Industry briefing19 April 2018
Johanna Hall
Executive Director Systems and Resources Sydney Metro
Welcome to Country
1. Minister for Transport & Infrastructure
2. Transport for NSW update
3. Sydney Metro overview and Northwest project update
4. Sydney Metro West project update
5. Sydney Metro City & Southwest project update
6. Questions and answers
Overview
The Hon. Andrew Constance MP
Minister for Transport and Infrastructure
Rodd Staples
Secretary Transport for NSW
Getting the planning right
Pursuing innovation
Making better places
Circular Quay renewal Redfern Precinct renewal Central Precinct renewal
Developing the pipeline
Working with industry
Graph
provided by
Macromonitor
Delivering connectivity with networks
Driving accountability and capability
Tom Gellibrand
A/Program Director Sydney Metro
• North South Rail Line – Schofields to Macarthur
• North South Rail Line Stage 1 St Marys to Badgerys Creek Aerotropolis (North Bringelly)
• Stage 1: committed 50:50 funding by State and Federal governments
• Scheduled to open in 2026 to support day one of airport operation
North South Rail Line
World class metro Vibrant places
Great service
Easy connections
Customer
Sydney Metro
Northwest
Great service
Metro train testing
100% of tunnel track is complete
More than 95% of total track has been laid
Easy connections
Stations taking shape
Cudgegong Station precinct south
Vibrant places
Legacy
Sustainability
Workforce Development
Aboriginal participation
SAFETY & WELLBEING COLLABORATION INTEGRITY
INNOVATION EXCELLENCE ACHIEVEMENT
Brendon Baker
Project Development Director Sydney Metro West
World class metro Vibrant places
Great service
Easy connections
Customer
Delivering new metro rail for Sydney
Industry Engagement Stage 1
Shaping the project scope
Metro West Initial Delivery Strategy
Key stages
2nd stage of industry engagement: 26 March 2018 to 18 May 2018
Next steps
Register interest using online form sydneymetro.info/industry
Registration closes 5pm, 23 April 2018
Face-to-face meetings and survey late April and May 2018
Contact the industry team: industry.sydneymetro@sydneymetro.info
Tim Parker
Project Director Sydney Metro City & Southwest
Tunnel and station excavation works
Central Station Main Works
Easy connections
Lifts and escalators
Easy connections
Line-wide works
Waterloo Station TO MARTIN PLACE TO CENTRAL
6 min
TO BARANGAROO
8 min
Artist’s impression only
2 min
Vibrant places
Integrated Station Development Indicative example
Integrated Station Development
Artist’s impression only
TO MARTIN PLACE TO CENTRAL
5 min
TO BARANGAROO
3 min
9 min
Procurement process
Simplified procurement
Authorised Engineering Organisation
City & Southwest procurement timing PACKAGE EOI/ROI RFT
Systems
Line-wide works Complete Released
Lifts and escalators Complete Released
Integrated Station Developments Victoria Cross Complete Released
Pitt Street Q2 2018 Q3 2018
Crows Nest Q2 2018 Q3 2018
Waterloo Q3 2018 Q4 2018
Martin Place1 Q3 2018 Q4 2018
Station Construction
Barangaroo Q4 2019 Q1 2020
Professional services
More information
Questions