3430357500Page 1 of 5

Improperly installed electrical components can result in personal injury and/or property damage. Installations should always be performed by a licensed electrician in compliance with national and local electrical codes.

W A R N I N G

Note: This installation packet pertains to the electrical systems required within the Further product line under Chicago and New York electrical codes.1 - Standard in-feeds are not allowed in Chicago or New York.2 - Standard Junction Blocks, Jumpers, and Duplex Receptacles are not allowed in Chicago.3 - Customer is to provide all cable, conduit, and fittings. A 1/2” Tite-Bite connector or equivalent is required for proper connection to provided junction block and beam bracket. (shown right)

New YorkConduit In-feed

ChicagoBeam Bracket

ChicagoElectrical BracketJunction Box

Components

SCALE 1.000

ChicagoPort Cover

System Overview

Hardwired Electrical Applications

Note - A hardwired beam should be fully assembled as shown.

Beam Bracket

Beam Bracket

Electrical Brackets

Electrical Brackets

GroundingStraps

Circuit 1

Circuit 1

Circuit 2

Circuit 2

Circuit 1

Circuit 2

Circuit 1

Circuit 2

Correct Incorrect

Note - Duplex receptacles which are placed back-to-back from one another must be wired to the same circuit to prevent potential arcing from wire interference.

Further

3430357500Page 2 of 5

Installation Instructions

1 - Remove cover plate from junction box.2 - Center junction box over the hub cover so the top edge is 12.625” from bottom edge.3 - Mark location of holes.4 - Drill pilot holes using a #29 bit, taking care not to damage the hub cover.

12.62510.875

In-Feed Junction Box - Flexible HubNote - A junction box is only necessary if a single in-feed is being split to multiple powered beams.

Otherwise, in-feed conduit may be attached directly to a beam bracket at the end of a run. Y-Connectors may also be used in conjunction with the beam brackets as shown below.

5 - Secure junction box to the hub cover using #8-32 thread cutting screws.

Hubs can sit directly over or adjacent to floor core.

1 In-feed to2 beams

with J-Box1 In-feed to

1 beam

1 In-feed to2 beams

with Splitter

Further

3430357500Page 3 of 5

Installation Instructions

Conduit In-Feed - New York

4 - Reinstall box cover plate.

3 - Wire In-Feed cables to power source in accordance all applicable electrical codes.

1 - Connect Conduit In-Feed to cover plate. Utilize the center knockout hole for proper spacing of jumpers.

5 - Connect In-Feed cable to H-Connector of Hub to Beam Jumper Kit.

2 - Connect power source to bottom knockout of Junction Box.

Note - Beam electrical components are standard for New York. See standard Further Installation Instructions for more details.

In-Feed Junction Box - Fixed HubNote - Usage guidelines for Flexible Hubs apply.1 - Attach the mounting bracket to top of hub. Screws will be reused from existing install.2 - Route in-feed through hub and attach to bottom of junction box, then attach the box to the mounting bracket. Side conduit may be attached before of after this step. 3 - Slide hub cover into side channel; press trim down over junction box.

Further

3430357500Page 4 of 5

Installation InstructionsBeam BracketNote - Beam Brackets are used to close off area containing duplex receptacles within beams. Any beam containing power must have a beam bracket installed on each end.1 - Insert bracket down into electrical port with bend facing inwards; slide towards end of beam until roughly 2.5” from outside edge.2 - Mount bracket down to beam surface using self-drilling screws and toothlock washers.3 - Repeat for second bracket on opposite end of beam.

Electrical Bracket

1 - Connect wires to terminals of duplex receptacle in accordance with all applicable electrical codes.2 - Mount receptacle to one side of electrical bracket using screws provided or hardware that comes with receptacle.3 - Mount receptacle or port cover to opposite side of bracket.4 - Press bracket assembly down into electrical port; attach to bottom of beam with two self-drilling screws.5 - Repeat for all beam electrical ports.

Note - Electrical Brackets are required in all port locations, and are used to mount both duplex receptacles and port covers. Port Covers are required in all port locations without receptacles.

Further

3430357500Page 5 of 5

Installation InstructionsGrounding the BeamNote - Two grounding straps are provided with each UN8BBKCH model. Both beam and top cap are

required to be grounded within the enclosed area created by the beam brackets.

4 - Connect grounding strap to ground source in accordance with all applicable electrical codes in order to ground the beam and brackets.

3 - Attach grounding strap to beam using provided #10-32 screw and toothlock washer.

1 - Position grounding strap near the center of the beam as to not interfere with brackets and can be easily connected to the ground source.2 - Drill a hole through the base of the beam using a #18 bit and tap for a #10-32 thread.

Grounding the Top Cap

5 - Connect grounding strap to ground source in accordance with all applicable electrical codes in order to ground the top cap.

3 - Attach provided #10-32 screw through hole from the top side until fully seated.

1 - Position grounding strap along the bottom of the top cap as to not interfere with brackets and can be easily connected to the ground source.

2 - Drill a hole through the top cap using a #18 bit and tap for a #10-32 thread.

Note - Grounding screwhead will be visible along mounting rail of top trim. Screw should either be placed to one end or centered consistently throughout install.