SE 313A Operating Systems Unit 1

Post on 06-May-2015

520 views 1 download

transcript

EP 704Unit 6

Project Time Management

Dr. J. Michael Bennett, P. Eng., PMP

UNENE, McMaster University, The University of Western Ontario

Version 2K6-X-08

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-2

Unit 6 Project Time Management

Revisions

2K6-X-08 Initial Creation

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-3

Unit 6 Project Time Management

EP 704 Road MapUnit 1 Introduction to Project ManagementUnit 2 The Project Management ContextUnit 3 Project Management ProcessesUnit 4 Project Integration ManagementUnit 5 Project Scope ManagementUnit 6 Project Time ManagementUnit 7 Project Cost ManagementUnit 8 Project Quality ManagementUnit 9 Project Human Resource ManagementUnit 10 Project Communications ManagementUnit 11 Project Risk ManagementUnit 12 Project Procurement Management

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-4

Unit 6 Project Time Management

Process Time Management

Here we estimate the time and sequencing of WBEs

Must have the WBS done

The material is presented as sequential but likely will be significant overlap

In smaller projects, activity sequencing and duration and schedule development will be a single process done by the PM

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-5

Unit 6 Project Time Management

Project Time Management Processes

6.1 Activity Definition

6.2 Activity Sequencing

6.3 Activity Resource Estimating

6.4 Activity Duration Estimating

6.5 Schedule Development

6.6 Schedule Control

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-6

Unit 6 Project Time Management

6.1 Activity Definition

.1 Inputs

.1 EEF .2 OPA . 3 Scope Statement .4 WBS .5 WBS Dictionary .6 PMP.2 Tools and Techniques .1 Decomposition .2 Templates .3 Rolling Wave Planning .4 XJ .5 Planning Component.3 Output . 1 Activity list .2 Activity Attributes . 3 Milestone List .4 Requested Changes

6.3 Activity Resource Estimating.1 Inputs .1 EEF .2 OPA .3 Activity List .4 Activity Attributes .5 Resource Availability .6 PMP

.2 Tools and Techniques . 1 Expert judgment .2 Alternatives Analysis .3 Published Estimating Data .4 PM Software .5 Bottom-up Estimating.3 Output .1 Activity Resource Requirements .2 Activity Attributes (Updates) .3 Resource Breakdown Structure .4 Resource Calendars (Updates) .5 Requested Changes

6.2 Activity Sequencing.1 Inputs .1 Scope Statement .2 Activity List . 3 Activity Attributes .4 Milestone List .5 Approved Change Requests.2 Tools and Techniques .1 Precedence diagramming (PDM) .2 Arrow diagramming (ADM) .3 Schedule Network Templates .4 Dependency Determination .5 Applying Leads and Lags.3 Output .1 Schedule Network Diagrams .2 Activity Lists (Updates) .3 Activity Attributes (Updates) .4 Requested Changes

PMI Project Time Management

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-7

Unit 6 Project Time Management PMI Project Cost Management

6.6 Schedule Control.1 Inputs .1 Schedule Management Plan .2 Schedule Baseline

.3 Performance Reports

.4 Approved Change Requests.2 Tools and Techniques .1 Progress Reporting .2 Schedule CC System .3 Performance Measurement .5 PM software .6 Variance analysis .7 Schedule Comparison Bar Charts

.3 Output .1 Schedule Model Data (Updates) .2 Schedule Baseline (Updates) .3 Performance Measurements .4 Requested Changes .5 Recommended Corrective Actions .6 OPA (Updates) .7 Activity List (Updates) .8 PMP (Updates) .9 Activity Attributes (Updates)

6.4 Activity Duration Estimating.1 Inputs .1 EEF .2 OPA .3 Scope Statement .4 Activity List .5 Activity Attributes .6 Activity Resource Requirements .7 Resource Calendars .8 PMP - Risk Register - Activity Cost Estimates

.2 Tools and Techniques .1 Expert Judgment .2 Analogous Estimating .3 Parametric Estimating .4 Three-point Estimates .5 Reserve Analysis.3 Output .1 Activity Duration Estimations .2 Activity Attributes (Updates)

6.5 Schedule Development.1 Inputs .1 OPA 2 Scope Statement .3 Activity List .4 Activity Attributes .5 Schedule Network Diagrams .6 Activity Resource Requirements .7 Resource Calendars .8 Activity Duration Estimates .9 Risk Register.2 Tools and Techniques .1 Schedule Network Analysis .2 Critical Path Method .3 Schedule Compression .4 What-if Scenario Analysis .5 Resource Leveling .6 Critical Chain Method .7 PM Software .8 Applying Calendars .9 Adjusting Leads and Lags .10 Schedule Model.3 Output .1 Project Schedule .2 Schedule Model Data .3 Schedule Baseline .4 Resource Requirements (Updates) .5 Activity Attributes (Updates) .6 Project Calendars (Updates) .7 Requested Changes .8 PMP (Updates)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-8

Unit 6 Project Time Management

6.1 Activity Definition

6.2 Activity Sequencing

6.3 Activity

Resource Est.

6.4 Activity

Duration Est.

6.5 Schedule Development

Enterprise Environmental

12.4 Select

Sellers

4.3 Develop

PMP

4.6 Int Change

Control

Scope Statement

Organizational Process Assets

5.2 Scope Definition

5.3 Create

WBS

9.2 Acquire

Project Team

7.1 Cost

Estimation

10.3 Performance

Reporting

4.7 Close Project

4.4 Project Execution

11.2-5 Risk

Planning

6.6 Schedule

Control

WBS+D

Res Avail

History, Calendar

Resource Availability

Resource Availability

Activity Cost Estimates

Risk Register

Performance Reports

Work Performance Information

OPA Updates

History, Calendar

PMP, SMP

Activity List, Attributes, Milestone List Requested Changes

Requested Changes

PMP Updates

Schedule Network Diagrams

Requested Changes

Requested Changes

Requested Changes

Requested Changes

Approved Change Reqs

Act Res Rqs, RBS, Res Cals

Activity Duration Estimates

Schedule; Model data; Sched Baseline; Res Reqs; Proj Cal UD

Perf Mease; UDs of AL, AA, ;PMP, Sked BL; Proj Sked

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-9

Unit 6 Project Time Management

6.1 Activity Definition

1 Decomposition2 Templates3 Rolling Wave4 XJ5 Planning Comp

1 Activity List

2 Activity Atts

3 Milestone List

4 Req’ed Changes

1 EEF2 OPA3 Scope Statement4 WBS5 WBS Dictionary6 PMP

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-10

Unit 6 Project Time Management

1 Activity List

Comprehensive list of all project schedule activities

Includes schedule identifier and enough detail for the team to understand what to do

Usd in the schedule model and the PMP

AL ≠ WBS components

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-11

Unit 6 Project Time Management

2 Activity Attributes

Such asActivity identifierActivity codesActivity descriptionPredecessor activitiesSuccessor activitiesLogical relationshipsLeads and lagsResource requirementsImposed datesAssumptions and constraints

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-12

Unit 6 Project Time Management

3 Milestone List

All milestones must be IDed

Mandatory or optional

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-13

Unit 6 Project Time Management

4 Requested Changes

AD can generate changes

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-14

Unit 6 Project Time Management

6.1.2 Activity Definition: T&T

1 Decomposition

2 Templates

3 Rolling Wave

4 XJ

5 Planning Component

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-15

Unit 6 Project Time Management

Recall Simon’s Tripartite Division

Level 1 – Milestones

Level 2 – WBSes

Level 3 – Schedule Activities

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-16

Unit 6 Project Time Management

EHB Example

Milestone – sign-off of Driver module

WBS – completed requirements

SA – review requirements with customer Stakeholders - ½ day 4 people

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-17

Unit 6 Project Time Management

1 Decomposition

Subdivides WPs into smaller components; called schedule activities

These are schedule driven not deliverable driven

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-18

Unit 6 Project Time Management

2 Templates

Useful from previous projects

Used to estimate resource skills, hours of effort, risk ID, etc

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-19

Unit 6 Project Time Management

3 Rolling Wave

Progressive elaboration

Detail near-term events

Leave the far-term adumbrated, to be detailed later at a more appropriate time

Early on, leave far-term at the milestone level

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-20

Unit 6 Project Time Management

4 XJ

Mumble mumble

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-21

Unit 6 Project Time Management

5 Planning Component

When insufficient definition of the scope is available to decompose the WBS, leave the last node as a PC

Control Account: a node to be developed further later

Planning Package: subcomponent above the WP but below the CA

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-22

Unit 6 Project Time Management

6.1.3 Activity Definitions: Outputs

.1 Activity List

.2 Activity Attributes

.3 Milestone List

.4 Requested Changes

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-23

Unit 6 Project Time Management

1 Activity List

Includes all schedule activities needed to be done on the project

IncludesActivity identifier

Work description in enough detail to schedule and understand the work

SAs are discrete units but are NOT WPs

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-24

Unit 6 Project Time Management

2 Activity AttributesExpansion of characteristics of SAs including

Activity IDActivity codeActivity descriptionPredecessor activitiesSuccessor activitiesLogical relationshipsLeads and lagsResource requirementsImposed datesConstraintsAssumptions

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-25

Unit 6 Project Time Management

3 Milestone List

List of all milestonesMandatory

Optional

Will be part of the PMP and used for Milestone Scheduling

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-26

Unit 6 Project Time Management

4 Requested Changes

Since we are fleshing out interior details of the WPs, changes will be needed as more detail is unfolded.

Fed through ICC of course.

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-27

Unit 6 Project Time Management

6.2 Activity Sequencing

1 PDM2 ADM3 Sched NW Temps4 Dependency Det.5 Leads and Lags

1 Scope Statement2 Activity List3 Activity Attributes4 Milestone List5 App’d Change Reqs

1 Sched NW Diags2 Act. Lists (Up)3 Act. Atts (Up)4 Req’d Changes

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-28

Unit 6 Project Time Management

Modalities of Scheduling

Gantt/bar charts

Milestone charts

NetworksADM

Precedence

PERT

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-29

Unit 6 Project Time Management

Problems with Each

Gantts do not show interdependencies

PERTs et al are time intensive, too much detail

Each is useful in their own right; not the final solution

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-30

Unit 6 Project Time Management

Example: Gantt, Milestone, PERT

1144141

21

53

76

4

1 2

54

6

3

7

2

4 53

6 7

3

2 2

4

1 3

1

14

7

2

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-31

Unit 6 Project Time Management

Network Fundamentals

Shown through a diagram. Visualization of:Activity interdependence

Project completion time

Impact of early/late starts

Trade-off analysis

“what if” scenarios

Cost of crashing

Slippages in planning/performance

Performance evaluation

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-32

Unit 6 Project Time Management

6.2.2 Tools & Techniques

1 Precedence Diagramming Method (PDM)

2 Arrow Diagramming Method (ADM)

3 Schedule Network Templates

4 Dependency Determination

5 Leads and Lags

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-33

Unit 6 Project Time Management

1 Precedence Diagramming Method (PDM)

Also called AON (activity on Node)

Puts effort on the node

Most common today

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-34

Unit 6 Project Time Management

PDM (pmbok)

Begin EndH

LK

JI

F G

EDC

A B

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-35

Unit 6 Project Time Management

Definitions (activities on node: AON)

Event is start or end of group of activities (circle)

Activity is work required to move from event to event (node time)

6/2 9/3

Complete testing

Final report

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-36

Unit 6 Project Time Management

Dependency Relations

Finish-to-Start (must finish before next can start)

Finish-to-Finish (must finish before next can finish)

Start-to-Start (must start before next can start)

Start-to-Finish (must start before next can finish)

All of these assume 100% completion; could have a percentage

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-37

Unit 6 Project Time Management

Network Analysis

A# Dur

ES

ACTIVITY DESCRIPTION

EF

LS LF

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-38

Unit 6 Project Time Management

Zero or 1?

Note do we start at day 0 or day 1?

Most folks start at 0

1 1

A 4

5 5

B 3

0 0

A 4

4 4

B 3

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-39

Unit 6 Project Time Management

Forward Pass

1 1

A 1

2 2

B 3

5 5

D 5

2 3

C 2

10

10

F 3

4 7

E 3

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-40

Unit 6 Project Time Management

Earliest-Latest Dates

1 1

A 1

2 2

B 3

5 5

D 5

2 3

C 2

10 10

F 3

4 7

E 3

12 12

7 9 3 4

1 1

4 4 9 9

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-41

Unit 6 Project Time Management

Backward Pas

A 1

B 3

-8

D 5

C 2

0

F 3

E 3

0 0

0

-8

-3 -3

-11 -11

-12 -12

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-42

Unit 6 Project Time Management

Critical Path

1 1

A 1

2 2

B 3

2 3

C 2

10 10

F 3

4 7

E 3

12 12

7 9 3 4

1 1

2 4

5 5

D 5

5 9

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-43

Unit 6 Project Time Management

Comments

Idea of Critical Path

Note FP is done to estimate finish date

BP is done when finish date is fixed and you want to know when to start

Must be the same

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-44

Unit 6 Project Time Management

1

0

ID

Customer

3

3 2

3Develop Questionnaire

13

10

6

38 Print Q

48

10

4

33Rev, Finalize Q

38

5

7

38 Develop

DA SW

50

12

5

38 Mail

labels

40

2

8

38Develop Test Data

40

2

1

48 Mail Qs, get Resps

9

113

65

a

50 Test

SW

55

5

3

13 Test Q

33

20

1

113 Input Res Data

b

120

7 c

120 Analyze Data

128

8 1

128 Prepare Report

d

183

10

-5-8 2555-5

3025

105100

10098

120112112105 130120

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-45

Unit 6 Project Time Management

2 Activity on Arrow (Arrow Diagramming Method)

Event is start or end of group of activities (circle)

Activity is work required to move from event to event (arrow)

6 9

Complete testing

Final report

2 weeks

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-46

Unit 6 Project Time Management

Sources and Sinks

6

23

33

8

77

11

10

9

Source (burst point)

Sink

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-47

Unit 6 Project Time Management

Comments

Idea of Critical Path

Can use optimistic, normal or pessimistic time estimates (Ro6?)

Can use “dummy” variables to help in sequencing

PERT for high variance

CPM for low

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-48

Unit 6 Project Time Management

Mathematical Choices

Critical Path Method (CPM)

Graphical Evaluation and Review Technique (GERT)

Program Evaluation and Review Technique (PERT)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-49

Unit 6 Project Time Management

PERT/GERT/Network Analysis

Basic Definitions

How to Crash Critical Paths (later)

Estimating ranges of completion times

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-50

Unit 6 Project Time Management

Graphical Evaluation and Review Technique (GERT)

Permits an iterative looping in the schedule (none of the others do)

Uses probabilistic estimates

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-51

Unit 6 Project Time Management

Program Evaluation and Review Technique (PERT)

Uses a weighted average like the Rule of Six

Good for calculating best, expected and worse case scenarios

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-52

Unit 6 Project Time Management

The Beta Distribution EV=(BC+4ML+WC)/6

0

0.2

0.4

0.6

0.8

1

1.2

1 4 7 10 13 16 19 22 25

Beta Distribution

BC ML WCEV

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-53

Unit 6 Project Time Management

Estimating the SD PERT-wise

σ = (WC-BC)/6

If you have many, you must add up the variances not the σs. (var = σ2)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-54

Unit 6 Project Time Management

Example

a b c d2,3,4 3,5,74,7,10

σ ab = 0.33 σbc = 1.0 σcd = 0.67

σad = √ σ2ab + σ2

bc + σ2cd

σad = √ (.332+1.02+0.672) = 1.25

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-55

Unit 6 Project Time Management

Definitions

DependenciesHard – must be done first

Soft – may be necessary or not (I can start high level design before all requirements are done)

External – beyond PM’s control

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-56

Unit 6 Project Time Management

Dummy Activities

1

D2

53

4

A

B

C

DUMMY

4<1,2,3

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-57

Unit 6 Project Time Management

Slack Time

= time between scheduled completion date and required date (to meet CP)

TE is earliest time event can take place

TL is latest time

ST = |TE – TL|

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-58

Unit 6 Project Time Management

PERT with Slack Time

2 4

53

6

1

36

7

2

TE=3TL=3

5

5

3

TE=0TL=0

TE=2 TL=5

TE=10TL=10

TE=15TL=15

TE=6TL=9

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-59

Unit 6 Project Time Management

Can Refine

ES = earliest start

EF = earliest finish

LS = latest start

LF = latest finish

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-60

Unit 6 Project Time Management

Full PERT

C(6,11) 5(14,19)

ACTIVITY IDENTIFICATION

ACTIVITY TIME

LATEST FINISH TIME

LATEST START TIME

EARLIEST FINISH TIME

EARLIEST START TIME

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-61

Unit 6 Project Time Management

PERT with Full Slack Times

B(6,15)9(6,15)

D(6,12) 6(11,17)

A(0,6)6(0,6)

H(12,16) 4(18,22)

G(12,14)6(17,19)

E(15,18) 3(15,18)

F(15,22) 7(15,22)

C(6,11) 5(14,19)

I(18,21) 3(19,22)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-62

Unit 6 Project Time Management PERTing Along

develop schedule

$?

?

res?

plan?

feedback

BL plans & schedule

no

no

no

noResource control

Management Approval

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-63

Unit 6 Project Time Management

How to Feedback?

Transfer resources from sps to cps

Eliminate activities

Add more resources

Use less time-consuming activities

Parallelize more

Shorten CP

Shorten earliest activities

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-64

Unit 6 Project Time Management

Shorten latest activities

Increase number of working hours/day

Use cheaper people

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-65

Unit 6 Project Time Management

Parallelizing to Shrink Critical Paths

1 2 3

1

2

3

4

4

0

16

4

16

0

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-66

Unit 6 Project Time Management

Nested PERTs

EB

C

F

D

A

FA 7 8

5

43

6

7

2

54

4

8

6

9

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-67

Unit 6 Project Time Management

PERT Life Cycle

1 lay out list of activities

2 order them and add arrows

3 review with line managers

4 doers add time estimates (unlimited Res)

5 PM adds calendar dates (limitations)

6 Checks reality of calendar dates

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-68

Unit 6 Project Time Management

Perturbation Analysis

Always check if times change dramatically

Primary Objectives are:Best time

Least cost

Least risk

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-69

Unit 6 Project Time Management

Secondary Objectives

Alternatives

Optimum schedules

Effective use of resources

Communications

Refinement of the estimating process

Ease of project control

Ease of time/cost revisions

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-70

Unit 6 Project Time Management

PERT Constraints

Calendar completion

Cash flow

Limited resources

Management approvals

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-71

Unit 6 Project Time Management

PERTs and CPMs

PERTs are event-orientedGood for R&D

Hard to tell percentage complete

Payouts at milestones

CPMs are activity-oriented% complete along lines can be done

Good for well-defined activities

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-72

Unit 6 Project Time Management

CPM best for

Well-defined projects such as construction

One dominant organization

Relatively small risk

One geographic location

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-73

Unit 6 Project Time Management

Project Software Support

Level I (Excel)Level II (MS)Level III (Artemis)Level IV (in-your-dreams)

REMEMBERSOFTWARE DOESN’T MANAGE PROJECTS:

PEOPLE DO

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-74

Unit 6 Project Time Management

SW Capabilities

System capacity

Network schemes (AD/PRE)

Calendar dates

Gantt charts

Flexible report generation

Updating

Cost control

Scheduled dates

Sorting

Filtering

Resource allocation

Plotting

Machine requirements

Cost

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-75

Unit 6 Project Time Management

3 Schedule Network Templates

Mature organizations will have general templates to begin the work

Especially if portions are repetitive. Such as floors on a high-rise, clinical trials, software module construction.

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-76

Unit 6 Project Time Management

4 Dependency Determination (3 kinds)

MandatoryNormal (see PDM 4 types)

DiscretionarySuch as a preferred way of executing a sequence of events when there are several OK paths

ExternalOutside the PM’s control such as delivery of necessary hardware, Y2K, laws, etc

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-77

Unit 6 Project Time Management

5 Leads and Lags

Lead permits the acceleration of the successor task. Eg. Can start chapter 2 15 days before chapter 1 is complete (F2S with 15 day lead)

Lags delay next task. Concrete must cure for 15 days. Therefore a F2S with a 15 day lag

Leads and Lags can be negative (but why?)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-78

Unit 6 Project Time Management

Lag Time

Suppose that B lags A by 3

1 1

A 4

8 8

B 3

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-79

Unit 6 Project Time Management

6.3 Activity Resource Estimating

1 EEF2 OPA3 Activity List4 Act Atts5 Resource Avail6 PMP

1 Xpert Judgment2 Alternative Anal3 Published E Data4 PM Software5 Bottom-up Est

1 Act Res Reqs2 Act Atts (ups)3 Res BD Structure4 Res Cals (ups)5 Req’d Changes

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-80

Unit 6 Project Time Management

6.3.1 ARE Inputs

EEFsUses infrastructure resource availability as per the nature of the company

OPAsPolicies for staffingRental or purchase of supplies, equipmentHistorical information

Resource AvailabilityIn the market now? Later?

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-81

Unit 6 Project Time Management

6.3.2 Tools and Techniques

1 Expert Judgment

2 Alternative Analysis

3 Published Estimating Data

4 PM Software

5 Bottom-up Estimation

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-82

Unit 6 Project Time Management

1 Expert Judgment

Experts in the area can tell us who we need

Any group or person having area-specific knowledge use\ful here

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-83

Unit 6 Project Time Management

2 Alternatives Analysis

Make-or-buy decisions

Who can do the work

May be necessary to outsource some of the schedule activities

Can we cannibalize other work?

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-84

Unit 6 Project Time Management

3 Published Estimating Data

There are commercially available books of production rates and unit costs for trades, material, equipment, in many countries or geographical areas

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-85

Unit 6 Project Time Management

4 PM Software

PM software can use RBSs, resource availability, resource calendars, to allocate for us

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-86

Unit 6 Project Time Management

5 Bottom-up Estimation

If we cannot estimate the needed resources, may need more decomposition into finer detail. Continue the decomposition until we can estimate and then roll back up

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-87

Unit 6 Project Time Management

6.3.3 ARE Outputs

1 Activity Resource Requirements

2 Activity Attributes (ups)

3 Resource Breakdown Structure

4 Resource Calendars (ups)

5 Required Changes

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-88

Unit 6 Project Time Management

1 Activity Resource Requirements

IDs types and quantities of resources required for each schedule activity.

Can then roll up for total for the work package

Will lead to the estimation numbers in the next section

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-89

Unit 6 Project Time Management

3 Resource Breakdown Structure

Same as WBS only for RBS

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-90

Unit 6 Project Time Management

6.4 Activity Duration Estimation

1 EEF2 OPA3 Scope Statement4 Act List5 Act Attributes6 Act Res Reqs7 Res Cals8 PMP

1 Xpert judgment2 Analogous Est3 Parametric Est4 Three-point Ests5 Reserve Anal

1 Act Duration Ests2 Act Atts (ups)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-91

Unit 6 Project Time Management

General

This is big

We take all of the preceding and roll it all up into the best time estimate that we can manage.

We need to know the size of the work and the production rates to time it out

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-92

Unit 6 Project Time Management

Other things

Need to know the expected working periods

Do you count weekends?

Also what is the normal metric for effort?ph?

pd?

pm?

py?

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-93

Unit 6 Project Time Management

6.4.1 Inputs to Activity Duration Est

1 EEF2 OPA3 Scope Statement4 Activity List5 Activity Attributes6 Activity Resource Requirements7 Resource Calendars8 PMP

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-94

Unit 6 Project Time Management

1 EEF

Historical data important

Also when durations are not driven by the work but by things like:

Curing time of concrete

Time to get approvals through government agencies

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-95

Unit 6 Project Time Management

2 OPA

Recorded data from previous work important here

Team effort records (sw for example, fp/m rates of individuals)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-96

Unit 6 Project Time Management

Historical Information

Can come from the PM morgue

In many engineering areas, there are tables

Steel girders, for example

Unions have rates

Commercial databases

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-97

Unit 6 Project Time Management

3 Scope Statement

Assumptions from the Scope; reporting periods can dictate maximum schedule durations

Review periods

Document submittals etc.

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-98

Unit 6 Project Time Management

6 Activity Resource Requirements

Trickery trickery trickery.

Will affect the schedule

EG; need 2 engineers to do the design

If only 1 is available, may take twice (or more likely more than twice) to complete

Applying n resources will not cut the time by 1/n. In fact may increase it.

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-99

Unit 6 Project Time Management

Resource Requirements

Is it the case that the work can be paralleled?

For example, two people can do the work twice as fast as one

But be careful: the fallacy of linear scaling

There comes a time when adding more people to the work only causes it to take longer

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-100

Unit 6 Project Time Management

5 Resource Capabilities

People do work at different rates

Senior people should be faster than juniors

Some areas are human-specificin coding, it has been measured, that holding all other variables constant, there can be a ten to one difference in coding rates (Weinstein, 1972)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-101

Unit 6 Project Time Management

8 PMP Inputs

Risk RegistryRisks are associated with resource availability and goodness of resources

Activity Cost EstimatesCan use activity cost estimates from the PMP here

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-102

Unit 6 Project Time Management

Remember the Cops and the Donuts

We need two estimates

SIZE

EFFORT

We also want to specify the confidence levels of our numbers

Rule of 6 good here

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-103

Unit 6 Project Time Management

Risk

Need to estimate the costs of risk

High risk means higher costs because of the risk oversight and possible mitigation

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-104

Unit 6 Project Time Management

6.3.2 T&T for Activity Duration Est

0 Introduction to Estimation

1 Expert Judgment

2 Analogous estimates

3 Parametric Estimating

4 Three-Point Estimates

5 Reserve Analysis (contingency)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-105

Unit 6 Project Time Management

0 Estimating in General

General Idea

Rules of Thumbs and SWAGs

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-106

Unit 6 Project Time Management

General Principles of Estimation

General Principles

Pitfalls of Estimation

General Volumetrics

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-107

Unit 6 Project Time Management

General Estimating

Estimates are just that!

Example: how long does it take you to drive to work?

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-108

Unit 6 Project Time Management

Distributions

How measurements might be distributed

Plot the length of 100 meter sticks

Plot the Julian birthday of every Canadian (JBD is the day of the year tat you were born. Jan01=1 and Dec 31=365)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-109

Unit 6 Project Time Management

The Normal Distribution

0

0.2

0.4

0.6

0.8

1

1.2

1 3 5 7 9 11 13 15 17 19

Normal Curve

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-110

Unit 6 Project Time Management

Normal Distribution

0

0.2

0.4

0.6

0.8

1

1.2

-9S

-7S

-5S

-3S

-1S 1S 3S 5S 7S 9S

Normal Curve

MEAN

6Σ 3.4 in 106

5Σ 1.0 in 105

4Σ 1.0 in 104

3Σ 1.0 in 103

2Σ 1.0 in 102

1Σ 1.0 in 101

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-111

Unit 6 Project Time Management

Six-Sigma

One and two tailed estimates

Ours are normally one-tailed

2 is 99%

3 is 99.9%

4 is 99.99%

5 is 99.999%

6 is 3 part in a million (99.9999)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-112

Unit 6 Project Time Management

Question?

You have a 2400 square foot house and you order your cleaner to clean it to within 6.

What is the size of the largest piece of dirt?A thimble?

A teacup?

A saucer?

A bathroom?

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-113

Unit 6 Project Time Management

General Estimating cont.

normally, use the average

the (1+4+1) / 6 is good

be realistic (factor in time of year)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-114

Unit 6 Project Time Management

Rules of Thumbs

My Uncle's example

The Rule of 3

The Back of the Envelope

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-115

Unit 6 Project Time Management

The Rule of 33 people in my house30 close neighbours300 on my jogging route3000 in my school draw30000 in my ward300,000 in London3,000,000 in Ontario-Toronto30,000,000 in Canada300,000,000 in NA (- Mexico)3,000,000,000 "consumers" in the world

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-116

Unit 6 Project Time Management

Rules of Thumbs (jon bentley)

How much water flows out of the Mississippi River in one day (cu miles)?

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-117

Unit 6 Project Time Management

Rule of 72

Exponential are difficult

Most of our problems ARE expos

If you invest a sum that must double in y years at an interest rate of r percent/yr then r*y = 72 holds. (RULE OF 72)

Example, how long will it take for $1,000 to double at 6%? 72/6=12 years ($2012)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-118

Unit 6 Project Time Management

Example

A program takes 10 seconds for size n=40

Increasing n by 1 increases time by 12% (expo)

Rule-of-72 says RT doubles when n increases by 6

By 60, then 1,000

By 160, 107 seconds

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-119

Unit 6 Project Time Management

Help Ma!

How BIG is 107 anyway?

Actually dear, 3.155x107 seconds in a year

Or seconds in a nanocentury

264 = 100,000,000 donuts/sec for 5,000 years

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-120

Unit 6 Project Time Management

The Delphi Approach

No clear way to estimate

Gather a group of Xperts

Give them the problem; they go away and independently estimate as well as they can

They meet and exchange information

Then they repeat the above

After 3-4 cycles they will normally converge on a unified answer

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-121

Unit 6 Project Time Management

A Little Quiz (thanks Jon)(give 1+4+1 confidence limits)

1. Canadian population Jan 1,2004

2. Year of Napolean's birth

3. Length of the Great Lakes/St Lawrence watershed

4. Maximum takeoff weight of a 747 (pds)

5. Mass of the earth

6. Number of Fathers of Confederation

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-122

Unit 6 Project Time Management

7. Latitude of London England

8. Number of airplanes in the air at this minute

9. Number of PCs in Canada

10.Number of bones in the adult human

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-123

Unit 6 Project Time Management

General Estimating cont.

make sure you have a complete SOW

work out the WBS completely

hand off to the person responsible to estimate and cost

collect them in the PP

note that you do this at EACH of the three levels of report generation

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-124

Unit 6 Project Time Management

Things to Avoid

warm fuzzies

too-new technologies

biggies

too-optimistic estimates

LINEARITY

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-125

Unit 6 Project Time Management

Linear Scaling

1 person can do the work in 8 days

2 can do it in 4

4 can do it in 2

8 can do it in 1

16 can do it in ½ a day

32 in a ¼

64 in an hour etc etc

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-126

Unit 6 Project Time Management

Examples

How many kilometers per year does a taxi driver drive if he works an 8 hours day 200 days a year?

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-127

Unit 6 Project Time Management

Conclusions, Crystal Balling

It Works!

can easily tailor the tool to the organization’s process and culture

can instrument to collect metrics

can do the EV easily

can prompt the user for missing steps

can archive for the Morgue

can collect quality metrics

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-128

Unit 6 Project Time Management

1 Expert Judgment

Remember my definition of xpert

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-129

Unit 6 Project Time Management

2 Analogous Estimates

Compares against work already done

Is really a form of expert judgment

Are most reliable whenPreviously done activities are very similar

Experts really know the area

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-130

Unit 6 Project Time Management

3 Parametric Estimating

When we know the rates

For example, function points and the Industrial Averages

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-131

Unit 6 Project Time Management

4 Three-Point Estimates

Most likely

Optimistic

Pessimistic

Useful for worst-case, best-case scenarios

Rule-of-Six gives better estimates

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-132

Unit 6 Project Time Management

4 Reserve Analysis (contingency)

Buffer in case of risky activities

Need to annotate the reasons for asking for one

Known-unknowns (contingency)

Unknown-unknowns (management reserves)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-133

Unit 6 Project Time Management

6.4.3 Outputs for Activity Duration Est

1 Activity duration estimates

2 Bases of estimates

3 Activity lists updates

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-134

Unit 6 Project Time Management

1 Activity Duration Estimates

Need also to list the confidence levels of the estimates

Prob or SD good here

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-135

Unit 6 Project Time Management

6.5 Schedule Development

1 OPA2 Scope Statement3 Act List4 Act Atts5 Sched N/W Diags6 Act Res Reqs7 Res Cals8 Act Dur Ests9 Risk Register

1 Sked N/W Anal2 CPM3 Sked Compress4 What-if Anal5 Res Leveling6 Critical Chain 7 PM Software8 Applying Cals9 Adjusting L&Ls10 Schedule Model

1 Project Sched2 Sched Model Data3 Sched Baseline4 Res Reqs (ups)5 Act Atts (ups)6 Proj Cals (ups)7 Req’d Changes8 PMP (ups)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-136

Unit 6 Project Time Management

Inputs from OPAs

Project calendar may dictate days when no work can be done.

Shifts may be constrained

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-137

Unit 6 Project Time Management

Input from Scope Statement

PSS can contain assumptions and constraints that affect schedule development; two main types1 Internally imposed dates

Agreed-upon contract datesWeather restrictionsGovernmental mandated compliance dates“Start no earlier than” and “Finish no later than” most commonly used

2 Externally imposed datesStakeholders can dictate important datesMilestones hat connect to external projects

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-138

Unit 6 Project Time Management

7 Calendars

These show when resources and the project are available for work assignment

Resources have vacations, religious holidays etc

A labour contract may limit the days of the week a person can work

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-139

Unit 6 Project Time Management

6.4.2 T&T for Schedule Development

1 Schedule Network Analysis2 Critical Path Method3 Schedule Compression4 What-if Analysis5 Resource Leveling6 Critical Chain Method7 PM Software8 Applying Calendars9 Adjusting Leads & Lags10 Schedule Model

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-140

Unit 6 Project Time Management

1 Schedule Network Analysis

This generates the project schedule

Uses the following techniques

Checks for loop or open ends

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-141

Unit 6 Project Time Management

2 Critical Path Method

Uses the earliest start and finish dates and the late start and finish dates without any regard to resource limitations

Worries about float

Does a forward pass and a backward pass

Uses a single estimate for each activity

Leads to a Critical Path and a deterministic schedule

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-142

Unit 6 Project Time Management

Types of Float

Free Float – time a task can be delayed without delaying the early start date of its successorTotal Float - time a task can be delayed without delaying the project completion dateProject Float - time the project can be delayed without delaying the externally imposed project completion date (by customer, management, project manager etc.)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-143

Unit 6 Project Time Management

Passes

To compute the likely finish time plus critical path(s)Forward pass

Start at the beginning

Backward passStart at the customer’s wanted finish date and work backwards

Can have negative float!

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-144

Unit 6 Project Time Management

Two ways to compress without descopingCrashing

Fast-tracking

3 Schedule Compression

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-145

Unit 6 Project Time Management

Crashing

Try to compute the CP

Work out the cost per week to crash

Start with lowest

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-146

Unit 6 Project Time Management

Crashing with CPM

A.4.

F.6

E.7C.2

D.2B.6

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-147

Unit 6 Project Time Management

Crash Data

Normal Crash Norm$ Crash$ CC/wk

A 4 2 10K 14K 2K

B 6 5 30K 42.5K 12.5K

C 2 1 6K 9.5K 3.5K

D 2 1 12K 18K 6K

E 7 5 40K 52K 6K

F 6 3 20K 29K 3K

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-148

Unit 6 Project Time Management

Crash details

Normal time

Crash timeNote; follows U-curve

CT is most compressed time

Compute (CC-NC)/(NT-CT)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-149

Unit 6 Project Time Management

Crashing

Try to compute the CP

Work out the cost per week to crash

Start with lowest

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-150

Unit 6 Project Time Management

Crashing Problems

May not be possible

Will INCREASE costs for sure

Assumes that you can take people off one task and add them to another (true in construction for example; may well NOT be true in IT!)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-151

Unit 6 Project Time Management

Fast Tracking

Do CP tasks that were planned in series, in parallel

Problems:Often forces rework

Increases risk

Requires more communications

May cost more (need new people)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-152

Unit 6 Project Time Management

4 What-if Scenario Analysis

As seen

Often uses Monte Carlo techniques to check out worst-case, best-case, random-case examples

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-153

Unit 6 Project Time Management

5 Resource Leveling

Critical path may over-allocate resources

Necessary to “level” them

An option in MSP

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-154

Unit 6 Project Time Management

Resource Loading and Leveling

Resource loading: amount of individual resources an existing project schedule requires during specific time periodsResource histograms show resource loadingOver-allocation means more resources than are available are assigned to perform work at a given time

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-155

Unit 6 Project Time Management

Resource Leveling

Resource leveling is technique for resolving resource conflicts by delaying tasks

Primary purpose of resource leveling: create a smoother distribution of resource usage & reduce over-allocation

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-156

Unit 6 Project Time Management

Resource Histogram for Large IT Project

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-157

Unit 6 Project Time Management

Histogram Showing an Over allocated Individual

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-158

Unit 6 Project Time ManagementResource Leveling Example

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-159

Unit 6 Project Time Management

6 Critical Chain

A better way

Each activity has a mean of execution time, not a constant

CC says, start as soon as you finish

Suppose A B, A = 4±2, B=6±3

CMP says B starts on Day 5, regardless

CC says, start on Day 3 if lucky

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-160

Unit 6 Project Time Management

CC comments

Idea is to take advantage of early finishes

What tends to happen in Anal Orgs is that the start date of each task is fixed

When CP task slips, whole project time slips

When it is early, people go fishing until the specified start date of the next task

CC starts ASAP and averages out under runs and overruns

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-161

Unit 6 Project Time Management

7 PM Software

Can be used to do the preceding techniques

Can print out nice diagrams of the schedules

Can compress/expand as needed

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-162

Unit 6 Project Time Management

8 Applying Calendars

Used to cover weather events etc. as seen

Can be used for scenarios such asOnly regular hours allocated

Two shifts

7x24 shifts

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-163

Unit 6 Project Time Management

9 Adjusting Leads & Lags

Can be modified in the simulation to see how sensitive the schedule is to adjusting leads and lags

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-164

Unit 6 Project Time Management

10 Schedule Model

This is the final sign-offed product that will be used for the duration of the project

Very important for ICC to check the effects of changes in scope, requirements

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-165

Unit 6 Project Time Management

Coding Structure

Activities should have a code (database?) so that you can sort/extract on different attributes of the activities such as

ResponsibilityGeographic areaBuildingProject phaseSchedule levelWBS classification

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-166

Unit 6 Project Time Management

6.5.3 Outputs from Schedule Development

1 Project Schedule2 Schedule Model Data3 Schedule Baseline4 Resources Requirements (ups)5 Activity Attributes (ups)6 Project Calendars (ups)7 Required Changes8 PMP (ups)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-167

Unit 6 Project Time Management

1 Project Schedule

Includes at least a start and end date for every schedule activity

Normally presented graphicallyNetwork Diagram

Bar (Gannt) charts

Milestone charts

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-168

Unit 6 Project Time Management

2 Schedule Model Data

Supporting data for all activity attributes, all schedule activities, all assumptions and constraints

Also may includeResource requirements by time period

Alternative schedules (best, worse)

Schedule contingency reserves

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-169

Unit 6 Project Time Management

3 Schedule Baseline

This is the approved-by-management schedule for tracking purposes

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-170

Unit 6 Project Time Management

6.6 Schedule Control

This must do 3 things1. Ensure that changes are agreed on

2. Determine that the schedule has changed

3. Managing the changes when they occur

Is another example of change control and if it is integrated properly, can be rolled up into it

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-171

Unit 6 Project Time Management

Schedule Control

1 Sched Man Plan2 Sched BL3 Perf Reps4 App’d Change Reqs

1 Prog Reporting2 Sched CC System3 Perf Meas’t5 PM Software6 Variance Anal7 Sched Bar Charts

1 Sked model (ups)2 Sked BL (ups)3 Perf Meas’s4 Req’d Changes5 Rec’d Corrects6 OPA (ups)7 Act List (ups)8 PMP (ups)9 Act Atts (ups)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-172

Unit 6 Project Time Management

6.5.1 Inputs to Schedule Control

1 Schedule Management Plan

2 Schedule Baseline

3 Performance Reports

4 Approved Change Requests

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-173

Unit 6 Project Time Management

3 Performance Reports

These flow out of communications

Indicate when we are falling behind and signal the need for change

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-174

Unit 6 Project Time Management

4 Approved Change Requests

Once an item has been baselined, it is put under CCM

Should be a form which is filled out and this, when approved by the CCB, is put into the Schedule Control process

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-175

Unit 6 Project Time Management

6.5.2 T&T for Schedule Control

1 Progress Reporting

2 Schedule CC System

3 Performance Measurement

5 PM Software

6 Variance Analysis

7 Schedule Bar Charts

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-176

Unit 6 Project Time Management

1 Progress Reporting

Records actual start and finish dates (as opposed to planned)

Has all EV measurements

Should be in an org-wide template form

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-177

Unit 6 Project Time Management

2 Schedule Change Control System

Formal procedure by which we do the changes

See unit 4.

Is a very important case of CCM

Is isolated here to stress its importance

Necessary approvals here important

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-178

Unit 6 Project Time Management

3 Performance Management

Need to understand the metrics of PM and assess if change is needed immediately or can it wait?

If the activity is on the CP, do it now

If off the CP, could wait a bit

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-179

Unit 6 Project Time Management

4 PM Software

Lets us know when corrective action is necessary

Could be a push technology (here be dragons!)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-180

Unit 6 Project Time Management

5 Variance Analysis

Critical for the EV portion of time

Float is key here

Need to sort sub-critical paths in terms of increasing float

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-181

Unit 6 Project Time Management

6 Schedule Comparison Bar Charts

Also called “double Gantting”

Two bars; one the actuals, one the planned. Is another way to track progress. Note the fallacy compared with EVM

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-182

Unit 6 Project Time Management

6.5.3 Outputs from Schedule Control

1 Schedule Model (ups)2 Schedule Baseline (ups)3 Performance Measurements4 Required Changes5 Required Corrects6 OPA (ups)7 Activity List (ups)8 PMP (ups)9 Activity Attributes (ups)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-183

Unit 6 Project Time Management

1 Schedule Model Updates

Any modification to the schedule

Must notify stakeholders

May trigger updates to other parts of the PMP

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-184

Unit 6 Project Time Management

Schedule Baseline Revisions

These are changes to the project’s start and finish date

Are major

May require rebaselining (a Baaaad thing)

Rebaselining is a Last Resort

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-185

Unit 6 Project Time Management

5 Corrective Action

Anything done to bring future performance in line with the planned estimates

Often involves expediting

Need to do a root cause analysis to avoid future deviations

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-186

Unit 6 Project Time Management

6 OPA Updates (Lessons Learned)

REALLY important

“Those who ignore the failure lessons of history are doomed to repeat them” G. Santayana

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-187

Unit 6 Project Time Management

Chapter Six: Time Management

2000 Edition

6.1 Activity Definition

6.2 Activity Sequencing

6.3 Activity Duration Estimating

6.4 Schedule Development

6.5 Schedule Control

Third Edition

6.1 Activity Definition

6.2 Activity Sequencing

6.3 Activity Resource Estimating

6.4 Activity Duration Estimating

6.5 Schedule Development

6.6 Schedule Control

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-188

Unit 6 Project Time Management

Case Study: Panama Canal (french)

Experts recommendedA sea-level canal (like Suez)

Reducing TL from 12 to 8 years

Reducing cost from $240M to $169M

Reducing the contingency from 25% to 10% (ignored cost of capital, cost of purchasing Panamanian railroad, administrative costs)

Estimators doubled the anticipated excavation volume by 100% (while doing the cost reduction)

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-189

Unit 6 Project Time Management

De Lesseps goes to Panama

Spent 1 week there

Reduced the cost estimate to $132M

Discounted the deadly climate as “an invention of adversaries”

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-190

Unit 6 Project Time Management

The Result:

20,000 Frenchmen died

Spent $287M for little work

Estimates were based on what they could SELL to the investors, not the actual cost

Philosophy: “get her started” and we’ll figure out something later

Big Dig!

2K6-X-08 Dr. J.M. Bennett, P.Eng., PMP EP 7046-191

Unit 6 Project Time Management

WBS Structures the Project NetworkProject

ProjectProject

ProjectProject

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11

Sub A11