Samoa Pulp Mill Case

Post on 22-Mar-2016

50 views 0 download

Tags:

description

Samoa Pulp Mill Case. PST Support to EPA Region IX Samoa, CA & Longview, WA. Northwest Area Committee Meeting – November 2013. Constructed in 1963 as a pulp manufacturing facility Abandoned in 2008 - PowerPoint PPT Presentation

transcript

Samoa Pulp Mill Case

PST Support to EPA Region IX

Samoa, CA & Longview, WA

Northwest Area Committee Meeting – November 2013

• Constructed in 1963 as a pulp manufacturing facility• Abandoned in 2008• 4 million gallons of caustic liquids (pH>13) & 10k

gallons of various acids (pH<1) remain onsite

Region IX Requested PST Support

• PST mobilized the chemical pump load and HMRT to Samoa, CA

• 165,000 gallons pumped from 2 pulp liquor tanks to 10 frac tanks

• Reduced risk of tanks overflowing due to rainwater accumulation

Projected Operations• Fabrication/construction of pipeline at Samoa facility to allow for

pumping of product from tanks to tank barge• Start 18NOV – anticipated duration 2-3 weeks

• Fabrication/construction of pipeline at KapStone Container Corporation (formerly Longview Fiber Company) for offload

• Start 02DEC – anticipated duration 2-3 weeks

• First barge loading of product in Samoa, CA• Start 06JAN – anticipated duration 7-10 days

• First barge unloading in Longview, WA• Start 19JAN – anticipated duration 7-10 days