ISSUE 41 December 18, 2020 Portico Projects… · 2020. 12. 22. · Portico Projects ISSUE 41...

Post on 05-Sep-2021

2 views 0 download

transcript

Upcoming Activities:

- Gym Goals & Flooring to start

- Counter tops to Install

- Final Painting to continue

- Door & Hardware to Start

- Toilet Partitions and accessories to start

- Plumbing fixture trim out Continues

- Electrical Trim out Continues

- Shade Structure & fencing to start

- North Portico – Asphalt to start

- North Portico – Roofing Continues

- North Portico – Painting continues

- Landscaping to start

Student Center & North

Portico ProjectsISSUE 41 December 18, 2020

Construction Update

Current Activities:

- Electrical Trim out Continues

- Plumbing fixture trim out Continues

- Millwork Continues

- Toilet Partitions and accessories have started

- Gym & Student Common space build back continues

- Final Painting continues

- Flooring Completes

- Sidewalks and curbs Complete

- North Portico – Roofing Continues

- North Portico – Painting starts

- Audio / visual work continues

Accent Painting

at Commons

Baffles at LoungeNew ADA Paving

Toilet partitions

being Installed