MJ Half‐day Tutorial 6/3/2013 8:30 AM
"Scrum: An Experiential Workshop"
Presented by:
Mitch Lacey Mitch Lacey & Associates, Inc.
Brought to you by:
340 Corporate Way, Suite 300, Orange Park, FL 32073 888‐268‐8770 ∙ 904‐278‐0524 ∙ sqeinfo@sqe.com ∙ www.sqe.com
Mitch Lacey Mitch Lacey & Associates, Inc.
Over the past fifteen years, Mitch Lacey has managed numerous plan-driven and agile projects. At Microsoft, Mitch honed his agile skills, successfully releasing core enterprise services for Windows Live, and transitioned from program manager to Agile Coach, helping others transition to agile practices. At Ascentium Corporation he became the Agile Practice Manager, coaching customers on agile practices and adoption worldwide. As a Certified Scrum Trainer and a registered Project Management Professional, Mitch shares his experience in project and client management through Certified ScrumMaster courses, agile coaching engagements, conference presentations, and his writings, including his new book The Scrum Field Guide: Practical Advice for Your First Year.
SQE Agile West 2013 Reference Material
1Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Understanding Scrum: An Experiential Workshop
Reference Material
Mitch LaceySQE Agile West 2013
Las Vegas
PLEASE NOTE
These slides are for REFERENCE ONLY!
We will not be using/covering the slides.
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
2Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
About Mitch Lacey
• Author: The Scrum Field Guide• 15+ years of project management experience• Agile 2012 Conference Chair, Dallas Texas• Former Agile Alliance Board Member• Former Scrum Alliance Board Member• Project Management Professional (PMP) • Certified Scrum Trainer (CST)
SQE Agile West 2013 Reference Material
Mitch Lacey Contact Info
• Twitter: mglacey• Linked In: http://www.linkedin.com/in/mitchlacey• Email: mitch@mitchlacey.com• Phone: +1 206 228 3544
SQE Agile West 2013 Reference Material
LinkedInvcard
SQE Agile West 2013 Reference Material
3Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
The Scrum Framework
SQE Agile West 2013 Reference Material
The Scrum Team
SQE Agile West 2013 Reference Material
Product owner
ScrumMaster
Core team (development team)
SQE Agile West 2013 Reference Material
4Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
The ScrumMaster
SQE Agile West 2013 Reference Material
Provides Leadership
Servant Leader
Protects the Team
Manages Social Risk
Team Facing
Roles in Scrum: ScrumMaster
• Goal: Build & Maintain a Healthy Team• Responsibilities
– Removes impediments / clears blocking issues– Protects the team from randomization– Is the team’s Scrum expert (exacts values and principles)– Defines and reports on Team productivity– Manages Daily Scrum– Coordinates Team time requests (e.g. Product Owner
meeting requests)
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
5Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
The Product Owner
SQE Agile West 2013 Reference Material
Provides Direction
Owns the ROI
Owns the Budget
Manages Feature Risk
Customer Facing
The Product Owner
Goal: Business & Customer Advocacy and Product (or service) GuidanceResponsibilities
– Optimizes the business value of the work– Represents and Manages Stakeholder interests– Owns the Product Backlog (requirements list)– Establishes, nurtures and communicates the
product vision– Monitors the project against its ROI goals and
investment vision– Makes decisions about when to create an
official release
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
6Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Committed
SQE Agile West 2013 Reference Material
Develops High
Priority Features
Estimates the Work
Cross Functional
Manages Technical
Risk
Self Managing
CollectiveOwnership
Roles in Scrum: The Core Team
• Goal: Execute on the Vision and Product Backlog – Accomplishes the Sprint Goal
• Responsibilities– Self Managing / Organizing
• Makes its own commitments• Manages its own work • Manages itself to its commitments
– Develops the highest-priority features on the Product Backlog
– Cross functional
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
7Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Roles in Scrum: The Team – What they Do
• Plan the work / own and update the estimates• Place value on following a plan but value
responding to change more (values)• Rely on the Product Owner for product
clarification questions (feature risk)• Authority and empowerment (does what’s
needed to achieve the goal)• Rely on the ScrumMaster to help clear
blocking issues (social risk)• Commit to the Sprint
SQE Agile West 2013 Reference Material
Roles in Scrum: The Team – How Big?
• Six is ideal– As little as three and as big as eight
• Co-located• Scrum scales by adding teams, not growing
team size
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
8Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Team Consultant Model
SQE Agile West 2013 Reference Material
Roles in Scrum: The Team - Agreement and Support
• Teams are cross functional• Team members need to support each other• ScrumMaster drives the team to consensus• Fist of Five Technique:
– 5 = 100% support– 4 = Good idea, wish it was mine – 3 = I can live with and support this– 2 = I would like to think about this more– 1 = I am against this and will fight moving in this
direction
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
9Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Ideal Team Size
SQE Agile West 2013 Reference Material
Source: Putnam, Lawrence H. and Myers, Ware. Familiar Metrics Management: Small is Beautiful Once Again. IT Metrics Strategies IV:8:12‐16, Cutter Information Corp., August 1998
491 medium sized projects with 35k‐95k SLOC
SQE Agile West 2013 Reference Material
Source: Putnam, Lawrence H. and Myers, Ware. Familiar Metrics Management: Small is Beautiful Once Again. IT Metrics Strategies IV:8:12‐16, Cutter Information Corp., August 1998
491 medium sized projects with 35k‐95k SLOC
“A distinct difference in the person-months needed to do a comparable amount of work begins to show up when group size exceeds eight people.”
SQE Agile West 2013 Reference Material
10Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
SQE Agile West 2013 Reference Material
The Product
Backlog
Levels of Planning: Being “Done” Example
SQE Agile West 2013 Reference Material
Task
Examples:1. Installation
Package Updated2. > 70% Code
Coverage Story
Sprint
Prod
Examples:1. Architectural
Diagrams Updated2. Automated User
Tests PassingExamples:1. SQL Optimization
and Tuning2. Data Security
Roles Updated
Examples:1. Stress Testing2. User Training
Completed
Examples:1. Failover Testing2. Release Readiness
Review
SQE Agile West 2013 Reference Material
11Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
SQE Agile West 2013 Reference Material
Definition of Done Exercise
Build your own definition of done!1 – in the book2 – on this webpage:http://www.mitchlacey.com/intro-to-agile/scrum/definition-of-done
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
12Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Product Backlog: What is it?
• Ordered, prioritized list of features and work• High level estimates (story points)
– Preferred: Story points: 1,2,3,5,8,13– Alternatives
• Exponential: 10, 20, 40, 80• T-shirt sizing: XS, S, M ,L, XL
• Items added at any time• Owned and prioritized by the Product Owner• Should reflect the vision (why the project exists and its
desire end state)
SQE Agile West 2013 Reference Material
Product Backlog Prioritization
SQE Agile West 2013 Reference Material
11
22
33
44
Up Next – more detail
Too far out – little detail
Highest PriorityWork on it now – lots of detail
Work that is 3‐5 sprints out – Some detail
SQE Agile West 2013 Reference Material
13Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
User Stories
• As a <user> I can/want <action> so that <result>
• As an administrator, I can look up this month’s patient report and am able to see who is over the user defined threshold
• Have business value• Are easily identifiable by the Product Owner, customers
and the team• Rely on the 3 C’s
– Card– Conversation– Confirmation
SQE Agile West 2013 Reference Material
INVEST in Your Product Backlog
• Independent– Dependencies lead to problems estimating and prioritizing– Can ideally select one item to work on without pulling in 18 others
• Negotiable– Product backlog items are not contracts– Leave or imply some flexibility
• Valuable– To users or customers, usually not to developers– Try rewriting developer-oriented backlog items to reflect value to users or
customers• Estimable
– Because plans are based on user stories, we need to be able to estimate them
• Small– Complex backlog items are intrinsically large– Compound backlog items are multiple items in one
• Testable– Make backlog items testable by having acceptance tests
SQE Agile West 2013 Reference Material
1 Bill Wake 2003
SQE Agile West 2013 Reference Material
14Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Make it DEEP
• Detailed Appropriately.– Stories coming up should be understood– Stories that will not be developed for awhile should be described
with less detail
• Estimated.– More precise at the top– Less at the bottom
• Emergent.– Stories grow and change. The more you learn, the more you
tweak
• Prioritized.– Valuable stories at the top, less so down the list
SQE Agile West 2013 Reference Material
Product Backlog Grooming
• The team should spend 5%-15% of Sprint time (1-6h) in reviewing the Product Backlog and estimating it for each Sprint (s)
• Similar to a specification only never out of date• Continuously prioritized and updated• Anyone can add to the product backlog
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
15Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
SQE Agile West 2013 Reference Material
Planning
Levels of Planning
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
16Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Levels of Planning: Being “Done”
• What is Done?– How do you know when your project is done?– How do your customers and stakeholders know?– How do you communicate it?
SQE Agile West 2013 Reference Material
Levels of Planning: Sprint Planning Meeting 1
• Scale duration depending on Sprint Duration– 1mo Sprint = 4h– 2w Sprint = 2h
• Defines what the team will build• Product Owner states what the
business wants (high value, high risk)
• Agrees on the goal of the sprint• When Team has enough
information, or time has ended, Planning Meeting 2 begins
SQE Agile West 2013 Reference Material
Vision
Product(s)
Releases
Sprint
Day
SQE Agile West 2013 Reference Material
17Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Levels of Planning: Sprint Planning Meeting 2
• Scale duration depending on Sprint Duration– 1mo Sprint = 4h– 2w Sprint = 2h
• Defines how the team will build the stories
• Tasks are small (2-14h)• Team owns Sprint Backlog
(builds, estimates, updates)• Team signs up for work,
collectively commits to the work• Attended by the Team (Product
Owner optional)SQE Agile West 2013 Reference Material
Vision
Product(s)
Releases
Sprint
Day
Sample Sprint Backlog
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
18Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
The Sprint Backlog
• Is the output of the planning meeting• Is used for the team to manage themselves and their
work during the sprint• Creates transparency between all Scrum team members
SQE Agile West 2013 Reference Material
Download my Sprint Excel Sheet
SQE Agile West 2013 Reference Material
http://www.mitchlacey.com/resources/sprint‐excel‐templates
SQE Agile West 2013 Reference Material
19Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Levels of Planning: Daily Scrum Meeting
• Occurs Daily• Team members answer three questions:
• What did you work on since the last meeting?• What will you work on today?• What impediments / blocking issues do you have?• (optional) What is your confidence that we will achieve the sprint goal?
• Timeboxed to 15m• Same time/place daily• No deep dive problem solving
(deal with that after)
SQE Agile West 2013 Reference Material
The Sprint: Reporting Progress - Burndown
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
20Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
The Sprint: Reporting Progress - Burndown
SQE Agile West 2013 Reference Material
Release Burndowns
• Use the same sprint burndown but instead of days, use it for sprints
• Should be updated after every sprint• Useful to allow the Product Owner to see the overall
release plan progress
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
21Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Sprint Review Meeting
• Occurs on the last day of the Sprint• Allows stakeholders to review the work done and provide
guidance on what to do next• One hour per week of sprint (e.g. two week sprint is two
hour meeting)• The team drives the meeting• Everyone attends• Can impact the upcoming Sprint planning sessions
– Reprioritize the backlog– Change high level estimates of work– Team composition may change
SQE Agile West 2013 Reference Material
What do we Review in the Review Meeting?
• Review the Sprint Goal• Review the commitments made by the team• Review work accomplished• Review the work that was not accomplished• Review the decision made• Demo the work• Summarize• Asks
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
22Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Retrospective
• Occurs on the last day of the Sprint• One hour per week of sprint (e.g. two week sprint is two
hour meeting)• Allows the team to inspect itself to learn about & change
behavior as needed• Facilitated by ScrumMaster• ScrumMaster and the Team prioritize the improvements• The sprint ends when the timebox expires,
typically after the retrospective
SQE Agile West 2013 Reference Material
Getting Started with Scrum
• Get a senior Sponsor in the company• Get a champion to drive the effort• Agree on who will play the roles• Set a date to “start scrumming” and prep the team to that
date• Build a prioritized Product Backlog and estimate it• Build the team and clear blocking issues (like not being co-
located)• Build a Sprint Backlog and start working• Use Burndowns• Conduct a demo and review• Inspect and Adapt• Repeat!
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
23Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Cadence
• Set a cadence and keep it• Put all meetings in calendars on day 1• Keep your daily Scrum on track• Use planning• Work to potentially shippable code• Always demo at the end
• CELEBRATE SUCCESS AT EVERY SPRINT!
SQE Agile West 2013 Reference Material
Getting People on Board with Scrum
• Be patient• Use the local network – get testimonials• Provide articles and books• Show incremental benefits• Get external speakers to talk to
management and teams• Ensure risk will not be penalized
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
24Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Be Warned
• Most projects deliver every 6-18 months.• Scrum reduces this through inspect and adapt• Things will be stressful• Fight the urge to be lazy• Stay disciplined
SQE Agile West 2013 Reference Material
What Causes Scrum to Fail?
• Making changes out of the gate• Thinking that “this can’t work in our company”• Not having an honest retrospective and doing
something about it• Bad ScrumMasters• Falling into old habits• Lacking authority and being empowered• Business culture does not support Scrum
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
25Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Scrum Resources• My contact
– http://www.mitchlacey.com– http://twitter.com/mglacey
• My book, The Scrum Field Guide• Jeff Sutherland Scrum Papers
– The Scrum Papers (jeffsutherland.com/scrum/ScrumPapers.pdf)
• Mike Cohn & Mountain Goat Software– http://www.mountaingoatsoftware.com/scrum
• Scrum Alliance– http://www.scrumalliance.org
SQE Agile West 2013 Reference Material
Offshoring – Making it Work
• About 3 time zones away seems to work• Phone/shared desktop pair-programming is essential
– Set management expectations that pairs will be based on work, not proximity
• Use technology!– Push to talk cell phones so every team member can talk anywhere any time– Use teleconferencing for all “formal” meetings like standups– Use VNC– Get webcams
• Face time matters, travel often.• Travel any time there are communication difficulties• Travel any time you feel trust is breaking down between the
locations• Do absolutely anything you can do to build a one-team culture• Do absolutely nothing to build the perception fragmented teams
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
26Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
Offshoring – Making it Work Part 2
• Have a project / team coordinator– The coordinator has the responsibility of relaying the backlog to
the offshore team and tracking progress.
• Have in-person kick-off meetings with the entire worldwide team
• Bring offshore people to the central office on a rotational basis to build team cohesion
• Have offshore teams take on as much independent work as possible, a whole feature set possibly
SQE Agile West 2013 Reference Material
Offshoring – Impediments to Manage
• Time zone differences• Culture and values• Inexperienced teams• Face-to-face communication• Language barriers• Trust• Building a common development environment and
codebase• Stronger Command & Control tradition in Asia• Offshore turn-over• Recruiting the right offshore workers
SQE Agile West 2013 Reference Material
SQE Agile West 2013 Reference Material
27Copyright 2007‐2013 Mitch Lacey (mitch@mitchlacey.com). No reproduction without written authorization.
When to Offshore
• Don’t Offshore:– First releases of complex and high-technology-risk projects– If your onshore development process is not in place (”CMMI
level 3”)• Process = the daily work in the teams• Process ≠ the corporate process guidelines
• Don’t Agile Offshore:– If you don’t have any onshore Agile experiences