Industrial Commission Update

June 20, 2019

Justin J. KringstadGeological Engineer

Director

North Dakota Pipeline Authority

2

Statewide Initial Oil Production Rates – 24hr

JJ Kringstad - North Dakota Pipeline Authority 2

3

Bakken/Three Forks Initial Production Rate: 24hr

JJ Kringstad - North Dakota Pipeline Authority 3

4

4,000+ BOPD 24hr Initial Production Rates

JJ Kringstad - North Dakota Pipeline Authority 4

5

Statewide Gas Performance

JJ Kringstad - North Dakota Pipeline Authority 5Average BKN/TF Well Performance Statewide

~12% Improvement

Over 2017

6

Statewide Initial Gas Production Rate: 24hr

JJ Kringstad - North Dakota Pipeline Authority 6

Bakken and Three Forks Gas Performance

JJ Kringstad - North Dakota Pipeline Authority 7

8JJ Kringstad - North Dakota Pipeline Authority 8

Top 20 IP Rates (Oil)

9JJ Kringstad - North Dakota Pipeline Authority 9

Top 20 IP Rates (Oil)

10JJ Kringstad - North Dakota Pipeline Authority 10

Top 20 IP Rates (Oil)

11JJ Kringstad - North Dakota Pipeline Authority 11

Top 20 IP Rates (Oil)

12JJ Kringstad - North Dakota Pipeline Authority 12

Top 20 IP Rates (Oil)

*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.

13JJ Kringstad - North Dakota Pipeline Authority 13

Top 20 IP Rates (Oil)Electrical Submersible Pump (ESP) Timeline

14JJ Kringstad - North Dakota Pipeline Authority 14

Impact of ESP on Production ProfilesWell: SIBYL USA 44-19TFH (Mountrail County)

*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.

15JJ Kringstad - North Dakota Pipeline Authority 15

Impact of ESP on Production ProfilesAdditional Examples

*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.

Well File: 32012 Well File: 33942

16JJ Kringstad - North Dakota Pipeline Authority 16

High Initial Production (IP) Scenarios

“Typical” type curve used as a

comparison example for how

high IP wells may perform

over time.

In this example, the entire

production curve over time is

uplifted relative to a “typical”

well. Well economics and

EUR are both improved.

In this example, only the early

life of the well is higher

relative to a “typical” well.

Early well economics improve,

but uncertainty exists if EUR

will improve or suffer with the

high IP rate.

In this example, the early life

of the well is higher relative to

a “typical” well. Early well

economics improve along with

an incremental EUR

improvement.

17JJ Kringstad - North Dakota Pipeline Authority 17

Oil IP Bin Comparison

*Month “0” is a partial month with daily production calculated using “Days on production”. Months 1+ use calendar days to calculate daily rate.

18JJ Kringstad - North Dakota Pipeline Authority 18

Oil IP Bin Comparison

19JJ Kringstad - North Dakota Pipeline Authority 19

Oil IP Bin Comparison – “Clean”

20JJ Kringstad - North Dakota Pipeline Authority 20

Oil IP Bin Comparison – “Clean”

21JJ Kringstad - North Dakota Pipeline Authority 21

Economic Incentive to Higher IP RatesExample: Payout Period Using $7 million well cost

22JJ Kringstad - North Dakota Pipeline Authority 22

Economic Incentive to Higher IP RatesExample: Rate of Return Using $7 million well cost

23JJ Kringstad - North Dakota Pipeline Authority 23

Economic Incentive to Higher IP RatesExample: Breakeven Pricing Using $7 million well cost

Cushing $56.74

Brent $64.23WTI + $7.49

Crude Oil Prices – June 20, 2019

24JJ Kringstad - North Dakota Pipeline Authority

Pricing Data: Bloomberg &

CME (LLS-Argus)Houston WTIWTI + $6.81

JJ Kringstad - North Dakota Pipeline Authority 24

North Dakota Oil Pricing

2525JJ Kringstad - North Dakota Pipeline Authority 25

US Crude Oil Storage Volumes and Spot Prices

2626JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 26

EIA Forecasted Oil Price

2727JJ Kringstad - North Dakota Pipeline Authority 27

2828JJ Kringstad - North Dakota Pipeline Authority 28

North Dakota Oil Production Forecast Assumes Current Technology – Enhanced Oil Recovery Not Included

2929JJ Kringstad - North Dakota Pipeline Authority 29

Major Oil Transmission Systems

Williston Basin Oil Production & Export Capacity, BOPDAssumes Current Technology – Enhanced Oil Recovery Not Included

Production forecast is for visual demonstration purposes only and should

not be considered accurate for any near or long term planning.

3131JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 31

Exact DAPL Expansion Timeline(s) Unavailable

32JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 32

Upcoming or

Recent Plant

Expansion

WBI Transmission

Andeavor

Major Gas Pipeline and Processing Infrastructure

WBI Energy – North Bakken Expansion Project

JJ Kringstad - North Dakota Pipeline Authority 33

Project Highlights

• 67 Miles - 20” Pipeline

• 19 Miles - 12” Pipeline

• $220+ Million

• 250,000 MCFD Capacity (expandable)

• Expandable to 375,000 MCFD

• End of 2021 Proposed Completion

• Residue Gas Service From North of

Lake Sakakawea to Northern Border

Pipeline in McKenzie County

WBI Energy – North

Bakken Expansion Project

JJ Kringstad - North Dakota Pipeline Authority 34

Project Highlights

• 67 Miles - 20” Pipeline

• 19 Miles - 12” Pipeline

• $220+ Million

• 250,000 MCFD Capacity (expandable)

• Expandable to 375,000 MCFD

• End of 2021 Proposed Completion

• Residue Gas Service From North of

Lake Sakakawea to Northern Border

Pipeline in McKenzie County

JJ Kringstad - North Dakota Pipeline Authority 35

Northern Border Pipeline

*Data Source: Northern Border IPS

• 42” Pipeline

• Carries Canadian (Port of Morgan) and Domestic Gas

• Receives Gas From ND Plants, WBI Transmission Interconnections, and WY Pipelines (Bison & Grasslands)

• Midcontinent Deliveries

JJ Kringstad - North Dakota Pipeline Authority

Simplified Example NB CalculationsConclusion: IF no other gas export options open and all other deliveries on other pipelines stay static, ND

gas production could increase 0.82-1.12 BCFD (from April-19) before Northern Border is 100% Bakken

production. BTU management becomes increasingly important for Bakken residue gas.

36

Northern Border Proposed Expansion Options

JJ Kringstad - North Dakota Pipeline Authority 37

Two Proposed Options:

Stateline/Watford City to Ventura

-580 Mdth Incremental (~525 MMCFD)

-Phase 1: Q3 2021

-Phase 2: Q4 2023

Stateline/Watford City to Cheyenne

-430 Mdth Incremental (~390 MMCFD)

-Phase 1: Q3 2021

-Phase 2: Q4 2022

Simplified Example NB CalculationsConclusion: IF no other gas export options open and all other deliveries on other pipelines stay static, ND

gas production could increase 0.82-1.12 BCFD (from April-19) before Northern Border is 100% Bakken

production. BTU management becomes increasingly important for Bakken residue gas.

• Gas Plants With C2+ Capture

~1,010+ BTU Residue Gas

• Gas Plants With C3+ Capture

~1,150+ BTU Residue Gas

JJ Kringstad - North Dakota Pipeline Authority 38

Bakken Natural Gas Infrastructure

3939JJ Kringstad - North Dakota Pipeline Authority 39

Regional NGL Infrastructure

Kinder

JJ Kringstad - North Dakota Pipeline Authority 40

North Dakota Captured* NGL’s

4141JJ Kringstad - North Dakota Pipeline Authority 41*Non-flared NGL’s & Assumes 10 GPM

NGL Pipeline Takeaway Options

42

4242JJ Kringstad - North Dakota Pipeline Authority 42

ONEOK Elk Creek NGL Pipeline

Project Highlights

• 900 Miles - 20” Pipeline

• $1.4 Billion

• 240,000 BPD Capacity

• Expandable to 400,000

BPD

• End of 2019 Proposed

Completion

• Y-Grade Transportation

JJ Kringstad - North Dakota Pipeline Authority 43

Justin J. Kringstad, DirectorNorth Dakota Pipeline Authority

600 E. Boulevard Ave. Dept. 405Bismarck, ND 58505-0840

Phone: (701)220-6227Fax: (701)328-2820

E-mail: jjkringstad@ndpipelines.com

Websites: www.pipeline.nd.gov

www.northdakotapipelines.com

Contact Information

JJ Kringstad - North Dakota Pipeline Authority 44