Post on 10-Feb-2016
description
transcript
1
The Replanting of Lochaber Hydro Power Station
by Andrew Thick
E V E N T S P O N S O R S
3
Topics to be covered today
• Scheme modelling;• Operating capability of Lochaber;• Turbine Selection;• Penstock works.
4
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
5
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
6
7
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
8
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
9
10
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
11
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
12
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
13
14
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
15
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
16
Schematic of the Lochaber Scheme
Loch Laggan & reservoir
Loch Treig
SpillSpill
Gravity Inflows Gravity
Inflows
Power-house
Tailrace
Spill
Surge Chamber
LochLinnhe
Spey reservoir
Penstocks
tunneltunnel
tunnel
17
18
Simplified Lochaber Scheme Model
QTspill
QP/H
QTin
Laggan
QTin
QTunnel
Treig
QLspillQLin
QLin
QLin
Qintakes
Qintakes
19
Energy Modelling Results
Trial 1 2 3 4 5 6 7
Installed Cap. (MW) 65 80 60 70 80 90 100
Overall Efficiency (%) 75 87 87 87 87 87 87
Headloss Coeff. (k) 0.021 0.0172 0.0172 0.0172 0.0172 0.0172 0.0172
Operating rule Ext Ext Max E Max E Max E Max E Max E
Laggan Spill (mcm) 2,034 1,794 4,160 1,709 1,227 1,074 801
Treig Spill (mcm) 154 121 857 201 54 10 7
Ave. Energy (GWh/yr) 467 569 523 574 581 583 580
20
Scheme Operating Capability Diagram
9.3 % Q90.7 % QAverage Operation
0 % Q100 % QNo Gravity Inflows
100 % Q0 % QMax. Gravity Inflows
21
Turbine Selection
The steps towards to turbine selection were:• Analysis of historical data of scheme operation• The number of generating units was selected – 5• Analysis of operating data from scheme model• Performance data from tendering suppliers was fed into the scheme model
22
Penstock works
Key aspects of the penstock works were:• Need to undertake the works minimising shutdown of generation.• Existing penstock system was very complex.• In order to maintain double isolation, the penstocks needed to be dewatered sequentially.• The works were complex with poor access. • Decision with RTA to laser scan the penstock system and create a 3-D model.
23
24
25
Penstock works
Key aspects of the penstock works were:• Need to undertake the works minimising shutdown of generation.• Existing penstock system was very complex.• In order to maintain double isolation for the penstocks needed to be dewatered sequentially.• The works were complex with poor access. • Decision with RTA to laser scan the penstock system and create a 3-D model.
26
27
28
Project Summary
• The generating plant has been replaced to give 25+ years life extension.
• The water to wire efficiency has been improved from 75% to 90+%.
• Energy production increased from 460 GWh/yr to 600+ GWh/yr.
• The scheme’s capability is better understood and limitations identified.
• The scheme was completed ahead of schedule and is operating successfully with minimal disruption to Smelter operations during construction
Contact Details
Andrew Thick BEng CEng MIMechEURS Infrastructure and Environment UK LimitedInternational House, Dover PlaceAshfordKent TN23 1HUUnited KingdomTel: +44 (0) 1233 658200hydropower@urs.com
Thank you for your kind attention