PROGRAM OF REQUIREMENTS

Office/Support spaces for 400 Staff

Tempered Parking for up to 100 fleet vehicles

DESIGN OBJECTIVES

Support Mission of the MTPD

Refreshed Presence and New Gateway to Campus

High Performance Building

Metro Transit Police Department Facility Update

1

Site

2

Massing of Building

3

Public Interface

4

Three Schemes

5

Hybrid Concept

6

Entry Plaza

7

MTPD – Project Schedule

8

2015 MTPD Award

Design Contract February

Heywood Campus Master plan and MTPD

update

FTH 2 Design RFP Issue

Month

Land Acquisition

Second Quarter

2016 MTPD Bid

Construction First Quarter

MTPD Construction Start Second

Quarter

2017 MTPD

Construction Completed November

2018 FTH 2

Construction Completed Summer

8