Madison Elementary School DistrictBond Project Update August 2013

Solar Update Madison #1

Solar Update Rose Lane Elementary

Solar Update Park Elementary

Solar - Schedule of Completion

• Structural and panel set- 8/22/13• Broken sidewalk replacement- 8/26/13• Installation of turf and DG- 9/16/13• Substantial completion- 9/23/13• First day of generation- 9/26/13• Final Completion- 10/14/13

The Next Step in Solar

Site evaluations later this weekPreliminary design by 8/29Submitting applications to APS for rebates by 8/30

Rose Lane Café Remodel

Madison Heights Café Remodel

Madison Meadows Site Work

Upcoming Projects

• Madison Heights kitchen remodel• Madison Meadows front office remodel• Non-skid surfacing on exterior stairs• Roof replacement at Heights• Daylighting in dining areas at Heights, Park and Rose Lane