8/2/2019 Weekly Construction Report_2011.10.15
1/22
Weekly Construction Progress Report
TITAN Contract No. : CAF-583
LEC Job No. : 511838
WCPR-01
Report Period : 2011. 10. 09 ~ 10. 15
TITAN Project - T
8/2/2019 Weekly Construction Report_2011.10.15
2/22
1. Construction Activity Summary
2. Weather Record
3. Safety Control Status
4. Quality Control Status
5. Construction Progress Summary
6. Quantitative Construction Progress Status
7. Three Weeks Construction Schedule
8. Construction Manpower Status
9. Material Delivery Status
10. Pending Matters --> Status of Pending Items
11. Areas of Concern
Contents
8/2/2019 Weekly Construction Report_2011.10.15
3/22
1. Weekly Construction Activity Summary
Last Week Due Date Highlight
**
**
Major Activities
1) Civil
* Prepare Site ITP for Steel Stucture 13-10-2011
* Site Visit to Precast Concrete Supplier/Vendor 10-11-2011
*
*
2) Structure
**
3) Mechanical
*
*
4) Piping
8/2/2019 Weekly Construction Report_2011.10.15
4/22
1. Weekly Construction Activity Summary
**
5) Electrical
*
*
6) Instrumentation
*
*
7) Painting / Insulation
*
*
8/2/2019 Weekly Construction Report_2011.10.15
5/22
Status This Week Highlight
**
**
Major Activities
1) Civil
* Prepare Bill of Quantity/Work Volume for Civil Works
* Prepare & Update Work Breakdown Schedule for Civil Structure Work
2) Structure
**
3) Mechanical
*
*
4) Piping
8/2/2019 Weekly Construction Report_2011.10.15
6/22
**
5) Electrical
*
*
6) Instrumentation
*
*
7) Painting / Insulation
*
*
8/2/2019 Weekly Construction Report_2011.10.15
7/22
Due Date Status
Ongoing
Ongoing
8/2/2019 Weekly Construction Report_2011.10.15
8/22
8/2/2019 Weekly Construction Report_2011.10.15
9/22
2. Weather Record
Sun Mon Tue Wed Thu
10/9 10/10 10/11 10/12 10/13
2.1 Weather Condition
a. Clear Morning- clear Morning- clear Morning- clear Morning- cloudy
b. Cloudy Evening-cloudy Evening-cloudy Evening-storm Evening-clear
c. Rainy * Morning
* Afternoon
* Evening
** Total (mm)d. Windy
2.2 Temperature (C) Min - 24o
C Min - 24o
C Min - 24o
C Min - 24o
C
a. Highest Max - 32o
C Max - 32o
C Max - 32o
C Max - 32o
C
b. Lowest
2.3 Remarks
Description
8/2/2019 Weekly Construction Report_2011.10.15
10/22
Fri Sat
10/14 10/15
Morning- clear Morning- clear
Evening-storm Evening-storm
Min - 24o
C Min - 24o
C
Max - 32o
C Max - 32o
C
8/2/2019 Weekly Construction Report_2011.10.15
11/22
3. Safety Control Status
3.1. Induction Meeting / Training
1) Staff/Supervisor MD 4 0 4
2) Labor 15 0 15
3.2. Inspection for Construction Equipment
1) Pass EA 0 0 02) Reject 0 0 0
3.3. Incident / Accident
1) Working Hours without LTA HR 960 0 9602) LTA(Lost Time Accident) EA 0 0 03) First-Aid-Case 0 0 0
UnitPrevious
(Cumul.)Last Week
Current
(Cumul.)
8/2/2019 Weekly Construction Report_2011.10.15
12/22
4. Quality Control Status
1. Inspection Status
Period CivilSteel
StructureEquip. Piping Elec/Inst
Painting/
InsulationOthers Total Remarks
Previous (Cumul.) 0 0 0 0 0 0 0 0
Last Week 0 0 0 0 0 0 0 0
Current (Cumul.) 0 0 0 0 0 0 0 0
2. Highlights in Last Week
1) To Review Construction Specification for Civil and Steel Structural. : 11-10-17
2) :
3) :
4) :
5) :
8/2/2019 Weekly Construction Report_2011.10.15
13/22
5. Summary of Construction Progress
Project Const.
Discipline Weight Weight
% % This WK Cumul. This WK Cumul. This WK Cumul. This WK Cumul.
1 Temp. Fac. 0.53 3.29 - 100.00 - 100.00 - 0.53 - 0.53
2 Civil 1.52 9.44 3.00 31.00 - 1.22 0.05 0.47 - 0.02
3 Stl-Str. 2.64 16.39 2.00 19.00 - - 0.05 0.50 - -
4 Equipment 1.96 12.17 - - - - - - - -
5 Piping 6.01 37.31 - - - - - - - -
6 Electrical 1.90 11.79 1.00 2.00 - - 0.02 0.04 - -
7 I & C 0.90 5.59 1.00 2.00 - - 0.01 0.02 - -
8 Paint/Insul. 0.59 3.66 - - - - - - - -
9 Pre-Comm. 0.06 0.37 - - - - - - - -
16.11 100.00 0.13 1.56 0.55Total
Percent Complete Weight Complete
Plan Actual Plan Actual
8/2/2019 Weekly Construction Report_2011.10.15
14/22
6. Quantitative Construction Progress2011. 10. 09 ~ 10. 15
Previous
(Cumul.)Last Week
Current
(Cumul.)%
Civil
Stl-Str.
Equip.
Discipl. Work Description UnitTotal
Q'ty
Progress
8/2/2019 Weekly Construction Report_2011.10.15
15/22
6. Quantitative Construction Progress2011. 10. 09 ~ 10. 15
Previous
(Cumul.)Last Week
Current
(Cumul.)%
Discipl. Work Description UnitTotal
Q'ty
Progress
Paint'g
Insul.
Total
8/2/2019 Weekly Construction Report_2011.10.15
16/22
Project Name : TITAN Project-T * Cut Off Date : * Remaining Days for Completi
Mon Tue Wed Thu Fri Sat Sun MonStart Finish Unit Plan Act. 10/10 10/11 10/12 10/13 10/14 10/15 10/16 10/17
Civil -
1 12/24 1/17 25 m 260 210 81%
2 1/14 d #VALUE! m 177 8
3
4 1/12 1/20 9 EA 96 48 50%
5 1/16 1/18 3 m 39 -
6 1/8 1/9 2 m 63 63 100%7 -
8 -
9 -
Piping
1 1/13 1/20 8 m 177 36 20%
2 1/8 1/8 1 m 39 39 100%
3 1/7 1/7 1 m 63 63 100%
4 1/6 1/6 1 m 39 39 100%
5 1/6 1/6 1 m 31 31 100%
Electrical 1/14 1/22 9 m 260 -
1 1/20 1/26 7 EA 96
Prog.
Last Week
Discipline / Category / Activity
7. Three(3) Week Schedule
2011-10-10
Schedule
Dur
Work Volume
For Example Only
8/2/2019 Weekly Construction Report_2011.10.15
17/22
8. Construction Manpower Mobilization Status Unit : Man-Week (M/W)
Previous
(Cumul.)Last Week
Current
Cumul. (b)
1 Temp. Fac. 0.0 #DIV/0!
2 Civil 0.0 #DIV/0!
3 Stl-Str. 0.0 #DIV/0!
5 Equipment 0.0 #DIV/0!
7 Piping 0.0 #DIV/0!
8 Electrical 0.0 #DIV/0!
9 I & C 0.0 #DIV/0!
10 Painting 0.0 #DIV/0!
11 Insulation 0.0 #DIV/0!
0.00 0.00 0.00 0.00 #DIV/0!Total
Original
Mob. Plan
(a)
Discipline
Actual
Remarks
Plan vs.
Actual :
(b/a)
[%]
8/2/2019 Weekly Construction Report_2011.10.15
18/22
9. Material Delivery Status
9.1 Materials Received Last Week
No. Unit1
2
3
4
5
6
7
8
910
11
9.2 Materials to be Received This Week
No. Unit
1 U/G Piping & Fitting for Project-T 8 Pckg. 2011.10.22 Onhold for C/C
2
3
45
6
7
8
9
10
11
12
Q'ty
Q'ty
No. P/O No. DescriptionDate of
Receiving
Remarks
No. P/O No. DescriptionDate of
ReceivingRemarks
8/2/2019 Weekly Construction Report_2011.10.15
19/22
9. Material Delivery Status
8/2/2019 Weekly Construction Report_2011.10.15
20/22
TITAN Project-T
Action DueB Date
** Fixed Lump-Sum Contract with TITAN* Ex edite TITAN's on Budget Increase PD
** LOI to Subcontractors* Ex edite TITAN's Decision on Budget Increase PD
** Preparation for Subcontract PCM/PE 14-Oct-11* Index * Main Text* T&C * SOW* BOQ * S ec* Drawings
** Project Coordination Procedure_R1* Main Text PD 26-Sep-11* Construction Weekly Re ort (Form) PD 03-Oct-11* Submit to TITAN PE(HO) 07-Oct-11
**
** RFQ/PO Pending Items PO SRD* Field Fab Tanks* Mixer & E ector* Fire-Fighting E t* Gas Detection Sys.
* E&I Cable/Wire* Pi ing Mat'l (2nd)* Pi ing S ecial Parts (1st)* Butterfly Valve
10. Status of Pending It
Cat. Works To Be Done
Overall/G
eneral
Engg
c
RFQ B/C TBE Nego14/06/11 23/06/11 19/07/11 22/08/1110/08/11 19/08/11 14/10/1119/09/11 28/09/11 19/10/1127/07/11 24/10/11 03/11/11
08/09/11 29/09/11
12/10/11 20/10/11 25/10/11
12/10/11
8/2/2019 Weekly Construction Report_2011.10.15
21/22
As of :
Prio Status/-rit Forecast
A
U * Sent Expediting e-Mail to TITAN on 10-Oct.
H * Be ready for Approval Processing* Construction Team to review T&C and SOW
* Updating Details of Const. Matters
DoneDone
Done(12-Oct) * Weekly Reporting shall be practiced
ETA(Site) * Indication of Date : DD-MM-YY
* Sight Glass, Flexible Hose, etc.* Site Procurement Item
ems2011-10-15
Reference / Remarks
8/2/2019 Weekly Construction Report_2011.10.15
22/22
11. Areas of Concern
2011-10-15
Srl No. Subject Description Remarks
1 Underground Services
Underground for BD/OCU at cable trench &
underground piping clashes with
Hydrant,Cabinet Hose Reel and Lighting Pole.
To Contruct New
Drawing Layout
2 Incoming MaterialTo revise Inspection Report and pending
missing Mill. Certificate to be received.Follow -up
3 U/G Piping Custom ClearanceTo expedite Titan for U/G Piping Custom
Clearance
ETA on Saturday
(10/22)
4
5