Solution Hotel - Hoval - Responsibility for energy and …€¦ · Description Hot water system:...

Post on 15-Apr-2018

215 views 2 download

transcript

Solution – Hotel

Content

1. Company description

2. Requirements

3. Specification

4. How does the solution look like?

5. Controls

6. Customer benefit

7. Costs

8. Summary

2 © Hoval / Mar-14 Hoval

The company

Jolie Ville Hotels

(former Mövenpick Jolie Ville)

Founded 1991 in Aegypten

Owner buys the brand Jolie Ville from Mövenpick and

starts expansion

Today cooperation with the German Hotel chain Maritim

3 © Hoval / Mar-14 Hoval

The company

International Congress Center (Sharm) 2006

© Hoval / Mar-14 Hoval 4

The company

Golf Hotel (Sharm): 1998 hot water and 2006 steam

system

© Hoval / Mar-14 Hoval 5

The company

Resort and Casino – Naama Bay (Sharm) 1990 ModulPlus

© Hoval / Mar-14 Hoval 6

Requirements

Efficient hot water and steam system (Split)

for expansion of Jolie Ville Hotel in Luxor – Kings

Island

400 additional rooms

Pool heating

Replacement of 42 electric heated tanks

Pool boiler house stand-by

Very tight time schedule: Finishing of the complete

project by X-mas (Guests have already bookings!)

Proofed system

Quality - Safety

4 © Hoval / Mar-14 Hoval

Description

Hot water system: 3-zones

Zone 1: 5 Bungalows and 3 Villas

Zone 2: 5 Bungalows

Zone 3: 34 Villas

21 existing Bungalows Replacement of 42 DHW-tanks

New pool with boiler, heat exchanger and filters

Steam system for most modern laundry

8

© Hoval / Mar-14 Hoval

Plant description

6 © Hoval / Mar-14 Hoval

Solution?

2 x THD-U 3000 11bar

7 © Hoval / Mar-14 Hoval

Solution?

Armatures steam header and steam reducing stations

11 © Hoval / Mar-14 Hoval

Solution?

12

2 x THW-I 45/35 NTE

6bar

6 x Modul-Plus F52

Correx

Expansions System

pumpen 264 m3/std

40m Höhe

PLC - Steuerung

© Hoval / Mar-14 Hoval

Hoval System Solution (P&ID)

8 © Hoval / Mar-14 Hoval

Hoval System Solution (P&ID

heat exchanger

14 © Hoval / Mar-14 Hoval

Hoval System Solution (P&ID)

steam boiler plant

15 © Hoval / Mar-14 Hoval

Hoval System Solution (Controls)

9 © Hoval / Mar-14 Hoval

Main Display of Touch Panel S7-200

17 © Hoval / Mar-14 Hoval

Benefit

Easy design "turnkey" solution

Time-saving

Low risk

Hotwater boilers THW-I 45/35 and

hotwater suppy devided in 3 zones:

Very high operating reliability

No interruptions

Hoval system One-stop solution

Time-saving thanks to easy projecting

16 © Hoval / Mar-14 Hoval

Investment cost

Total investment cost (exw) EUR 852‘000,--

Consisting of:

- 2 x THW-I 45/35 NTE 6bar

- 2 x THD-U 3000 E 11bar

- 6 x Modul Plus F52 Correx solution

- 2 x THD-U 3000 E 11bar (Sharm El Sheik)

19 © Hoval / Mar-14 Hoval

Conclusion

© Hoval / May-11 22

Competence as solution supplier

Hoval