+ All Categories
Home > Documents > 03. Design Brief

03. Design Brief

Date post: 01-Jun-2018
Category:
Upload: leed-en
View: 219 times
Download: 1 times
Share this document with a friend

of 31

Transcript
  • 8/9/2019 03. Design Brief

    1/81

    M&E Services Design BriefConceptual Design Stage

    THE SEN HOTEL

    27 Dec 2012

    232512Revision 03

    Aurecon (Vietnam) Co LtdSuite 1304 - Centec Tower72-74 Nguyen Thi Minh Khai StrDistrict 3, Ho Chi Minh City, Vietnam

    Telephone: +84 8 3823 9994Facsimile: +84 8 3824 6880Email: [email protected]

  • 8/9/2019 03. Design Brief

    2/81

    Document Control

    Document ID: P:\232512 IDIP HOTEL SPN (76-78 NTMK)\TECH\MEP\REPORTS\DESIGN BRIEF\CONCEPT\DESIGN BRIEF ENG REV02.DOC

    Rev No Date Revision Details Typist Author Verifier Approver

    01 07 Dec 2012 Issued for Conceptual Design TT TT DP TB

    02 24 Dec 2012 Issued for Conceptual Design TT TT DP TB

    03 27 Dec 2012 Issued for Conceptual Design TT TT DP TB

    A person using Aurecon documents or data accepts the risk of:

    a) Using the documents or data in electronic form without requesting and checking them for accuracy against theoriginal hard copy version.

    b) Using the documents or data for any purpose not agreed to in writing by Aurecon.

  • 8/9/2019 03. Design Brief

    3/81

    The Sen Hotel Page 1

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    1. Introduction 4

    2. Building Services Common Design Objectives 5 2.1 Life cycle cost 5

    2.1.1 Reliability and availability of services 5

    2.1.2 Ease of Operation and Maintenance 5

    2.1.3 Ingress of dust, water and pests 5

    2.1.4 Coordination of Services 5

    3. Weather Condit ion at Project Site 6 3.1 Site Location 6

    3.2 Ambient Temperatures Used in the Design 6

    4. Fire Protection Systems 7 4.1 Codes and Regulations 7

    4.2 Description of Fire Protection Systems 7

    4.3 General Requirements for Fire Protection System 7

    4.3.1 Fire Prevention requirements: 7 4.3.2 Fire Fighting requirements: 8

    4.3.3 Proposed Design of Fire Protection system: 8

    4.4 Automatic Fire Alarm System 8

    4.4.1 General 8

    4.4.2 Operation of the System 9

    4.4.3 Main Components of the Fire Alarm System 9

    4.5 Fire Fighting System 11

    4.5.1 Portable Fire Extinguisher System 11

    4.5.2 Fire Fighting for the entire building includes: 11

    4.6 Automatic Fire Sprinkler System 12 4.6.1 Sprinkler Head Installation and Technical Data 12

    4.6.2 Piping system 12

    4.6.3 Accessories: 12

    4.7 Fire Hose and Hydrant System 13

    4.7.1 Fire Hose Location and Technical requirements 13

    4.7.2 External Fire Hydrant Location and Technical requirements 13

    4.7.3 Piping system 14

    4.7.4 Accessories: 14

    4.8 Pumping System and Operation 14

    4.9 Portable Fire Extinguishers 14

    4.10 Fire Trip Shut Down 15

    4.11 Special Fire Protection Systems 15

    5. Electrical 16 5.1 Codes and Regulations 16

    5.2 Medium Voltage System 16

    5.2.1 Electric Power Demand: 16

  • 8/9/2019 03. Design Brief

    4/81

    The Sen Hotel Page 2

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    5.3 General Power Supply and Transformers: 16

    5.3.1 The Medium Voltage Power System 16

    5.3.2 The Power Back-up System – Diesel Engine Power Generators: 17

    5.3.3 The Fuel System for Diesel Engine Power Generators 17

    5.4 Low Voltage System 17

    5.4.1 Low Voltage – Main Switchboard (MSB) 18 5.4.2 Distribution Board 18

    5.4.3 General Power Outlets (GPO) 19

    5.4.4 Lighting 19

    5.4.5 Lightning Protection 20

    5.5 Earthing 21

    5.6 Telephone & ADSL Cable System 21

    5.7 Public Address System 21

    5.8 CCTV System 22

    5.9 Door Access Control System 22

    5.10 MATV and Cable TV System 22 5.11 Mobile Telephone Booster System 22

    5.12 UPS System 23

    5.13 Building Management System (BMS) 23

    6. Lift Systems 24 6.1 Codes and Regulations 24

    6.2 Design Criteria 24

    6.3 Fireman’s Lift 24

    6.4 Calculation 24

    7.

    Air Condit ioning and Mechanical Ventilation 25

    7.1 Codes and Regulations 25

    7.2 Design Conditions 25

    7.2.1 Designed Temperatures in Air Conditioned Spaces 25

    7.2.2 Design Parameters 25

    7.2.3 Noise Criteria (by acoustic consultant) 26

    7.3 Air Conditioning Systems 26

    7.3.1 General Description 26

    7.3.2 Main Equipment Of Chiller Systems 26

    7.4 Mechanical Ventilation 27

    7.4.1 Stair Pressurisation System 27 7.4.2 Pressurisation System 27

    7.4.3 Smoke Spill System 28

    7.4.4 Fresh Air System 28

    7.4.5 Toilet Exhaust System 28

    7.4.6 Commercial Kitchen Exhaust System 28

    7.4.7 M&E Plant Room Ventilation System 29

  • 8/9/2019 03. Design Brief

    5/81

    The Sen Hotel Page 3

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    7.4.8 Carpark Ventilation System 29

    8. Plumbing & Sanitary Systems 30 8.1 Codes and Regulations 30

    8.2 Water Supply and Storage 30

    8.3 Potable Water System 30

    8.4 Sanitary Drainage 31 8.5 Waste Water Treatment Plant 31

    8.6 LPG System 32

    8.7 Storm Water Drainage 32

    8.8 Condensate Drainage 32

    Appendix A. Vietnamese Translation Appendix B. Calculations

    - Power Demand

    - Hot & Cold Water Demand- Fire water Demand- Lift analysis

  • 8/9/2019 03. Design Brief

    6/81

    The Sen Hotel Page 4

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    1. Introduction

    The purpose of this design brief is to outline all of the Mechanical and Electrical systems thatwill be designed and installed as part ofThe Sen Hotel project located at76 – 78 Nguyen ThiMinh Khai Str ., District 3, HCMC.

    The project comprises the construction of an18 storey building, 1 technical storey, Level 1 to 3is Multi-Function, Level 4 to 17 is Hotel Guest room, Level 18 for Spa.

  • 8/9/2019 03. Design Brief

    7/81

    The Sen Hotel Page 5

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    2. Building Services Common Design Objectives

    The following common design objectives will be followed throughout the building servicesdesign, in order to meet the development’s objectives, operational requirements and standardsand to comply with the agreed design criteria.

    2.1

    Life cycle costThe building services design will aim to achieve optimum life cycle costs and will take intoconsideration: Capital costs Energy costs Running, Operational costs and Maintenance costs Equipment life expectancy

    2.1.1 Reliability and availability of services

    The design will provide a high level of reliability and availability of services to ensure thedevelopment’s normal operation. This will be achieved through:

    Robustness of services. The specification of highly reliable equipment and material. Monitoring of operating and alarm conditions. Proven installation details and methods

    2.1.2 Ease of Operation and Maintenance

    Ease of operation and maintenance will be considered in all engineering services, withan emphasis on the following; Simplicity and ease of operation Uniformity of equipment and fittings including brand and size. Ease of maintenance and accessibility of services

    2.1.3

    Ingress of dust , water and pests All services will be designed to eliminate/ minimise the ingress of water, dust and pests.

    Equipment/ fittings of the correct IP rating will be specified where required by theenvironmental or operating conditions

    2.1.4 Coordination of Services

    All services will be well coordinated to provide an integrated installation of pipe work,ductwork, cable trays, light fittings, etc…

    The services will be well supported using prefabricated brackets, unistrut, and rodsuspension. Typical support details will be provided in the design as required

    Services contractors will be required to produce multi-discipline workshop drawings to

    ensure full coordination.Provision will be made for future expansion of the building services in terms of plantspace and any built-in or in-ground provision, such a conduits, riser shafts etc.

  • 8/9/2019 03. Design Brief

    8/81

    The Sen Hotel Page 6

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    3. Weather Condition at Project Site

    3.1 Site Location Location: HO CHI MINH CITY Latitude: 10o 8’ N

    Longitude: 106o

    7’ E Elevation: 19 m

    3.2 Ambient Temperatures Used in the Design Summer Dry Bulb: 37.0oCDB Summer Wet Bulb (mean): 29.0oCWB Summer Daily Range: 11K Hot month of the year: April or May

  • 8/9/2019 03. Design Brief

    9/81

    The Sen Hotel Page 7

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    4. Fire Protection Systems

    4.1 Codes and Regulations

    The Fire Protection System will be designed in accordance with the well recognizedinternational standards and local codes, regulations for fire services as follows: TCVN 5760:1993 Fire Extinguishing Vietnamese Fire Code TCVN 5738:2000 Fire Alarm TCVN 2622:1995 Vietnamese Fire Code for building construction TCVN 6160:1996 Vietnamese Fire Code for High Rise Building TCVN 6161:1996 Vietnamese Fire Code for Market & Commercial Building TCVN 3890:2009 Fire protection equipments installation for Building TCVN 7336:2003 Vietnamese Fire Code for Sprinkler system QCVN 06-2010 Fire safety QCVN 08-2009 Basement carpaking NFPA 13-14 USA Fire Code ACCOR Design Guidelines for Fire Safety

    4.2 Descript ion of Fire Protection Systems

    The Fire Protection System consist the followings: Fire Alarm System Automatic Fire Sprinkler System Fire Hose and Hydrant System Other systems associated with the Fire Protection System include;:

    Smoke exhaust system (for basements and corridors, fire lift lobbies…) Public Address system (Emergency warning intercom system) Main power supply and stand-by generator system Normal, Emergency and Exit lighting systems Earthing and Grounding system Lightning Protection system Potable water supply system Waste water drainage system

    The Fire Escape Routes and Fire Rated Zones will be described in Architectural and Structuraldesign briefs and are excluded from this M&E Design Brief.

    4.3 General Requirements for Fire Protection System

    Based on the class of fire as defined in TCVN 7336:2003 and relevant NFPA, this building isclassified under “Ordinary Hazard Class 1 of Occupancy” for Hotel. The generalrequirements of the Fire protection system will meet with the design objectives are as below:

    4.3.1 Fire Prevention requirements: Minimize the cause of fire. In case of fire provide an early warning and immediate

    response to isolate and kill the fire before it can spread to the adjacent areas and

    cause more serious damage. In case of fire building occupants can be evacuated to a safe zone in a fast and

    safe manner In case of fire in the basement areas, plant rooms, flats in the building, the exact

    location shall be identified and the fire shall be fought immediately Provide fire stoppers for all M&E ductwork & pipework through fire walls & slabs.

  • 8/9/2019 03. Design Brief

    10/81

    The Sen Hotel Page 8

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    4.3.2 Fire Fighting requirements: The Fire Fighting Equipment specified will be highly reliable, and provide

    availability of services at all times. The fire can be immediately identified andfought.

    Fire Fighting Equipment will be selected to provide simplicity and ease of operation,and meet the project requirements and local weather conditions.

    Fire Fighting Equipment will be selected to achieve a long life expectancy and willbe of the latest technology. The selected Fire Fighting Equipment will meet with the requirements of relevant

    standards as defined in clause 4.1

    4.3.3 Proposed Design of Fire Protection system:

    The Fire Alarm (FA) System will be installed in all areas of the building. The FA systemwill be of the addressable type.

    In addition to it’s monitoring and alarm functions, the Fire Alarm System will alsointerface with other building systems via software and the Local Area network.

    The system will; Identify the fire, report to the Fire Control Panel the exact location of the fire, make

    a public announcement and alert the Fire Officer immediately Control and Monitor the Fire Sprinkler, Hose and Hydrant system The system will allow for connection and transfer of signals to and from the BMS,

    digital telephone system, Lifts, Mechanical Ventilation, Power Cut-off, Public Address system etc to enable evacuation and fire fighting in the fastest possiblemanner

    Store a history file of all system events such as alarm, fault, status, operatoractivities etc. This will be stored on disk. A record of the last 2,000 events will bemaintained on disk which can be printed out upon request.

    Incorporate alarm bells with signal alarms and specific sound as required The specified system will be immune to external Electro-Magnetic Interference

    (EMI) generated by radio transmission equipment or power lines.

    The Automatic Fire Sprinkler and Fire Hose & Hydrant systems will be installed in allpublic areas, basements, shell and core areas, corridor and kitchen apartments.

    In addition to the fire alarm and protection system, fire extinguishers or other special fireprotection systems (independent Automatic Fire Extinguishing foam system forgenerator/ fuel pump room) will also be provided.

    4.4 Automatic Fire Alarm System4.4.1 General

    The Fire Alarm system will identify the fire and report to the Fire Control Panel the exactlocation of fire and subsequently alert all of the building users of the situation.

    Automatic fire alarm system will consist of the following: Central Fire Alarm Control Board Data Gathering Panels Fire Alarm Graphic Annunciation Panels or Mimic Panels Standard LED Annunciation Panels Automatic Smoke and Heat Detectors. Manual Break Glass Stations. Fire Alarm Speakers and Visual Alarms Printers, Power Supply and Complete Wiring System. Lightning Protection and Surge Suppression for Fire Alarm System.

  • 8/9/2019 03. Design Brief

    11/81

    The Sen Hotel Page 9

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    4.4.2 Operation of the System

    When a signal is received from detectors or control modules the central fire alarm boardwill start warnings in the network, to control computer and fire alarm panels.

    After a pre-determined period, if the warning signals still exist, the central fire alarmboard will then start warnings to the following equipments and systems:

    Public address system ACMV system Alarm bells and alarm lights Address to pre-determined telephone numbers Stand-by power allows the system to operate normally for 24 hours after failure of

    the main power (this is to meet with the Local Fire Department’s Requirement)

    The system is also capable of; Filing and printing 2,000 items of data, Making automatic checks to confirm status and inform maintenance schedule

    4.4.3 Main Components of the Fire Alarm System

    Fire Alarm DetectorsTwo types of Fire Alarm Detectors will be included; Addressable Smoke Detectors (Photo Electric type): Bedrooms, Meeting rooms Addressable Heat Detectors (Fixed Temperature): Kitchen

    The numbers of detectors and applicable type of detector for each particular area will beinstalled to comply with the relevant standards.

    Addressable Smoke Detectors

    The Smoke Detectors will be installed in the required areas and shall be at the locationnot exceeding 0.3m from the ceiling, 5m from the walls and the distance between thedetectors will not exceed 10m.

    Addressable Heat Detectors

    The Heat Detectors will be continuously working and beyond the fire detection function,it will employ a self-testing and heat measurement function. Monitoring from the main firecontrol panel will be displayed in 3 stages;

    Normal Status Fault Status Alarm Status: when smoke temperature rise is 5oC/minute or reaches 60oC

    Technical data of Addressable Smoke & Heat Detector are as below: Operating Voltage: 16V to 24VDC max 28VDC Operating Current (quiescent): 100 µA Operating Current (alarm): 6 mA Operating Temperature, humidity: -20oC to +50oC, 95%RH Alarm temperature: +80oC Standard for Fire detector: EN54

    Addressable Input/Output Modules

    Addressable INPUT modules shall be used for monitoring of Pressure Switches, WaterTank High/Low level, Pump Start/Stop status and other contact inputs. It shall be able toconnect directly along the individual addressable loop. An independent programmable

  • 8/9/2019 03. Design Brief

    12/81

    The Sen Hotel Page 10

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    software zone shall be provided for each interface unit. The addressable input moduleshall be equipped with a built-in red LED which shall be flashed in the event ofactivation.

    Addressable OUTPUT modules shall provide a control output from the control unit toother equipment’s control centre and shall have a separate, fully supervised input toenable the control unit to obtain positive feed back to confirm that the output function has

    been carried out.Technical data of Input/Output Module are as described below; Analog PLUS line: APMK = 1, 2 Input/Output Signal: Jumpers setting NO/NC Operating Temperature, humidity: -10oC to +60oC, 95%RH Standard for Fire detector: EN54

    Addressable Sounder Base The addressable Sounder Base is applied for Hotel Bed rooms. The sounder base “listens in” to the communication between the attached sensor

    head and the fire alarm control panel (FACP) to adopt the same address as thedetector, but as a unique device type on the loop.

    The FACP can then use that address to command an individual sounder — or agroup of sounders — to activate. The command set from the panel can be tailoredto the specific event, allowing selection of volume, tone, and group.

    The addressable sounder base is type of built in isolator to isolate all sounder basepoints , Depending the Manufacturer ‘s recommendation that the External wires mayneeded.

    Main Fire Alarm Panel (FACP)

    The Main Fire Alarm Panel (FACP) shall be of the addressable type, connecting 125data points per loop with additional 20% spare capacity for future system expansion. Thesystem allows connecting and transferring signals to/from the BMS, digital telephonesystem, Lifts, Mechanical Ventilation, Power Cut-of, Public Address System. Mainfunctions of MFAP are: Reporting, input events, graphic display and printing Provide information continuously and accurately Integrated in Automatic Fire Alarm system Large storage capacity Control functions includes:

    o Reset button

    o Signal receive button

    o Alarm signals shut down button

    o Alarm bells

    o Interchange signals

    Maintenance Schedule

    The Main Fire Alarm Panel (MFAP) shall be installed at the Fire Control Room tomonitor and control the entire fire alarm system.

    Break Glass button, Bells and LED Indicators

    All manual call points shall be installed at 1.5m high, in corridors and stair case and willbe visible to people. Bells shall be installed at 2.2m high.

  • 8/9/2019 03. Design Brief

    13/81

    The Sen Hotel Page 11

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    Technical data of Addressable Emergency Break Glass Unit are as below:

    Operating Voltage: 16VDC to 26VDC Operating Current: 60 to 100 mA / f≥ 5Hz Technical data of

    Programmable Alarm Bells are as below:

    Operating Voltage: 9V to 30VDC

    Operating Current: 3 to 9mA Operating Temperature: -25oC to +85oC

    Sound Power level at 1m: 95 dBTechnical data of Display LED are as below:

    Operating Voltage: 20V to 30VDC

    Operating Current: 155mA (3.7W) at 24VDC

    Operating Temperature: -20oC to +60oC

    Cabling System

    System includes: Signal cables, junction boxes and accessories

    Signal cables shall be 2 x 1.0 mm2 fire resistance cable, power cables for bells andmodules shall be 2 x 1.5mm2 fire resistance cables or pvc-insulated cables in metalconduit with 1 hour fire rating (min.) embedded in wall or in ceiling.

    Power Supply

    All devices shall be able to operate on mains power supply of 220VAC, -15% to +10%with 48Hz to 62Hz

    Each power supply unit shall be equipped with stand-by battery of nominal voltage of24VDC with the capacity to maintain its operation for at least 24 hours after mainsfailure.

    4.5 Fire Fighting System4.5.1 Portable Fire Extinguisher System

    For the purposes of initial fire fighting there will be provision of fire extinguishers, in theform of bottles as Dry chemical type bottles and CO2 type for all public areas, lobby,electric room,…

    4.5.2 Fire Fighting for the entire building includes: Automatic Fire Sprinkler system which will cover all public areas, lobbies, corridors,

    reception, basement car-park and all bedrooms Fire hose / fire hydrant system: fire hose will be installed in all areas of the building

    and external fire hydrant will be installed outside the building. The distancebetween the external hydrant cabinets will not exceed 100m

    Fire Pumps Station: combine fire pump system for automatic fire sprinkler systemand fire hose & hydrant system and will includes: 1 Fire pump control panel, 2electric drive fire pump, 1 jockey pump, 1 pressure tank 100L, continue supply aminimum water flow rate of 74 l/s to the highest point of the building and maintainthe pressure of the system be unchanged at all time.

    Automatic fire fighting foam system to provide for the fuel pump room. Fire Water Storage Tank: the min. storage capacity is 305 m³ use for automatic

    sprinkler, fire hydrant and hose reel and includes:

    Fire sprinkler system: 207 m3

  • 8/9/2019 03. Design Brief

    14/81

    The Sen Hotel Page 12

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    Fire hose system: 170 m3.

    (See attached Appendix for calculation sheets)4.6 Automatic Fire Sprinkler System

    The Automatic Fire Sprinkler System will consist of the following main equipment: Fire Alarm Cabinet with Flow Switch located on the wall in the landing area of the fire

    escape staircase. Sprinkler Head,:- Concealed type of 68oC, K=80, 15mm will be installed for bedrooms, corridors,

    lobby- Exposed type of 68oC, K=80, 15mm will be installed for public areas, BOH

    Area of sprinkler operation, the density for 120m2 (in accordance with TCVN 7336, section6.4) is 4.8 L/min.m2 or 476 L/min will be designed for continuously operating for 30minutes.

    Sprinkler Pendant Head of 93oC, K=80, 15mm will be installed for plantrooms, Kitchen Sprinkler upright Head, of 68oC, K=160, 20mm will be installed in basement and carpark

    areas. Sprinkler PendantHead, of 68oC, K=160, 20mm will be installed in restaurant areas.

    Area of sprinkler operation for Ordinary Hazard Class 1 and 2 Occupancies, the densityfor 240m2 (in accordance with TCVN, section 6.4) is 7.2 L/min.m2 and 14.4 L/min.m2 willbe designed for continuously operating for 60 minutes.

    The Fire protection system has an automatic pressure within the pipework. Minimum pressurein the system is 1.0 bar.

    When there is a fire, sprinkler head will automatically operate with the designed flow rate andpressure. Flow Switch will be activated and send fire alarm signal to the Main Fire Alarm Paneland sound an alarm.

    The automatic sprinkler system will continuously operates in 60 minutes until the fire officerarrives and fire hose system be used.

    4.6.1 Sprinkler Head Installation and Technical Data

    The upright sprinkler heads will be installed for carpark, planroom areas. The pendentsprinkler heads will be installed in all public areas, office, bedroom, restaurant of thebuilding as defined. Distance between sprinkler heads is 3.0m to 4.0m, distance from thewall is 1.5m to 2.0m and with the maximum cover area for each sprinkler head will beaccording to NFPA 13.

    Sprinkler heads shall be of glass bulb, bronze or chrome finish, nominal temperature is68oC, 93oC.

    Sprinkler head are showed on layout plan.4.6.2 Piping system

    Branch pipe to the sprinkler heads shall be in a range of D25 to D150

    The risers from the pump station will be completed with Alarm Valves at each floorFrom the main risers, branch pipe will connecting the sprinkler heads to the system.

    4.6.3 Accessories:

    Other accessories in the automatic sprinkler system will include: Control Valves for automatic fire sprinkler system including;

    o Main Stop Valve

  • 8/9/2019 03. Design Brief

    15/81

    The Sen Hotel Page 13

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    o Alarm Valve

    o Waste & Test Valve

    o Pressure Gauge Flow Switch, Water Motor Alarm Gong Main Supply Pressure Gauge Pressured Tanks Pressure Reducing Valves Drain Manifold from Control Valves. Pump Initiating Pressure Switches (including wiring). Alarm Pressure Switches wired to the Main Fire Alarm Panel Individual Stop Valves for each Main Supply into the Control Valve

    Station. One Annular Testing Assembly complete with Isolating Valves on inlet

    and Outlet. The Annular Element complete with Protective Guard shallbe permanently fitted to wall near spares cabinet.

    Spares Cabinet, complete with sufficient spare sprinklers and sparesprinkler spanner.

    4.7 Fire Hose and Hydrant System4.7.1 Fire Hose Location and Technical requirements

    Fire Hose Cabinet (Internal Fire Hydrant) and Fire Hosereel systems will be installedinside staircases (Fire Hydrant) and in the Corridor (Fire Hosereel) of all floors as per thelocal fire department’s requirements.

    The basis of design is described below; Number of hose working simultaneously: 2 Water flow rate at each Int. Fire Hydrant: 2.5 L/s Water flow rate at each Fire Hosereel: 0.55 L/s Minimum pressure at each Fire Hose: 2.5 bar (25m head) Continuously operating time: 3 hours Length of hose will not be exceeded 30m and will be designed so that 2 hoses can

    serve any one point area of the floor. Fire Hose Cabinet will be installed at 1.25m high from finished floor level and near

    the entrance/exit of staircases, visible to the people and for ease of operation.Each hose hydrant cabinet will have 1 flexible hose, 50mm diameter, 20m length,nozzle 13mm diameter and associated connectors. Each hosereel cabinet will have1 flexible hose, 25mm diameter, 30m length, nozzle 13mm diameter andassociated connectors.

    4.7.2 External Fire Hydrant Location and Technical requirements

    An external Fire Hydrant system will be installed outside of the apartment building.

    The basis of design is described below; Number of hydrants working simultaneously: 1 Water flow rate at each hydrant: 10 L/s Minimum pressure at each hydrant: 2.5 bar Continuously operating time: 1 hours

    ( see note at Appendix B: FireWater Demand) External Fire Hydrant will be installed at the nearest point to the entrance/exit of the

    building, visible to building occupants and located for ease for operation.

  • 8/9/2019 03. Design Brief

    16/81

    The Sen Hotel Page 14

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    4.7.3 Piping system

    The Main and Branch pipe to the Fire Hose and Hydrant will be in the range of 50mmdiameter to 150mm diameter. The main pipe will be Galvanized steel, 100mm to 200mmdiameter.

    The Main Water will also connect with the Fire Department Connection of 150mm

    diameter which will be completed with 4 x 65m diameter Connection Adaptors which willallow the fire truck to take water directly from the fire fighting water storage tank orsupply directly from fire trucks to the building fire protection system.

    4.7.4 Accessories:

    The associated devices to complete the installation are as below: Flow Switch at each floor Pressure Gauge Pressure Tank Isolation Valves, Pressure Reducing Valves

    4.8 Pumping System and Operation

    The water supply from the water storage tank to all fire fighting device such as fire sprinklerheads, fire hose reels and fire hydrant hoses will be provided by a pumping station. ThePumping Stations will consist of; 02 Electric drive - Fire water pump Electric drive - Jockey pump - this pump will be operated continuously to maintain the

    designed pressure for the system Water Expansion Tank: 100L

    Fire protection system is designed to operate in fully automatic or manual modes. Inautomatic mode, the pump system will be operated when a signal is received from the flowswitch and alarm valve via the Fire Control Panel.

    In manual mode the pump system can be operated via a manual starter switch installed inFire Services Switch Board (FSSB) or at the Fire Alarm Control Board in the Security

    room.The power supply to FSSB shall be directly from the diesel power generator bus-bar in theLV-Main Switch Board.

    Fire water pump status will be displayed and continuously updated at the Fire ControlBoard. In normal mode, the signal from the flow switch will display as normal and water isavailable.

    4.9 Portable Fire Extinguishers

    Portable Fire Extinguishers will be provided to hazardous areas such as: Plant rooms Pump rooms Lift motor room

    At each Fire Hose CabinetPortable fire extinguishers will be selected to suit specific hazards requirements: Dry chemical: for all public areas, carparks, corridors, lobby, BOH, Retails CO2 : for transformer room, generator room, consumer switch room, server room, control

    room fire blankets for Kitchen

    External extinguishers will be located in the weather proof enclosures

  • 8/9/2019 03. Design Brief

    17/81

    The Sen Hotel Page 15

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    4.10 Fire Trip Shut Down

    Any real alarm signals at the fire control panel will provide a fire trip signal to LVMSB to cut allbreakers fed from Transformer source, to start Emergency Generator and close the breaker tofeed for Emergency busbar.

    The signal is also sent to all distribution boards for ventilation in order to control the operation of

    various mechanical fans in accordance with the Code requirements.

    4.11 Special Fire Protection Systems

    Special fire protection systems will be provided to hazardous areas such as: Automatic operation Foam agent system for oil storage & LPG storage room. Fire suppression system (“ANSUL” as Accor specified dated 23 Oct 09) for Fryer Kitchen

    Hood Fire suppression system for electric room.

  • 8/9/2019 03. Design Brief

    18/81

    The Sen Hotel Page 16

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    5. Electrical

    5.1 Codes and Regulations

    The Electrical Systems will be designed in accordance with the International Standards, thelocal codes and regulations as stated below: 11 TCN 21-84 Power Substation Design Requirements NEC National Electric Code NFPA National Fire Protection Association AS 1680 Code of practice for interior lighting and visual environment AS 1768 Lightning Protection AS 1201 Tubular fluorescent lamps for lighting service AS 3000-2007 Australian Standard Wiring Rules ACCOR Design Guideline of Electrical

    5.2 Medium Voltage System5.2.1 Electric Power Demand:

    The estimated electrical power demand of the entire building, including the lobby areashas been derived in compliance with the recommendations of CIBSE and based uponthe following assumptions; Diversity Applied: 0.6 (For Public, commercials); 0.4 (For Bed rooms) Transfomer spare Capacity: 10% for transformer will be applied (see calculation

    sheet in appendix 2 for reference). Restaurant kitchens : Central LPG 100% back-up power for whole building

    See Appendix for Calculations5.3 General Power Supply and Transformers:

    Sources of Power Supply for the project will mainly from: City lines and transformers Standby Diesel Power Generators of the building

    The Power Sub-station connected to City Power Supply will be located at ground floor andgenerally consist of:

    5.3.1 The Medium Voltage Power System

    Under normal conditions the proposed Power Supply for the building will be derived fromthe City power line and will comprise two medium voltage 22kV feeders which will formpart of a City owned ring main.

    Cable sizes and types associated with the MV supply will be 24 KV ratedXLPE/PVC/SWA/PVC 240mm2 cables and will be installed in uPVC pipe. (Note: therating of Medium Voltage Line should be confirmed by EVN, local electric network)

    The cables will terminate into medium voltage switchgear which will be generally LoadBreak Switches that are SF6 switchgear recommended by Accor’ comments rated at24kV and 630A, but set to suit the estimated building load. The switchgear willincorporate all necessary metering and protection relays.

    Power to the building will then be distributed via 22KV / 0.4 KV 3P 4W 50Hz cast resindry-type (1250 kVA) step down voltage transformer(s) which will be housed within thebuilding. The transformer(s) will be complete with over temperature sensors which willopen their respective protective device(s) as required under fault conditions.

  • 8/9/2019 03. Design Brief

    19/81

    The Sen Hotel Page 17

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    Both the MV switchgear and step down transformers will require housing withindedicated rooms which require a fire rating of ninety minutes.

    The medium voltage system will also be complete with a dedicated earthing systemwhich will comprise a network of electrodes, cabling and copper earth bars as required.Resistance to earth will be 1ohm.

    5.3.2 The Power Back-up System – Diesel Engine Power Generators:Under loss of normal power conditions the building power supply will be derived fromprivate stand by diesel power generator of 1000 kVA.

    The diesel generator(s) will automatically start in the event of a power failure. Thegenerator(s) will provide power to the building within 10 seconds of loss of supply via an Automatic Transfer Switch (ATS).

    The generator will be sized to provide 100% backup power for the building

    The fuel oil tank for the generators will be at basement level and will provide 1 day ofdiesel storage.

    5.3.3 The Fuel System for Diesel Engine Power Generators A fuel storage tank of 5,000 litres for 24Hrs at basement with the fuel pumps &

    pipework system. Fuel from these fuel tanks will be pumped automatically to the generators. The day tank will be mounted on ground inside R.C wall enclosure. The storage tank will be located within an R.C chamber filled with sand. Any fuel leakage will require comtaining within the R.C chamber and will not leak to

    the ground.

    5.4 Low Voltage System

    Low voltage for the building will be distributed at 380V and 50Hz derived via the mediumvoltage system and the step down transformers. The transformers will supply a main

    switchboard (MSB) which will require housing within a dedicated, ninety minute fire rated roompreferably at ground level. Sub main power from the MSB will be distributed to all FloorDistribution Boards and Services SwitchBoards such as MSSB, FSSB and HSSB via busduct orcable through the vertical riser shafts.

    XLPE/PVC 600V cables not exceeding 300mm2 will be installed in cable conduit or cable tray .

    Where cables penetrate through fire rated walls or floor slabs, fire stoppers will be installed.

    Final circuit power will be distributed to the connection points by means of single core PVC orPVC/PVC cables in trunking and conduits. Concealed or cast-in conduits in all areas will be ofPVC type, except within the M&E Plant rooms where galvanized steel conduit will be provided.

    Minimum size of copper conductor shall be 2.5sqmm for lighting and 4 sqmm for power circuits

    Color code: Red, Yellow and Blue for three phasesBlack for NeutralGreen-Yellow strip for Earthing

    All wiring will be contained within one floor with the exception of the lighting system for staircases, where one circuit will be used for multiple floors.

  • 8/9/2019 03. Design Brief

    20/81

    The Sen Hotel Page 18

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    Meters will be located in Main Low Voltage Switchboard (MSB) of the building and FloorDistribution Boards where required for Hotel, Retail, Hotwater production, Kitchen for localpower measurement.

    The low voltage distribution system will also incorporate an LV Earthing network which willcomprise electrodes, cabling and copper earth bars as required. The LV earthing system willconnect to the MV earthing system as required by AS3000:2007and Local Codes.

    5.4.1 Low Voltage – Main Switchboard (MSB)

    The MSB will be divided into essential and non-essential sections as required and willhave a fault withstand capacity in compliance with the project fault level calculations. Allswitchgear inside the switchboard will have an interrupting capacity of not less than50kA symmetrical for MSB fed from two units of recommended 1600 kVA dry-typetransformers.

    The MSB will generally consist of electrical control and protection devices, indicators andpower cables. The protection system will be designed for multiple levels of protection. Incase of short circuit, earth leakage or over current (> 300mA), the relevant protectiondevice will isolate all faulty equipment from power the supply within 0.01s to 4s

    Motorised low voltage Air Circuit Breakers (ACB), rated at 65 KA and 380V will beinstalled at incoming/out going ways for the generator, transformer and auto transferswitches. The remaining outgoing circuits will be protected by either ACBs or MouldedCase Circuit Breakers as deemed sufficient during the course of the design.

    The Automatic Transfer System (ATS) will automatically connect the generator power tothe building distribution system upon loss of normal supply. The system willautomatically return to its normal condition as soon as main city power is resumed andstable.

    5.4.2 Distribution Board

    From the MSB the LV distribution system will reticulate throughout the building asdescribed in section 5.4.1. Sub main cabling will generally terminate at distribution andsection boards and Mechanical control panels. Where practicable distribution boards willbe “off the shelf” items. Distribution Boards will provide power for the following systems; Lighting, emergency and exit lighting GPO, junction boxes supplying power for working areas in offices. M&E plant (intake/ exhaust fans, air conditioners, water pumps and fire protection)

    Supply areas of a distribution board will not be over 50m.

    Distribution boards will be installed in electrical rooms or cupboards which shall have atleast 90 minutes fire rated enclosures.

    Where cables penetrate through fire rated walls or floor’s slabs, fire stoppers or firestopped bags will be installed.

    Fire stopped bags will be automatically blown in case of fire and prevent fire spreadingto adjacent areas.

    The distribution boards will generally consists of electrical control and protection devicesand power cables. Protection system will be designed for multiple levels of protection. Incase of short circuit, earth leakage or over current (> 100mA), the relevant protectivedevice will isolate the faulty circuit from the power supply 0.01s to 4s.

    Distribution Board will be complete with a sufficiently sized earth bar to earth theswitchboard’s cabinet and other electrical equipments’ earthing terminals.

  • 8/9/2019 03. Design Brief

    21/81

    The Sen Hotel Page 19

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    5.4.3 General Power Outlets (GPO)

    The wiring for small general power outlets and lighting final circuits will be of a singlecore PVC cables installed in conduit. Concealed or cast-in conduits in all areas will be ofPVC type, excepted M&E Plant rooms and external areas, where galvanized steelconduit will be provided.

    All wiring will be contained within one floor except lighting system for stair cases, ofwhich one circuit will be used for multiple floors.

    Generally, 220V, 2P+E type 10A universal GPOs will be provided throughout. Metal-cladoutlets will be used in all M&E plant-rooms, and weather proof outlets will be usedoutdoors or in wet locations.

    In circulation or public areas, GPOs will be provided every 20 m as deemed practicable.5.4.4 Lighting

    Lighting systems and levels will be designed according to CIBSE and ACCORrecommendations.

    All luminaires will incorporate high frequency ballasts and low energy lamps.

    General services Air lock 200 lux Reception desk: 400 lux Reception Hall 300 lux Lift landing 150 lux Lift cabin (floor) 50 lux Restaurant 200 lux Restaurant self (Breakfast) 200 lux Buffet 300 lux Meeting room 400 lux Corridors – stairs 150 lux Waiting rooms 200 lux Bar 200 lux Toilets 200 lux Offices 500 lux Shops 300 lux Kitchen 500 lux Archive 200 lux

    Bedroom Average 100 lux Bed head 150 lux Desk 250 lux Bathroom (average) 150 lux Bathroom mirror (face level) 350 lux

    Parking Floor (parking area) 50 lux Parking place 100 lux Access 75 lux Facades, Landscape (By Architects)

    Luminaries for the general areas and outdoors shall be controlled by lighting controlboard.

  • 8/9/2019 03. Design Brief

    22/81

    The Sen Hotel Page 20

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    Luminaries will consist of the followings:

    Normal lighting system:

    The normal lighting system will meet the full requirements of the design guidance andquoted standards, and the required interior design for lighting in apartments and lobbyareas.

    Automatic lighting system:

    The automatic lighting system will provide minimum luminance for movement at night.The system will be programmed to reduce or turn off systems in low hours of occupancyin landlord and common areas.

    Emergency and Exit lighting system:

    The emergency and exit lighting system will provide a luminanace level of at least 5-10lux for movements in case of power failure and exit lighting.

    Emergency luminaries will be provided as follows: Within 5 m of an exit

    Within 2 m of lobby intersection Within 2 m of any change of floor level Within 2 m of any fire fighting appliance/ fire alarm call station For all toilets In each lift car

    Emergency lightings will be installed with Ni-CD charger and the charger is capable ofproviding stand-by power in 2 hours. Exit lighting Stair lighting Emergency lighting

    Type of Lamps:

    LED, CFL, & T5 lamps are recommended. Halogen lamps are required as decoration, but they should not be more than 35W. T5 is recommemed for Indoor Parking. Electronic Ballast are recommended for Fluorescent Lighting Fixtures

    5.4.5 Lightning Protection

    A lightning protection system is required and will generally comprise of the followingelements: An Ealier Stream Air Termianl on roof with 54m protection area, Class III;

    Insulated Lightning Designed Purposed down-conductors run in riser to earth pits. Conventional Air terminal

    o Air terminals will be solid copper ensuring good corrosion resistance.

    o Down conductors will be bonded to the air terminal network at roof level andto any other extraneous metalwork such as rainwater gutters and hand railsetc.

    o Resistance of the lightning protection system will be less than 4 ohms in thepeak dry season of the year.

    o Cables connection and earthing rods will be cad welded to ensure permanentconnection at welded points.

  • 8/9/2019 03. Design Brief

    23/81

    The Sen Hotel Page 21

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    The lightning protection system will be bonded to the building earth system asrequired in AS300:2007 and Local Codes.

    Surge protection devices will be installed at the main switchboard and at otherpoints throughout the system where considered prudent to do so – this may includewhere sensitive electronic devices are housed.

    The system will be connected to the building earthing network Transient EarthClamp.

    5.5 Earthing

    The main earthing terminals for the LV & MV lines will be located in the main LV room andwhich will be linked to a system of copper earthing rods driven into the soil outside orunderneath of the building.

    The external casing of the LV switchboard, transformer, MV switchgear and the protectiveconductor will be bonded to the main earthing terminals.

    The common earthing system will have a resistance to earth of 1 Ohm.5.6 Telephone & ADSL Cable System

    The Telephone system:

    3 telephone sockets and 02 instrument in each Bedroom, at Writing Desk, Bedside and Toilet.Bedside Telephone sockets are always installed near window bedside. The recommendedcable is CAT6 in bedrooms.

    Incoming lines will be provided by the Telecommunication Service providers: VNPT,Viettel, SaigonPost, EVN..

    A central MDF will be located in MDF room, 2nd basement floor and integrated to the PMSsystem.

    Cabling into floor risers. CAT6 for DATA cabling, fibre optic for vertical riser

    Intermediate Distribution Frames (IDFs).

    PABX, Hub, Server – By others. ADSL system, provide final RJ45 outlets for guest rooms, reception, office; and provide wifi forpublic area.

    5.7 Public Address System

    The public address system will divide the building into zones depending on the location ofstaircases. Each zone will be installed with an amplifier and interconnected speakers. Thesystem consists of a small micro phone located at the head end of the public address systemand 1 module to alarm and deliver recorded voice messages in the event of fire alarm oremergency conditions.

    When the first alarm signal has been delivered to an area, the signal at the entrance will beincreased 50db at the second alarm and 10db for each of following alarm, but not over 6 times.

    Public announcement will be made by sound or bell 4 times and will be followed by voicerecorded messages in the languages of Vietnamese, English, Chinese and French.

    The system will be complete with an integral battery system which will provide power to thesystem in the event of a complete power failure for a minimum period in compliance with localregulations. In addition the system will incorporate the following functions;

    The PA system with battery back-up for 2 hours is located at MDF Room, 2nd basement.

    Another micro will be put in security room, 2nd basement floor

  • 8/9/2019 03. Design Brief

    24/81

    The Sen Hotel Page 22

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    10W wall speakers for car parking areas.

    6W surface/ wall speakers for stair case areas.

    6W ceiling speakers for Retail, Restaurant and public areas.

    3W ceiling speakers for lift lobby, corridor areas at each level.

    5.8 CCTV System A CCTV system will be provided which will consist of I.P. cameras, multiplexer controller,monitor, Digital Network video recorder and control panel.

    Cameras will be provided at:

    Building Entrance / Exit

    Main lobby, lift lobby at ground floor and public areas.

    Car parking & external areas.

    Inside lift car (dome camera type will be used).

    Monitors will be installed in Security control room in 1st basement.

    The monitor c/w software can access, monitor, playback.. up to 500 channels (cameras) perone monotor and can manage up 5 monitors.The Storage of recorder units required for min. 78 hours, up to 30 channels, storage capacity isapproximately 500GB, the data will be back up to DVD by maintenance team.

    5.9 Door Access Control System

    The system will be complete with electronic lock for guest room, security room, MDF room, liftcars.

    Monitor stair close/ open status only.

    5.10 MATV and Cable TV SystemThe system will be complete with channel amplifiers, splitters inside the riser ducts and coaxialcables in conduit to the TV outlets of each guest room.

    Incoming TV cables shall be installed by the serviced providers and be connected to TVcenter panel – Building Owner’s scope.

    Provide 2 x RG11 Spare TV cables will be installed from MATV – Tel room to roof forfuture satellite connection.

    RG11 will be installed from TV center panel to each floor riser.

    RG6 will be installed from Amplifiers to splitters and TV outlet sockets at public areas andguest rooms.

    CAT6 to be recommended for using for upgrading to IPTV in future. Pay per view designed by the AV consultant/designers

    5.11 Mobile Telephone Booster System

    Mobile Booster System will be installed by Authorities, Provide Room in 2nd Basement, Powerc/w kWH meter for this system.

    The system shall be approved by Local Telecommunication Authority.

  • 8/9/2019 03. Design Brief

    25/81

    The Sen Hotel Page 23

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    System includes the follow:

    Antennas

    Single, Dual Band Amplifier(s)

    Cabling

    Complete System

    5.12 UPS System

    Individual UPS systems will be provided to each Fire Alarm, Security and other ELV systems.

    5.13 Building Management System (BMS)

    A BMS system will be provided for the common areas of the project such as car-parks, halls,lobbies recreation areas and commercial areas. The BMS will consist of the following mainfunctions; Display and monitoring of all connected equipment Facility Alarm handling and alarm management Provides graphical interface to all sub systems

    Provides central energy efficiency control strategies Provides for data gathering Enables report management and interaction with standard office software packages

    The below listed equipment will be controlled and monitored by this BMS: All A/C equipments All Central Supply and Exhaust Fans All DX system serving 24/24 hours operation areas. Main Fire Alarm Control Panel All Sprinkler Flow Switches. All Fire Pumps, Tank Levels. All Transfer & booster pumps All Drainage pumps & STP equipments Main Power Metering, (Apartment’s meters controlled by Local Power Co.) Main LV Switchboard. Power Distribution Boards for Public floors. All public lighting. All Generators, fuel pumps. All passenger & service lifts All bedside control panel

    The BMS provided by this design will be of digital generation with the latest technologyprotocols such as BACnet, Web Access, Modbus, Lonworks etc.

  • 8/9/2019 03. Design Brief

    26/81

    The Sen Hotel Page 24

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    6. Lift Systems

    6.1 Codes and Regulations BS 5655: Standards for Lifts & Escalators BS EN 81-1: Specifications and safety rules for the installation of electric lifts

    CIBSE – D: Transportation in building LOCAL CODES & REGULATIONS: TCVN 5744, 6395, 6904, 6906 & 7168: Safety rules for design, manufacturer, installation,

    maintenance and usage of electric lifts, escalators ACCOR Design Guideline of Elevator

    6.2 Design Criteria% Arrival Rates: 15% min.Up-Peak Interval: 50 seconds max.The designed Passenger Lift System will provide the following functions; Percentage Arrival Rate or Percentage of Handling Capacity in 5 minutes Up-Peak Interval or Waiting Time Acceleration requirements Micro Processor Destination Control System for energy saving and higher efficiency

    6.3 Fireman’s Lif t

    As Local Authority required.

    6.4 Calculation

    See calculation sheet in Appendix. Summay as below

    The owner selected option 1 wi th 3 li fts 1150kg for al l bui lding ( f rom 1 st FL toRoof)

  • 8/9/2019 03. Design Brief

    27/81

    The Sen Hotel Page 25

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    7. Air Conditioning and Mechanical Ventilation

    7.1 Codes and Regulations

    The air-conditioning and mechanical ventilation systems will be designed in accordance with thelocal regulations & design weather data and the recommendation of: ASHRAE: The American Society of Heating, Refrigerating and Air

    Conditioning Engineers – HVAC Application 2007 CIBSE – Vol. B: The Chartered Institution of Building Services Engineers. BS EN 12101 Smoke and Heat Control System AS 1668-Part 2: SAA Mechanical Ventilation & Air Conditioning AS 1861: Refrigerated Air Conditioners AS 1324: Air Filters for use in Air Conditioning and general

    Ventilation SMACNA: Sheet Metal and Air-Con Contractors, National Association DW144 Specification for sheet metal ductwork QCVN 06:2010/BXD: Vietnam National Technical Regulation on Fire Satety of

    Building and Structures

    QCVN 08: 2009/BXD Vietnam Building Code for Urban Underground Structures – Part 2. The Parkings TCVN 6160 Fire Protection requirements for high rise building TCVN 5687:2010 Ventilation - Air conditioning - Heating ACCOR Design Guideline of HVAC

    7.2 Design Conditions7.2.1 Designed Temperatures in Air Conditioned Spaces

    Guestroom: 23oC ± 1oC (no humidity control to be provided)Restaurant, Offices: 23oC ± 2oC (no humidity control to be provided)Hall, Foyer, Lobby: 23oC ± 2oC (no humidity control to be provided)Lift lobby: 26oC ± 2oC (no humidity control to be provided)

    7.2.2 Design Parametersa) Fresh air:

    AREA Density Fresh air

    ■ Bar 1 m2/person ■ 7 L/s/person

    ■ 10 L/s/person ifsmoking allowed

    ■ Restaurant, Meetingroom:

    1.5 m2/person 7 L/s/person

    ■ Hall, Lobby, Foyer: 5 m2/person 7 L/s/person■ Bedroom: 2 person/bedroom 17 L/s/bedroom

    ■ Administrative Office: 5 m2/person 8 L/s/person

    ■ Bedroom Corridor: - 1.0 AC/hr

    b) Mechanical ventilation■ Hotel toilet: 30 m3/hr/WC & 30 m3/hr/Bath■ Public toilet: 60 m3/hr/WC & 30 m3/hr/Urinal

  • 8/9/2019 03. Design Brief

    28/81

    The Sen Hotel Page 26

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    ■ Ventilation for basement carpark: 6/10 ACH (2 speed fans)■ Ventilation for plantroom: CIBSE Guide B2/ ASHRAE

    7.2.3 Noise Criteria(by acoustic consultant) For reference:

    Guestroom: NC 30

    Office: NC 35 - 40Main Lobby: NC 45

    7.3 Air Condit ioning Systems7.3.1 General Description

    The agreed Air-Conditioning System to be water cooled chiller system:■ The Water cooled Chillers & pumps located at technical floor, Cooling towers

    located on roof■ DX Air Conditioning system serving areas which requires 24hours air conditioning

    services.7.3.2 Main Equipment Of Chiller Systems

    CHILLER PERFORMANCE:High efficiency

    HEAT EXCHANGER:

    The selected Condensing Unit is of cooling only, water-cooled type to ensure highestequipment performance and meet with specific architectural features of the building.

    REFRIGERANT:

    The selected refrigerant for Condensing Unit is of R134a, of which CFC index will beZero or is allowed to use under international convention MONTREAL PROTOCOL 1987

    concerning protection of ozone layer.Refrigerant R134a is available on local market. Therefore, the replacement andinterruption of the operation during maintenance will be minimal.

    COMPRESSORS:

    The selected compressors are Screw/ Centrifugal Compressors with technicaladvantages such as low noise, anti-vibration and maintenance free. Physical dimensionsof the equipment are small and economic in operation.

    PRIMARY AIR HANDLING UNITS

    Primary Air Handling Units (PAUs) will be provided to pre-treat Fresh Air Intake quality

    from Ambient Air Temperature and Humidity to the designed air temperature andhumidity before supply to each FCU and required spaces, these PAUs shall be includedenergy recovery module to pre-cool fresh air intake before treating mainly inside thePAUs.

    The PAU is a combined of required modules or sections, weatherproof type and willconsist of the following major sections:

    ■ Fresh Air Dampers and Intake Section. This section shall be completed withPrimary Air Filter Panel and access door

  • 8/9/2019 03. Design Brief

    29/81

    The Sen Hotel Page 27

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    ■ Bag Air Filter Module and Blank Section for maintenance■ Energy Recovery Section and access door■ Cooling Coil Section■ Fan Section and access doorThe PAUs will be located at the tecnical floor and roof floor to provide pre-treated freshair to all AHU/ FCU via VCDs

    FAN COIL UNIT

    Concealed FCUs will be provided to supply air to all small air conditioned rooms ofindependent temperature control.

    Technical data of FCU is as follows:

    ■ Constructed into a block, including following main components:

    Panel-Filter

    Cooling Coil

    Fan

    All FCUs are concealed in ceiling void. Return air and Fresh air intake will be connectedto FCU via insulated return air plenum box, ductwork and air diffusers.

    AIR DIFFUSERS

    Air diffusers will be designed so as to ensure air flow are supplied to all areas and meetspecific requirements of each area.

    Types of air diffusers include: Linear Diffusers, Square Diffusers, Rectangular Diffusers,Eggrate Grilles or round dics valve.

    AIR DUCT

    Air duct will be designed to SMACNA, DW142 and ASHRAE standards.

    7.4 Mechanical Ventilation7.4.1 Stair Pressurisation System

    The Stair Pressurization System will be designed in accordance with British Standardsand local codes (TCVN) and will consist of the following elements;

    ■ Axial Air fans (fire rated type)

    ■ Ductwork, Grilles and Volume Control Dampers

    ■ Control signals from alarm panels and priority power

    Minimum pressure in stair on operation is 50Pa or equivalent to +5kg/m2 for all closeddoors.

    Staircase type N1 will be designed for this building ( By Architecture). So, pressurizationsystem will not require for these staircase.

    7.4.2 Pressurisation System

    The Stair Pressurization System will be designed in accordance with British Standardsand local codes (TCVN) and will consist of the following elements;

    ■ Axial Air fans (fire rated type)

  • 8/9/2019 03. Design Brief

    30/81

    The Sen Hotel Page 28

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    ■ Ductwork, Grilles and Volume Control Dampers

    ■ Control signals from alarm panels and priority power

    Minimum pressure in stair on operation is 50Pa or equivalent to +5kg/m2 for all closeddoors.

    Lift well will be pressurized with 20 Pa as required by QCVN.

    Buffer rooms in Basements will be pressurized with 20 Pa as required by QCVN.

    7.4.3 Smoke Spill System

    The Smoke Spill System will be designed in accordance with British Standards or NFPAand generally consists of the followings:

    The Smoke Spill System shall be operated via Fire Control Panel and Manual on/offoperated by Fireman.

    Smoke exhaust shall be provided to lcorridors.

    Smoke exhaust shall be sized to achieve the greater of:

    ■ 10 air changes per hour to the above mentioned spaces.

    ■ Sufficient capacity to provide relief air for stair pressurization systems.

    Smoke exhaust systems shall be fitted with motorized dampers and sub-ducts tomaintain fire separation between floors whilst providing zones smoke control.

    7.4.4 Fresh Air System

    The cooling fresh air supply system will generally consist of the following;

    ■ Central PAU located at the roof level/ technical floor to provide cooling air to FCU.

    ■ Fresh air duct in vertical shaft.

    7.4.5 Toilet Exhaust System

    For Podium levels.

    The Toilet Exhaust System will be designed in accordance with British Standards andwill be collected to central PAU with energy recovery and generally consisting of thefollowing elements;

    ■ Centrifugal exhaust fan in PAU

    ■ Exhaust air duct in ceiling space and vertical shaft and go to PAU.

    For Hotel levels.

    The Toilet Exhaust System will be designed in accordance with British Standards andwill be an common system generally consisting of the following elements;

    ■ Central exhaust fan in PAU on roof■ Exhaust air duct in vertical riser; exhaust air grille in each toilet and exhaust air go

    into PAU before discharge to outside.

    7.4.6 Commercial Kitchen Exhaust System

    The Commercial Kitchen Exhaust System will be designed in according with BritishStandards and generally consisting of the following elements;

  • 8/9/2019 03. Design Brief

    31/81

    The Sen Hotel Page 29

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    ■ Cooking hood by kitchen supplier

    ■ Bifurcated fan

    ■ Exhaust air duct in riser up to roof

    7.4.7 M&E Plant Room Ventilation System

    Mechanical ventilation system of M&E plant rooms and technical room such as thetransformer Room, Genset room, Lift Motor Rooms, LV Main Switch Room, PumpRooms will be designed in according with British Standards and will generally compriseof the following items;

    ■ Axial Air fans

    ■ Ductwork, Air Grilles and Volume Control Dampers

    ■ Diffuser, Exhaust Air Grilles

    ■ Electrical works and Controls

    Mechanical ventilation system for M&E plant rooms will be activated via thermostat .

    Lift machine room, MSB room and MDF room shall be air conditioning

    7.4.8 Carpark Ventilation System

    The Car-park Exhaust Air System will be designed in according with British Standardsand generally comprises of the following elements;

    ■ Two (2) speed axial fans with the capability of operating effectively at 400°C atleast 1 hour (in case of fire).

    ■ Ductwork, Exhaust Grilles and Volume Control Dampers with downstream fire ratedductwork.

    ■ Required space for routing of ductwork

    ■ Exhaust Grilles will be installed at both Low level (350mm above floor level) andHigh level (at bottom or side of duct). Air flow rate for low level exhaust will bearound 30% ~ 50% of total air flow rate.

    ■ Associated CO Sensor Switches and Electrical works

    ■ Basement Exhaust Discharge Louvers will be located +2.0m from ground zerolevel.

    The Car park Supply Air System will be designed in according with British Standard andthe capacity will be 80% of exhaust air flow rate.

    The basement Supply and Exhaust Air System shall be operated normally via on/offswitches when needed or via programmable controller and they shall be also activatedvia fire alarm panel and manual control from fire department centre during fire mode.

  • 8/9/2019 03. Design Brief

    32/81

    The Sen Hotel Page 30

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    8. Plumbing & Sanitary Systems

    8.1 Codes and Regulations

    The systems will be designed in accordance with the international standards, local codes andregulations as follows:

    QCVN 14:2008 Vietnamese national code for plumbing TCVN 7441: 2004 LPG system – Design standard.

    TCVN 4474:1987 Vietnamese Standard for Internal Drainage System Design TCVN 4473:1988 Vietnamese Standard for Internal Plumbing System Design TCVN 5673:1992 Vietnamese Standard for Internal P&D System Design TCXD 51:1984 Vietnamese Standard for External Drainage System Design TCXD 33:1985 Vietnamese Standard for External Drainage System Design British Standards/ AS ACCOR Design Guideline for Plumbing

    8.2 Water Supply and Storage

    The incoming water supply will be taken from the city water line and will be stored in the rawwater storage tank of 45m3 at 2nd basement level and will be treated and pumped to transferwater tanks of 136m3 at 1st basement level. Water will be pump to Roof water tank of 36m³located at roof level for domestic and 10m³ for colling tower (including 100m³/ day for coolingtower make-up)

    Water consumption criteria: Cold water: 650 ltr/ bedroom (Hotel without laundry - Accor required) Hot water (DHW): at temperature 55oC 60oC:

    - Bedroom: 150 ltr/ bedroom (Accor required)- Kitchen: 3000 ltr for a 168 bed hotel (Accor required)

    Total summary increase in CW & DHW 30% in tropical climates

    Total holding water storage tanks of the entire building at any time will be designed for13 hourconsumption ( Based on area the owner allow to locate water tank).

    Water supply filtration system will consist of automatic filters and UV treatment.

    8.3 Potable Water System

    Water via screen filtration & UV system located on roof will be distributed throughout thebuilding for potable water supplies, toilet flushing purposes etc. The distribution system will becompleted with pressured pumps (for the top three levels) and Pressure Reduction Valves.

    Provide connection point of swimming pool make-up water directly from the raw water storagetank.

    Provide Water meters for Retails, Hotel Kitchen, HVAC, Irrigation and Hot Water Consumptionfor local monitoring

    Provide Flow restrictors as below:- Wash Basin - 6 LPM- Hand Shower - 12 LPM- Rain Shower - 20 LPM- Kitchen Sink - 24 LPM (1/2" Tap) or 30 LPM (3/4" Tap)…

  • 8/9/2019 03. Design Brief

    33/81

    The Sen Hotel Page 31

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    Hot water system

    Provide Central water heat-pump with the water source from condensing/ chilled water ofChillers. Hot water will be stored in electric water heater storage tank which heat water to 70oCfor thermal shock order to disinfect the water.

    Hot & Cold Water Pipe Material will be of Copper type.

    8.4 Sanitary DrainageDomestic drainage system from sanitary wares(lavatory, floor drain…), with combinedventilation stacks to the roof.

    Domestic drainage system will be discharged to WWTP and then be treated in accordance withVietnamese Standard (grade B) by the WWTP before discharging to city sewer system.

    Sanitary wares (water closet,uniral) with combined ventilation stacks to the roof.

    soilpipes will be discharged to septic tank, waster after septic tank connect to WWTP and thenbe treated in accordance with Vietnamese Standard (grade B) by the WWTP before dischargingto city sewer system.

    Kitchen drainage system from kitchen wares (kitchen basin, glass washer, …), with combinedventilation stacks to the roof will lead to grease trap at 3rd basement before discharging toWWTP.

    WWTP system uses high technology standard, which prevents unwanted smell and ease ofmaintenance and are common types being used in high-rise buildings.

    Waste Water Pipe Material will be of Cast iron.

    8.5 Waste Water Treatment Plant

    Waste water treatment plant to treat waste water to meet the QCVN14-2008, grade B (see table1 below) before discharge to public drain.

    Table 1. Element pollution of waste water and limited of authorize

    Item Parameters Unit Limitation ofgrade B

    Limited for people over50 bedrooms (K=1)

    1. pH 5-9 5-9

    2 BOD5 (20oC) mg/l 50 50

    3 TSS -Total suspended solid mg/l 100 100

    4 TDS - total dissolvent solid mg/l 1000 1000

    5 Sunfua (H2S) mg/l 4.0 4

    6 Amoni (follow N) mg/l 10 10

    7 Nitrat (NO3-) mg/l 50 50

    8 Oil-fat (in food) mg/l 20 20

    9 Total surface active mg/l 10 10

    10 Photphat (PO43-) mg/l 10 10

    11 Coliform MPN/100ml 5000 10

    The flowchart of WWTP will be described as below:

  • 8/9/2019 03. Design Brief

    34/81

    The Sen Hotel Page 32

    ♦ 232512 ♦ Conceptual Design ♦ Rev.03 Date of Issue : 27 Dec 2012

    Domestic inlet waste water screens MBBR tank Aerotank tank → biofor tank settling tank sludge storage sterilization tank to public drain.

    All above functional tanks will be concrete except the settling tank to be made by stainlesssteel.

    8.6 LPG System

    LPG cylinders will be stored in the LPG storage room located on ground accordance to TCVN7441:2004

    LPG system will be supplied to kitchen in restaurant, food-court, include:

    Gas stations will include bottles containing 48kg in parts with a total weight does not exceed700kg setting outside of the building and far from the building a minimum of 1.0m, these bottleswill be installed gas phase. LPG gas phase shall be going with pressure from 4-6kg/cm.LPG gas phase will be through the pressure reducing valve (level 1) down to 35kpa, LPG mainpipe will distributed all the vertical pipes of the building.LPG gas before supplying to the restaurants kitchen and food-court will be through gas meterand the pressure reducing valve down to 5kPa located at technical shaft. At kitchen restaurant and food-court kitchen, LPG gas will be reduced pressure down to 0.4kPaat applications.

    8.7 Storm Water Drainage

    Storm water from roof and garden will be collected and discharged directly to the publicdrainage system

    8.8 Condensate Drainage

    Condensate drain pipes from FCUs/ PAUs will be connected to the nearest waste water riser.

  • 8/9/2019 03. Design Brief

    35/81

    APPENDIX A

    Vietnamese Translation

  • 8/9/2019 03. Design Brief

    36/81

    Thuyeát Minh Kyõ ThuaätThieát keá sô boäKHAÙCH SAÏN THE SEN

    27.12.2012232512 Phiên b ản 03

    Aurecon Vietnam Co.,LtdPhoøng 1304, Toøa nhaø Centec72-74 Nguyeãn Thò Minh Khai, Quaän 3,Tp. Hoà Chí Minh, Vieät Nam

    Ñieän thoaïi: + 84 8 3823 9994Fax: + 84 8 3824 6880Email: [email protected]

  • 8/9/2019 03. Design Brief

    37/81

    Qu ản lý tài li ệu

    Document ID : P:\232512 IDIP HOTEL SPN (76-78 NTMK)\TECH\MEP\REPORTS\DESIGN BRIEF\CONCEPT\DESIGN BRIEFVIET REV02.DOC

    Phiênbản

    Ngày Chi ti ết phiên b ản Nh ập li ệu Tác gi ả Kiểm tra Phê duy ệt

    01 07.12.2012 Phát hành Thi ết kế sơ bộ TT TT DP TB

    02 24.12.2012 Phát hành Thi ết kế sơ bộ TT TT DP TB

    03 27.12.2012 Phát hành Thi ết kế sơ bộ TT TT DP TB

    Người sử dụng tài li ệu ho ặc s ố liệu c ủa Aurecon ph ải ch ấp nh ận các r ủi ro khi th ực hi ện cáchành động sau:

    a) S ử dụng các tài li ệu ho ặc s ố liệu d ưới hình th ức b ản điện tử mà không yêu c ầu ho ặc kiểm tratính chính xác so v ới bản in g ốc.

    b) S ử dụng các tài li ệu ho ặc s ố liệu với mục đích nào đó mà không được s ự đồng ý b ằng v ănbản của Aurecon.

  • 8/9/2019 03. Design Brief

    38/81

    Khách s ạn The Sen Trang 1

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    MUÏC LUÏC1. Giôùi thieäu 1

    2. Muïc Tieâu Chung Trong Thieát Keá 2 2.1 Ñoä tin caäy 2 2.1.1 Söï tin caäy vaø tính khaû thi cuûa heä thoáng 2 2.1.2 Ñôn giaûn trong vaän haønh vaø duy tu baûo döôõng 2 2.1.3 Ngaên buïi, nöôùc vaø coân truøng 2 2.1.4 Tích hôïp caùc haïng muïc trong quaù trình thieát keá 2

    3. Ñieàu Kieän Thôøi Tieát Taïi Coâng Trình 3 3.1 Ñòa ñieåm xaây döïng: 3 3.2 Nhieät ñoä khoâng khí ngoaøi trôøi ñöôïc duøng trong thieát keá: 3

    4. Heä Thoáng Phoøng Chaùy Chöõa Chaùy 4 4.1 Caùc Tieâu Chuaån ÖÙng Duïng Trong Thieát Keá 4 4.2 Moâ Taû Heä Thoáng Phoøng Chaùy Chöõa Chaùy 4 4.3 Yeâu Caàu Ñoái Vôùi Heä Thoáng PCCC Cho Coâng Trình 4 4.3.1 Yeâu caàu veà phoøng chaùy: 5 4.3.2 Yeâu caàu veà chöõa chaùy: 5 4.3.3 Giaûi phaùp thieát keá Heä thoáng Phoøng Chaùy Chöõa Chaùy: 5 4.4 Heä Thoáng Baùo Chaùy Töï Ñoäng 6 4.4.1 Giôùi Thieäu Chung Veà Heä Thoáng: 6 4.4.2 Nguyeân Taéc Hoaït Ñoäng Cuûa Heä Thoáng: 6 4.4.3 Caùc Thieát Bò Chính Cuûa Heä Thoáng Baùo Chaùy: 7 4.5 Heä Thoáng Chöõa Chaùy: 10

    4.5.1

    Caùc phöông tieän chöõa chaùy ban ñaàu: 10

    4.5.2 Heä thoáng chöõa chaùy baèng nöôùc cho toaøn toaø nhaø bao goàm: 10 4.6 Heä Thoáng Chöõa Chaùy Baèng Ñaàu Phun Nöôùc Töï Ñoäng: 10 4.6.1 Caùch boá trí ñaàu phun Sprinkler vaø thoâng soá kyõ thuaät: 11 4.6.2 Maïng ñöôøng oáng: 11 4.6.3 Caùc boä phaän khaùc: 11 4.7 Heä Thoáng Chöõa Chaùy Hoïng Nöôùc Vaùch Töôøng Vaø Hoïng Nöôùc CNhaø: 12 4.7.1 Caùch boá trí hoïng nöôùc vaùch töôøng vaø thoâng soá kyõ thuaät: 12 4.7.2 Caùch boá trí hoïng nöôùc chöõa chaùy ngoaøi nhaø vaø thoâng soá kyõ thu 12 4.7.3 Maïng ñöôøng oáng: 12 4.7.4 Caùc boä phaän khaùc: 13 4.8 Heä Thoáng Maùy Bôm Vaø Nguyeân Taéc Hoaït Ñoäng: 13 4.9 Bình Chöõa Chaùy Löu Ñoäng 13 4.10 Ñoùng Ngắt Ñieän Khi Coù Baùo Chaùy 14 4.11 Heä thoáng chöõa chaùy ñaëc bieät 14

    5. HEÄ THOÁNG ÑIEÄN 15 5.1 Caùc tieâu chuaån öùng duïng trong thieát keá 15

  • 8/9/2019 03. Design Brief

    39/81

    Khách sạn The Sen Trang 2

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    5.2 Heä thoáng ñieän Trung theá vaø Traïm bieán aùp 15 5.2.1 Coâng suaát ñieän nguoàn: 15 5.3 Giôùi thieäu chung veà nguoàn ñieän vaø traïm bieán theá: 15 5.3.1 Heä thoáng nguoàn trung theá: 15 5.3.2 Heä thoáng nguoàn döï phoøng – Maùy phaùt ñieän chaïy daàu Diesel: 16 5.3.3 Boàn chöùa daàu cho Maùy phaùt ñieän döï phoøng: 16 5.4 Heä thoáng ñieän haï theá 16 5.4.1 Tuû ñieän haï theá chính (MSB) 17 5.4.2 Tuû ñieän phaân phoái 17 5.4.3 Ñieän oå caém 18 5.4.4 Heä thoáng ñeøn chieáu saùng 18 5.4.5 Heä thoáng baûo veä choáng seùt 19 5.5 Heä thoáng tieáp ñaát 20 5.6 Heä thoáng ñieän thoaïi & ADSL 20 5.7 Heä thoáng thoâng baùo coâng coäng 21 5.8 Heä thoáng CCTV 21 5.9 Heä thoáng kieåm soaùt ra vaøo, khoùa cöûa 21

    5.10 Heä thoáng truyeàn hình veä tinh vaø truyeàn hình caùp 22 5.11 Heä thoáng taêng cöôøng soùng ñieän thoaïi 22 5.12 Heä thoáng UPS 22 5.13 Heä Thoáng Ñieàu Khieån Toøa Nhaø (BMS). 22

    6. Thang Maùy 24 6.1 Caùc Tieâu Chuaån ÖÙùng Duïng Trong Thieát Keá 24 6.2 Caùc Tieâu Chí Thieát keá 24 6.3 Thang daønh cho cöùu hoûa 24 6.4 Tính toaùn 24

    7. Heä Thoáng Ñieàu Hoøa Khoâng Khí Vaø Thoâng Gioù 25 7.1 Caùc Tieâu Chuaån ÖÙùng Duïng Trong Thieát Keá 25 7.2 Ñieàu Kieän Thieát Keá 25 7.2.1 Nhieät Ñoä Khoâng Khí Taïi Caùc Khu Vöïc Coù ÑHKK: 25 7.2.2 Thoâng Soá Thieát Keá 25 7.2.3 Ñoä oàn 26 7.3 Heä Thoáng Ñieàu Hoøa Khoâng Khí 26 7.3.1 Moâ Taû Chung 26 7.3.2 Caùc thieát bò chính 26 7.4 Heä thoáng thoâng gioù cô 28 7.4.1 Heä Thoáng Ñieàu Aùp Caàu Thang 28

    7.4.2

    Heä Thoáng Huùt Khoùi 28

    7.4.3 Heä Thoáng Caáp Gioù Töôi 28 7.4.4 Heä Thoáng Huùt Gioù Nhaø Veä Sinh 28 7.4.5 Heä Thoáng huùt khoùi beáp nhaø haøng 29 7.4.6 Heä Thoáng Thoâng Gioù Caùc Phoøng Maùy, Kyõ Thuaät 29 7.4.7 Heä Thoáng Thoâng Gioù Taàng Haàm 29

    8. Heä Thoáng Caáp Thoaùt Nöôùc Vaø Xöû Lyù Nöôùc Thaûi 30

  • 8/9/2019 03. Design Brief

    40/81

    Khách sạn The Sen Trang 3

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    8.1 Caùc Tieâu Chuaån ÖÙng Duïng Trong Thieát Keá 30 8.2 Heä Thoáng Caáp Nöôùc Vaø Tröõ Nöôùc 30 8.3 Heä Thoáng Nöôùc Sinh Hoaït 30 8.4 Heä Thoáng Thoaùt Nöôùc Thaûi 31 Heä thoáng thoaùt nöôùc sinh hoaït: 31 Heä thoáng thoaùt phaân: 31 8.5 Traïm Xöû Lyù Nöôùc Thaûi 31 8.6 Heä thoáng LPG trung taâm 32 8.7 Heä Thoáng Thoaùt Nöôùc Möa 32 8.8 Heä Thoáng Thoaùt Nöôùc Ngöng Tuï 33

    Phụ lục A. Phiên bản ti ếng Vi ệt Phụ lục B. Tính toán

    - Power Demand- Hot & Cold Water Demand- Fire water Demand- Lift analysis

  • 8/9/2019 03. Design Brief

    41/81

    Khách sạn The Sen Trang 1

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    1. Giôùi thieäuMuïc tieâu cuûa taäp thuyeát minh kyõ thuaät naøy laø moâ taû sô löôïc toaøn boä cseõ ñöôïc thieát keá vaø laép ñaët cho coâng trìnhKhaùch saïn The Sen toïa laïc taïi soá76 – 78 NguyeãnThò Minh Khai , Quaän 3, Tp. HCM.

    Coâng trình bao goàm18 taàng, 1 taàng kyõ thuaät vaø 3 taàng haàm. Taàng 1 ñeán taàng dòch vuï, taàng 4 ñeán taàng 17 laø phoøng nguû, taàng 18 cho chăm soùc söùc khoûe.

  • 8/9/2019 03. Design Brief

    42/81

    Khách sạn The Sen Trang 2

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    2. Muïc Tieâu Chung Trong Thieát KeáMuïc tieâu chung trong vieäc thieát keá caùc haïng muïc kyõ thuaät laø nhaèm ñaùpaùn, yeâu caàu söû duïng vaø caùc tieâu chuaån thieát keá kyõ thuaät tieân tieán. Thieát keá ñuùng muïc ñích söû duïng Giaûi phaùp toái öu veà kinh teá

    Thieát keá kyõ thuaät nhaèm ñaït nhöõng tieâu chí toái öu veà kinh teá cuï theå laø cchi phí veà tieâu hao naêng löôïng, chi phí vaän haønh, duy tu baûo döôõng vaø tuoå

    2.1 Ñoä tin caäyThieát keá nhaèm ñaùp öùng yeâu caàu söû duïng, cuï theå laø thieát keá heä thoángvaø vaät tö ñaït ñoä tin caäy cao. Caùc yeáu toá quan taâm: Voán ñaàu tö Hieäu quaû söû duïng naêng lượ ng Chi phí vaän haønh, baûo döôõng Tuoåi thoï thieát bò.

    2.1.1 Söï tin caäy vaø tính khaû thi cuûa heä thoáng Heä thoáng vaän haønh chaéc chaén Tieâu chuaån cao cho thieát bò vaø vaät lieäu. Quaûn lyù caùc cheá ñoä vaän haønh, baùo ñoäng. Tuoåi thoï thieát bò cao.

    2.1.2 Ñôn giaûn trong vaän haønh vaø duy tu baûo döôõngThieát keá kyõ thuaät nhaèm ñaùp öùng muïc tieâu vaän haønh vaø duy tu baûo döôñôn giaûn, cuï theå laø nhöõng yeáu toá sau: Vaän haønh ñôn giaûn vaø deã daøng. Thieát bò maùy moùc ñoàng boä veà nhaõn hieäu vaø quy caùch, coù ñoä tin caä Duy tu baûo döôõng deã daøng, phuï tuøng thay theá luoân coù saün ñeå thay the

    2.1.3 Ngaên buïi, nöôùc vaø coân truøngThieát keá nhaèm loaïi tröø hoaëc giaûm thieåu nöôùc, buïi vaø coân truøng xaâm nbò. Thieát bò vaø phuï kieän vôùi caáp ñoä baûo veä (IP) phuø hôïp vôùi moâi tröôø

    2.1.4 Tích hôïp caùc haïng muïc trong quaù trình thieát keáPhoái hôïp chaët cheû trong quaù trình thieát keá nhaèm ñaït ñöôïc söï tích hôïp vaølaép ñaët caùc haïng muïc kyõ thuaät.Heä thoáng vôùi giaù ñôõ, thanh giaèng, ti treo cheá taïo taïi nhaø maùy, chi tieát latheå hieän trong baûn veõ thieát keá.Nhaø thaàu seõ cung caáp caùc baûn veõ trieån khai thi coâng ñeå baûo ñaûm laép ñDöï truø caùc khoaûng troáng cho vieäc laép ñaët môû roäng trong töông lai nhö khcaùc ñöôøng oáng ñi ngaàm, caùc oáng chôø, caùc truïc ñieän xuyeân taàng..

  • 8/9/2019 03. Design Brief

    43/81

    Khách sạn The Sen Trang 3

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    3. Ñieàu Kieän Thôøi Tieát Taïi Coâng Trình3.1 Ñòa ñieåm xaây döïng:

    Ñòa ñieåm: Tp. Hoà Chí Minh Vó ñoä: 10o 8’ Baéc Kinh ñoä: 106o 7’ Ñoâng Cao ñoä so vôùi möïc nöôùc bieån: 19 m

    3.2 Nhieät ñoä khoâng khí ngoaøi trôøi ñöôïc duøng trong thieát keá:Baàu khoâ / baàu aåm vaøo muøa heø: 37oC DB / 29oC WBNhieät ñoä thay ñoåi haøng ngaøy: 11KThaùng noùng nhaát trong naêm: Thaùng Tö hoaëc thaùng Naêm

  • 8/9/2019 03. Design Brief

    44/81

    Khách sạn The Sen Trang 4

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    4. Heä Thoáng Phoøng Chaùy Chöõa Chaùy4.1 Caùc Tieâu Chuaån ÖÙng Duïng Trong Thieát Keá

    Heä thoáng PCCC ñöôïc thieát keá theo qui ñònh cuûa tieâu chuaån Vieät nam veà PChaùy vaø caùc tieâu chuaån quoác teá sau: TCVN 5760:1993 PCCC cho Nhaø vaø Coâng trình TCVN 5738:2000 Heä thoáng baùo chaùy töï ñoäng-Yeâu caàu thieát ke TCVN 2622 – 1995: PCCC cho Nhaø vaø Coâng trình - Yeâu caàu thieát k TCVN 6160 – 1996: PCCC nhaø Cao taàng - Yeâu caàu thieát keá. TCVN 6161 – 1996: PCCC cho Chôï & Trung taâm thöông maïi - Yeâu

    caàu thieát keá. TCVN 3890 – 2009: Phöông tieän PCCC cho Nhaø vaø Coâng trình TCVN 7336 – 2003: Heä thoáng Chöõa chaùy töï ñoäng. QCVN 06 – 2010: Quy Chuaån kyõ thuaät Quoác Gia veà an toaøn chaù QCVN 08 – 2009 Coâng trình ngaàm Ñoâ thò - Baõi ñoå xe Tieâu chuaån NFPA 13, 14: TC Myõ – ñaàu phun nöôùc töï ñoäng & hoïng CC ACCOR Höôùng daãn thieát keá cuûa Accor

    4.2 Moâ Taû Heä Thoáng Phoøng Chaùy Chöõa ChaùyCaùc haïng muïc PCCC chính bao goàm:

    Heä thoáng baùo chaùy töï ñoäng (Fire Alarm System) Heä thoáng chöõa chaùy töï ñoäng (Fire Sprinkler System) Heä thoáng chöõa chaùy vaùch töôøng (Fire Hydrant and Hose Reel System)

    Caùc haïng muïc kyõ thuaät khaùc cuûa coâng trình coù lieân quan ñeán coâng taùc PCCC:

    Heä thoáng quaït taïo aùp buoàng thang thoaùt hieåm Heä thoáng ñieàu hoøa khoâng khí, heä thoáng huùt caáp gioù haàm kyõ thuaät,

    maùy moùc thieát bò Heä thoáng thoâng baùo coâng coäng Nguoàn cung caáp ñieän chính vaø döï phoøng cho coâng trình Heä thoáng ñeøn chieáu saùng bình thöôøng, khaån caáp vaø söï coá Heä thoáng tieáp ñaát, heä thoáng choáng seùt Heä thoáng caáp thoaùt nöôùc sinh hoaït

    Caùc haïng muïc kieán truùc vaø keát caáu cuûa coâng trình coù lieân quan ñeán cohieän trong phaàn thuyeát minh kieán truùc vaø thuyeát minh keát caáu vaø khoâng thuyeát minh kyõ thuaät naày.

    4.3 Yeâu Caàu Ñoái Vôùi Heä Thoáng PCCC Cho Coâng TrìnhTheo baûn phaân loaïi coâng trình theo möùc ñoä nguy cô phaùt sinh ñaùm chaùy (Tcoâng trình tieâu bieåu naày thuoäc nhoùm“Caùc cô sôû coù nguy cô phaùt sinh ñaùm chaùy trung- Ordinary Hazard 1”,tuy nhieân heä thoáng PCCC cho coâng trình ñöôïc thieát keá seõcaùc yeâu caàu sau:

  • 8/9/2019 03. Design Brief

    45/81

    Khách sạn The Sen Trang 5

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    4.3.1 Yeâu caàu veà phoøng chaùy:Phaûi aùp duïng caùc giaûi phaùp phoøng chaùy ñaûm baûo haïn cheá toái ña khaû Trong tröôøng hôïp xaûy ra hoaû hoaïn thì phaûi phaùt hieän ñaùm chaùy nhanh ñeåkhoâng ñeå ñaùm chaùy lan ra caùc khu vöïc khaùc sinh ra chaùy lôùn khoù cöùu chnghieâm troïng.

    Bieän phaùp phoøng chaùy phaûi ñaûm baûo sao cho khi coù chaùy thì ngöôøi vaø tdaøng sô taùn sang caùc khu vöïc an toaøn moät caùch nhanh choùng nhaát.Trong baát cöù ñieàu kieän naøo khi xaûy ra chaùy ôû nhöõng vò trí deã xaûy ra chathuaät, ga ra xe... trong toaø nhaø phaûi phaùt hieän ñöôïc ngay ôû nôi phaùt sinh chchöõa kòp thôøi.Phaûi coù caùc giaûi phaùp choáng chaùy lan cho caùc heä thoáng oáng kyõ thuaät

    4.3.2 Yeâu caàu veà chöõa chaùy:Trang thieát bò chöõa chaùy cuûa coâng trình phaûi ñaûm baûo caùc yeâu caàu sau:Trang thieát bò chöõa chaùy phaûi phuø hôïp vaø chöõa chaùy coù hieäu quaû ñoái

    saøng ôû cheá ñoä thöôøng tröïc, khi xaûy ra chaùy phaûi ñöôïc daäp taét ngay.Thieát bò chöõa chaùy trang bò cho coâng trình phaûi laø loaïi deã söû duïng, phuø ñieàu kieän khí haäu taïi ñòa phöông.Trang thieát bò heä thoáng PCCC ñöôïc trang bò phaûi ñaûm baûo hoaït ñoäng laâu Trang thieát bò phaûi ñaït ñöôïc caùc tieâu chuaån cuûa Myõ, Chaâu AÂu cuõng nhVieät Nam.

    4.3.3 Giaûi phaùp thieát keá Heä thoáng Phoøng Chaùy Chöõa Chaùy: Heä thoáng baùo chaùy töï ñoäng ñöôïc laép ñaët taïi taát caû caùc khu vöïc coù ngutrình baèng heä thoáng baùo chaùy ñòa chæ.

    Vôùi heä thoáng baùo chaùy ñòa chæ ngoaøi chöùc naêng baùo chaùy thoâng thöôønnaêng keát noái vaø ñieàu khieån caùc heä thoáng kyõ thuaät lieân quan baèng caùc chuyeân duïng vaø phaàn meàm ñieàu khieån: Töï ñoäng phaùt hieän chaùy nhanh vaø thoâng tin chính xaùc ñòa ñieåm xaûy ra

    hieäu baùo chaùy khi phaùt hieän chaùy thaønh tín hieäu baùo ñoäng roõ raøng btröng, ñoàng thôøi moâ taû cuï theå ñòa chæ baèng maøn hình ñoà hoïa (theå hieñeå nhöõng ngöôøi coù traùch nhieäm coù theå thöïc hieän ngay caùc giaûi phaù

    Ñieàu khieån vaø giaùm saùt toaøn boä heä thoáng chöõa chaùy töï ñoäng baèng Heä thoáng coù chöùc naêng ñieàu khieån lieân ñoäng vaø nhaän tín hieäu phaûn

    vôùi caùc heä thoáng kyõ thuaät khaùc coù lieân quan nhö thang maùy, thoâng gi... nhaèm phuïc vuï cho coâng taùc sô taùn vaø chöõa chaùy trong thôøi gian nga

    Caùc söï coá ñöôïc löu tröõ trong boä nhôù vaø ñöôïc in ra giaáy ñoàng thôøi hoamaùy in phuïc vuï cho vieäc xaùc ñònh söï coá hoaëc coâng taùc giaùm ñònh cuûnaêng.

    Baùo ñoäng chaùy baèng aâm thanh ñaëc tröng (coøi, chuoâng...) Coù khaû naêng choáng nhieãu, khoâng baùo giaû, khoâng bò teâ lieät moät phaà

    gaây ra tröôùc khi heä thoáng phaùt tín hieäu baùo chaùy.

  • 8/9/2019 03. Design Brief

    46/81

    Khách sạn The Sen Trang 6

    ♦ 232512 ♦ Thiết kế sơ bộ ♦ Phiên b ản 03 Ngày phát hành : 27.12. 2012

    Toaøn boä caùc thieát bò cuûa heä thoáng baùo chaùy töï ñoäng ñöôïc thieát keá chuaån ISO 9001, 9002, caùc thí nghieäm UL, FM, VDS, tieâu chuaån NFPA 72phuø hôïp vôùi ñaëc ñieåm khí haäu, moâi tröôøng Vieät Nam

    Heä thoáng chöõa chaùy töï ñoäng Sprinkler vaø heä thoáng hoïng nöôùc vaùch tcho taát caû caùc khu vöïc coâng coäng, taàng haàm, phoøng nguû khaùch saïn, h

    Heä thoáng chöõa chaùy töï ñoäng baèng boät cho phoøng bôm daà


Recommended