Agenda Item #4 11/19&20/01 MC Mtg. LMP Base Cases Presented to: NEPOOL Markets Committee November 19, 2001 Robert B. Burke. Contents. LMP Publishing Process LMP Overview Static Base Case What was analyzed? How it was analyzed Summary of Results Next Steps. Static Cases. Purpose: - PowerPoint PPT Presentation

transcript

LMP Base Cases

Presented to:

NEPOOL Markets Committee

November 19, 2001

Robert B. Burke

Agenda Item #411/19&20/01 MC Mtg.

Contents

• LMP Publishing Process

• LMP Overview

• Static Base Case– What was analyzed?

– How it was analyzed

– Summary of Results

• Next Steps

Static Cases

• Purpose:– Demonstrate software development progress

– Provide Participants with samples effects of possible

transmission line outage

– Test new unit dispatch software (EMP, UDS/SPD)

Future Releases

• Purpose:– Provide Participants with snapshot of actual system dispatch

with possible LMP values

– ISO will try to choose a dispatch cycle from the prior month with

congestion

– Test changes to new unit dispatch software (EMP, UDS/SPD)

Participant Input

• Technical session to review static cases– December 5 - Springfield Sheraton

– Register on-line at the ISO web site

• Are there additional “static” cases you would like

to see?– Email by December 14:

cstedu@iso-ne.com

– ISO will review suggestions and release results of those cases

analyzed

What is LMP?

• Locational Marginal Price - cost of supplying the

next MW of load

• When congestion is present, locational marginal

prices may be different by zone

3 Bus Example - 1

Generator-1Capacity = 300 MW$10/MW

Generator-2Capacity = 200 MW$15/MW

Generator-3Capacity = 200 MW$20/MW

Load 2 = 499 MWMarket Clearing Price = $20

Load 1 = 100 MWMarket Clearing Price = $20

100 MW

200 MW

400 MW

99 MW

3 Bus Example - 2

Generator-1Capacity = 300 MW$10/MW

Generator-2Capacity = 200 MW$15/MW

Generator-3Capacity = 200 MW$20/MW

Load 2 = 499 MWLMP = $20

Load 1 = 100 MWLMP = $10

Thermal limit 150 MW

150 MW

100 MW350 MW

149 MW

What is Presented?

• Static base case

• Each Analysis Represents a Separate

Transmission Line Outage

• Resulting LMP values

Static Cases

• Started with secure network

• Actual system from September 4, 2001

• Hour Ending 15

• Load 18,375 MW

Data

• Load

• Generation

• Tie line flow

• Units on-line

• Unit bid data

• UDS/SPD agreed with Couger

How analysis was run

• Transmission Line removed from service

• Contingency analysis performed

• Contingencies identified

• Overload identified (binding constraint)

What’s in & What’s not

We included: • Power Flow Model

• Unit Bid Model

and enforced:

• Unit Capacity Limits

• Unit Ramp Rate Limits

• Generic Constraints

We didn’t include:• Transaction Model

• Inc/Dec Bid Model

• Reserve Model

• Market Power Mitigation

Cases Analyzed

Case Primary Transmission Line Removed1 Golden Hills-Mystic (349XY)2 Quaker Hill-Three Rivers 115 kV (197)3 Scobie-Sandy Pond (326)4 Card St.-Lake Road 345 kV (330)5 Norwalk-Northport 138 kV cable (1385)6 Grand Ave-Elm West (89003B)7 E. Springfld-E.Spring.Jct.-Piper 115 kV(1723)8 Canal-Carver St. 345 kV (322)9 Essex-Williston 115 kV (K23)10 Brayton-W. Farnum 345 kV (315)

PIPER

EASTSPRINGFIELD

FAIRMONTNORTH

BRECKWOODWEST

SPRINGFIELDAGAWAM

77

LINE 1723

SHAWINIGANCHICOPEE

LINE 1322

LINE 1254

LUDLOW

ORCHARD

ELM

POCHASSIC

SILVER

LINE 1433

Line 1723(E. Springfield - E. Springfield Junction - Piper)

PRECONTINGENCY STATELMP = $39.59

PIPER

EASTSPRINGFIELD

FAIRMONTNORTH

BRECKWOODWEST

SPRINGFIELDAGAWAM

LINE 1723

SHAWINIGANCHICOPEE

LINE 1322

LINE 1254

197 (193)

LUDLOW

ORCHARD

ELM

POCHASSIC

SILVER

LINE 1433

Line 1723(E. Springfield - E. Springfield Junction - Piper)

CONTINGENCY STATE

PIPER

EASTSPRINGFIELD

FAIRMONTNORTH

BRECKWOODWEST

SPRINGFIELDAGAWAM

LINE 1723

SHAWINIGANCHICOPEE

LINE 1322

LINE 1254

192 (193)

LUDLOW

ORCHARD

ELM

POCHASSIC

SILVER

LINE 1433

Line 1723(E. Springfield - E. Springfield Junction - Piper)

LMP WCMA Zone = $66.62LMP CT Zone = $39.20LMP other Zone = $38.25

SCOBIE

SEA BROOKSANDY POND

LINE 326

LINE 394

LOAD CENTER

GREGGSGREGGSMERRIMACK

LINE A253

LINE 363

LINE B202

LINE R187LINE C196LINE Q171

Line 326(Scobie - Sandy Pond)

PRECONTINGENCY STATELMP = $39.11

SCOBIE

SEA BROOKSANDY POND

LINE 326

LINE 394

LOAD CENTER

GREGGSGREGGSMERRIMACK

LINE A253 315(305)

LINE 363

LINE B202

LINE R187LINE C196LINE Q171

Line 326(Scobie - Sandy Pond)

CONTINGENCY STATE

SCOBIE

SEA BROOKSANDY POND

LINE 363LINE 326

LINE 394

LOAD CENTER

GREGGSGREGGSMERRIMACK

LINEA253

LINE B202

LINE R187LINE C196LINE Q171

302(305)

Line 326(Scobie - Sandy Pond)

LMP ME Zone = $15.50 LMP NH Zone = $31.28LMP WCMA Zone = $40.41 LMP NEMAB Zone = $41.78LMP other Zones = $40.11

Future Analyzes

• Possible additional studies from this static base

case

• Release LMP values for a dispatch cycle once a

month– Zonal LMP values

– Binding Constraints

Need more information?

• SMD Overview and Locational Marginal Pricing

training session– Sessions last week in November and first week in December

• Register on-line– Customer, Seminars and Training