Kanban Production Control System. CC cell. MF assembly. Withdrawal Kanban. Production Kanban. Kanban Production Control System. T=0. CC cell. MF assembly. Withdrawal Kanban. Production Kanban. Kanban Production Control System. T=1. CC cell. MF assembly. Withdrawal Kanban. - PowerPoint PPT Presentation

transcript

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=0

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=1

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=1

CT of 1st lot=1+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=2

CT of 1st lot=1+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=2

CT of 1st lot=1+4

CT of 2nd lot=2+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=3

CT of 1st lot=1+4

CT of 2nd lot=2+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=3

CT of 1st lot=1+4

CT of 2nd lot=2+4

CT of 3rd lot=3+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=4

CT of 1st lot=1+4

CT of 2nd lot=2+4

CT of 3rd lot=3+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=4

CT of 1st lot=1+4

CT of 2nd lot=2+4

CT of 3rd lot=3+4

CT of 4th lot=4+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=5

CT of 1st lot=1+4

CT of 2nd lot=2+4

CT of 3rd lot=3+4

CT of 4th lot=4+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=5

CT of 1st lot=1+4

CT of 2nd lot=2+4

CT of 3rd lot=3+4

CT of 4th lot=4+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=6

CT of 1st lot=1+4

CT of 2nd lot=2+4

CT of 3rd lot=3+4

CT of 4th lot=4+4

Kanban Production Control System

MF assemblyCC cell

Withdrawal Kanban

Production Kanban

T=6

CT of 1st lot=1+4

CT of 2nd lot=2+4

CT of 3rd lot=3+4

CT of 4th lot=4+4

CT of 5th lot=6+4