Part - I Project Scope
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Objectives and Scope - I
• Project Name : Saudi Mobily WiMAX & LTE Project 5508500
• In order to meet the requirement of Mobily multiple networks deployment, Huawei presents multi-
mode BTS solution which is applicable for WiMAX/TDLTE multi-mode deployment and smooth
evolution from WiMAX to LTE
• Scope :
• 1)Huawei 265 WIMAX sites upgrade, and 150 new sites based on Huawei WIMAX coverage cities.
• 2) 99 new TDL and WIMAX co-sites will be built in the New cities.
• 3) 477 new TDL and WIMAX co-sites will be built in Easten, Madinah and Yanbo area.
• Huawei will introduce a new LTE network with two SAE geographically separated in location
within the same access network using single ran solution which will put up with the exceeding
data demands of end users.
Page 3
Huawei Existing City 415
New City 99
Easten&Madinah,Yanbo 477
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Objectives and Scope - II
• Two new ASN-GW’s will be added to the existing network and will be installed in GOSI–Dammam and Silver-Khobar. Huawei is proposing two possible scenarios for the Target Network Topology. The distribution is done based on geographic location of cities keeping in mind the transmission delay consideration. Both scenarios are as following:
Page 4
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
www.huawei.com
3 May 2011
Part - II Project Swap Scenarios
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Page 6
Contents
Swap Scenario analysis
Swap Process
2
3
Swap Strategy1
Rollback Process4
Proposed Solution
6
Risk Analysis5
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 7
1) Swap Strategy for WiMAX
Cluster swap
Low HighMedium
Swap a complete network
Cluster-based Swap
Swap site by site
Cluster-based Swap is the most practical strategy
Project complexity and risk
Number of sites to be Swapped (i.e. sites per cut-over night)
Low
High
� Cluster scale: 7~10 sites
�Based on RF proposed Clusters : An efficient Solution
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
1) Swap Strategy for MW (Transmission)
Page 8
Cluster swap
Low HighMedium
Swap a complete network
Link-based Swap
Swap site by site
Link-based Swap is the most practical
strategy
Project complexity and risk
Number of sites to be Swapped (i.e. sites per cut-over night)
Low
High
� Cluster scale: 6~10 sites
�Swapping a complete MW Link : An efficient Solution
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 9
Cluster 1
Existing ASN_GW
Cluster N
CSN
Huawei ASN_GW
• Step 1: Install and commission Huawei ASN_GW/ DBS3900
• Step 2: During MDT : power off existing sites in Cluster (n)
• Step 3: power on new sites in the cluster (n)
• Step 4: Drive test the cluster (n)
• Step 5: Remove existing equipment
Existing BTS
Existing BTS
New DBS3900
New DBS3900New DBS3900
New DBS3900 Existing BTS
Existing BTS
Swap Strategy----Cluster Mode
2) WiMAX Swap Strategy
Cluster ModeStrategy
Easy Project Management and Schedule Control.Cut-over risk can be controlled easily.Have a chance to roll back.
Advantages
Some modification to existing network for cooperating with new system (different network planning schemeSignal may face interference on boundary region
Risk
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 10
2) Microwave Swap Strategy• Depending on the Site Scenario
aGW
BTS/eNB
BTS/eNB
BTS/eNB
BTS/eNB
BTS/eNB
BTS/eNB
100Mbps, 1+0
150Mbps, 1+0
Configuration:1 pcs CSHA card1 pcs IFU2 card
RTN910RTN910
Configuration:1 pcs CSH card3 pcs IFU2 card1 pcs EM6F card
RTN950RTN950
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 11
Contents
Swap Scenario analysis
Swap Process
2
3
Swap Principles and Strategy1
Rollback Process4
Proposed Solution
9
Risk Analysis5
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 12
Scenario Analysis for WiMAX site SwapBased on the experience of Huawei Swap Project, 4 scenarios for the BTS Swap are provided as follows: Easy swap mean that There is extra space, power and accessibility for new DBS3900. The reverse is hard swap
Scenario No.Scenario Definition
Swap Type TX Antenna Space Indoor (space, power)Down Time
Person RemarksGF RT
1 A YES YES YES 2h 1-
2 B YES No YES 5h 3h 3-
3 C No No YES 5h 4h 3
4 D No No No 6h 6h 3-
Note:“A” means “classification A, Easy Swap & high priority”;“B” means “classification B, Hard Swap & Second priority”;MDT will apply by cluster, and Down time of cluster should consider by maximum down time of site
Click hereFor more information
Click hereFor more information
Click hereFor more information
Click hereFor more information
Please click here to go to WiMAX and MW Combined Scenarios
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 13
DBS3900 site Swap Scenario A�Easy Swap-A, with Extra Transmission, Space & Power:� Definition.
� There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS.
� There have transmission for Huawei DBS3900 to commissioning (use existing IDU or Mobily switch)
� Key point•Completing civil work in advance (Outdoor RRU rack, Minor civil work)•Lay out jumper, Feeder, fiber cables & power cables in advance.•Completing the hardware installation and commissioning (integration) of Huawei DBS3900 in advance(DBS3900, RRU, DC-Box & Antenna), and block huawei’s cells•Downtime•Site downtime ≈2 hour•deactivate all sectors of sumsung’s wimax site remotely•Active Huawei’s blocked sectors remotely•Drive test, confirm service is normal and put site on air.•Power off Samsung BTS
Go back Main menu
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 14
DBS3900 site Swap Scenario B�Hard Swap, with Extra Transmission, indoor space, power:� Definition.
• There have extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS.• There have No Extra space for Huawei antennas•Key point•Completing Civil work in advance (Outdoor RRU rack, Minor civil work)•Lay out jumper, Feeder, fiber cables & power cables in advance •Completing the hardware installation and commissioning (integration) of Huawei DS3900 in advance(DBS3900, RRU, DC-Box),and block huawei’s cells•Downtime•site downtime ≈5 & 3 hour•Power off Samsung BTS•Remove sumsung’s antennas and install huawei’s antennas •Unblock huawei’s cells remotely and do the drive test•Confirm service is normal and put site on air
Go back Main menu
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 15
DBS3900 site Swap Scenario C�Hard Swap, with Extra indoor space, power:� Definition.
• There have extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS.• There have No Extra transmission for Huawei DBS3900 to commissioning & No Extra space for Huawei antennas
� Key point•Completing Civil work in advance (Outdoor RRU rack, Minor civil work)•Completing the hardware installation and commissioning of Huawei DS3900 locally in advance(DBS3900, RRU, DC-Box)
•Lay out jumper, Feeder, fiber cables & power cables in advance � Downtime
•site downtime ≈5 & 4 hour•Power off sumsung’s BTS •Remove sumsung’s antennas and install Huawei’s antennas•Cutover transmission from Samsung BTS to Huawei DBS3900•integrate this site locally and unblock cells•Do Drive Test and confirm service is normal, then put site on air
Go back Main menu
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 16
DBS3900 site Swap Scenario D�Hard Swap:� Definition.
• There is no extra footprint for Huawei DBS3900 installation. � Key point
•Completing Civil work in advance (Outdoor RRU rack, Minor civil work)•Lay out jumper, Feeder, fiber cables & power cables in advance•Completing the hardware installation (BBU and DCDU within MDT time)
� Downtime•site downtime ≈6 hour•Sumsung’s team Power off sumsung’s BTS and remove their equipment•Remove sumsung’s antennas and install Huawei’s antennas•Install huawei’s BBU and DCDU in space position and power on huawei’s DBS3900•Do commissioning and integration locally•unblock cells•Do Drive Test and confirm service is normal, then put site on air
Go back Main menu
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 17
ScenarioScenarioScenarioScenario DescriptionDescriptionDescriptionDescription Advantage Risks Remarks
Scenario 1Install and then dismantle(Temp
frequency available)
This solutions is available . All the Installation and alignment can be done without MDT. It can be roll back
Small risk when MDT
Scenario 2Install and then dismantle(Temp
frequency unavailable)
This solutions is available when there is no Temp frequency. It can be roll back
Alignment time depending on the size of new antenna . Medium risk.
Scenario 3Direct swap then
install new link
This solution is available when there is no space available on the original infrastructure and no space to erect a new structure on the tower.
Link outage vary from case to case, depending on the size of the newly install antenna and path distance. And it can not be roll back. High risk.
Scenario 4 Re-rout
The outage downtime is short in solution. The link only stays down during the cutover. After re-routing, it can release some spaces on the congested infrastructure for future swap.
Need new licensed frequency and LOS risk .
MW Swap Scenario: Please click here to go to WiMAX and MW Combined Scenarios
Click hereFor more information
Click hereFor more information
Click hereFor more information
Click hereFor more information
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
MW Swap Scenario 1:To have enough space to install new Microwave antenna and use temp frequency
Swap Solution:� Swap Process (in daytime, First times)
① To Install a new MW link, It is including IDU, ODU, antenna, all of used cable;
② Power on the new link and mute the ODU, then configure the frequency with temp frequency and make the alignment.
③ Configuration the service after finish the alignment .④ Power off the new link.
New antenna candidate place: another side →
up↗
down↘
existing antenna
Go back Main menu Next Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
MW Swap Scenario 1 To have enough space to install new Microwave antenna
and use temp frequency
●●●●Swap Process (in midnight MDT time.)
① Power off the original microwave equipment link
② Power on the new microwave link and configure the
frequency as perdesign again;
③ After finish step 2, connect Lan cable(fiber) to Winmax
and
monitor it.
Go back Main menu Previous Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
MW Swap Scenario 2:To have enough space to install new Microwave antenna and use existing link frequency, namely have no temp frequency
Swap Solution:� Swap Process (in daytime, First times)
① To Install a new MW link, It is including IDU, ODU, antenna, all of used cable;
② Power on the new link and mute the ODU, then configure the frequency with original frequency and service.
③ Power off the new link.
New antenna candidate place: another side →
up↗
down↘
existing antenna
Go back Main menu Next Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
MW Swap Scenario 2 To have enough space to install new Microwave antenna
and use existing link frequency, namely have no temp
frequency
●●●●Swap Process (in daytime MDT time, the second times,
Downtime is from 5 hours to more than 8 hours, It depends
on the antenna size.)
① Power off the original microwave equipment link
② Power on the new microwave link and make alignment;
③ After finish step 2, connect Lan cable(fiber) to Winmax
and
monitor it.
Go back Main menu Previous Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
MW Swap Scenario 3
No enough space to install new Microwave antenna and mounting pole
Swap Solution:
� Swap Process (in daytime, First times)
① To install a new IDU and other indoor equipment and used cable. And prepare ODU&antenna.
② Test hardware and finish site configuration of IDU separately in each site.
Go back Main menu Next Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
MW Swap Scenario 3
No enough space to install new Microwave antenna and
mounting pole on tower.
� Swap Process (in midnight, the second times, Downtime is
from 5 hours to more than 8 hours, It depends on the
antenna size. )
①Power off the original microwave equipments and
dismantle existing link. Then install new antenna&ODU
rapidly;
②Power on new microwave equipments and make
alignment;
③Configure the service and connect lan(fiber) cable to
Wimax, especially check new MW link status.Go back Main menu Previous Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Site Swap Scenario 4No enough space to install new Microwave antenna on the existing radio’s tower leg to the existing far-end site, but has spaces on other tower legs which can be utilized to divert the traffic to adjacent chains.
Swap Solution:
� Swap Process (in daytime, First times)① To install a new mounting pole for microwave antenna on other tower
legs.② To install a new MW link including IDU, ODU, antenna, all of used
cable;③ MW pre-commissioning with new frequency to ensure operation
availability;④ To Configure the Ethernet service and ping each other between Near
site and far-site.
Go back Main menu Next Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 25
Site Swap Scenario 4
No enough space to install new Microwave antenna on the
existing radio’s tower leg to the existing far-end site, but
has spaces on other tower legs which can be utilized to
divert the traffic to adjacent chains.
� Swap Process (in midnight, the second times)
①Power off the original microwave equipments;
②Power on new microwave equipments;
③Configure the existing frequency to Huawei microwave
equipment.
Go back Main menu Previous Page
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Combined Scenarios for WiMAX and MW
SerialNo.
Swap Type
WiMAX Scenario Definition MW Scenario Definition
Scenario TX AntennaSpace
Indoor(space,power)
Scenario
Temp Freq AntennaSpace
Re-Routing Required
1 A1 A YES YES YES 1 YES YES No2 A2 A YES YES YES 2 No YES No3 A3 A YES YES YES 3 N/A No No4 A4 A YES YES YES 4 N/A No Yes5 B1 B YES No YES 1 YES YES No6 B2 B YES No YES 2 No YES No7 B3 B YES No YES 3 N/A No No8 B4 B YES No YES 4 N/A No Yes9 C1 C No No YES 1 No YES No
10 C2 C No No YES 2 No YES No11 C3 C No No YES 3 N/A No No12 C4 C No No YES 4 N/A No Yes13 D1 D No No No 1 No YES No14 D2 D No No No 2 No YES No15 D3 D No No No 3 N/A No No16 D4 D No No No 4 N/A No Yes
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
1. Scenario A1• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei
DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. Also for MW the temp freq is available as well as the space on tower for installation of antennas before MDT.
• Key points: – 1) Install WiMAX BTS and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Finish LOS for MW before MDT using Temp frequency.– 4) Install WiMAX antennas and out door equipment before MDT.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario A1 , please click here.– For Details on MW Equipment Handling in Scenario A1 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
2. Scenario A2• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei
DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.
• Key points: – 1) Install WiMAX BTS and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Install WiMAX antennas and out door equipment before MDT.– 4) Finish LOS during MDT using the existing frequency.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario A2 , please click here.– For Details on MW Equipment Handling in Scenario A2 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
3. Scenario A3• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei
DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.
• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Install WiMAX antennas and out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW)– 5) Finish LOS during MDT using the existing frequency.– 6) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 7) Test Service.– 8) Dismantle the existing WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario A3 , please click here.– For Details on MW Equipment Handling in Scenario A3 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
4. Scenario A4• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei
DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.
• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Install WiMAX antennas and out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW)– 5) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due
to capacity planning or have losses in the link. Need Re-Routing.– 6) Finish Re-Routing.– 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 8) Test Service.– 9) Dismantle the existing WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario A4 , please click here.– For Details on MW Equipment Handling in Scenario A4 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
5. Scenario B1• Definition: There is extra indoor space , power and accessibility to allow Installation of the Huawei
DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. Also for MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT.
• Key points: – 1) Install WiMAX BTS (indoor + RRU) and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Finish LOS for MW before MDT using Temp frequency.– 4) Install WiMAX antennas during MDT after dismantling existing antenna’s.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario B1 , please click here.– For Details on MW Equipment Handling in Scenario B1 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
6. Scenario B2• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900
parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.
• Key points: – 1) Install WiMAX BTS (excluding antennas) and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Finish LOS during MDT using the existing frequency.– 4) Install WiMAX antennas during MDT.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario B2 , please click here.– For Details on MW Equipment Handling in Scenario B2 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
7. Scenario B3• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900
parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.
• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT using existing transmission.– 3) Install WiMAX out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW).– 5) Install WiMAX antennas during MDT (Replacing Existing Antennas).– 6) Finish LOS during MDT using the existing frequency.– 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 8)Test Service.– 9) Dismantle the existing WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario B3 , please click here.– For Details on MW Equipment Handling in Scenario B3 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
8. Scenario B4• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900
parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.
• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT using existing transmission.– 3) Install WiMAX out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW)– 5) Install WiMAX antennas during MDT. (Replacing existing antennas)– 6) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due
to capacity planning or have losses in the link. Need Re-Routing– 7)Finish Re-Routing.– 8) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 9) Test Service.– 10) Dismantle the existing WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario B4 , please click here.– For Details on MW Equipment Handling in Scenario B4 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
9. Scenario C1• Definition: There is extra indoor space , power and accessibility to allow Installation of the Huawei
DBS3900 parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. Also for MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT.
• Key points: – 1) Install WiMAX BTS (indoor + RRU) and MW before MDT.– 2) Finish LOS for MW before MDT using Temp frequency.– 3) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 4) Install WiMAX antennas during MDT after dismantling existing antenna’s.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6)Test Service.– 7) Dismantle the existing MW and BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario C1 , please click here.– For Details on MW Equipment Handling in Scenario C1 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
10. Scenario C2• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900
parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.
• Key points: – 1) Install WiMAX BTS (excluding antennas) and MW before MDT.– 2) Finish LOS during MDT using the existing frequency.– 3) Commission WiMAX BTS during MDT by swpping transmission with existing BTS.– 4) Install WiMAX antennas during MDT.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario C2 , please click here.– For Details on MW Equipment Handling in Scenario C2 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
11. Scenario C3• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900
parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.
• Key points: – 1) Install WiMAX BTS (excluding antennas) before MDT.– 2) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 3) Install MW during MDT. (Replacing existing MW).– 4) Install WiMAX antennas during MDT (Replacing Existing Antennas).– 5) Finish LOS during MDT using the existing frequency.– 6) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 7)Test Service.– 8) Dismantle the existing WiMAX BTS during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario C3 , please click here.– For Details on MW Equipment Handling in Scenario C3 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
12. Scenario C4• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900
parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.
• Key points: – 1) Install WiMAX BTS (excluding antennas) before MDT.– 2) Commission WiMAX BTS during MDT by swapping transmission of existing BTS.– 3) Install MW during MDT. (Replacing existing MW)– 4) Install WiMAX antennas during MDT. (Replacing existing antennas)– 5) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due
to capacity planning or have losses in the link. Need Re-Routing.– 6) Finish Re-Routing.– 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 8) Test Service.– 9) Dismantle the existing WiMAX BTS and MW during MDT.
• Details:– For Details on WiMAX Equipment Handling in Scenario C4 , please click here.– For Details on MW Equipment Handling in Scenario C4 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
13. Scenario D1• Definition: There is no extra indoor space to allow Installation of the Huawei DBS3900 parallel to the
existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. For MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT.
• Key points: – 1) Install WiMAX BTS (outdoor excluding antenna) and MW before MDT. – 2) Finish LOS for MW before MDT using Temp frequency.– 3) Install WiMAX BTS during MDT by first dismantling existing BTS.– 4) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 5) Install WiMAX antennas during MDT after dismantling existing antenna’s.– 6) Switch off existing MW equipment during MDT and Switch On Huawei Equipment.– 7) Test Service.– 8) Dismantle the existing MW.
• Details:– For Details on WiMAX Equipment Handling in Scenario D1 , please click here.– For Details on MW Equipment Handling in Scenario D1 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
14. Scenario D2• Definition: There is not extra space to allow Installation of the Huawei DBS3900 parallel to the existing
BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.
• Key points: – 1) Install WiMAX BTS (outdoor excluding antennas) and MW before MDT.– 2) Finish LOS during MDT using the existing frequency.– 3) Install WiMAX BTS during MDT by first dismantling existing BTS.– 4) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 5) Install WiMAX antennas during MDT. (Replacing Existing Antennas).– 6) Switch off existing MW equipment during MDT and Switch On Huawei Equipment.– 7) Test Service.– 8) Dismantle the existing MW.
• Details:– For Details on WiMAX Equipment Handling in Scenario D2 , please click here.– For Details on MW Equipment Handling in Scenario D2 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
15. Scenario D3• Definition: There is no extra space to allow Installation of the Huawei DBS3900 parallel to the existing
BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.
• Key points: – 1) Install WiMAX BTS (out door excluding antennas) before MDT.– 2) Install WiMAX BTS during MDT by dismantling existing equipment.– 3) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 4) Install MW during MDT. (Replacing existing MW).– 5) Install WiMAX antennas during MDT (Replacing Existing Antennas).– 6) Finish LOS during MDT using the existing frequency.– 7) Switch off existing MW equipment during MDT and Switch On Huawei Equipment.– 8)Test Service.
• Details:– For Details on WiMAX Equipment Handling in Scenario D3 , please click here.– For Details on MW Equipment Handling in Scenario D3 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
16. Scenario D4• Definition: There is no extra space to allow Installation of the Huawei DBS3900 parallel to the existing
BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.
• Key points: – 1) Install WiMAX BTS (out door excluding antennas) before MDT.– 2) Install WiMAX BTS during MDT by dismantling existing equipment.– 3) Commission WiMAX BTS during MDT by swapping transmission of existing BTS.– 4) Install MW during MDT. (Replacing existing MW)– 5) Install WiMAX antennas during MDT. (Replacing existing antennas)– 6) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due
to capacity planning or have losses in the link. Need Re-Routing.– 7) Finish Re-Routing.– 8) Switch Off existing MW equipment during MDT and Switch On Huawei Equipment.– 9)Test Service.
• Details:– For Details on WiMAX Equipment Handling in Scenario D4 , please click here.– For Details on MW Equipment Handling in Scenario D4 , please click here.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 43
Contents
Swap Scenario analysis
Swap Process
2
3
Swap Principles and Strategy1
Rollback Process4
Proposed Solution
9
Risk Analysis5
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 44
End-to-End Swap Work Process
Driver test and Statistical counters
Network optimization
Customer Acceptance test
Design Review & Benchmarking
Survey & Design
Swap Solution Review
Swap Implementation
Optimization & Acceptance
Develop Swap strategy
Critical Review of existing network design and parameter mapping
Performance benchmarking
Site Survey
Site Audit and related design
Site RF design approval
Complete end-to-end solution
Solution Analysis/Review
Swap solution and approval
Swap preparation
Swap Demo &Training (Sub-Urban)
Implementation
0 3 6 9
12 15 18 21 24 27 30 33 36 39 42 45 48
010
20
30
40
50
60
70
80
90
100
Number of Sites
• Network information collection & assessment
•Radio network survey & engineering survey
•Network swap planning •Swap implementation •Network Monitor and Optimization
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
End-to-End Swap Work Process for WIMAX
WIMAX SWAP SOP V1.1
Cutover Flowchart for SWAP
• Standard Operation Procedure For WIMAX Swap :
• Cutover Flowchart For WIMAX Swap :
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 46
Contents
Swap Scenario analysis
Swap Process
2
3
Swap Principles and Strategy1
Rollback Process4
Proposed Solution
9
Risk Analysis5
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 47
Rollback PrinciplesWiMAX Rollback criteria:
•Base on number of sites unsuccessfull in SWAP cluster
WiMAX Rollback Actions:•Troubleshooting unsuccessfull sites during MDT•Request support to rollback to samsung.
MW Rollback criteria:• Base on number of sites unsuccessfull in SWAP cluster
MW Rollback Actions:
• Troubleshooting unsuccessfull sites during MDT• Request support from Trx team if required.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 48
Contents
Swap Scenario analysis2
Swap Principles and Strategy1
Rollback Process4
Risk Analysis5
Swap Process3
Proposed Solution6
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Risks Analysis
• WiMAX Risks Involved:– On time support required to dismantle existing equipment and incase of rollback.
• MW Risks Involved:• 1. Some Fiber sites are not confirmed. This will affect the LOS &site survey. This still affect our implement
design.• 2. Swap risk:
– Customer request use the existing link’s frequency. It means we will face 2 scenarios: • Enough space to install. Can roll back but can not forecast how long the downtime it will be .• No space to install: first dismantle existing link, then install new link and alignment. This can not roll
back, high risk. And all the work on the tower need to be done in the day time.
• RNP Risks Involved:• In the swap period, everyday the network will have new provisional boundary with Samsung sites.
Because of this the HO KPI may be bad.But for that the wimax service is fixed wireless service so there is not some real heavy affection to the users.
• About the detail performance risk considering and solution preparation, Huawei need to first collect the Samsung current network information then do the analyse and report to Mobily.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 50
Contents
Swap Scenario analysis2
Swap Principles and Strategy1
Rollback Process4
Swap Process3
Proposed Solution6
Risk Analysis5
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Recommended Proposal:
1. Proposal One: – First Swap Wimax Sites– Then Swap MW transmission
2. Proposal Two: (Recommended)– Start Swap Wimax in Region A and SWAP MW in Region B simultaneously .
3. Proposal Three:– Precondition: Match RF cluster with MW link design
• 3.A: First Swap WiMAX according to RF clusters, Once all Wimax sites are Swapped in a particular MW link, then Swap MW for that Link.
• 3.B: Swap Both MW and WiMAX Simultaneously in same RF cluster. (Some sites might be require two or even more MDT’s depending on MW link design)
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Benefits Of Recommended Proposal:
HUAWEI TECHNOLOGIES CO., LTD.
www.huawei.com
Huawei Confidential
Security Level:2011-5-3
Part Part Part Part ---- IIIIIIIIIIIIInstallation Key PointInstallation Key PointInstallation Key PointInstallation Key Point
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
INDOOR EQUIPMENT [Key points]
• Types of indoor equipment include:
– DCDU [DC-Power Distribution Unit]
– BBU [Base Band Unit for WiMAX]
• Transmission Rack in Block-8 Should be utilized for installation unless
specified otherwise. [Block 8 is the right most 60 cm*60cm block when
entering the shelter ]
• 63A fuses should be used to connect DCDU with exist ing DC-
Distribution BOX [DCDB] installed usually on wall i n block 7 of the
shelter.
• If DCDB is full then the direct connection with rec tifier can be made but
power team approval is required from Mobily.
– DCDB uses round fuses while rectifier uses fuse with pins on top and
bottom.
Page 54
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
DCDU
Page 55
•Has 9 power outputs = Load 0- Load 5 for RRU , Load 6,7 for BBU power1&2Leave the last one blank•Should leave 1U gap between Equipments for cable routing and heat dissipation•Proper Labeling required as shown in picture
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
BBU 1/2
Page 56
FAN
UPEU0
Slot7 BMPT
Slot6 reserved
Slot4 USCU
UPEU1
Slot5
Slot0 BBBI
Slot1
Slot2 BBBI
Slot3
BMPT = Main Processing and transmitting UnitBBBI = Base Band Processing and Radio interface UnitUPEU = Universal power and Environmental Interface Unit
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
BBU 2/2
Page 57
BBBI CPRI0 for fiber connections to RRU
BMPT FE/GE0 for transmission [Mw IDU or Cisco Switch]GPS for GPS signal cableETH for Local commissioning
UPEUPWR for power connection with DCDUMON1/2 Input and output of environment alarm signals.EXT-ALM Boolean-value signals and monitoring the ext environment.
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
OUTDOOR EQUIPMENT [Key points]
• Outdoor Equipments Include:
– RRU
– GPS Antenna
– Antenna RF
– Combiner
• GPS should be connected to BBU through antenna arre stor.
• Color Coding for feeder Antenna – Combiner , and CPR I for RRU – BBU is
extremely important to get rid of any cross connect ions.
• Swap Sites = RF Antenna azimuth for Existing [Samsu ng] Antennas should be
noted before installation of Huawei RF antennas.
• Three RRU power cables should be routed in one PVC pipe.
• Three RRU CPRI cables should be routed in one PVC p ipe.
• Its important to note RRU type Wimax/LTE , before i nstalling on pole/rack.
Page 58
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU
Page 59
WiMAX RRU:
2614MHz~2624
MHz
TD-LTE RRU:
2582MHz~2602
MHz
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 60
1.RRU Rack overview - 1
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
1.RRU Rack overview - 2
Page 61
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU Installation 1/3
Page 62
Main bracket
Auxiliary bracket Main bracket
2
Auxiliary bracket
Main bracket 1
LTE RRU
Wimax RRU
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU Installation 2/3
Page 63
LTE TDD RRU
WiMAX TDD RRU
Same direction
WiMAX TDD RRU
1 2
3 4
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU Installation 3/3
Page 64
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Combiner
Page 65
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU- Combiner Connection
Page 66
LTE TDD RRU
BD
CA
ANTA_TX/RXANTB_TX/RX
BD C A
AD D A
BC C B
WiMAX RRU
Bottom View of LTE RRU
Top View of Combiner
ANTA_TX/RX
BD C A
AD D A
BC C B
Bottom View of WiMAX RRU
Top View of Combiner
NOTE :
COMBINER ALWAYS TO BE INSTALLED ON LTE SIDE OF THE POLE !!!
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Antenna
Page 67
Bottom View of Antenna and Combiner
A B DC
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Antenna Installation [Color Coding]
Page 68
Sector 2 Yellow Sector 3 BlueSector 1 RedSector 2 Yellow Sector 3 BlueSector 1 Red
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
GPS Antenna Installation
• The location requirements for installing the GPS antenna are as follows:– Install the GPS antenna in open
air. The installation place should have no obstacles at the angle of 10° above the horizon.
– Keep the antenna away from high buildings and accessory construction on the roof.
– Install the GPS antenna on a platform as large as possible. The antenna must have an upright visual angle greater than 90°.
Huawei Technologies
LTE BMPT
WIAMX BMPT
Note :In phase 1 we just leave this cable there because we don’t insert the LTE board yet.In phase 2 we can do the connection
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
1) Total RRU’s = 6 [3 for Wimax, 3 for LTE ]2) Total CPRI’s required = 9 [3 for Wimax , 6 for L TE ] which means each WiMAX RRU will use only 1 CPRI and each LTE RRU will us e 2 CPRI’s.3) For Project Phase 1 [Wimax 30MHZ]CPRI connection will be as follows:WiMAX RRU Sector 0 : no connection WiMAX RRU Sector 1 : no connectionWiMAX RRU Sector 2 : ConnectionLTE RRU Sector 0 : Connection [CPRI 0 only]LTE RRU Sector 1 : Connection [CPRI 0 only]LTE RRU Sector 2 : no Connection4) For Project Phase 2 [Wimax 10MHZ, LTE 20 MHZ]WiMAX RRU Sector 0 : ConnectionWiMAX RRU Sector 1 : ConnectionWiMAX RRU Sector 2 : ConnectionLTE RRU Sector 0 : ConnectionLTE RRU Sector 1 : ConnectionLTE RRU Sector 2 : Connection
Page 70
RRU-BBU Connection 1/2
WiMAX RRU:
2614MHz~2624MHz
TD-LTE RRU:
2582MHz~2602MHz
RRU Phase-1
[Wimax 30 MHZ]
Wimax Sector
0
Wimax Sector
1
Wimax Sector
2
LTE Sector
0
LTE Sector
1
LTE Sector
2
BBU Slot 3
BBBI CPRI 0 X X X Yes X XBBBI CPRI 1 X X X X Yes XBBBI CPRI 2 X X Yes X X X
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU-BBU Connection 2/2
Page 71
From LTE CPRI_0From LTE CPRI_1 From WiMAX CPRI_0
Please put the remaining cable under BBU rack orderly!
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU-BBU Connection Phase-1[Wimax 30MHz]
Page 72
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
RRU-BBU Connection Final
Page 73
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Optical Cables – CPRI color coding
Page 74
LTE CPRI fiber sector1(0,1) sector 2(0,1)
sector 3(0,1)
CPRI_0
CPRI_1
1
0
WiMAX CPRI fiber sector1, sector 2, sector 3
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Connect the TX cable to MW IDU
Page 75
WiMAX BMPT Board:
Huawei MW IDU Service Board:
Nera MW IDU:
Note :The reserved IDU port will be finalized after confirm with Mobily
ETH-PortOptical-Port
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Inserting LTE boards to BBU
Page 76
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
Changing Cable Connection for LTE
Page 77
LTE CPRI_0LTE CPRI_1
Original connection:
Target connection:
HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential
www.huawei.com
3 May 2011