+ All Categories
Home > Documents > © 2008 Gustavo Adolfo Llanos

© 2008 Gustavo Adolfo Llanos

Date post: 10-Feb-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
103
1 SHEAR CAPACITY OF POST-TENSIONED CONCRETE GIRDERS WITHOUT SHEAR REINFORCEMENT By GUSTAVO ADOLFO LLANOS A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE UNIVERSITY OF FLORIDA 2008
Transcript

1

SHEAR CAPACITY OF POST-TENSIONED CONCRETE GIRDERS WITHOUT SHEAR REINFORCEMENT

By

GUSTAVO ADOLFO LLANOS

A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT

OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE

UNIVERSITY OF FLORIDA

2008

2

© 2008 Gustavo Adolfo Llanos

3

For my father, who was my friend and mentor.

4

ACKNOWLEDGMENTS

I would like to thank the chair and members of my supervisory committee for their

mentoring, and the Florida Department of Transportation for its generous support. I thank my

family and friends for their loving encouragement, which motivated me to complete my study.

5

TABLE OF CONTENTS page

ACKNOWLEDGMENTS ...............................................................................................................4 

LIST OF TABLES ...........................................................................................................................7 

LIST OF FIGURES .........................................................................................................................8 

LIST OF ABBREVIATIONS ........................................................................................................11 

ABSTRACT ...................................................................................................................................12

CHAPTER

1 OBJECTIVES .........................................................................................................................14 

2 APPROACH ...........................................................................................................................15 

3 LITERATURE REVIEW .......................................................................................................16 

4 GIRDER DESIGN ..................................................................................................................20 

5 BEAM NOMENCLATURE ...................................................................................................24 

6 GIRDER CONSTRUCTION AND MATERIAL PROPERTIES ..........................................25 

7 PRESTRESSING ....................................................................................................................40 

7.1  Prestressing Application ..............................................................................................40 7.2  Instrumentation ............................................................................................................40 7.3  Results: Seating Losses ................................................................................................41 

8 MATERIAL PROPERTIES ...................................................................................................55 

9 SHEAR TEST SETUP AND PROCEDURES .......................................................................56 

10 RESULTS AND DISCUSSION: SHEAR TESTS .................................................................61 

10.1  Test C1U3 ....................................................................................................................61 10.2  Test C2U3 ....................................................................................................................61 10.3  Test C3U2 ....................................................................................................................62 

11 EFFECT OF SUPPORT CONDITIONS ON BEHAVIOR ...................................................74 

12 STRUT AND TIE ANALYSIS: C3U2 ..................................................................................86 

6

13 COMPARISON WITH THEORETICAL CAPACITIES ......................................................97 

14 SUMMARY AND CONCLUSIONS ...................................................................................100 

LIST OF REFERENCES .............................................................................................................102 

BIOGRAPHICAL SKETCH .......................................................................................................103 

7

LIST OF TABLES

Table page 6-1 Dates of C beams ...............................................................................................................39 

7-1 Jacking force measured with load cell ...............................................................................53 

7-2 Working P-gages for each C beam ....................................................................................53 

7-3 Measured changes in stress due to seating losses ..............................................................53 

7-5 Elastic losses for C beams ..................................................................................................53 

7-6 Long term losses in C2 ......................................................................................................54 

8-1 Average cylinder strengths ................................................................................................55 

8-2 PT-bar strengths .................................................................................................................55 

13-1 Post-tensioned beam nominal moment capacities .............................................................99 

13-2 Post-tensioned beam shear capacity results .......................................................................99 

8

LIST OF FIGURES

Figure page 3-1 Strength of concrete beams failing in shear for various a/d ratios .....................................19 

4-1 Full beam section ...............................................................................................................20 

4-2 Girder cross section and post-tensioning tendon details ....................................................21 

4-3 Reinforcement and tendon layout ......................................................................................22 

4-4 Deck configuration and reinforcement ..............................................................................23 

5-5 Beam nomenclature ...........................................................................................................24 

6-1 Pouring of beam .................................................................................................................27 

6-2 End block reinforcement ....................................................................................................28 

6-4 Strain gages leads exiting duct ...........................................................................................30 

6-5 Placement of U-bars ...........................................................................................................31 

6-6 Formwork of beam and vibrating of concrete ....................................................................32 

6-7 Bottom anchorage with PT duct and grouting tube.. .........................................................33 

6-8 Beam being poured ............................................................................................................34 

6-9 Pouring of beam finished ...................................................................................................35 

6-10 Hand pump for grouting.....................................................................................................36 

6-11 Deck formwork and mild steel reinforcement ...................................................................37 

6-12 Finished beam ....................................................................................................................38 

7-1 Hydraulic jack used to stress tendons ................................................................................44 

7-2 Tendon designation for C beams .......................................................................................45 

7-3 Location of gages for C beams ..........................................................................................46 

7-4 Tendon stress during post-tensioning of beam C1 .............................................................47 

7-5 Tendon stress during post-tensioning of beam C2 .............................................................48 

7-6 Example of seating and elastic losses ................................................................................49 

9

7-7 Summary of seating losses .................................................................................................50 

7-8 Summary of elastic losses ..................................................................................................51 

7-9 Long term strains in beam C2 ............................................................................................52 

9-1 Test setup and instrumentation for C beams ......................................................................56 

9-2 Support Conditions for C1U3 and C2U3 ...........................................................................57 

9-3 Test C1U3 ..........................................................................................................................58 

9-4 Test C2U3 ..........................................................................................................................59 

9-5 Test C3U2 ..........................................................................................................................60 

10-1 Load vs. displacement for C1U3 .......................................................................................63 

10-2 C1U3S14 plot ....................................................................................................................64 

10-3 First and final crack pattern for C1U3 ...............................................................................65 

10-4 Load vs. displacement for C2U3 .......................................................................................66 

10-5 C2U3S14 plot ....................................................................................................................67 

10-6 First and final crack pattern for C2U3 ...............................................................................68 

10-7 Load vs. displacement for C3U2 .......................................................................................69 

10-8 First and final crack pattern for C3U2 ...............................................................................70 

10-9 Strain gages S13, S14, and S15 .........................................................................................71 

10-10 Crack causing transfer of flexure to strut and tie ...............................................................72 

10-11 Cracks around PT anchorage .............................................................................................73 

11-1 Support condition for C1U3 ...............................................................................................77 

11-2 Support condition for C2U3 ...............................................................................................78 

11-3 Computer model of beam C at an a/d ratio of 3.0 ..............................................................79 

11-4 Bearing friction model .......................................................................................................80 

11-5 Definition of transverse support displacement ..................................................................81 

11-6 Effect of support restraint on the beam capacity ...............................................................82 

10

11-7 Load vs. displacement for C1U3 and C2U3 ......................................................................83 

11-8 Plot of C1U3S14, C2U3S14, total bottom displacement for C1U3 and C2U3 .................84 

11-9 Final crack patterns ............................................................................................................85 

12-1 C3U2 strain gages S13, S14, and S15................................................................................89 

12-2 Crack causing transfer of flexure to strut and tie ...............................................................90 

12-3 Change in strain as loading ................................................................................................91 

12-4 Strut and tie model .............................................................................................................92 

12-5 Strain gage plot for S5, S6, and S18 ..................................................................................93 

12-6 Change in strain as loading ................................................................................................94 

12-7 Strut and tie model .............................................................................................................95 

12-8 Strain gage plot for S5, S6, and S18 ..................................................................................96 

13-9 Forces in strut-and-tie model .............................................................................................98 

11

LIST OF ABBREVIATIONS

a/d shear span to depth

fpu specified tensile strength of prestressing steel (ksi)

Icr cracked moment of inertia (in.4)

LVDT linear variable displacement transducer

Mn nominal moment capacity (kip*ft)

PT post-tensioning

w/c water cement ratio

Vc shear contribution of concrete (kip)

Vs shear contribution of the steel stirrups (kip)

ΔT total lateral displacement (in)

θ strut angle

β factor relating effect of longitudinal strain on the shear capacity of concrete

12

Abstract of Dissertation Presented to the Graduate School of the University of Florida in Partial Fulfillment of the Requirements for the Degree of Doctor of Philosophy

SHEAR CAPACITY OF POST-TENSIONED CONCRETE GIRDERS WITHOUT SHEAR

REINFORCEMENT

By

Gustavo Adolfo Llanos

December 2008

Chair: Homer Hamilton Major: Civil Engineering

The objective of this study was to evaluate the behavior of post-tensioned I-girders with

end blocks. The beams had two parabolic tendons and two straight that were anchored at each of

the ends of the beam. Post-tensioning of the beams was done in the laboratory with the objective

of measuring losses due to seating, elastic, creep and shrinkage.

Outside of the end block, approximately 3 ft from each end, there was no shear

reinforcement. U-bars were used in the top flange to provide composite action between the deck

and girder. Without the presence of shear reinforcement loading configurations used short shear

span to depth ratios to see if a shear failure would occur.

In the field these beams were observed to have no bearing pads and rested directly on

concrete. Two post-tensioned beams with the same loading pattern were tested to failure with

only the support condition varying, one neoprene and one resting directly on concrete. This was

done to see if the stiffness would be affected by the support conditions. A third test was

conducted for a shorter shear span to observe the type of failure that would occur. Each girder

was instrumented to measure strains, vertical deflections and crack initiation at relevant points.

13

Finally, capacities were predicted using three methods, ACI, AASHTO, and Strut-and-Tie.

These predicted values were compared to experimental capacities to observe the disparity

between the two.

14

CHAPTER 1 OBJECTIVES

One of the early forms of prestressing used in Florida for short span bridges was a precast,

post-tensioned I-girder with end blocks. These girders were used in simply supported conditions

in which the beam would bear directly on the concrete pier cap with only a layer of tar paper

separating the two. These beams are particularly interesting because they are post-tensioned

with both parabolic and straight threadbar tendons and have no shear reinforcement. Mild steel

reinforcement is provided only at the end blocks approximately 3 ft from each end, presumably

to protect against anchorage failure.

15

CHAPTER 2 APPROACH

Three beams were constructed using construction drawings from actual bridge girders in

service as a basis for design. The beams were tested in three-point bending. Two of the beams

have a shear span to depth (a/d) ratio of 3.0 and the third had an a/d of 2.0. The first two beams

were tested with and without neoprene to determine how the behavior might change when the

horizontal reaction varies. The third beam evaluated the shear capacity with no mild steel shear

reinforcement.

16

CHAPTER 3 LITERATURE REVIEW

Schlaich et al.1 presented the strut-and-tie model. This method is similar to a truss model.

Compression is carried by concrete and is represented by struts. Diagonal struts are oriented

parallel to the expected axis of cracking. Tension forces are carried by stirrups, longitudinal

reinforcement, or prestressing steel. These tension members are called ties. Where the truss

members intersect is called nodes. Concrete represents the strength in the nodes. The anchorage

of the ties is important when considering the nodes strength. The strut-and-tie model allows

yielding in the ties before the failure of the concrete members such as the nodes and struts. The

nodes are classified depending on the forces acting on it. A minimum of three forces need to act

on a node to maintain equilibrium. There is also a region called an extended nodal zone which is

the intersection of the strut width and the tie width.

To use the strut-and-tie model the member is classified in regions, B and D. The B-regions

(B for beam or Bernoulli) are based on the Bernoulli hypothesis that strain distribution in a plane

remains linear for any loading condition such as bending, shear, axial forces and torsional

moments. D-regions (D for discontinuity, disturbance or detail) are the parts of the structure

where the strain distribution is nonlinear. These regions are labeled this way because of the

changes in geometry or due to changes in loading conditions. Strut-and-Tie models are best for

modeling short shear spans like B-regions.

The American Concrete Institute (ACI)2 provides examples of several different strut and

tie models for a variety of structural members. Guidelines are given when calculating the

strength of the struts, tie, and nodes. Reduction factors are provided for nodal zones under

different loading conditions. Examples are given for idealized prismatic struts and for bottle-

shaped struts. Bottle-shaped struts are present when there is diagonal reinforcement to prevent

17

splitting of the concrete. ACI reproduces Figure 3-1 from “Prestressed Concrete Structures3”.

The figure represents the shear strength of beam loaded at various a/d ratios. For beams loaded

at a/d ratios o f less than 2.5, D-regions control the design of the beam. For a/d ratios greater

than 2.5, B-regions are best for modeling the beams strength.

Ramirez4 (1994) does a full member strut-tie design of a precast pretensioned beam with

depressed strands at midspan. He compares his results with the ACI code which uses a sectional

approach. At the time the article was presented there were no requirements considering the

interaction of adjacent strands. A strut and tie model is presented which shows the detailing

needed to prevent splitting. A strut and tie model of the forces in the compression flange is also

presented. Proper detailing of the web flange connection is necessary to insure that cracking does

not occur. This could leave the flange ineffective in resisting longitudinal stresses.

Alshegeir and Ramirez5 (1992) performed testing of three full-scale pretensioned

AASHTO type I and II beams. Following testing an analysis was done. The use of higher

strength concrete would improve ultimate capacities by strengthening the nodes and the struts.

The size of the bearing plates at the load and support determine one of the dimensions in the

nodal zone. The dimensions in the nodal zone determine the stresses in them. The nodes in the

support and the load point encourage the use of the full uniaxial compressive strength of

concrete. This is because of all of the framing elements are in compression. When tension ties

are present in the node the use of a reduced uniaxial compressive strength should be used.

MacGregor and Wight6 (2005) explain six methods for shear design. The first is a Truss

Analogy also known as Strut and Tie model which considers one load case and analyzes the

mechanism resisting that load. The second is the traditional ACI design procedure which uses a

Vc, the shear contribution of concrete, term that is factored depending on the type of concrete

18

and also by an empirical function. ACI uses a Vs, the shear contribution of the stirrups, term

which implies that the cracks are forming at an angle close to 45 degrees. The following three

methods are variations of the Compression Field Theory (CFT). CFT looks at the web of the

beam cracking due to principal tension stresses in the web. Since the web is cracking the web

losses ability to transmit tension force. A mechanism similar to a truss carries tension forces

through stirrups and compression forces between the cracks. The first CFT method, CFT-84, did

not consider Vc and only considered the stirrups for contribution to shear capacity. The second

method, MCFT-94, took into account the contribution of concrete similar to ACI but factored Vc

by β which considers the strut angle, θ. This version uses tables for getting β and θ. The latest

version, MCFT-04, gives equations for calculating θ to allow for a simpler approach to getting β.

The last method is the Shear Friction Method. This method considers the shear contribution to

shear capacity of concrete to be friction between sections throughout a beam. These sections

represent the inclined cracks or shear slip planes. Although these sections should be considered

at an incline for simplicity they are taken to be straight. This allows us to consider the three main

methods for predicting shear capacities and what they consider in analyzing shear capacity.

Bakht and Jaeger7 (1988) study the bearing restraint in slab-on-girder bridges. Models are

done for steel on steel and steel on concrete bearings. The presence of horizontal restraints at the

girder bearings provides stiffness to the beam. Bridges with relatively new bearing pads provide

bearing restraint that can reduce the total moments due to applied loads by 9%. When compared

to theoretical deflections, there was a 20 to 30% decrease in measured deflections. It is

suggested that bearings permitting free movement of the girder not be provided for short spans

bridges that can be designed for thermal effects and bearing restraint forces. Providing bearing

restraints can provide a single span bridge with a substantial increase in capacity.

19

Figure 3-1. Strength of concrete beams failing in shear for various a/d ratios

20

CHAPTER 4 GIRDER DESIGN

The constructed girders were modeled after post-tensioned beam configurations used in

Florida bridge construction in the 1950’s. The nearly 47-ft long beams had four 1-in. diameter

post-tensioning bars., which was a slight alteration from the original plans that called for 1 1/8-

in. diameter (Figure 4-1). Although the plans called for high strength creepless alloy steel, Grade

150 bars (fpu = 170ksi) were used in the prototype based on availability. The properties of steel

that the plans called for were not know. Two bars were placed in a parabolic configuration with

the other two bars placed at the bottom of the beam in a straight configuration (Figure 4-2). Mild

steel was placed in the end block for 34 in. at each end of the beam (See Figure 4-3). The

longitudinal steel in the end block extended just beyond the last stirrup. The U-shaped bars

located at the top of the beam were intended to ensure composite action and do not extend a

sufficient distance into the beam to provide added shear capacity. A 2 ft 4 in. wide by 7 in. thick

deck was placed on the girder to imitate actual service conditions (Figure 4-4). The deck

reinforcement consisted of two rows of transverse #5 bars and two rows of longitudinal #4 bars.

46' - 10"

10 - #6 bars 8 - #5 bars 10 - #6 bars

8" 8"

Figure 4-1. Full beam section

21

PARABOLIC BARS

STRAIGHT BARS

8" 8"

6" 6"

16"

6 1/2

"6"

10"

Figure 4-2. Girder cross section and post-tensioning tendon details

22

1' - 8"

4" 4 SP @ 3" 3 SP @ 6"

2 7/16"6"

4"1' - 4

"

2 1/

2"

1" PT BAR

Figure 4-3. Reinforcement and tendon layout

23

2 - #4 @ 14"3 - #5 @ 12"

#5 bar @ 12" sp.

#5 bar @ 6" sp.

2' - 4"

7"

Figure 4-4. Deck configuration and reinforcement

24

CHAPTER 5 BEAM NOMENCLATURE

The following sections describe testing conducted on several different beam configurations

with a number of different load configurations. The beams, tests, and instrumentation will be

referred to using the same system. C2U3 is an example of beam 2 with an a/d of approximately

3. C1U3L3 is an example of an LVDT number 3 in beam 1 with an a/d of approximately 3.

_ _ _ _ _ _ _Beam

TestInstrumentation Label

Gage Number Sequentially Numbered<One or Two Digits>

P - Strain Gage on Post-Tensioning BarR - Strain Gage Rosette on ConcreteS - Single Strain Gage on Concrete

L - LVDT

C1U3 (a/d = 3.0)C2U3 (a/d = 3.0)C3U2 (a/d = 2.0)

Figure 5-5. Beam nomenclature

25

CHAPTER 6 GIRDER CONSTRUCTION AND MATERIAL PROPERTIES

Construction was performed at the Florida Department of Transportation Structures

laboratory in Tallahassee, Florida. Formwork was constructed of welded steel panels that were

assembled to provide a single form for the full length of the beam. Steel reinforcement was

fastened to the formwork and rested on chairs in order to keep them in place while concrete was

poured (See Figure 6-2 and Figure 6-3). 40 mm galvanized steel duct was used to hold a single

post-tensioning bar. The duct was fastened to formwork and strapped to chairs at incremental

points along the beam length to maintain the parabolic or straight configuration during casting.

Assembly started with placing the bottom forms on the top flange of a steel I-beam, which

was placed on the strong floor. One side of the formwork was erected. Mild steel cages were

assembled and placed at each end. Plywood bulkheads were fabricated that enclosed the ends of

the beam form.

Anchorages were 1-3/4 in. x 6 in. x 10 in. steel plates with countersunk holes. The holes

were conical in shape. The anchorages are fitted with 1 in. anchor nuts. The anchorages were

dome shaped so that when fitting against the bearing plate there is one line of contact surface.

The anchorages were fastened to the plywood bulkhead in the proper configuration and angle.

The duct was then formed and installed from anchorage to anchorage along with tubes and vents

necessary to facilitate grouting. Strain gages were applied to the prestressing bars as detailed in

the instrumentation section. A hole was cut into the duct surrounding theses gages to pass the

wires connecting to these gages. The bars were then carefully inserted into the duct with anchor

nuts installed. The hole was sealed and the wires were lead out of the beam (See Figure 6-4). U-

bars were held in place by tying them to a longitudinal bar running along the top of the beam

26

(See Figure 6-5). The opposite form was then installed with all-thread rod used as form ties.

Final adjustments in duct and reinforcement were made after the form ties were in place.

The beams were cast using ready mix concrete that was bucketed to the form with the

laboratory crane (Figure 6-8). The water cement ratio was 0.41 and the aggregate size and type

was ¾ in. Florida Limestone. One concrete truck was needed for the entire beam. The concrete

was vibrated using both internal and external vibration. Twelve cylinders were taken to test

compressive strength of the concrete. When cylinder strengths tested at or above 3600psi the

beam was stressed as detailed in the following section.

Immediately after stressing the PT ducts were grouted. The grouting procedure was as

follows. The grout used was a Portland cement and water mixture mixed to w/c=0.45. Several

batches of grout were mixed in a 5-gallon bucket single batch and used to fill the ducts with the

hand pump shown in Figure 6-10. The grout was injected from one end of the beam and was

continuously pumped until it ran out of the vent pipe at the opposite anchorage. The grouting

proceeded from bar 1 duct to bar 4 duct.

After grouting, the deck formwork and mild steel reinforcement were placed (Figure 6-11).

The deck was poured using the same method as the beam. The finished beam is shown in Figure

6-12.

27

Figure 6-1. Pouring of beam

28

Figure 6-2. End block reinforcement

29

Figure 6-3. End block reinforcement resting against a chair

Chair

30

Figure 6-4. Strain gages leads exiting duct

31

Figure 6-5. Placement of U-bars

32

Figure 6-6. Formwork of beam and vibrating of concrete

33

A

B

Figure 6-7. Bottom anchorage with PT duct and grouting tube. A) inside view, B) outside view.

34

Figure 6-8. Beam being poured

35

Figure 6-9. Pouring of beam finished

36

Figure 6-10. Hand pump for grouting

37

Figure 6-11. Deck formwork and mild steel reinforcement

38

Figure 6-12. Finished beam

39

Table 6-1. Dates of C beams Beam Casting of

Beam Casting of Deck

Post-Tensioning

Grouting Testing

C1 12-5-07 1-15-08 12-10-07 12-10-07 2-20-08 C2 1-30-08 3-26-08 2-5-08 2-5-08 4-30-08 C3 4-11-08 6-2-08 4-16-08 4-16-08 7-25-08

40

CHAPTER 7 PRESTRESSING

7.1 Prestressing Application

A 60 Mp Series 04 jack was used to stress the PT bars. The jack is a 80 ton hydraulic

actuator designed to stress a single threadbar tendon. The jack is fitted with a socket at the nose

that fits the PT bar nut and can tighten just prior to release.

The target prestress for each tendon was 93 kips. Prestress was measured with load cells

placed between the anchor plate and the jack. As each bar was being stressed the nut needed to

be tightened with a wrench that was attached to the jack. The jack was placed on the anchorages

at the North end of the beam (as it was oriented during stressing). Refer to Figure 7- for a picture

of the jack.

To avoid exceeding allowable concrete stresses, the bars were stressed in two stages in the

following order: 2,3,1,4 (Figure 7-2). The first stage consisted of stressing each tendon to 50%

of the desired final stress in the order indicated. The stressing sequence was then repeated to

reach the final desired stress. Table 7-1 shows the jacking force at each stage for each beam.

7.2 Instrumentation

Strain gages were applied to the bars to allow measurement of prestress losses and tendon

stresses during load testing. Tandem gages were placed on the bars near each end of the beam

(Figure 7-3). Using the measured strains, stresses were calculated by factoring them by Young’s

modulus. Some of the gages were damaged during installation and prestressing of the tendons.

Table 7-2 shows the surviving strain gages for C1 and C2. None of the gages in C3

survived or provided data that could be used to measure stresses.

41

7.3 Results: Seating Losses

Measurements were taken during post-tensioning to determine seating losses, elastic

losses, friction losses and early creep losses. Seating losses in prestressing bar anchorages occur

when the bar is released and the anchor nut is allowed to settle against the anchor plate. As the

bar is being prestressed, the anchor nut is tightened with a wrench to minimize the seating losses

when the tendon is released. When the bar is released the remaining space is closed, which is

termed take up.

Seating losses can be measured by observing the change in strain that occurs when the jack

is released. This is best done when using the strain data from the gages located nearest the

stressing end of the beam. Strain gages at the dead end will be affected by friction losses from

wobble or drape. Figure 7-4 and Figure 7-5 show a time trace of the stress in each tendon. The

stress was calculated from strain data using a Young’s modulus of 28,500 ksi. The plots display

only the data from strain gages that were operating properly and include the average of each

tandem pair of strain gages when both were operating correctly and single readings when only

one of the gages was working properly. The plots illustrate the staging used to stress the

tendons. Each was initially stressed to approximately half of the target prestress, followed by

another round of prestressing to reach the target prestress.

Figure 7-6 illustrates how elastic losses and seating losses were determined from the

strains measured in the bars during post-tensioning. The graph shows the plots of two tandem

strain gages converted to stress. As noted on the plot, seating loss was the immediate reduction

in stress as the jack was released. The maximum strain of the averaged tandem pair of strain

gages was used. The three subsequent sharp drops in stress are the elastic losses caused by

stressing each of the adjacent tendons.

42

The jacking stresses and loss in stress due to seating are summarized in Table 7-3. The

seating losses for beam C1 bars 3 and 4 and beam C2 bar 1 were measured using strain gages at

the stressing end of the beam. Seating losses for bars 3 and 4 in beam C2 were measured using

the strain gages at the dead end. In addition, the prestress loss as a percentage of the jacking

stress is shown for both stages. Seating losses for the straight tendons (3 and 4) were

consistently in the range of 2% regardless of the jacking stress. The parabolic tendon, however,

was 2 to 3 times this value. This could have been due to the anchor plate not being perpendicular

to the post-tensioning bar. This could have caused the bar to sit lower on the countersunk hole

while stressing. When the bar is released the bar would pull up higher and sit tighter into the

anchor plate.

The take up at the stressing end anchorage was calculated using this sudden change in

strain and multiplying it by the length of the tendons, 46ft 10in. and are presented in Table 7-4.

Typical set can be about 0.03 in. but varies depending on the type of anchorage (Lin and Burns

1981).

Table 7-5 shows the elastic losses due to stressing of adjacent tendons. The change in

strain for each tendon was measured as each of the following bars in the sequence were stressed.

For example, during stage 1 stressing of tendon 4 in beam C1, the measured decrease in stress of

tendon 3 was 1.8 ksi. The attendant loss of prestress was 3.9% based on the stress in tendon 3

just prior to stressing tendon 4. In general, the highest losses were caused by immediately

adjacent tendons. For instance, the maximum loss in tendon 1 (3.0%) was caused by the

adjacent tendon 2.

43

Using the AASHTO8 method for calculating losses due to elastic shortening the first and

second stage of stressing was calculated to be 2.6 ksi. A comparison could not be done due to a

lack of data.

A wobble coefficient was calculated for Bar 4 beam C1. This was done by taking the

maximum stress in the bar, measured by the strain gage, at the jacking end and comparing the

stress at the same point in time at the dead end of the beam. Using these two stresses a wobble

coefficient of 0.0007 per ft was measured. The American Concrete Institute, ACI, gives a range

for the wobble coefficient of 0.0001 to 0.0006 for high-strength bars grouted in metal sheathing

(ACI 2005).

To observe long-term losses, tendon stresses in C2 were measured for approximately 2.5

days after stressing (Figure 7-9). The percentage of losses due to short-term creep and shrinkage

effects were 6.3 and 5.6 percent (See Table 7-6). A loss of 1.6 ksi is calculated using the

AASHTO method. Equation 5.9.5.4.2a-1 and 5.9.5.4.2b-1, from AASHTO 2007, were used for

calculating shrinkage and creep, respectively. Using our initial prestress force this yields a loss

of approximately 1.7%.

44

Figure 7-1. Hydraulic jack used to stress tendons

45

Bar 1Bar 2

Bar 4Bar 3

Figure 7-2. Tendon designation for C beams

46

P13 & P14

P9 & P10

P5 & P6

P1 & P2

P15 & P16

P11 & P12

P7 & P8

P3 & P4

BACK BAR

FRONT BAR1' - 0" +-

1' - 0" +-

Figure 7-3. Location of gages for C beams

47

Time (seconds)

Stre

ss (k

si)

Stre

ss (M

Pa)

0 500 1000 1500 2000 25000

20

40

60

80

100

120

0

150

300

450

600

750C1U3P11C1U3P12C1U3P14C1U3P15C1U3P16

Figure 7-4. Tendon stress during post-tensioning of beam C1

48

Time (seconds)

Stre

ss (k

si)

Stre

ss (M

Pa)

0 500 1000 1500 2000 2500 30000

20

40

60

80

100

120

0

150

300

450

600

750C2U3P3C2U3P9C2U3P10C2U3P13C2U3P14

Figure 7-5. Tendon stress during post-tensioning of beam C2

49

Time (seconds)

Stre

ss (k

si)

0 500 1000 1500 200040

42

44

46

48

50Average Stress in C1 Bar 3

Seating Loss

Elastic Loss

Creep

Figure 7-6. Example of seating and elastic losses

50

1 2 3 4Tendons

Pre

stre

ss L

oss

(%)

0

1

2

3

4

5

6

7

8

9

10C1 Stage 1C2 Stage 1C1 Stage 2C2 Stage 2

Figure 7-7. Summary of seating losses

51

Pre

stre

ss L

oss

(%)

0

2

4

6

8

10

12

14C1C2

1 2 3 4Tendons

Figure 7-8. Summary of elastic losses

52

Time (seconds)

Stre

ss (k

si)

Stre

ss (M

Pa)

0 50000 100000 150000 200000 2500000

20

40

60

80

100

120

0

150

300

450

600

750

C2U3P3C2U3P13C2U3P14

Figure 7-9. Long term strains in beam C2

53

Table 7-1. Jacking force measured with load cell

Stage Jacking Force (kip)

C1 C2 C3 1 46.7 45.7 46.7 2 94.5 93.4 93.5 Table 7-2. Working P-gages for each C beam C1 C2 P11 P3 P12 P9 P14 P10 P15 P13 P16 P14

Table 7-3. Measured changes in stress due to seating losses

Bar Stage Jacking Stress (ksi) Seating Loss (ksi) Prestress Loss (%) C1 C2 C1 C2 C1 C2

1 1 --- 42.8 --- 3.13 --- 7.3 2 --- 99.7 --- 4.46 --- 4.5

3 1 48.6 49.9 1.0 0.74 2.1 1.5 2 100 99.2 1.3 0.47 1.3 0.5

4 1 48.0 53.5 1.4 1.50 2.4 2.8 2 103 103 2.2 2.46 2.1 2.4

Table 7-4. Measured take-up

Tendon Stage 1 (in.) Stage 2 (in.) C1 C2 C1 C2

1 --- 0.06 --- 0.09 3 0.02 0.02 0.02 0.01 4 0.03 0.03 0.04 0.05

Table 7-5. Elastic losses for C beams

Tendon Jacking Tendon

Stage 1 Stage 2 C1 C2 C1 C2 Δf (ksi) %loss

Δf (ksi) %loss

Δf (ksi) %loss

Δf (ksi) %loss

1 4 --- --- 0.51 1.3 --- --- 0.46 0.5 3 1 0.9 2.0 0.81 1.7 1.1 1.1 1.21 1.2 3 4 1.8 3.9 1.75 3.4 2.4 2.4 1.91 2.0

54

Table 7-6. Long term losses in C2 Tendon Δf (ksi) %loss1 5.99 6.3 4 5.52 5.6

55

CHAPTER 8 MATERIAL PROPERTIES

For each beam tested cylinder strength were tested for the beam itself and the deck. The

average strengths for the beam and the deck are presented in Table 8-1. Samples of the post-

tensioning bars were also taken and tested, their average material properties are presented in

Table 8-2.

Table 8-1. Average cylinder strengths Beam Beam Cylinder Strengths (ksi) Deck Cylinder Strengths (ksi) C1 7.96 3.34 C2 8.64 5.47 C3 8.64 4.89

Table 8-2. PT-bar strengths EUL @ 0.50% Stress (ksi) 140.2 Tensile Strength (ksi) 169.9 Elongation (%) 7.8 Young’s Modulus (ksi) 30152.5

56

CHAPTER 9 SHEAR TEST SETUP AND PROCEDURES

Three tests were conducted using a three point loading scheme shown in Figure 9-1. Two

tests were conducted using a shear span to depth (a/d) ratio of 3.0. One of these tests (C1U3)

was set up with the beam bearing directly on the concrete pedestal support (Figure 9-2). The

second test (C2U3) was set up with the beam bearing on a neoprene pad (2in. thick). This was

done to observe the effect of the support conditions on the beam behavior. The third test (C3U2)

was loaded at a/d = 2.0 and was bearing on a neoprene pad. This test was intended to evaluate

the shear behavior of the short shear span and no shear reinforcement.

The load was applied through a 1½-in. thick reinforced neoprene bearing pad at a loading

rate of 0.25 kips/second. Displacements were measured at the load point and each of the

supports. Beam end movement was measured at the top and bottom. A load cell was used to

measure load under the actuator. The detailed instrumentation for each test is shown in Figure 9-

3 through Figure 9-5. Strain was measured with 60 mm strain rosettes and strain gages. For test

C2U3 five 30 mm strain gages were used in the deck and top flange of the beam in addition to

the 60 mm gages. Test C3U2 used sixteen 30 mm strain gages in the top flange and deck of the

beam in addition to the 60 mm gages.

4" 4"

9"2'

- 9"

9"2'

- 9"

46' - 10"

a

LVDT

LVDTLVDT

LVDT

Load Cell

Figure 9-1. Test setup and instrumentation for C beams

57

A B Figure 9-2. Support Conditions for A) C1U3 and B) C2U3

58

4" 4"

9"2'

- 9"

9"2'

- 9"

46' - 10"

12' - 1"

L1

L2

L3

L4

L5 L8

L6 and L7 on each side of load plate

A

1"6" 4"

10"

2' - 8

" 1' - 7

"

3' - 1

0"

1' - 10"1' - 1"

2' - 7"7' - 10"

10' - 1"11' - 1"

12' - 1"

S14S13S12

S10 S11S9 R7

R6

R5

R4

S16S15

S8S7S6R3R2R1S5S4S3

S1 S2

Top View at Load Point

1' - 1

"1'

- 2"

DECK/GIRDERINTERFACE

B

Figure 9-3. Test C1U3 A) setup B) instrumentation

59

4"

9"2'

- 9"

9"2'

- 9"

46' - 10"

12' - 1"

L1

L2

L3

L4

L5 L6 L10

L7 and L8 on each side of load plate

L9

10' - 7"

13' - 7"

4"

A

10' - 1"11' - 1"

12' - 1"13' - 1"

14' - 1"15' - 1"

1' - 1

0"

9' - 1"

20' - 0"

S15S14S13

R2R1R3

S6S5S4S1S2S3

S29

S31

S30

S26

Top View at Load Point

S28

S27 S20

S19

S17S18

2' - 6"6"

6"

S21

S22

S23

S24

S25

2"2"2"2"2"

DECK

NOTE

NOTE

S10

S12

S11S9 S7S8

1' - 2"2' - 2"

3' - 2"

10"1' - 10"

2' - 10"

1' - 1

"1'

- 2"

S16

DECK/GIRDERINTERFACE

B

Figure 9-4. Test C2U3 A) setup B) instrumentation

60

4"

9"2'

- 9"

9"2'

- 9"

46' - 10"

8' - 0"

L1

L2

L3

L4

L5 L6 L10

L7 and L8 on each side of load plate

L9

6' - 6"

9 ' - 6"

4"

A

6' - 0"7' - 0"

8' - 0"9' - 3"

10' - 0"11' - 0"

1' - 1

0"

5' - 0"

S15S14S13

R2R1

S17

S8S7

S2S1

S9

S3

S10

S4

S11

S5

S12

S6

S20

S19

Top View at Load Point

5"5"

S18

S16

2' - 0"

S29

S30

S31

S32

S33

2"2"2"2"2"

DECK

NOTE

NOTE

1' - 1

"1'

- 2"

DECK/GIRDERINTERFACE

S21

S22

S23

S24

S25

4"

2"2"

S26

S27

S28

S34

S35

S36

B

Figure 9-5. Test C3U2 A) setup B) instrumentation

61

CHAPTER10 RESULTS AND DISCUSSION: SHEAR TESTS

10.1 Test C1U3

Figure 10-1 showed linear-elastic behavior for test C1U3 up to a load of 74 kips where the

first flexural crack occurred. The crack was detected by gage S14, which was located on the

beam bottom under the load point (Figure 10-2). Gage S14 showed that the flexural crack

formed at a tensile strain of nearly 400 microstrain. Figure 10-3 showed the location of the first

crack. As loading continued, further flexure cracks formed under the load point as the stiffness

decreased. The beam reached its maximum capacity at a shear of 135 kips where a flexure-

compression failure occurred in the deck under the load point. Figure 10-3 showed the final

crack pattern.

10.2 Test C2U3

The initial behavior of C2U3 was similar to C2U3 up to and including cracking. Figure

10-4 showed linear elastic behavior up to a load of 74 kips where the first flexural crack

occurred. The crack was detected by gage S14, which was located on the beam bottom under the

load point (Figure 10-5). Although the initial strain behavior was linear, the behavior appeared

to soften as the cracking load of 74 kips was reached the strain spiked. Figure 10-6 showed the

location of the first crack. At a load of approximately 92 kips the beams began to soften.

Softening in the beam was shown by the change of slope in the load displacement curve.

Beyond this point the beam was cracking more frequently. The load-displacement eventually

plateaus, indicating that the tendons have yielded. The beam reached its maximum capacity at a

shear of 127 kips where a flexure-compression failure occurred in the deck under the load point.

Figure 10-6 showed the final crack pattern.

62

10.3 Test C3U2

Figure 10-7 is the load displacement plot for test C3U2. The beam showed linear-elastic

behavior until a load of 86 kips. A crack was also heard and observed at this load. Figure 10-8

showed where the first crack initiated. As loading continued cracks were observed. Strain gages

S13, S14, and S15 showed when some of these cracks occurred (See Figure 10-9). S14 showed a

constant growth in strain until a load of 92 kips where the strain immediately changed slope and

began to lose tensile strain. The strain measured at 92 kips was 386 microstrain. Cracks also

formed at 109 kips and at 155 kips. The load displacement curve shows that the beam was

cracking a significant amount during this range of loads. At a load of 156 kips a large crack was

observed running through the web and into the transition zone between the web and the end

block (See Figure 10-10). At a load of approximately 179 kips the load displacement curve

began to flatten with little increase in capacity relative to displacement indicating that the bar

were yielding. At a load of 187 kips cracks were observed around the anchor plate for the

parabolic PT bars (See Figure 10-11). The test was terminated at this point to avoid an explosive

failure. The final crack pattern can be seen in Figure 10-8. The peak load measured during

testing was 187 kips. This widespread cracking and large deflection indicate that the prestressing

bars had reached yield. The final failure mode, however, was not determined because the test

was terminated prior to reaching the peak capacity.

63

Displacement (inches)

Sup

erim

pose

d S

hear

(kip

)

0 0.5 1 1.5 2 2.5 30

25

50

75

100

125

150

Figure 10-1. Load vs. displacement for C1U3

64

Superimposed Shear (kip)

Stra

in (m

icro

stra

in)

0 25 50 75 100 125 150-500

-400

-300

-200

-100

0

100

200

300

400

500

S14

Figure 10-2. C1U3S14 plot

65

Figure 10-3. First and final crack pattern for C1U3

66

Displacement (inches)

Sup

erim

pose

d S

hear

(kip

)

0 1 2 3 4 5 60

25

50

75

100

125

150

Figure 10-4. Load vs. displacement for C2U3

67

Superimposed Shear (kip)

Stra

in (m

icro

stra

in)

0 50 100 150-1000

-750

-500

-250

0

250

500

750

1000

S14

Figure 10-5. C2U3S14 plot

68

Figure 10-6. First and final crack pattern for C2U3

69

Displacement (in.)

Sup

erim

pose

d S

hear

(kip

)

0 0.5 1 1.5 2 2.5 30

50

100

150

200

Figure 10-7. Load vs. displacement for C3U2

70

Figure 10-8. First and final crack pattern for C3U2

71

Superimposed Shear (kip)

Stra

in (m

icro

stra

in)

0 50 100 150 200-100

0

100

200

300

400

500

S15S14S13

S13

S14

S15

Figure 10-9. Strain gages S13, S14, and S15

72

Figure 10-10. Crack causing transfer of flexure to strut and tie

73

Figure 10-11. Cracks around PT anchorage

74

CHAPTER 11 EFFECT OF SUPPORT CONDITIONS ON BEHAVIOR

C1U3 and C2U3 were conducted with a shear span to depth ratio (a/d) of 3.0. The first

test, C1U3, used support conditions shown in Figure 11-1 in which the beam was bearing

directly on concrete. The second test, C2U3, used neoprene pads under each of the supports

(Figure 11-2). Both tests had the same loading scheme and loading rate, the support conditions

were the only variable between the two tests. The intent of the test was to explore the difference

in behavior between the two support conditions. This information will be used to guide the

interpretation of data on future load tests.

Typically, beams are modeled assuming the beam is supported by a pin and roller, which

offers no resistance to transverse movement. Conversely, arches are modeled with pinned

supports, which provide and infinitely stiff support and ensure pure arching action. These

modeling choices are made with the understanding that the actual conditions are situated

somewhere between these bounds. Shallow arches require very stiff support conditions to ensure

pure compression. Furthermore, very small transverse movements allowed at the reaction will

shift the behavior from arching to flexure.

To estimate the magnitude of load that must be resisted by the supports in the laboratory,

the beam specimen was modeled using membrane elements as shown in Figure 11-3. A

rectangular cross-section was used with a thickness of 17 in., which is the average thickness of

the specimen. The element was 5.8-ft long by 3.92-ft deep, and a modulus of elasticity of 4030

ksi was used, which corresponds to a compressive strength of 5 ksi. The transverse and vertical

reactions for a unit load required to maintain pure arching are shown in the figure.

While pure arching was not expected to occur using the tested support conditions, some

effect was anticipated. Figure 11-4 shows the expected restraint provided by the supports used in

75

the testing. For the direct bearing testing, the transverse reaction is expected to be a function of

the frictional force generated by the direct concrete contact. For the neoprene bearing pad test,

the reaction is expected to be a function of the shear stiffness and the transverse displacement of

the bottom of the beam. Figure 11-5 defines the transverse support displacement.

Figure 11-6 shows the effect of the transverse reactions on the internal forces. As the HL

reaction increases, then the tension force required to maintain equilibrium is reduced. If the

horizontal reaction is sufficient, then T will go to zero.

The overall behavior of the two tests is illustrated in the load vs. displacement curves

shown in Figure 11-7. As discussed previously, the shear at which cracking occurred was

approximately 74 kips for both tests. Furthermore, the behavior up to cracking appears very

similar between the two beams, indicating that the different support conditions had little effect

before the beam cracked. This lack of difference is likely due to the relatively small amount of

support movement needed to relieve arching action before cracking occurs.

Figure 11-8 shows the flexural tensile strain under the load point and the total lateral

displacement of the beam bearing (ΔT) defined as:

RLT Δ+Δ=Δ (10-1)

where the variables are defined in Figure 11-5. The total transverse movement of the bearings

on both beams is nearly identical up to cracking. The total movement measured for C1U3 and

C2U3 at a superimposed shear of 70 kips was 0.080 and 0.085 inches respectively.

For comparison, one of the transverse support restraints was removed from the model

shown in Figure 11-3 to determine the total transverse movement expected. The resulting total

movement was 0.108 in., which is comparable with the observed values. For the direct concrete

bearing condition, it is suspected that support blocks settled as load was applied, which relieved

the arching action prior to cracking. Furthermore, the movement was so small that the neoprene

76

bearing pad generated little transverse reaction. In conclusion, the bearing conditions used in

these tests appeared to have little effect on the early behavior of the beams. If similar bearing

conditions are encountered in the field, then it is expected that little difference might be seen in

the field under load test conditions.

After first crack the beam behavior began to diverge (Figure 11-7). The direct bearing test

showed a higher post-cracking stiffness with a 6.8% higher capacity than that of the neoprene

bearing test. The ultimate displacement, however, was approximately 59.0% of the neoprene

bearing test. Further evidence of post-cracking bearing restraint is seen in the divergence of ΔT

as ultimate capacity is approached (Figure 11-8). After cracking, the total outward support

movement of C2U3 was greater than that of C1U3 indicating that the transverse force generated

at the support for C1U3 was beginning to effect the behavior. This difference is an indication

that the frictional force generated was greater than that provided by the neoprene bearing pads.

In conclusion, the direct contact bearing provided more restraint than that of the neoprene

bearing pad, thus resulting in higher capacity and less ductility.

The two final crack patterns can be seen in Figure 11-9. For C1U3 cracks were not

observed to spread into the top flange as they were in C2U3. Since the cracks are smaller in

C1U3 its cracked moment of inertia, Icr, is larger than that of C2U3. The stiffness of a member

is dependant on its moment of inertia, the higher the Icr, the smaller the deflection. This behavior

is observed while comparing the two load vs. displacement plots in Figure 11-7.

Both C1U3 and C2U3 displayed the same behavior until cracking occurred. Once cracking

becomes present the two tests begin to react in different ways because of the support conditions.

The inability of C1U3’s ends to slide freely cause a marginal increase in capacity, 8 kips, but

lead to a sudden failure, C2U3 had a ductile failure which is more desirable.

77

Concrete Block

FloorTies for Concrete Blocks

A B Figure 11-1. Support condition for C1U3

78

Concrete Block

Floor

Neoprene Pad

A B Figure 11-2. Support condition for C2U3

79

1

0.250.751.671.67

Figure 11-3. Computer model of beam C at an a/d ratio of 3.0

80

P

HL=mRLor

HL=DLKNEOPRENE

RL

HR=mRRor

HR=DRKNEOPRENE

RR

Figure 11-4. Bearing friction model

81

DRDL Figure 11-5. Definition of transverse support displacement

82

RL

HLT

C + HL

P

A B

Figure 11-6. Effect of support restraint on the beam capacity

83

Displacement (inches)

Sup

erim

pose

d S

hear

(kip

)

0 1 2 3 4 5 60

50

100

150

C1U3C2U3

Figure 11-7. Load vs. displacement for C1U3 and C2U3

84

Superimposed Shear (kip)

Stra

in (m

icro

stra

in)

DT (

inch

es)

0 50 100 150-1000 -2

-500 -1

0 0

500 1

1000 2

S14 for both C1 and C2

StrainC1U3

StrainC2U3

DTC2U3

DTC1U3

Figure 11-8. Plot of C1U3S14, C2U3S14, total bottom displacement for C1U3 and C2U3

85

A B

Figure 11-9. Final crack patterns for A) C1U3 and B) C2U3

86

CHAPTER 12 STRUT AND TIE ANALYSIS: C3U2

Figure 10-7 is the load displacement plot for test C3U2. The beam shows linear-elastic

behavior until a load of 86 kips. As loading continued flexure cracks were observed. Strain

gages S13, S14, and S15 are located at the bottom of the beam and measure the initial flexure

cracks. At a load of 153 kips a large crack was observed running through the web and into the

transition zone between the web and the end block (Figure 12-2). When this crack occurs the

beam stops behaving as a flexural member and begins to behave as a strut and tie model. Figure

12-3 shows the strain through the height of the beam as loading continues. The strain

distribution is linear until a load of 153 kips where the strain is no longer linear due to cracking.

Evidence of this change in behavior can be observed in Figure 12-4.

Figure 12-5 shows that the gages on the top of the deck, S5 and S6, grow constantly in

compression until 153 kips where the strain suddenly drops. Corresponding to the sudden drop

in strain for gages S5 and S6 there is a jump in compressive strain in gage S18. This shows that

when this crack occurs the compressive strain is transferred from the deck and into the

compression strut.

As loading increases the parabolic bars begin to carry load. When this happens a node is

created at the junction between the original strut and the parabolic bars, or tie. As the second tie

carries additional force the node travels towards the anchorage. The compression forces begin to

change direction at the node towards the support. At a load of approximately 179 kips the load

displacement curve begins to flatten with little increase in capacity relative to displacement. The

flattening of the load displacement curve shows that the PT bars are beginning to yield. At a

load of 188 kips cracks were observed around the anchor plate for the parabolic PT bars.

Cracking around the anchor plate confirm that the parabolic tendons were carrying all the tensile

87

force in the strut and tie model. The PT bars, or the tie, is what caused the beam to fail. The

bars could no longer carry any additional force.

Figure 10-7 is the load displacement plot for test C3U2. The beam shows linear-elastic

behavior until a load of 86 kips. As loading continued flexure cracks were observed. Strain

gages S13, S14, and S15 are located at the bottom of the beam and measure the initial flexure

cracks. At a load of 153 kips a large crack was observed running through the web and into the

transition zone between the web and the end block (Figure 10-10). When this crack occurs the

beam stops behaving as a flexural member and begins to behave as a strut and tie model. Figure

12-3 shows the strain through the height of the beam as loading continues. The strain

distribution is linear until a load of 153 kips where the strain is no longer linear due to cracking.

Cracking in the beam has occurred before 153 kips as shown by gages S13 and S14 yet the

progression of strain is still linear that load. This is confirmation that the beam has full

composite action between the deck and beam, beam theory applies, and the section is behaving

as a B-region. B-regions typically begin at a distance of one member-depth away from a

discontinuity. This distance is used as a guideline and is not precise. The load point for this test

lies at approximately one member –depth away from the transition between the end block and

the I-shape in the section. Evidence of this change in behavior can be observed in Figure 12-4.

Figure 12-5 shows that the gages on the top of the deck, S5 and S6, grow constantly in

compression until 153 kips where the strain suddenly dropped. Corresponding to the sudden

drop in strain for gages S5 and S6 there was jump in compressive strain in gage S18. This

showed that when this crack (Figure 10-10) occurred the compressive strain was transferred from

the deck and into the compression strut (Figure 12-4).

88

As loading increased the parabolic bars begin to carry load. When this happened a node is

created at the junction between the original strut and the parabolic bars, or tie. As the second tie

carried additional force the node traveled towards the anchorage. The compression forces began

to change direction at the node towards the support. At a load of approximately 179 kips the

load displacement curve began to flatten with little increase in capacity relative to displacement.

The flattening of the load displacement curve showed that the PT bars are beginning to yield. At

a load of 188 kips cracks were observed around the anchor plate for the parabolic PT bars.

Cracking around the anchor plate confirm that the parabolic tendons were carrying all the tensile

force in the strut and tie model. The PT bars, or the tie, is what caused the beam to fail. The

bars could no longer carry any additional force.

89

Superimposed Shear (kip)

Stra

in (m

icro

stra

in)

0 50 100 150 200-100

0

100

200

300

400

500

S15S14S13

S13

S14

S15

Figure 12-1. C3U2 strain gages S13, S14, and S15

90

Figure 12-2. Crack causing transfer of flexure to strut and tie

91

Strain (microstrain)

Hei

ght f

rom

Bot

tom

of B

eam

(in)

-300 -200 -100 0 100 200 3000

10

20

30

40

50 153 kip 120 kip 80 kip 0 kip

Figure 12-3. Change in strain as loading

92

Parabolic Bar

Figure 12-4. Strut and tie model

93

Superimposed Shear (kip)

S5

and

S6

Stra

in (m

icro

stra

in)

S18

Stra

in (m

icro

stra

in)

0 50 100 150 200-400 -100

-300 -75

-200 -50

-100 -25

0 0

100 25

200 50

300 75

400 100

S5 S6

S18

S5

S6

S18

Figure 12-5. Strain gage plot for S5, S6, and S18

94

Strain (microstrain)

Hei

ght f

rom

Bot

tom

of B

eam

(in)

-300 -200 -100 0 100 200 3000

10

20

30

40

50 153 kip 120 kip 80 kip 0 kip

Strain Plot

Figure 12-6. Change in strain as loading

95

Figure 12-7. Strut and tie model

96

Superimposed Shear (kip)

S5

and

S6

Stra

in (m

icro

stra

in)

S18

Stra

in (m

icro

stra

in)

0 50 100 150 200-400 -100

-300 -75

-200 -50

-100 -25

0 0

100 25

200 50

300 75

400 100

S5 S6

S18

S5

S6

S18

Figure 12-8. Strain gage plot for S5, S6, and S18

97

CHAPTER 13 COMPARISON WITH THEORETICAL CAPACITIES

It is generally accepted that when the shear span to depth ratio (a/d) is less than about 2.5,

then the behavior is better modeled by strut and tie method. When a/d greater than 2.5, then

semi-empirical sectional models are usually employed to determine capacity. This section

provides a comparison of the calculated capacity of the beam and the experimentally measured

capacity. When the shear span ratio is in the range used for these tests (2.0 and 3.0) the failure

mode can vary widely depending on the beam configuration, detailing, and material properties.

These failure modes can be flexural, shear-compression, web-shear, or anchorage, or a

combination thereof. Consequently, the calculated values presented in this section cover the

range of possibilities to determine those that best fit the actual measured capacity and behavior.

Nominal moment capacity, Mn, was calculated using strain compatibility (See Table 13-1).

The stress strain curve generated from the average yield and ultimate strengths from bar tension

tests was used to calculate moment capacity. The material properties used to calculate moment

capacity were: the compressive strength of concrete was 7.98 ksi, the prestress in the bars was

109 ksi, the yield stress for the bars was 140 ksi, and Young’s modulus for the bars was 28500

ksi.

Shear capacity was calculated using the methods prescribed in AASHTO LRFD and ACI.

Using the ACI method gave the most conservative results compared to the two other methods.

With an a/d of 2 the experimental capacity was 367% of the theoretical result. The experimental

results for the a/d ratios of 3 were 318% and 291% of the theoretical result. MCFT was more

accurate as you increased the distance of the loading point from the support. The second a/d of 3

test yielded the most accurate result being within 58% of the theoretical result (See Table 13-2).

98

A strut-and-tie model was performed for an a/d ratio of 2. From testing it can be seen that

the PT bars were yielding. Since the bars were yielding, the forces in them were found by

multiplying the area of the bars, 0.85 sq in., by their yielding stress. Each tie had two PT bars

and their yielding stress was 140 ksi, which was found from testing data. By making a cut at the

load point and summing the moments about the node just below the load point, the force at the

reaction can be found. With the forces in the bars and at the reaction known the forces in the

struts were found by nodal analysis. The calculated forces in each of the members can be seen in

Figure 13-9.

Comparing the experimental to predicted capacities for shear or flexure it could be seen

that flexure provided the best representation of the beams capacity. This was due to the beams

unusual configuration.

172 kip

211 kip

- 299 kip

- 501 kip

238 kip @ 6 deg.

238 kip

(-) Compression

479 kip @ 8 deg.

Figure 13-9. Forces in strut-and-tie model

99

Table 13-1. Post-tensioned beam nominal moment capacities

a/d Mexp Mn Mexp/ Mn(kip*ft) (kip*ft) (kip*ft)

2 1507 1428 1.06 3 1685 1519 1.11 3 (2nd Test) 1587 1519 1.05 Table 13-2. Post-tensioned beam shear capacity results

a/d ACI Strut & Tie MCFT VEXP Vn VEXP / Vn Vn VEXP / Vn Vn VEXP / Vn

(kip) (kip) (kip) (kip) 2 196 42 4.67 172 1.14 84 2.33 3 142 34 4.18 --- --- 84 1.69 3 (2nd Test) 133 34 3.91 --- --- 84 1.58

100

CHAPTER 14 SUMMARY AND CONCLUSIONS

Post-tensioned beams were constructed and post-tensioned. This set of testing conducted

destructive load tests to post-tensioned beams which had no shear reinforcement outside of the

end block, approximately 3 ft from each end of the beam. The beams had two straight bars and

two parabolic bars. The bars were anchored using 1 ¾ in. thick steel plates. Post-tensioning

stresses were monitored and recorded. Losses were calculated using measured strains during

stressing. Seating, Elastic, short-term Creep and Shrinkage losses were able to be measured. The

short-term creep and shrinkage losses were measured for approximately 2.5 days. Losses due to

creep and shrinkage were higher than calculated values from AASHTO 2007. Creep and

shrinkage are measured over longer periods of time than the period which was measured during

our tests which may have altered the comparison. Tests were done to observe the effect of

support conditions on the behavior of the beam. The support conditions were of interest because

of the variability of them in the field. The beams were observed to be resting on tar paper and

steel plates. A test was done with a shorter shear span to see if the beam would fail in shear.

Shear was of interest because of the lack of reinforcement in the beams. This lack of

reinforcement has produced low bridge ratings for the beams. The following conclusions were

made:

• The measured take-up was in the range recommended by Lins and Burns (1981) for straight bars.

• Parabolic bars had slightly higher take up values due to their alignment with the anchor plate.

• A concrete on concrete bearing surface behaved the same as a beam with neoprene bearing pads up until cracking occurred. Once cracking occurred the stiffnesses of the beams differed resulting in a more ductile failure mode for the neoprene bearing pads.

• Bearing surfaces did not change the failure mode, which was a flexural failure.

101

• The concrete surface only provided a slight increase in capacity over the neoprene pad but led to a non-ductile failure.

• Loading the beam at an a/d ratio of 2 did not cause the beam to fail in shear even with the absence of shear reinforcement.

• The failure at an a/d 2 was due to the PT bars yielding which was best represented by a strut-and-tie model or its moment capacity.

• The moment capacity for each of the tests, a/d of 2 and 3, provided the most accurate representation of the beams capacity.

102

LIST OF REFERENCES

1. Schlaich, J.; Schäfer, K.; and Jennewein, M. “Toward a Consistent Design of Structural Concrete,” PCI Journal, V. 32(3), No. 3, 1987, pp. 74-151.

2. ACI Committee 318 (ACI), “Building Code Requirements for Structural Concrete and Commentary (ACI 318-05/ACI 318R-05),” American Concrete Institute, Detroit, 2005.

3. Collins, M.P., Mitchell, D., “Prestressed Concrete Structures.” Prentice Hall Inc., Englewood Cliffs, 1991, 766 pp.

4. Ramirez, J.A., “Strut-Tie Design of Pretensioned Concrete Members.” ACI Structural Journal, V. 91, No. 4, Sept.-Oct. 1994, pp. 572-578.

5. Alshegeir, A. and Ramirez, J.A., “Strut-Tie Approach in Pretensioned Deep Beams.” ACI Structural Journal, V. 89, No. 3, May-June 1992, pp. 296-304.

6. MacGregor, J. and Wight, J., “Reinforced Concrete: Mechanics and Design.” Pearson Preston Hall, Upper Saddle River, N.J.

7. Bakht, B. and Jaeger, L.G., “Bearing Restraint in Slab-on-Girder Bridges.” Journal of Structural Engineering, V. 114, No. 12, December 1988, pp. 2724-2740.

8. American Association of State and Highway Officials (AASHTO), “AASHTO LRFD Bridge Specifications.” Washington, DC. 2007.

103

BIOGRAPHICAL SKETCH

Gustavo Adolfo Llanos was born in 1984. He was born and raised in Miami, Florida, and

is the youngest of two brothers. He graduated from Miami Killian High School in 2002. He

earned his B.S. in civil engineering from Florida State University (FSU) in 2006. He is pursuing

his M.E. in structural engineering from the University of Florida (UF). Upon completion of his

master’s degree, Gustavo will be working with BCC Engineering in Miami, Florida.


Recommended