Validation of Solar PV Power Forecasting Methods for High...

Post on 06-Feb-2018

215 views 1 download

transcript

New Energy Horizons Opportunities and Challenges

Validation of Solar PV Power Forecasting Methods for High Penetration Grid Integration

IEEE Power and Energy Society

General Meeting July 26, 2012

James Bing, NEO Virtus Engineering, Inc. Obadiah Bartholomy, Sacramento Municipal Utility District

Pramod Krishnani, Belectric North America Inc.

New Energy Horizons Opportunities and Challenges

Project Sponsors and Partners

CPUC

2

CSI Solar RD&D Program www.calsolarresearch.ca.gov

CSI RD&D Program Manager

New Energy Horizons Opportunities and Challenges

TOPICS • PROJECT BACKGROUND • TECHNICAL BACKGROUND • EXPERIMENTAL DESIGN • PRELIMINARY RESULTS • ONGOING WORK • CONCLUSIONS

3

New Energy Horizons Opportunities and Challenges

PROJECT BACKGROUND

• California Public Utilities Commission High Penetration PV Program

• Sacramento Municipal Utility District 100MW Feed-in-Tariff

• Parallel Research Effort (DOE FOA: Improving the Accuracy of Solar Forecasting)

4

New Energy Horizons Opportunities and Challenges

CPUC High Penetration PV Program • CPUC established CSI RD&D Program in 2007

– Allocated $50 million for research, development, demonstration and deployment (RD&D) projects to further the overall goals of the CSI Program

– Adopted the “CSI RD&D Plan” • CSI RD&D Plan established:

– Goals and objectives – Allocation guidelines for project funding – Criteria for solicitation, selection and project funding

• Three Target Areas Established for Program Funding: – Grid-Integration: 50-65% – Production Technologies: 10-25% – Business Development and Deployment: 10-20%

5

New Energy Horizons Opportunities and Challenges

Sacramento Municipal Utility District 100MW Feed-in-Tariff

• SMUD max summer load ~3GW • Feed in Tariff = 100MW or ~3% of peak load • ~36 MW of hidden “behind the meter” PV • SMUD capacity expected to grow, goal of 125 MW

net metered PV by 2016 • Power integration issues are very (grid) site

dependant: Forecast capability addresses/informs planning, automation and curtailment/mitagation issues

6

New Energy Horizons Opportunities and Challenges

NDFD Grid, Primary & Secondary Sites SMUD Service Territory

7

New Energy Horizons Opportunities and Challenges

Sacramento Municipal Utility District Multi-forecaster Benchmarking

•SMUD will be using irradiance network and FiT systems to benchmark forecast performance for 4 forecasters in addition to Neo Virtus beginning in August

•Forecasters will provide hourly forecasts, uncertainty and 5 minute variability on hour ahead up to 5 days in advance for each irradiance sensor and FiT system output

•Sandia Labs will quantify forecast accuracy for various weather conditions and timeframes

•Goal is to understand broadly state of the art in forecast accuracy and ability to trust forecast performance for different timeframes

8

New Energy Horizons Opportunities and Challenges

TOPICS • PROJECT BACKGROUND

• TECHNICAL BACKGROUND • EXPERIMENTAL DESIGN • PRELIMINARY RESULTS • ONGOING WORK • CONCLUSIONS

9

New Energy Horizons Opportunities and Challenges

TECHNICAL BACKGROUND

• Irradiance Fundamentals • PV Power Simulation Fundamentals • Current Solar Forecasting Methods • NEO Virtus Day Ahead Forecasting

of AC Power

10

New Energy Horizons Opportunities and Challenges

Irradiance Fundamentals

11

• Direct Normal Irradiance (DNI) • Diffuse Horizontal Irradiance (DHI) • Global Horizontal Irradiance (GHI): GHI = DNI cos ϴ +DHI • 1000W/m2 GHI ≈ Full Scale or 1pu (nominal at sea level)

New Energy Horizons Opportunities and Challenges

Irradiance Fundamentals

12

• Plane of Array Irradiance (POA) = Incident Irradiance on PV array • POA can be calculated with a knowledge of:

– Direct Norman Irradiance (DNI) and Diffuse Horizontal Irradiance (DHI) and – PV system Azimuth, Tilt, Lat/Lon, Shading Obstruction, Date & Time

New Energy Horizons Opportunities and Challenges

PV Power Simulation Fundamentals

13

New Energy Horizons Opportunities and Challenges

Current Solar Forecasting Methods

Technology Time Horizon Coverage Satellite 12hr to 7 days Global

Mesoscale NWP models

12hrs to months Global/ Regional

Aggregated Ground Sensors

1hrs to 3hrs Regional

SkyImager 30min to 3hrs 2 to 10km radius

Array Scale Sensors

1 to 30 minutes Array Size

14

New Energy Horizons Opportunities and Challenges

NEO Virtus Method for Day Ahead Forecasting AC Power

15

Collect Forecast Cloud-cover (NEO uses NDFD data): Cloud fraction (%)

Collect PV Array Data: Azimuth, Tilt, Lat/Lon, Shading, Capacity, Inverter, etc.

Simulate: • Sun Position Model: zenith & azimuth angles (º) • Irradiance Transmittance Model: DNI & DHI (W/m^2) • PV Array Geometry & Shading Model: POA (W/m^2) • Photovoltaic Conversion Model: DC Power (Wdc) • Inverter & Losses Model: AC Power (Wac)

CLOUDCOVERFORECAST+

PV ARRAY SPECS

IRRADIANCETRANSMITTANCE

MODEL

SOLARGEOMETRY

MODEL

PV ARRAYGEOMETERY+

SHADING

PV CONVERSIONMODEL

INVERTER+LOSSES MODEL

AC POWEROUT

New Energy Horizons Opportunities and Challenges

TOPICS • PROJECT BACKGROUND • TECHNICAL BACKGROUND

• EXPERIMENTAL DESIGN • PRELIMINARY RESULTS • ONGOING WORK • CONCLUSIONS

16

New Energy Horizons Opportunities and Challenges

EXPERIMENTAL DESIGN

Build & deploy irradiance monitoring network Monitor utility scale PV system power production Validate irradiance forecast performance territory-wide 0-3 hour ahead Day ahead Validate PV power production forecast for SMUD

Feed-In-Tariff (FIT) PV Systems 0-3 hour ahead Day ahead

17

New Energy Horizons Opportunities and Challenges

Primary & Secondary Irradiance Monitoring Station Specifications

18

• Irradiance Monitoring Network – 5 primary monitoring stations

• GHI, DHI, DNI • Ambient temperature • 1 minute averages

– 66 secondary monitoring stations • GHI • Ambient temperature • 1 minute averages

New Energy Horizons Opportunities and Challenges

Secondary Station Design & Fabrication

19

• Irradiance Monitoring Network – 5km grid Sacramento – NDFD Lambert conformal

projection – Installed on SMUD utility

poles – Automated data retrieval

via cellular modem – 14 month continuous data

New Energy Horizons Opportunities and Challenges

Primary & Secondary Monitoring Stations

20

New Energy Horizons Opportunities and Challenges

Day Ahead Irradiance & PV Power Forecast Validation

21

1-minute, 5km resolution GHI & Temp database

NEO Forecast vs. Measured irradiance validation

NEO Forecast vs. Measured PV

power production validation

New Energy Horizons Opportunities and Challenges

Solar Forecasting Error Analysis

Relative (percent) Error*: RMSE/Capacity MAE/Capacity MBE Data were filter for zenith angle >90 (no night

time data were used). No plant availability information was

provided: we assumed 100% availability. * Hoff, Perez, Kleissl, Renne, Stein: “Reporting of Relative Irradiance Prediction Dispersion Error”

22

New Energy Horizons Opportunities and Challenges

TOPICS • PROJECT BACKGROUND • TECHNICAL BACKGROUND • EXPERIMENTAL DESIGN

• PRELIMINARY RESULTS • ONGOING WORK • Territory-wide measured irradiance data

animation

23

New Energy Horizons Opportunities and Challenges

PRELIMINARY RESULTS

• NEO 20-36 Hour (Day Ahead) Forecasting Model PV Production 5/1/12 to 7/2/12 • R2 = 0.9398 • RMSE/Capacity = 8.61% • MAE/Capacity = 5.57% • MBE = -2.39%

24

New Energy Horizons Opportunities and Challenges

NEO’s Day Ahead Forecast vs. Measured One SMUD FIT PV System 5/1/12 to 7/2/12

25

R² = 0.9398

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

Fore

cast

ac

prod

uctio

n (%

capa

city)

Measured ac production (% capacity)

SMUD FIT PV Array

New Energy Horizons Opportunities and Challenges

NEO’s Day Ahead Forecast vs. Measured PV Production (one system)

26

0

2

4

6

8

10

12

14

16

18

6/3/2012 6/4/2012 6/5/2012 6/6/2012 6/7/2012 6/8/2012

BP01 measured ac (avg 1 min)

BP01 forecast ac

New Energy Horizons Opportunities and Challenges

Unforeseen Issues, Lessons Learned

• Shadows cast by overhead lines and crossbars causing “artifacts” in daily data – Sandia & SMUD are working out algorithm to filter data

• Data logger flash memory failures – Code was changed and manufacturer replaced failed units

• Secondary sensors cannot be cleaned economically – Precision Spectral Pyrranometers which can be cleaned

and maintained are used for system-wide calibration

27

New Energy Horizons Opportunities and Challenges

Overhead Wire Shading Anomalies

28

0

5

10

15

20

25

30

35

0

100

200

300

400

500

600

700

800

900

1000

1100

5:30 6:30 7:30 8:30 9:30 10:30 11:30 12:30 13:30 14:30 15:30 16:30 17:30 18:30 19:30 20:30

Tem

pera

ture

(°C)

Irra

dian

ce (W

/m2 )

Time (Pacific Standard Time)

Global Horizontal Radiation 6/25/11 SMUD/NEO Virtus Secondary Station #64

DAS# 64 POLE# UD122802 LAT: 38.59662 LON: -121.48561 Temp (⁰C)

0

5

10

15

20

25

30

35

0

100

200

300

400

500

600

700

800

900

1000

1100

5:30 6:30 7:30 8:30 9:30 10:30 11:30 12:30 13:30 14:30 15:30 16:30 17:30 18:30 19:30 20:30

Tem

pera

ture

(°C)

Irra

dian

ce (W

/m2 )

Time (Pacific Standard Time)

Global Horizontal Radiation 07/09/11 SMUD/NEO Virtus Secondary Station #64

DAS# 64 POLE# UD122802 LAT: 38.59662 LON: -121.48561 Temp (⁰C)

New Energy Horizons Opportunities and Challenges

Global Network Calibration

29

• Eppley Precision Spectral Pyranometer (PSP)

New Energy Horizons Opportunities and Challenges

TOPICS • PROJECT BACKGROUND • TECHNICAL BACKGROUND • EXPERIMENTAL DESIGN • PRELIMINARY RESULTS

• ONGOING WORK • CONCLUSIONS

30

New Energy Horizons Opportunities and Challenges

ONGOING WORK

Development of 0-3 hour ahead forecasts using sensor network Territory-wide GHI Feed in Tariff PV Systems Production Filtering of signal noise caused by cross arm

and wire shading Global calibration of sensor network

31

New Energy Horizons Opportunities and Challenges

TOPICS • PROJECT BACKGROUND • TECHNICAL BACKGROUND • EXPERIMENTAL DESIGN • PRELIMINARY RESULTS • ONGOING WORK

• CONCLUSIONS

32

New Energy Horizons Opportunities and Challenges

CONCLUSIONS

Solar forecasting technology is in the earliest stages of development Error metrics, time horizons and benchmarks

are being developed Numerous forecasting technologies are under

development Performance validation efforts for individual

forecasting technologies are being conducted There are front runners but currently no clear

winners in this technology race

33

New Energy Horizons Opportunities and Challenges

34

QUESTIONS?

James M. Bing, PE jbing@neovirtus.com

Obadiah Bartholomy OBartho@smud.org

Pramod Krishnani

pramod.krishnani@belectric-usa.com

NEO Virtus Engineering, Inc.