Post on 30-May-2018
transcript
GG-COM-TM-013-A, Rev. 1
LESSONS FROM DECOMMISSIONING PLANNING IN THE UK
Feb 2017Peter Ryall
2 |
Genesis provide advice over the full asset lifecycle to help energy companies maximize the value of their assets worldwide.
Globally, Genesis have worked on over 150 DAR studies & projects in the last 18 years.
As well as supporting energy companies, Genesis have also advised the UK Government, regulators and industry bodies on key areas of DAR planning and cost estimation.
We have developed standardised in-house early phase cost estimating tools for determining DAR liabilities
DAR
DECOMMISSIONING, ABANDONMENT & RESTORATION (DAR) EXPERIENCE
Awarded the MaureenDecommissioning ProjectHazID by Phillips Petroleum
1998 1999 2002 2007 2012 2013 2014 2015 2016201020042000
Sig
nific
ant E
vent
s Awarded the first ever Facilities, Environmental & Decommissioning Support contract by the DTI (UK)
Reference case study to investigateDecommissioning Options for Shell forthe Brent Field
Bayu-Undan Darwin LNG Abandonment Study for Conoco-Phillips (Australia)
Awarded global DAR EFA by ENI to support their global asset portfolio.
Awarded Miller Decommissioning Appraisal Studies by BP
Ichthys Abandonment Cost Estimation Study for INPEX
Flotta Terminal DAR Study for Talisman Energy
Following significant global market interest Genesis embarks on thedevelopment of a proprietary DAR Estimating and Reference database
Commissioned by OGUK to write the Comparative Assessment Guidelines for UK Industry
Completed a DAR Efficiencies Study incorporating a technology review for the OGA.
Total Frigg DAR HSE Studies
3 | DAR
IMPACT OF DAR COSTS – DEPENDS ON THE TIME
FID
At FIDDecommissioning is barely a
blip on the project PV economics
In Late LifeDecommissioning decisions drive the residual value of
the facility
4 |
LATE LIFE PLANNING
Late Life
Objectives:
- Maximise residual value
- Provide certainty in likely costs
- Understand risks & opportunities to allow flexible response to events
Value of Front-End Thinking
5 |
UK PLANNED DECOMMISSIONING 2016-2025
• Approx. £18bn planned between 2016 and 2025.
• 40-50% cost in well P&A.
Source: Oil & Gas UK
6 |
MAXIMISE RESIDUAL VALUE
OPEX
Production
Decom costs
1. There has been a sudden reaction to the reduction in oil price, causing forced decommissioning for some assets leading to possible efficiency losses. Industry and government aligning on best practice.
2. Drilling is a major part of DAR cost and biggest area for savings:
• Wireline logging for scanning linked with stimulation to improve productivity to offset the costs. Early identification of problem wells for P&A.
• Wireline logging and preparation of commissioning can be performed by LWIV for subsea wells.
• Collaboration across assets to give area LWIV campaigns to yield economies of scale
5. For platform removal biggest savings by providing schedule flexibility to lift contractor:
• Early engagement – design competition
• Plan for NUI or Lighthouse mode
7 |
Commence DAR studies early– Refresh early abandonment costs based on latest data– Allow time for investigation of alternative strategies– Provide time for surveys – Allow time for external review and stake-holder engagement for non-conventional
approach
Well Survey to highlight any issues
PROVIDE COST CERTAINTY
8 |
Identify Risks and Opportunities to operation during late field life
Scheduling activities back from a planned cessation of production date reduces flexibility to respond to risks and opportunities:– Product price fall– Competitive vessel rates– Collaborative opportunities
Provide flexibility in Safety Case to permit potential future operating philosophy
DAR
RISK & OPPORTUNITIES
Oil Price VariationUK Topsides Removal Costs
9 |
DECOMMISSIONING REGULATORY OVERVIEW
UK Australia
Regulatory Body BEIS NOPSEMA
Platforms & Other facilities
OSPARStarts with a presumption of complete removal.
Derogation possible for steel jackets and concrete structures through CA process.
OPGGSA
Base case is removal.
Partial removal or abandonment can be considered on a case by case basis if demonstrated to be ALARP and at an acceptable level.Pipelines OSPAR
Case by case dependent on the outcome of agreed CA.
CA Comparative Assessment
BEIS Dept. Business, Energy and Industrial strategy
NOPSEMA National Offshore Petroleum Safety and Environmental Management Authority
10 | DAR
UK COMPARATIVE ASSESSMENT (CA)
Recommend
Safety• Decom
Personnel• Other users of
the sea• During decom /
post-decom
Environment• Discharges• Resource
consumption• Long-term
environmental impact
Technical• Maturity of
scope• Technology
Readiness
Societal• Impact on
activities eg. Fishing
• Provision of jobs or infrastructure
Economic• Cost• Risks &
Uncertainties
Evaluate
Studies
Coarse Screening
Screening Criteria
Identify Options
A B C D
B
A B C D
Independent Review
Stakeholder Engagement
Cost estimation tools
Environmental and safety studies
11 |
Undertake DAR studies early:– to identify main cost drivers and investigate ways to reduce costs.– Allow time for surveys and stakeholder engagement if non-standard approach taken– Allows flexibility to accelerate or defer or change plans to react to risks or opportunities
Apply Front-End thinking to optimise late-life activities: Release synergies between OPEX, production enhancement and decommissioning costs
Regular review of plans to account for changed circumstances
Comparative assessment process yields basis to support an ALARP position for Australian projects
DAR
CONCLUSIONS
THANK YOU
Contact usEnquiries can be directed to: peter.ryall@genesisoilandgas.com+61(0)8 9320 0177