· Substantial completion · Requested changes · Recommended corrective actions

See the Procurement Chapter

530

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 532/642

--

-

-...-

-...-

--- - --

What are key outputs of contract closure?

531

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 533/642

· Product verification · Financial closure · Update and index records · Performance reporting · Procurement audits · Lessons learned · Formal acceptanceSee the Procurement Chapter

532

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 534/642

- -- - - - - - - What is a contract management plan?

533

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 535/642

A plan for how each contract will be administered

See the Procurement Chapter

534

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 536/642

-

- - -

--

- - -

What is a procurement management plan?

535

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 537/642

Part of the project management plan

Describes how procurements will be planned, executed and controlled

See the Procurement Chapter

536

~

WI'

WI'

...

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 538/642

-

-----What is required for a legal contract?

537

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 539/642

· Offer · Acceptance · Consideration · Legal capacity · Legal purpose

See the Procurement Chapter

538

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 540/642

-

-

- - -

-

-

--

What is a contract?

539

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 541/642

May include all of the following: · Legal terms · Business terms · Contract statementof work · Marketing literature · DrawingsSee the Procurement Chapter

540

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 542/642

Describe the proj ect manager's role in procurement.

541

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 543/642

· Understand the procurement process · Make sure the work described in the contractis complete · Be involved in the whole contracting process · Help tailor the contract to the project · Incorporate mitigation and allocation of risks into the contractSee the Procurement Chapter

542

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 544/642

-----Name the advantages of centralized contracting.

543

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 545/642

· Increased expertise in contracting · Standardized practices · Clear career path

See the Procurement Chapter

544

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 546/642

- - - Narne the disadvantages of centralized contracting.

545

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 547/642

· One person works on many proj ects · May be difficult to obtain contracting help when needed

See the Procurement Chapter

546

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 548/642

-----Narne the advantages of decentralized contracting.

547

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 549/642

· Easier access to contracting expertise · More loyalty to the project · More focusedcontract expenence

See the Procurement Chapter

548

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 550/642

--

-- --- - -

-- -

---

-- -

Name the disadvantages of decentralized contracting.

549

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 551/642

· No home for the contracts person after the project · Less focus on improving contracting expertise · Inefficient use of resources · Little standardization of contracting processes from one project to the nextSee the Procurement Chapter

550

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 552/642

--

--

-

-- -- - -- --

-

What does make-or-buy refer to?

551

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 553/642

Analyzing whether the performing organization should do the work or buy the services/supplies fromoutside the organization

See the Procurement Chapter

552

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 554/642

- - - - What are the main types of contracts?

553

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 555/642

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 556/642

What is a cost reimbursable contract?

--

555

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 557/642

All costs are reimbursed

See the Procurement Chapter

556

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 558/642

What is a cost plus fixed fee contract?

557

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 559/642

All costs are reimbursed

The fee is fixed at a certain monetary amount

See the Procurement Chapter

558

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 560/642

What is a cost plus percentage of cost contract?

559

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 561/642

All costs are reimbursed, plus a specific percentage of costs as fee or profit

See the Procurement Chapter

560

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 562/642

What is a cost plus incentive fee contract?

561

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 563/642

Costs are reimbursed plus an incentive, usually an additional fee, for exceeding performance criteria that have been determined in advance

See the Procurement Chapter

562

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 564/642

-- -- ---

--

- - --

-- -- --

What is a time and material contract?

563

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 565/642

Usually a fixed hourly rate or a fixed cost per item, plus a reimbursable component for expenses or materials

See the Procurement Chapter

564

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 566/642

------What is a fixed price contract?

565

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 567/642

There is only one fee for accomplishing all the work

See the Procurement Chapter

566

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 568/642

---

-

--

- - - -

What is a fixed price plus incentive fee contract?

567

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 569/642

Total price is fixed, but an additional amount may be paid for exceeding performance criteria determined in advance

See the Procurement Chapter

568

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 570/642

- --

-- - - What is a fixed price economic price adjustment contract?

-

-

569

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 571/642

A fixed price contract with an allowable adjustment for price increase, due to cost increases in later time periods

See the Procurement Chapter

570

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 572/642

-- -- - - - Describe how contract administration efforts will be different witheach contract form.

-

-

571

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 573/642

This critical concept cannot be summarized here.

See the Procurement Chapter in PMP Exam Prep for more on this topic.

See the Procurement Chapter

572

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 574/642

-

-

What is a purchase order?

- -

573

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 575/642

A unilateral contract

See the Procurement Chapter

574

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 576/642

What are incentives? What might they be used for?

575

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 577/642

Help bring the seller's objectives in line with the buyer's Incentives for: · Time · Cost · Quality · ScopeSee the Procurement Chapter

576

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 578/642

Who has the cost risk in a cost reimbursable contract? In a fixed price contract?

577

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 579/642

Risk in a cost reimbursable contract is borne by the buyer Risk in a fixed price contract is borne by the seller

See the Procurement Chapter

578

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 580/642

---

-- -- -

- --

-

-- --

Name the types of contract statements of work.

579

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 581/642

· Performance · Functional/detailed · Design

See the Procurement Chapter

580

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 582/642

--

--- -

- - - - -

-

What are procurement documents?

581

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 583/642

· Request for proposal (RFP) · Invitation for bid (IFB) · Request for quotation (RFQ)

See the Procurement Chapter

582

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 584/642

- -- -- --

- -

- - -

-

What are standard contract terms and conditions? What are special provisions?

583

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 585/642

Standard Contract Terms and Provisions: Terms and conditions which are used forall contracts within the company Special Provisions: Terms and conditions created for the unique needs of the project Created with the input of the proj ect managerSee the Procurement Chapter

584

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 586/642

--- ---

- -- - - -- - - Name common terms and conditions that may be in a contract.

585

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 587/642

Please review the long list of terms and conditions and what they mean in PMP Exam Prep, Procurement Chapter.

See the Procurement Chapter

586

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 588/642

--

- - - - - - What is a letter of intent?

-

587

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 589/642

A letter from the buyer, without legal binding, saying the buyer intends to hire the seller

See the Procurement Chapter

588

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 590/642

-

-

- - - -

- -

What does privity refer to?

589

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 591/642

Contractual relationships between two or more

companies

See the Procurement Chapter

590

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 592/642

-----What does non-competitive procurement mean?

591

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 593/642

Work awarded to a single source or sole source without competition

See the Procurement Chapter

592

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 594/642

When are evaluation criteria created and used? What do they refer to?

593

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 595/642

Created during plan contracting Rationale that the buyer will use to weight or score suppliers' proposals Used during select sellers to pick a supplier

See the Procurement Chapter

594

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 596/642

What is a bidder conference? What should be watched out for?

595

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 597/642

A meeting with prospective sellers to make sure all understand the procurement and have a chance to ask questions Watch for: · Collusion · Sellers not asking questions · All questions and answers are distributed to allSee the Procurement Chapter

596

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 598/642

------What is a qualified seller list?

597

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 599/642

A list of sellers who have been pre-approved

See the Procurement Chapter

598

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 600/642

-

'--"'"

------What are the objectives of negotiation?

599

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 601/642

· Obtain a fair and reasonable price · Develop a good relationship with the other side

See the Procurement Chapter

600

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 602/642

-

------Name some negotiation tactics.

601

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 603/642

· · · · · · · · · · ·

Attacks Personal insults Good guy/Bad guy Deadline Lying Limited authority Missing man Delay Extreme demands Withdrawal Fait accompli

See the Procurement Chapter

602

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 604/642

-

--

- - ---

- -

Name some of the project manager's activities during contract administration.

603

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 605/642

· Review invoices · Integrated change control · Interpret the contract · Monitor performance against the contract · Risk managementPlease see the long list in PMP Exam Prep, Procurement Chapter.See the Procurement Chapter

604

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 606/642

-

-----Why might there be conflict between the contract administrator and the proj ect manager?

605

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 607/642

The contract administrator is the only one with the power to change the contract (including the project scope)

See the Procurement Chapter

606

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 608/642

-'What is a contract change control system?

607

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 609/642

A system created to modify the contract and to control changes to the contract

See the Procurement Chapter

608

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 610/642

--

--- -

- -

What must be done for all contract changes?

609

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 611/642

They must be formally documented

See the Procurement Chapter

610

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 612/642

What is the purpose of a buyer-conducted performance review?

611

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 613/642

Identify seller's successes or failures, and allow the buyer to rate the seller's ability to perform

See the Procurement Chapter

612

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 614/642

-- -- -Define claims administration.

-- --

613

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 615/642

Managing contested changes and constructive changes (claims) requested by the seller

See the Procurement Chapter

614

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 616/642

-

- -- ---

What is the key function of a records management system?

615

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 617/642

Maintain an index of contract documentation and records to assist in retrieval Part of the project management information system

See the Procurement Chapter

616

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 618/642

--

- -

--

Name the guidelines for interpreting what is or is not included in the contract.

617

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 619/642

See the Procurement Chapter in PMP Exam Prep for more on this topic.

See the Procurement Chapter

618

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 620/642

-

-----What is the purpose of contract closure in the procurement management process?

619

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 621/642

· Perform a procurement audit· Complete the work done under contract

See the Procurement Chapter

620

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 622/642

- What is a procurement audit?

- - -

621

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 623/642

Structured review of the procurement process and determination of lessons learned to help other procurements

See the Procurement Chapter

622

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 624/642

-

-"

-

What does professional and social responsibility mean?

623

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 625/642

· Ensure individual integrity · Contribute to the proj ect management know ledge base · Enhance personal professional competence · Promote interaction among stakeholdersFor the PMP exam, make sure you read the extensive information on this topic inPMP Exam Prep, Prof Responsibility Chapter.See the Prof. Responsibility Chapter

624

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 626/642

What does "ensure individual integrity" mean?

625

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 627/642

· Follow PMI's code of professional conduct · Tell the truth in reports · Follow copyright and other laws · Treat others with respect · Report violations · Do not put personal gain over project needs · Do not give or take bribes

See the Prof. Responsibility Chapter

626

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 628/642

What does "contribute to the project management knowledge base" mean?

627

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 629/642

· Share lessons learned · Write articles · Mentor others · Perform research on best practices

See the Prof. Responsibility Chapter

628

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 630/642

--

"--'

-- -- -- -- -- -- --

What does "enhance personal professional competence" mean?

629

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 631/642

· Understand your own strengths and weaknesses · Continue to learn · Look for new practices

See the Prof. Responsibility Chapter

630

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 632/642

-

- -- -What does "balance stakeholders' interests" mean?

--

--

631

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 633/642

Part of "promote interaction among stakeholders", it means: · Work to get clear and complete project objectives and project requirements · Understand stakeholders'interests · Recommend approaches that strive for fair resolutionSee the Prof. Responsibility Chapter

632

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 634/642

--

--

-- - -- -- -- -- -What does "interact with team and stakeholders in a professional and cooperative manner" mean?

--

633

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 635/642

Part of "promote interaction among stakeholders", it means: · Respect cultural differences · Understand others' needs · Follow practices in other countries, as long as they do not violate laws · Provide others with proj ect charter, schedule and proj ect management plan they need to do their workSee the Prof. Responsibility Chapter

634

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 636/642

--

-- -- -- -Notes:

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 637/642

Notes:

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 638/642

-

- - - - Notes:

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 639/642

Notes:

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 640/642

- Notes:

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 641/642

Notes:'

8/19/2019 Flashcards for Passing the PMP and CAPM Exams

http://slidepdf.com/reader/full/flashcards-for-passing-the-pmp-and-capm-exams 642/642