Date post: | 17-Dec-2015 |
Category: |
Documents |
Upload: | victor-miller |
View: | 213 times |
Download: | 0 times |
© Ameresco, Inc. 2012, All Rights Reserved
Oconto FallsSchool DistrictMarch 2012 Update
Energy Performance
Progress Report
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update
2
Introduction
This presentation is designed to provide the Oconto Falls School District with a brief update of the project status and the improvements being implemented. Ameresco will be providing these monthly updates until the project is completed.
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update
3
Executive SummaryThe Oconto Falls School District’s energy saving project is growing in construction tempo as we move into Spring. The interim energy cost savings for the 2012-13 FY will be generated largely from electrical savings since natural gas savings work (heating) will not be completed until building comfort heat has been shutdown for the season. The District’s energy savings benefit from this project is approximately $6,700 from an annual guaranteed savings of $137,400. Total construction costs incurred to date are approximately $738,000.
Even though the project was approved by the School Board early last fall, project funding availability for this project became available in early December 2012.
A number of the facility improvement measures, which were expected to be completed before cold weather set-in, were only partially completed with on going work resuming once warmer seasonal weather returns.(i.e. building envelope, window film). Finalization of water conservation work was also placed on hold rather than restricting student access to restrooms during plumbing/floor removal and replacement at Washington.
© Ameresco, Inc. 2012, All Rights Reserved
4
Timeline
Projected Activity Estimated Date
Contract Signature (September 2012) Complete
- FIM Abrams Bell/PA System Upgrade Complete
- High School (Old Gym) Roofing Replacement Complete
Project Financing (December 2012) Complete
Subcontractor Awards/Contract Incremental Based Progress
General Construction Start In Progress
Project/Construction Management December 2012- July 2013
Project Completion July 2013
District Project Completion Acceptance July/August 2013
Utility Rebate Applications August 2013
Post Construction Savings Measurement and Verification
August – September 2013
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
5
Activities• The Abrams Bell replacement and high school roof
replacement work was completed before December
• Kitchen Electrical Modifications have been completed
• IT Solutions: Flat Panel Computer Monitors had been ordered but the District is considering alternative hardware
© Ameresco, Inc. 2012, All Rights Reserved
6
Project Summary and Status
LOCATIONS IMPROVEMENT DISCRIPTIONPRE-
CONSTRUCTIONUNDER
CONSTRUCTION COMPLETEDistrict-wide Lighting retrofits & controls X District-wide Water retrofits X District-wide Building Envelope X
HS & District Office Window Film (exterior low-e) X
District-wide Building Automation & Digital Control X District-wide IT Solutions and Printing Savings X
OFHS Domestic Water Heater Replacement X OFHS Electrical Transformer Upgrade X
OFESPartial Boiler Plant Upgrade & Domestic
Water Replacement X HS & WMS Kitchen Modifications X
HS Roofing – Old Gym Area C X WMS Domestic Water Replacement / Expansion X
OFES & Abrams Bell / PA System Replacement X (Abrams Complete)
OFES Window Replacement (Phase I) X Abrams Boiler Plant Upgrade X
District-wideExterior Wall Restoration (Does not
Include the HS) X
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update
7
Percentages for Construction and Annual Savings
% Energy Savings FY 2012-13: Savings is estimated based on = ((# of months since FIM completion/FY2012-13 months remaining ) x annual FIM costs savings)/annual Project savings
Estimated Start/Finish
IMPROVEMENT DISCRIPTION
Construction Complete %
% Annual Savings FY
2012-13March -
April Lighting retrofits & controls 0 % 0 %
January – June Water retrofits 75 % 1.2 %
December – June Building Envelope 85 % 3 %
April – May Window Film (exterior low-e) 0 % 0 %February -
June Building Automation & Digital
Control 0 % 0 %
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update
8
Estimated Start/Finish
IMPROVEMENT DISCRIPTION
Construction Complete %
% Annual Savings FY
2012-13December –
March * IT Solutions and Printing Savings 0 % 0 %
February – March
Domestic Water Heater Replacement 0 % 0 %
February – June Electrical Transformer Upgrade 0 % 0 %
April – JunePartial Boiler Plant Upgrade & Domestic Water Replacement 0 % 0 %
February – March Kitchen Modifications 100 % 0 %
November - December Roofing – Old Gym Area C 100 % 1 %
* Designates change in completion date from previous month% Energy Savings FY 2012-13: Savings is estimated based on = ((# of months since FIM completion/FY2012-13 months remaining ) x annual FIM costs savings)/annual Project savings
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update
9
Estimated Start/Finish
IMPROVEMENT DISCRIPTION
Construction Complete %
% Annual Savings FY
2012-13February -
MarchDomestic Water Replacement /
Expansion 0 % 0 %
June* Bell / PA System Replacement 50 % 0 %June – July Window Replacement (Phase I) 0 % 0 %April - June Boiler Plant Upgrade 0 % 0 %
April - June Exterior Wall Restoration (Does not Include the HS) 0 % 0 %
Estimated Total Percentages ~22% ~ 5.2%
- Continued
* Designates change in completion date from previous month
% Energy Savings FY 2012-13: Savings is estimated based on = ((# of months since FIM completion/FY2012-13 months remaining ) x annual FIM costs savings)/annual Project savings
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
10
Bell / PA System ReplacementSTATUS: 50%
Abrams Elementary - Complete
Oconto Falls Elementary School – On Hold until summer break
The replacement start date for the OFES PA system is being delayed to minimize potential disruption during the school year. As long as the existing system is functional, work will be completed at the start of summer break. The summer break timing will allow for multiple day outage and improved building access.
Benefits/Results♦ School wide notification of activities and events ♦ Capital Budget Savings
Photo taken during installation
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
11
Roof Replacement – HS Old Gym
STATUS: Construction Complete 100%Roofing section was leaking and in need of a complete replacement. A new 30 year Roof was designed, installed with all flashing work complete.
Benefits/Results♦ Elimination of the potential for roof leakage causing interior water damage♦ Capital Budget Savings♦ Operational and Maintenance Savings
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
12
Water Conservation RetrofitSTATUS: In-Progress (District-wide) - 75% The water conservation retrofit and upgrade work is nearly complete.
The work replacing China fixtures at Washington Middle School remains to be started. Fixture replacement also requires concrete work and floor restoration to replace in-floor fixtures and below grade piping.
Benefits/Results♦ Water Conservation♦ Operational and Maintenance Savings♦ Capital Budget Savings
Example of Typical Fixture replacement at Washington (not actual photos)
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
13
Building Envelope
STATUS: 85%Interior: Complete Exterior: On Hold until Spring temperatures returnUncontrolled air leakage has been stopped with the installation of weather stripping, wall/roof joint seals, window frame caulking and wall ventilation penetrations seals.
Outdoor roof curbing and air intake hoods will be sealed once warmer seasonal temperatures return
Benefits/Results♦ Energy Savings (heating and cooling)♦ Capital Budget Savings
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
14
Lighting Retrofits and Controls STATUS: In-ProgressDelivery of Materials is expected in late February. On-site work is tentatively scheduled for early March.
FALS & New Path scopes removed from implementation
Benefits/Results♦ Energy Savings♦ Operational and Maintenance
Savings
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
15
Building Automation & Digital Control STATUS: In-ProgressBuilding automation work is in progress with controls contractors completing design work.
This includes the conversion of remaining Pneumatic controls to Direct Digital Controls.
On-site work expected to start early March
Benefits/Results♦ Energy Savings♦ Operational and Maintenance
Savings
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
16
IT Solutions & Printer SavingsSTATUS: PendingMonitor Replacement on hold for District hardware decision.
IT Solutions, including Power Management, Toner/Ink Reduction, Rules-Based Printing, Printer Consolidation Software applications will also in March be implemented
Benefits/Results♦ Energy Savings♦ Operational and Maintenance
Savings
© Ameresco, Inc. 2012, All Rights Reserved
Ameresco Update - March
17
Kitchen Electrical Modifications STATUS: 100% CompleteHigh School & Washington Middle School; Upgrade the work scope to 2011 National Electrical Safety Code(2011 NEC). Add electrical overcurrent protection and new receptacles.
Benefits/Results♦ Operational and Maintenance
Savings♦ SAFTEY: Minimize District Assets
Liability
© Ameresco, Inc. 2012, All Rights Reserved
Next Steps
18
Lighting Retrofit – March start Finalized Engineering Design Material selection and procurement Warm weather related construction start Project Scope changes and Continuous Improvement Ameresco is continuing implementation with minor
schedule shifts to accommodate limited scopes for seasonal temperatures or improved summer break access
Technical
© Ameresco, Inc. 2012, All Rights Reserved
AMERESCO Information and Resources
19
Kent WolfBusiness Development Manager
952.942.5142 ext. 4690Cell: 612.804.6274
Ameresco-Midwest Region9855 West 78th Street, Suite 310
Eden Prairie, MN [email protected]
Thank You
Please visit our website: www.ameresco.com
Services Press Releases Case Studies