MEASUREMENT OF BUILDING WORK (A)
Task -01
1.1 Any construction work measurement is getting an important place. So we should know important and principles of measurements. We want to get correct and accurate measurement for this we use SMM7 this standard method of measurement provides a uniform basis for measuring building works and ombidies the essentials of good practice. Bills of quantity shall fully describe and accurately represent the quantity and quality of the works to be carried out. More detailed information than is required by these rules shall be given where necessary in order to define the precise nature and extent of the required work.
SMM7’s including following type of information Use of the tabulate rules 1. Generally 2.Classification table Quantities
1. Supplementary rules Descriptions Drawing information Catalogued or standard components Work of special types Procedure where the drawn and specification information required by these rules in
not available Fixing, base and background Composite item Work not covered Symbols and abbreviations Work to existing buildings General definition
For this information we can take measurement easily and quickly so SMM7 is more important for building works.
Principles of measurement practices
For the measurement quantity surveyor using by following stationeries this are called as surveyor’s stationeries.
(1) Query sheet Size- A4
Use- Some dimensions are not including on plan that time asking question for architecture we use this sheet,
Modal-
BCAS Page 1
MEASUREMENT OF BUILDING WORK (A)
QUERY ANSWER
Architect’s Signature: -........................
(2)Dimension sheet Size- A4
Use- Get measurement Modal- 9mm
b.
14mm T
15mm D
16mm S
55mmDis
14mm T
15mm D
16mm S
56mm Des
b. – Binding marginT – Timesing columnD – Dimension columnS – Squaring columnDes – Description column
BCAS Page 2
MEASUREMENT OF BUILDING WORK (A)
MEASUREMENT PROCEDURES
When we entering dimension should fallow following information(1). Spacing of itemEntering two or more separate item we spaced 12mm each
Description
Bk.Wall
Fr. Wk
(2).Waste calculation or method of reaching dimensions
BCAS Page 3
500mm
1000mm
125mm
3000mmm
125mm
12mm Spacing
T D
1.000.50
0.130.133.00
S
MEASUREMENT OF BUILDING WORK (A)
Description
External length
External width 3450
BCAS Page 4
2/225 450
2000
2500
112.5
5062.5
2500
3000
2000
225 112.5
2/225 450
3000
T D S
MEASUREMENT OF BUILDING WORK (A)
(3).Order of dimension
All dimensions are entering in meters with two decimals in dimension column. Dimension is entered in following order.
Horizontal length Horizontal width or breadth Vertical height or depth
Description
L-Length W-Width/breadth H-Height/Depth 02-Number
(4).Timsing
BCAS Page 5
T D
L W H
02
S
T
2/½/
D
5.25 2.10
S
11.025
MEASUREMENT OF BUILDING WORK (A)
Description
(5).Grouping of dimension
BCAS Page 6
Area = ½ × 5.25×2.10
5250
21002100
5250
MEASUREMENT OF BUILDING WORK (A)
Description
Disposal load
Tr. Excn.
&
Disposal of exct. Mat.
BCAS Page 7
850
10000
1000
A1 A2
1500
10001500
2000
T D
10.00 0.85 1.00
1.001.501.502.00
S
11.764
1.50
3.004.50
MEASUREMENT OF BUILDING WORK (A)
Bk.Wall
(6).Alternative of dimension
Description
BK.Wall. NIL
(7).Measurement of irregular figures
BCAS Page 8
T D
XXX XXX XXX XXX
S
- -NIL -
MEASUREMENT OF BUILDING WORK (A)
Description
r=225
Task-01
1.3 Indentify and describe the major part of a bill of quantities (P3)
After entering Abstract sheet next we use bill page so BOQ has major 5patrs these are follows 1). Preliminaries
Preliminaries Items we separate two parts.
Not specific to work section Specific to work sectionThis items not specific to work section but This items are specific to work sections on
BCAS Page 9
A
r r=1500
A=πr2
2000
1500
A= ½ ×A×H
2000
4000
1500
A=½×(A+B)×H
2000
V=πr2h
T π/
½/
½/
π/
D
1.50 1.50
2.001.50
6.001.50
0.230.232.00
S
xxx
3.00
9.00
2.05
MEASUREMENT OF BUILDING WORK (A)
that has cost.Eg:- 1.Tendering process 2.Contractual requirements for insurances 3.Site facilities for the employer’s representative and payments to the local Authorities.
the work time only after working these are removed or finished so that has cost such as,1.Water for work2.Supervision3. Temporary work.
Temporary road Hats / office Electric supply
4. Scaffolding.
2).Sectional trade bill
There would be a number of sectional trade bills in accordance with the scope, or complexity of the project. All the measured work in according with the SMM7 will be inserted in to sectional trade bills, such as,
*Bill No.2D-Ground work
*Bill No.3F-Masenry
*Bill No.4E-In-site concrete etc.
3).Preambles.
Preambles are clauses usually inserted at the head of each work section bills, and principally contained descriptions, together with another relevant information of which the contractor should be aware in pricing. Inserting the preamble in the BOQ the length of the work descriptions are reduced and the specifications is not necessary if they provide the information. Another procedure is to combine all preamble clauses in a separate bill, following preliminaries.
Functions of preambles
۩ Specify quality of materials.
۩ Specify the standard of the workmanship required .
۩ Assist in pricing measured work.
۩ Repetition of same information item by item will be avoided and hence the work
Descriptions will be more concise.
4).Money provision.
BCAS Page 10
MEASUREMENT OF BUILDING WORK (A)
There are two types of money provisions that are inserted in to a BOQ
1. Prime cost sums.
The term “Prime cost sum” (PC sum) is a sum provided in the bill of quantities for works or services to be executed by a nominated subcontractor, or for materials or goods to be obtained from a nominated supplier such sums are exclusive of any profit required by the main contractor and provision is made for its addition following the Pc sum general and special attendance by the main contractor on nominated subcontractors is provided as an item in the preliminaries bill. These can be entered either as fixed or time related charges.
A Provide the PC sum of Rupees 200000for the
Supply of 12 Nr sanitary appliances, to be
Obtained from M/S sanitaryware ltd. 200000 00
B Add main contractor’s profit
C Provide the PC sum of Rupees1500000 of or
The installations of a lift to be exacted by a
Nominated sub-contractor. 1500000 00
D Add special attendance %
E Add Main contractor’s profit %
2. Provisional Sums
Where the work cannot be descried and given in accordance with SMM (SL) rules, It shall be given as a provisional sum and identified as for either defined or undefined work. In defined work items a description and indication of the amount of work. Can be given and the contractor will be deemed to have made due allowance in programming, planning and pricing the preliminaries. Whore these details cannot be supplied the work is classified as undefined and the contractor will be deemed not to have made any allowance in programming, planning and pricing the preliminaries. Work by local authorities and statutory undertaking are the subject of provisional sums.
A Allow the general provisional sum of Rupees
100000 to cover the cost of any unforeseen
Works. This sum is to be expanded the
discretion of the Architect/Engineer. 100000 00
BCAS Page 11
MEASUREMENT OF BUILDING WORK (A)
5).General summary.
There general summary is to provide monetary collection at the end of each group of work sections such as D-Ground works, F-Masonry the total of which are then trans tarred to the final summary.
1. General summary.
D-Ground work
E-In-suit concrete
F-Masonry
G-Creasing timber
H-Covering
Total carried to final summary
Rs($) Cts(P)
XXX XXX
2. Final summary.
1.Preliminaries /General condition
2.prime cost and provisional sum
3. Measred work.
4. Contingencies.
Total carried to form of tender.
Rs($) Cts(P)
XXX XXX
BCAS Page 12
MEASUREMENT OF BUILDING WORK (A)
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1.
2.
Bill No:-1A50-Nominated suppliersPreambles.
1. Iron mongaries give by ABC nominated sub contractors.
2. All iron mongaries made by pure steel and brash.
Nominated suppliersAllow a pc sum of Rs 200000 supplying of necessary iron mongaries a.b.d.
15 % for main contractor’s profit
Pc sum
%
Sum
15
BCAS Page 13
MEASUREMENT OF BUILDING WORK (A)
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1. 1.11.21.3
2.
3.
Bill No:-2D-20 Excavating and fillingPreambles.
1. Machineries are use for cutting down trees and tree stumps
2. Mechanical or manually excavation shall use as appropriate.
3. Excavated materials shall disposal 150m away on site.
4. Imported gravel shall use for filling.
5. 150mm tick layer shall compact manually.
6. 2nd class timber shall use for the earth work support.
SITE PREPARATIONCutting down trees.Girth 600-1500Girth 1500-3000Girth >3000
Removing tree stumps girth >3000
Clearing site vegetation including
NrNrNr
Nr
M2
574
2
136
BCAS Page 14
MEASUREMENT OF BUILDING WORK (A)
4.5.6.7.
8.
9.10.
all bushes, hegges and tree stumps girth ≤ 600
EXCAVATION150mm top soil Pit max depth ≤ 2000Pit max depth ≤ 1000Tranch max depth ≤ 1000
EARTH WORK SUPPORTESide of excavation max depth ≤1000Distance between opposing faces ≤2000
DISPOSALSurface waterExcavated materials a.b.d
M2
M3
M3
M3
M2
IM2
136 23 01 19
88
Item 62
Total forwarded to next page
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
11.
12.
13. 14.
Total brought from previous page
FILLING TO EXCAVATIONThick > 0.25m a.b.d
FILLING TO MAKE UP LEVELSThick > 0.25m a.b.d
SURFACE TREATMENT Compacting bottoms of excavation a.b.dTrimming sides of cuttings
M3
M3
M2
M2
09
19
56 88
BCAS Page 15
MEASUREMENT OF BUILDING WORK (A)
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1. 2. 3. 4. 5.
Bill No:-3
E10-Mixing/Curing/Curing in-situ concrete
Preambles.1. Mechanical or manually
mixing shall use as mixing concrete.
2. 1:3:6 mass concrete shall use for foundation.
3. Concrete shall cure by manually.
4. Concrete shall compact manually.
5. Grade 25 reinforced concrete shall use.
ISOLATED FOUNDATIONSFoundations a.b.dBed foundation thick ≤ 150 a.b.dConcrete in slab thick 150-450mm a.b.dConcrete in columns DPC to 1st floor a.b.dConcrete in stair case DPC to 1st floor a.b.d
M3
M3
M3
M3
M3
07 12 18 02 02
BCAS Page 16
MEASUREMENT OF BUILDING WORK (A)
1. 2. 3. 4. 5. 6. 7.
E20- Formwork for in-situ concrete
Preambles.1. 25mm thick 2nd class
plywood shall use for formwork.
SIDES OF FOUNDATIONSSides of foundation ht ≤250 a.b.dColumn base ht ≤ 1000Formwork for sides soffits of slab ht to soffits<3000, Thick≤ 200Soffits of landings a.b.dEdges of suspended slab height ≤250 a.b.dSides of column dpc to 1st floor a.b.dStair case 1000mm width, 150mwaist, and 150 rise a.b.d
MM2
M2
M2
M2
M2
M2
27 18
136 02 68 40 11
Total forwarded to next page
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1 2 3.
Total brought from previous page
E30-Reinforcement for in-situ concrete
Preambles.1. Yield steel bar reinforcement
shall use for column base, slab, beam, and stair case.
2. Tor steel bar reinforcement shall use for stirrups.
3. Lap length shall be 24xd4. Staircase lap length shall be
52xd
BARY-12 bar reinforcement a.b.d R-12 bar reinforcement a.b.dY-16 bar reinforcement a.b.d
ttt
02 0.2 01
BCAS Page 17
MEASUREMENT OF BUILDING WORK (A)
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
.
1. 2.
Bill No:-4F10-Brick / Block walling
Preambles.1. 215x102.5x65 common brick
shall use for brick wall.2. 1:6 cement: motar shall use.3. Bricks are bonded with English
bond.
WALLS225mm thick wall dpc to 1st floor a.b.d112.5mm thick wall a.b.d
F20- Natural stone rubble walling.
Preambles.1. Natural stone shall use for
rubble walling2. 1:6 cement:Motar shall use for
m2
m2 130 04
BCAS Page 18
MEASUREMENT OF BUILDING WORK (A)
1.
1.
bonding.
WALLS450mm thick wall a.b.d
F30- Assessorial / Sundry items for brick/ Block/ Stone walls.
Preambles.1. 20mm thick dpc for shall use 2. Apply 2 cots of hat dpc tar
planted with find sand. 3. 1:4 cement: sand shall use for dpc.Damp proof coursesDpc width >300 a.b.dF31- Precast concrete sills / Lintels / Copings / Features.
Preambles.1. PCC lintel shall use.2. Lintels include 4Nos Y10 bar
reinforcement. 3. R6 reinforcement Links shall
use.
m2
m2
48
27
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1. 2. 3. 4. 5. 6.
.
Total brought from previous page
LINTELS
225x150x2100 Lintel a.b.d112.5x100x1800 lintel a.b.d225x150x1500 lintel a.b.d1950x225x150 lintel a.b.d1650x225x150 lintel a.b.d675x222x150 lintel a.b.d
NrNrNrNrNrNr
01 03 01 05 01 02
BCAS Page 19
MEASUREMENT OF BUILDING WORK (A)
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1. 2. 3. 4. 5.
Bill No:-5G20- Carpentry/Timber framing/First fixing
Preambles.1. 1st class timber shall use for
roofing2. Wall plate shall fixed with on
the wall3. Other plates are fixed on the
post.4. Valance board shall for gutter
board.
PLATE75x100 wall plate a.b.d50x175 ridge platea.b.d100x100 post a.b.d
mmmmm
39 02 03 20 275
BCAS Page 20
MEASUREMENT OF BUILDING WORK (A)
6. 50x125 parlin a.b.d50x100 rafters a.b.d25x225 velancy board fix to wooden surface.
m 46
Total forwarded to general summary ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
.
Bill No:-6H32-Plastics profiled sheet cladding / Covering / Siding.
Preambles.1. Asbestors sheet shall use for roof covering.2.50x50 batten shall use3.600m canters spacing shall use 4.4000x1000 sheet shall use.
ROOF COVERING21° pitch sheet a.b.d
M2 71
BCAS Page 21
MEASUREMENT OF BUILDING WORK (A)
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
.
1.
Bill No:-7J30-Liquid Applied tanking / Damp proof membrance.
Preambles.1. Gage 1000 polytheen shall
use for damp proofing.2. 150 side and end lap for use
dpm.3. 2 cots of polytheen shall use
for dpm.
Tanking and damp proofingDPM a.b.d
m2 71
BCAS Page 22
MEASUREMENT OF BUILDING WORK (A)
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1.
Bill No:-8K40- Demountable suspended ceiling.
Preambles.1. 15mm thick smooth soffit
plywood shall use for ceiling.2. 1st class plywood shall use. 3. Plywood shall fix with wooden
surface.
CEILLINGPlywood ceiling a.b.d
m2 79
BCAS Page 23
MEASUREMENT OF BUILDING WORK (A)
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Bill No:-9L10- Windows / Roof light / screens / covers.
Preambles.1. Windows and window frames
are made by 1st class timber.2. Window frames fixed with wall
surface.3. Casements fixed with wooden
frames.4. Windows including 300mm
trellis.
BCAS Page 24
MEASUREMENT OF BUILDING WORK (A)
1. 2. 3. 4.
1. 1.1 1.2 1.3 2. 2.1 2.2 2.3
Windows and window frame1500x2100 three Casements glazed window a.b.d1500x1500 window a.b.d1200x1500 two Casements window a.b.d450x 300 fan light a.b.d
L20- Doors /Shutters / Hatches
Preambles.1. 1st class treated timber shall
use for door frame.2. Decorated ply wood door shall
use for front door.3. Timber panelled door shall
use 4. PVC door shall use for toilet.
DOORS1230x2040 plywood door a.b.d1550x1990 door a.b.d930x1740 pvc door a.b.d
DOOR FRAME AND DOOR LININGS75x100 jambs a.b.dHeads a.b.dTransoms a.b.b
NrNr
NrNr
NrNrNr
NrNrNr
02 03
01 02
03 01 01
21 07 02
Total forwarded to next page
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
1
Total brought from previous page
L40- General glazing
Preambles.1. 3mm thick standard plain
glaze shall use.2. Glaze fixed with wooden
surface.3. Fixed wooden bed and
springs. m2 5
BCAS Page 25
MEASUREMENT OF BUILDING WORK (A)
STANDARAD PLAIN GLASSPlain glass a.b.d
Total forwarded to general summary
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNTBill No:-10M20-Plastered / Rendered / Roughcast Coatings.
Preambles.1. 20mm thick smooth bed shall
do the internal plastering.2. 20mm thick semi rough bed
do the external plastering.
BCAS Page 26
MEASUREMENT OF BUILDING WORK (A)
1. 2.
1 1.1 1.2
2 2.1
3. Plastered against brick surface.
4. 1:1:5 Cement, lime, mortar shall use for plastering.
5. Material shall mix with manually.
6. Plastered for dpc to 1st floor.
WALLSInternal width >300 a.b.dExternal width >300 a.b.d
M40- Stone/ Concrete/ Quarry /Ceramic tilling/ Mosaic.
Preambles.1. 600x600 ceramic tiles shall
use for floor tilling.2. 8mm thick tiles shall use3. 100x600 ceramic tiles shall
use for skirting.4. 10mm thick ceramic tiles shall
use for skirting.5. Joint two tiles with matching
colour tile grouts.6. 20mm thick 1:4 cement, sand
bed shall use tilling.7. Clay ridge tile shall use
roofing. 8. Tilling for 1500mm height rise
and 1000mm width trade stair case.
FLOORSFloor tiles a.b.dLanding a.b.d
TREADSStair case
m2
m2
m2
m2
L
203 83
81 02
05
Total forwarded to next page ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
3 3.1
4 4.1
Total brought from previous pageRISERSStair case a.b.d
SKIRTINGS
L
m
05
150
BCAS Page 27
MEASUREMENT OF BUILDING WORK (A)
4.2
1. 1.1 1.2.
2. 2.1
Skirting a.b.dRidge tile a.b.d
M60- Painting/Clear finisihing
Preambles.1. Tyner mix with the paint.2. Painting with general surface. 3. 2 Carts of oil paint shall use.4. Paint mix with manually.
General surfaceInternal painting dpc to 1st floor a.b.dExternal painting a.b.d
GLAZED WINDOWSSpan area a.b.d
m
m2
m2
m2
02
390 106
30
Total forwarded to general summary ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Bill No:-11P20- Unframed isolated trims/ Skirting / Sundry items.
Preambles.
BCAS Page 28
MEASUREMENT OF BUILDING WORK (A)
1.
1 2 3 4 5 6 7 8
1. Decorated hand rails shall make.
2. Hand rails made with steel.
ISOLATED HAND RAILS AND GRAB RAILS.Hand rail a.b.d
P21- Ironmongery
Preambles.1. Ironmongeries fixed only
wooden surface. TYPE OF ITEM,UNIT OR SET STATED150 brase butts fix only o wooden surfaces.Casement rings a.b.dCasement stays a.b.dCasement fastners a.b.dMotice lock a.b.dEyelence a.b.d100mm brase butts a.b.d Barral ball a.b.d
L
Nr
NrNrNrNrNrNrNr
06
15 02 29 29 05 01 44 01
Total forwarded to general summary ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Bill No:-12R10-Rainwater pipe work /Gutters.
Preambles.
BCAS Page 29
MEASUREMENT OF BUILDING WORK (A)
1. 2. 3. 4. 5.
1.83mm diameter pipe shall use 2.Pipe fixed to brick wall. 3.Pipes are connected with pvc brackets 750 counter.
PIPESDown pipe a.b.dExtra over a.b.d sp jts to pipes.100mm sqd pvc gutter fixed with pvc gutter brackets in 200center a.b.dE.o pvc bendE.o pvc running had to gutters.
LNrL
NrNr
14 02 46
04 02
Total forwarded to next page
BCAS Page 30