Post on 29-Nov-2014
description
transcript
Building the Future
Current Activities this Week:
Site/Playing field:
Grading site on the East side of building to be ongoing.
Cleaning up areas in preparation of plaza work is ongoing.
Underground drainage and irrigation at the playing field
is ongoing.
Concrete Flatwork:
Area 1-Suite and Press level tub intermediate stairs are
ongoing.
Area 1- Platform for Stadium Suite bar area is complete.
Area 3-Base slab at cauldron club extended out for
curtain wall installation is complete.
Finishing of exposed concrete walls to be ongoing.
Area 1- SOG work at SW toilet entry to be completed.
Masonry:
Block installation at NW transformer area to be ongoing.
Block installation at Terrace Bar is ongoing.
Block installation at SW toilet entry to be ongoing.
Sealing and final wash of block on the East side to begin.
Stone:
Area 1-Stone installation in area H to be ongoing.
Steel:
Installation of roll up doors in concessions is ongoing.
Installation of stone support steel at Stadium Suite is
ongoing.
Area 3-Subroof under Stair #1 to be ongoing.
Installation of SE corner screen wall tubes is ongoing.
Installation of bar joists and roof decking in area H to begin.
Installation of dock overhead doors to begin.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
Brandon Valdez-Turner
From: Nick Durand
Office: Kansas City
Date: 2.23.2011
Re: Sporting Kansas City
Project Update – Week of
2.23.2011
Installation of field drainage and irrigation
lines.
Installation of Suite level intermediate stairs.
Building the Future
Roofing and Sheet metal:
Area 1-Alucobond metal panel installation at Suite and
Press level on field side is near complete.
Alucobond metal panel and subgirt installation is
ongoing at Concourse buildings.
Drilling anchors for exterior fins is ongoing in all areas.
Area 3-Concourse building roofing is ongoing in the SE.
Louver installation at East side is complete.
Gutter shrouds at canopy gutter are ongoing.
Canopy deck flashing installation is ongoing.
Polycarbonate:
Area 1-Polycarbonate installation is ongoing.
Area 2-Polycarbonate installation is ongoing.
Metal Stud Framing/Drywall/Ceilings:
Area 1- Drywall installation is near complete.
Area 3-Drywall installation and finishing is near complete.
DAFS installation is ongoing at exterior soffits.
Stud framing for North screenwall/ metal panels is ongoing.
Drywall installation in concessions/retail areas is
Ongoing.
FRP installation in Concessions is ongoing.
Ceiling grid installation is ongoing on all levels.
Glass:
Area 1-Storefront at 24-27 lines installation is
complete.
Area 1-installation of aluminum door frames is ongoing.
Area 1-installation of store fronts at VIP entrance is
complete.
Installation of storefronts at Main Concourse retail
buildings is ongoing.
Installation of Press level Solar innovation sliders is
ongoing.
Area 1- installation of interior storefronts is ongoing.
MEP:
Ductwork installation in the west tower is complete
and is ongoing on the East side field level.
Plumbing rough is complete in the west tower and is
ongoing on the East side field level.
Installation of metal panels at concessions.
Block work at SW toilet entrance.
Building the Future
Site-SE and SW transformers have been energized.
NW transformer is now set and primary cables are being pulled to transformer.
Installation of the backbone cable is complete and is terminated
in the IT rooms.
All racks and cabinets in the West tower have been
assembled and termination of cables is near complete.
Concession building rough in for all MEP is near complete.
Installation of permanent lights and speakers in soffits is ongoing.
Fixtures and devices are being installed in the West
tower and termination of branch circuits is ongoing.
South scoreboard module installation is complete.
Sub air equipment is installed and all secondary
work is complete.
Area 1-installation of toilet fixtures on Suite and Field level
is ongoing.
Broadcast cable pulls from loading dock to the Video
Production room is ongoing.
Tie –in of canopy gutters to downspouts is ongoing.
North scoreboard structure installation to begin.
Elevators:
F1 elevator installation is near completion.
P2 & P3 elevator installation is ongoing.
P4 & P5 elevator installation is ongoing.
P1 has been delivered and installation to begin.
Painting:
Area 1-Painting at Field level is ongoing.
Area 1-Painting in Main Concourse buildings is ongoing.
Area 1-Painting on Press and Suite level is near complete.
Sealing of exposed concrete floors is ongoing.
Resinous flooring at field level is ongoing.
Resinous flooring in Concessions, Suite, and Press
is ongoing.
Painting of stair structure and walls is ongoing.
Tile:
Tile in Suites on Suite level is complete.
Tile installation in club areas at Suite and Press levels
has begun.
Tile in restrooms at all levels is ongoing.
Installation of storefronts at V.I.P entrance.
Tile installation at Field Club.
Building the Future
Food Service:
Countertop installation in Concessions is complete.
Installation of all counters and kitchen equipment at Mezz level, Suite level, and Press
level to be ongoing.
Cooler installation in concessions and cauldron club is near complete.
Exhaust hood installation in cauldron club to begin.
Projected Activities occurring next Week:
Concrete Flatwork:
Area 1-Suite and Press level tub intermediate stairs to be
completed.
Finishing of exposed walls to be completed.
Cauldron Club topping slab installation to begin.
Stone/masonry:
Block installation at NW transformer area to be complete.
Block installation at Terrace Bar to be ongoing.
Block installation at SW toilet entry to be complete.
Stone installation in area H to be ongoing.
Steel:
Installation of roll up doors in concessions to be complete.
Installation of stone support steel at Stadium Suite to be
ongoing.
Area 3-Subroof under Stair #1 to be complete.
Installation of SE corner screen wall tubes to be complete.
Installation of bar joists and roof decking in area H to
be completed.
Installation of dock overhead doors to be ongoing.
Roofing and Sheet metal:
Canopy gutter shroud installation to be ongoing.
Area 3-North East concourse roof to begin.
Installation of metal panels at concessions to be ongoing.
Field measuring for metal panels at Stadium Suite to be
complete.
Installation of coping cap at concourse roof to be ongoing.
Painting is ongoing in RR’s at Main
Concourse.
Overhead door installation at loading dock.
Building the Future
Metal Stud Framing/drywall soffits:
Area 1- Drywall installation to be complete.
Area 3-Drywall installation and finishing to be complete.
DAFS installation to be ongoing at exterior soffits.
Stud framing for North screenwall/ metal panels to be complete.
Drywall installation in concessions/retail to be complete.
FRP installation in Concessions to be ongoing.
Ceiling grid installation to be ongoing on all levels.
Glass:
Area 1-Aluminum door frame installation to be ongoing.
Installation of storefronts at Main Concourse buildings
to be ongoing.
Installation of interior glazing at Field and Mezz. level to
be near complete.
Installation of Solar innovation sliders at back of suites on
Press level to be ongoing.
MEP:
NW transformer to be energized.
Installation of North Scoreboard to be ongoing.
Preliminary hydrostatic testing of the fire sprinkler lines to begin.
Energizing mechanical equipment to begin commissioning/start up.
Paint:
Area 1-Painting of the Suite and Press level areas to
be near complete.
Painting of the Main Concourse buildings to be ongoing.
Painting at Field level to be ongoing.
Sealing of concrete floors to be ongoing.
Painting of stair #4 and #9 to be complete.
Resinous flooring to be ongoing in concessions.
Playing Field:
Installation of underground drainage and irrigation lines
to be ongoing.
Drilling for fin anchors is ongoing.
Locker installation at field level.
Building the Future
Additional Photos:
Framing for metal panels at North main
concourse.
Subroof installation under Stair #1.
Tile and millwork installation at Executive Suites.
South scoreboard module installation is complete.