In-Line Cell Manager Configuration and Loading Date: Octobre2014.

Post on 25-Dec-2015

219 views 1 download

Tags:

transcript

In-Line Cell Manager Configuration and Loading

Date: Octobre2014

2

Cell Manager Configuration Module

• CoreView In Line Software consists of two main Modules• Measurement Unit (CoreView Teach for In-Line)• Cell Manager

• On each computer which is connected to the WLS400A system, the Measurement Unit is installed

• The Cell manager is installed on one of the units computer.

• In-Line configuration of both Units and the Cell Manager is done through a configuration module: C:\Cognitens\bin64\Inline.Configuration.UI.exe which is executed in the Cell Manager Unit.

3

Configuration Interface

Computer Name

Cell NameHas to be the same in all Cell Units

Unit Name

Press for Cell Manager Configuration

Important:Don’t forget to press Apply after you finish with all the configuration.

4

Cell Manager Configuration

Path to result file generated in XML format. (For Back compatibility)

5

Cell Manager Configuration

GateWay Computer IP Address

6

Cell Manager Configuration

Currently only Diagnostic report is supported

7

Cell Manager Configuration

No Change Required

8

Configuration Interface

Press to configure Units

Important:Don’t forget to press Apply after you finish with all the configuration.

9

Unit Configuration

Full Path to local CTP. Including computer nameMultiple CTP supported

10

Unit Configuration

DataServer Computer name. IP address is also supported

11

Unit Configuration

No Change Required

12

Unit Configuration

Full path to Bundle Folder. Has to be the same on both units

13

Load In-Line Measurement System

• To Load the In-Line Measurement System run: C:\Cognitens\bin64\Inline.Cell.UI.exe

• The In-Line Cell UI enables:• Loading\Unloading all the Measurement In-Line process• Review the existing bundles and set the Delete option for

the output data (this includes all the images and point cloud)

• Once the Loading off all the processes is done the system is ready to execute In-Line measurement process

14

Load In-Line Measurement System – Bundle Configuration

Red Bundles are marked Not to delete automatically

This will delete the outputs on both computers after the results are generated

Use this to delete existing outputs which were not deleted automatically

15

Load In-Line Measurement System

Press to start the process

16

Load In-Line Measurement System

Press to Stop the process

All Process have to be Green and ReadyAnd Cell Manager Connected to GateWay