Post on 17-Nov-2014
description
transcript
Problem (1)
Bottlenecks
A Granite Quarry has to perform following operations:-
1. Blast the granite hill;2. Load the boulders into trucks;3. Truck the boulders to the crusher;4. Crush the boulders into granite stones;5. Sieve the granite stones.
Data.
No. of shovels = 3 All three shovels can operate at the same time Time taken by the each shovel to load the truck = 10 minutes No. of crushers = 3 Crushers operational at a given time = 2 Maximum output from each crusher = 520 tones / hr The ‘octopus’ can process 1200 tones/hr Total loading time for loading a truck = 10 minutes Time for a trip from pit to crusher = 15 minutes Time for unloading at the crusher = 10 minutes Time for a trip from crusher to the pit = 10 minutes Each truck can carry 80 tones of ore Operation time for company = 24 hours a day, 7 days a week Production of the company = 24,000 tones per day
a) Determine the minimum no of trucks required
Number of Trips / truck
Total cycle time for one truck to pick up ore from shovels and depositing them at the
crusher and back to the shovel = 10 + 15 + 10 + 10 = 45 minutes
Number of minutes in a day = 60 x 24 = 1440 minutes
Total Cycle time for one truck to pick up ore from shovels One cycle time
Therefore
1440 = 32 Trips 45
i
Number of tones a truck can carry / day
A tuck can carry 80 tones in one tripNumber of round up trips / truck can make in a day = 32
Number of tones in a day = load in each truck x Total trips in a day
= 80 x 32 = 2560 tones
Trucking Operation:
The company operates 24 hrs / day, 7 day a week to meet the signed contract to
supply the customer, i.e. 24,000 tones/ day, in addition the assumption we made that
there is no depletion or wastage of time and final product supplying to the customer,
therefore, amount extracted is equal to the amount of granite produced. Thus
Output of trucks operations = granite produced = 24,000 tones per day
Minimum number of Trucks required in a day. To find the minimum number of trucks, in a day, required to meet the daily output
requirements we divide the total output in a day by amount of tones carried by a truck
in a day i.e.
24,000 / 2560 = Minimum number of trucks required in a day ≈ 10 trucks
b) Percent Utilization
i. Percentage utilization of shovels:
Each shovel can load a truck in 10 minutes, and each truck can carry 80 tones of load.
As there are three shovels working, therefore load of 80 tones by one shovel can make it
in every 10 minute.
Thus, in one hour, 6 loads of 80 tones = 80 x 6 = 480 tones (Amount loaded by one
shovel)
ii
By three Shovels. In One Hour 3 shovels load = 480 x 3 = 1440 tones
In 24 Hours 3 shovels can load = 1440 * 24 = 34,560 tones (Maximum Utilization)
Percentage utilization of shovels.
= (24,000 ÷ 34,560) x 100 = 69.44 %
ii. Percentage utilization of Trucks:
Number of hours in a day = 24 hrs.Number of minutes in 24 hours = 24 x 60 = 1440 Mins.
Every 45 minutes a truck completes one whole cycle from the quarry to the pit.
Minimum No. of trucks in a day = 10
Every 45 minutes one load of 80 tones by one truckIn 1440 minutes 32 loads of 80 tones = 32 x 80 = 2560 tones
As there are 10 trucks working in a day:
In 1440 minutes (32 x 80) x 10 = 25,600 tones (Maximum Utilization)
Percentage utilization of trucks.
Percentage Utilization = (Actual utilization ÷ Maximum utilization) x 100
Where actual utilization = 24,000
Thus, = (24,000 ÷ 25,600) * 100 = 93.75%
iii. Percentage utilization of crusher:
No. of operational Crushers at any given time = 2Maximum output from both crushers in one hour = 2 x 520 = 1040 tones
In 24 hours output from crushers = 1040 x 24 = 24,960 (Maximum Utilization)
iii
Percentage utilization of crushers.
(Actual utilization ÷ Maximum utilization) * 100
Actual utilization = 24,000
Thus: = (24,000 ÷ 24,960) * 100 = 96.15%
iv. Percentage utilization of Octopus
Output of the octopus in hour = 1200 tonesTotal output in a day = 1200 x 24 = 28800 tones (maximum utilization)
Percentage Utilization
(Actual utilization ÷ Maximum utilization) * 100, where Actual utilization = 24,000
Thus: = (24,000 ÷ 28,800) x 100 = 83.33%
Shovels = 69.44%Trucks = 93.75%Crushers = 96.15%Octopus = 83.33%
c) Bottleneck Operation. The apparent bottleneck is the crushers it has highest maximum percent utilization
recorded as 96.15%.
d) Recommendation.
OPT (Optimized Production technology) cited by (Galloway, Rowbotham and
Azhashemi, 2000 P-251), which places the primary focus upon the bottleneck process or
processes, Suggest that all non-bottlenecks must be optimized to help relieve the
bottleneck. To relieve the bottleneck company may emphasize on Bottleneck allocation
methodology (BAM) attempts to blend the best features of other popular production
planning philosophies. As a result, BAM could offer a better-integrated schedule with
more flexible production planning results. In this case the crushers are creating
bottlenecks, part of the reason could be the third crushing lines which went for repair and
maintenance,
iv
lets say that third crushing line will be operational with in the time limit contract than the
following will be answer working will all crushing lines.
No. of operational Crushers at any given time = 3Maximum output from both crushers in one hour = 3 x 520 = 1560 tones
In 24 hours output from crushers = 1560 x 24 = 37,440 (Maximum Utilization)
(Actual utilization ÷ Maximum utilization) * 100
Actual utilization = 24,000
Thus: = (24,000 ÷ 37,440) * 100 = 64.10% utilization
As we can see the percent utilization will be reduced by staggering 32%, than again the
new bottleneck will be recoded in trucks percentage utilization i.e 93.75%, In that case
necessary investment is much needed to avoid creating any bottlenecks
v
Problem (2)
Line Balancing
a) Precedence Diagram
A11
D11
G7
B7
C12 E5 F13
H9 I 15
b) Calculating the minimum number of workstations. (Ignoring precedence requirement and idle time)
Total time requirement = 90 seconds
No. of workstations = (Number of outputs x total time) / Working time
No. of outputs = 1000 toys
Total time of tasks = 1.5 minutes.
Factory operates for 450 minutes per day (Counting all breaks)
Thus, = (1000 x 1.5) / 450 = 3.33 ≈ 4 workstations
C. Calculating the control cycle time for assembly process
C.C.T = (seconds in a minute x total minutes) / total output
= (60 x 450) / 1000 = 27 minutes
vi
d. Line Balancing.
A11 D11 B7 C12 E5 F13 H9 G7 I15
22 24 22 22
Workstation 1 Workstation 2 Workstation 4 Workstation 5
e. Calculating Idle Time.
i. The overall Percentage idle time for the process
An average it took 27 seconds to produced one toy
Available time = 450 x 4 workstations = 1800
Required time = 1000 x 90 = 90,000 seconds = 1500 minutes
Idle time = total time – required time = 1800 – 1500 = 300 minutes
Overall percentage idle time = (idle time / total time) x 100
(300 / 1800) x 100 = 16.66%
ii. The percentage idle time at each workstation
[(Process time – cycle time) / cycle time] x 100
Therefore,
Work station 1:
Process time = 22, Cycle time = 27
= [(22-27) / 27] x100 = 18.51%
Workstation 2:
Process time = 24, Cycle time = 27
= [(24-27) / 27] x 100 = 11.11%Workstation 3:
vii
Process time = 22, Cycle time = 27
= [(22-27) / 27] x 100 = 18.51%
Workstation 4:
Process time = 22, Cycle time = 27
= [(22-27) ÷ 27] x 100 = 18.51%
Problem (3)
viii
Statistical Process Control
Measurement of abandon call rates nation-wide taken every hour
Abandon call rates
HourAvg. of 9
measurementHour
Avg. of 9 measurement
HourAvg. of 9
measurement1 16.1% 5 16.5% 9 16.3%
2 16.8% 6 16.4% 10 14.8%
3 15.5% 7 15.2% 11 14.2%
4 16.5% 8 16.4% 12 17.3%
a)
µ = 16.1σ = 1
E( x ) = µ E( x ) = 16.1
σx = σ/√ n= 1/√12
σ x = 0.288
b) 3 σ Control limits
UCL x = µ + 3(σ/√ n)
= 16.1 + 3(0.288)
UCL x = 16.9
LCL x = µ - 3(σ/√ n) = 16.1 - 3(0.288)
16% 17% 18% 17% 13% 16% 16% 17% 15%
ix
LCL x = 15.2
c)
X = 16.1+16.8+15.5+16.5+16.5+16.4+15.2+16.4+16.3+14.8+14.2+17.312
X = 16
Graph shows 3 outlines
Sample no X
10 14.811 14.212 17.3
Out of control criteria due to one or more assignable causes
Problem no. (4)
x
Workers Method.
a. Construct a worker-machine bar chart and use it to determine the number of items that the worker can produce during an eight-hour day at 100% of standard.
@ 100% of standard, the total cycle time is calculated as 2.45 min and worker will work (8 hours) 480 min / per day.
Therefore, Capacity per day = 480 min / 2.45 min
= 195 units / day / worker
b. (i) 115% of Standard pay; (i.e 15% bonus)
If the bonus of 15% is to be paid, items must be shaped 100 / 115 of the standard time
S.no Worker Machine 1 Machine 2
1 Unloading M1 = 0.25 Unloading M1 = 0.25 Running time = 1.65
2 Reloading M1 = 0.30 Reloading M1 = 0.3
3 Internal time M1= 0.40 Running time M1 = 1.90
4 Internal time M2 = 0.52
5 Idle time = 0.30 Idle time = 0.12
6 Unloading M2 = 0.30Unloading M2 = 0.30
7 Reloading M2 = 0.38 Reloading M2 =0.38
Total cycle time = 2.45 Total cycle time = 2.45 Total cycle time = 2.45
% Utilization = 87.76
% Idle time = 12.24
% Utilization = 100
% Idle time = 0
% Utilization = 95.10
% Idle time = 4.90
xi
Therefore, new external time M1 = (100 / 115) x 2.45 Min
= 2.13 min
= 2.45-2.13 = 0.32
The new external time M1 = 2.13-1.90
= 0.23 min
Reduced from = 0.55 min
The new external time M2 = 2.13-1.65
= 0.48 min
Reduced from = 0.68
New Process Cycle 115% of Standard pay.
S.no Worker Machine 1 Machine 2
1Unloading
M1 = 0.25
Reducing
time by
0.23
Unloading
M1 = 0.25 Reduction
time by
0.23
Running time = 1.65
2Reloading
M1 = 0.30
Reloading
M1 = 0.3
3 Internal time M1= 0.40 Running time M1 = 1.90
4 Internal time M2 = 0.52
5 Idle time = 0.30
6Unloading
M2 = 0.30 Reducing in
time by 0.48
Unloading
M2 = 0.30Reduction
the time
by 0.487Reloading
M2 = 0.38
Reloading
M2 =0.38
8 Total cycle time = 2.45 Total cycle time = 2.45 Total cycle time = 2.45
(ii) 130% of Standard pay; (i.e 45% bonus)
xii
If the bonus of 30% is to be paid, items must be processed 100 / 130 of the standard time (2.45 min).
Therefore, new external time M1 = (100 / 130) x 2.45 Min
= 1.88- 1.90
Critical Path
xiii
a. Network Diagram
A2 C4 F4 H4 J3
D4 G7 L6
B4 E1 I6 K5
b. Critical Path
A2 + D4 +G7 + H4 + J3+ L6 = 26 weeks
c. Normal completion time
Because critical path is the longest part in the project and total calendar time for required
project, therefore normal completion time for the project is however 26 weeks to
complete this project
d. Over time Management
Manager signed the contract to complete the project in 45 weeks and the normal
completion time is 26 weeks which actually is two weeks over the normal completion
time, thus total penalty for two weeks worth $650, breaking down further to activity A
manager it saves $5 against $ 325 and one week of completion, furthermore if the
manager pays $275 for activity D, which manager can actually saves $50 for another
week, therefore the project will be finished with in 24 weeks and manager spends $595,
instead of $650, which saves extra $55
d. Action against activity F
If the activities outside the critical path speed up or slow down (within limits), total
project time does not change, similarly activity F (slack time), does not descend under
critical path, thus there wouldn’t be any delay in project, there fore manager will not take
any actions against activity F
Problem 6
xiv
Data
D= annual demand in units for inventory item = 40x52= 2080 units
S = setup or ordering cost for each order = $10
H= holding or carrying cost per year =$20 x 23%= $4.60
(a) E.O.Q =
=
= ~ 96 units
(b) Demand / Order Quantity = 2080 units
96 units
= ~ 22 order / year
(c) Total annual cost = Setup cost + Holding cost
=
=
= $269.5
(d) E.O.Q =
xv
2x D x S H
2 x 2080 x $10 $4.60
HQ
2DQ
S +
1269
2
0
269100 +
2xDxS H
=
= 316.23
= ~ 317 units
Demand / Order Quantity = 500 units 317 units
= 1.58
= ~ 2 order per year
Total annual cost (500 units) = Setup cost + Holding cost
=
=
= $316.23
(e) The sensitivity level is low with these demands variable. There would be no doubt
that the costs are being cheaper with the increase of quantity (demand).
xvi
2 x 500 unit x $100 $1
HQ
2
D
QS +
1317
2
500
317100