+ All Categories
Home > Documents > 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

Date post: 07-Jul-2018
Category:
Upload: suresh-kumar
View: 219 times
Download: 5 times
Share this document with a friend

of 88

Transcript
  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    1/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    CONTENTS

     INTRODUCTION .............................................................................................. 6 

    EXECUTIVE SUMMARY ..................................................................................... 8 

    PROJECT AT A GLANCE .................................................................................. 13 

    1  NEED AND JUSTIFICATION FOR THE PROJECT .................................... 15  

    1.1  I NTRODUCTION  ............................................................................................................................. 15 1.2  POWER SCENARIO IN I NDIA ............. ............. ............ ............. ........... ............. ............ ............. ...... 16 

    1.3 

    JUSTIFICATION FOR THE PROJECT  .................................................................................................. 22 

    2  DETAILS ABOUT THE PROPOSED PROJECT LOCATION IN ANANTAPURDISTRICT ............................................................................................ 25 

     

    2.1  I NTRODUCTION  ............................................................................................................................. 25 2.2  AREA AND POPULATION IN ANANTAPUR DISTRICT  ................................................................... 25 2.3  RAINFALL AND CLIMATE  ............................................................................................................. 26 2.4  TEMPERATURE  .............................................................................................................................. 26 2.5  PROPOSED PROJECT LOCATION  .................................................................................................. 27 2.6  LAND REQUIREMENT AND LAYOUT OF THE PROPOSED PROJECT .............................................. 29 2.7

     

    LAND AVAILABILITY AND ACQUISITION FOR THE PROJECT ....................................................... 30 

    3  RADIATION DATA AND PROJECTED POWER GENERATION FROM THEPROJECT ACTIVITY ............................................................................. 31 

    3.1  SIMULATION REPORT OF THE POWER PLANT  ............................................................................. 33 

    4  SELECTION OF TECHNOLOGY .............................................................. 37  

    4.1  EXISTING SOLAR PHOTOVOLTAIC TECHNOLOGIES  .................................................................. 37 4.2  THIN FILM MODULES  ................................................................................................................... 38 

    4.3 

    COMPARISON BETWEEN CRYSTALLINE, THIN FILM AND CPV .................................................. 38 

    TECHNOLOGIES  ........................................................................................................................... 38 4.4  CONCLUSION ON SELECTION OF TECHNOLOGY  ......................................................................... 39 

    5   POWER PLANT DESIGN CRITERIA ....................................................... 40 

    5.1  DESIGN AND SIMULATION PROJECTIONS BY PVSYST  ............................................................ 40 5.2  PV POWER PLANT ENERGY PRODUCTION  ................................................................................. 41 5.3  PV POWER PLANT CAPACITY FACTOR  ......................................................................................... 41 5.4  SELECTION OF INVERTER AND COMPONENTS  ........................................................................... 42 

    5.5 

    SELECTION OF MONITORING SYSTEM  ....................................................................................... 42 5.6  DESIGN CRITERIA FOR CABLES AND JUNCTION BOXES AND  ................................................... 43 

    6  DESCRIPTION OF MAJOR COMPONETS OF THE POWER PLANT ............ 44 

    6.1  SOLAR PV MODULES  ................................................................................................................... 45 6.2  CENTRAL INVERTORS  .................................................................................................................. 45 6.1  MODULE MOUNTING SYSTEM  ...................................................................................................... 47 6 1 G 48

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    2/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    8.2  TRANSFORMERS........................................................................................................................... 59 8.3  HT, LV &  11KV METERING PANEL  .......................................................................................... 60 8.4  CABLES  ........................................................................................................................................ 61 

    8.5 

    LT POWER CABLES  ..................................................................................................................... 61 8.6  CONTROL CABLES  ........................................................................................................................ 61 

    8.7  POWER EVACUATION CABLE  ...................................................................................................... 62 8.8  GRID SYNCHRONIZATION SCHEME  ............................................................................................ 62 

    9  OPERATION AND MAINTENANCE REQUIREMENTS ............................... 63 

    9.1  DC SIDE OF THE POWER PLANT  ................................................................................................. 63 9.2  AC SIDE OF THE POWER PLANT  .................................................................................................. 63 9.3  MODE OF OPERATION  ................................................................................................................. 64 

    9.4 

    MAINTENANCE REQUIREMENTS  .................................................................................................. 65 

    9.5  SPARE PARTS MANAGEMENT SYSTEM  ......................................................................................... 65 9.6  MAINTENANCE OF O &  M MANUALS.......................................................................................... 66 9.7  OPERATION &  MAINTENANCE ORGANIZATION OF THE PLANT ................................................. 66 9.8  TRAINING  ..................................................................................................................................... 67 

    10  ENVIRONMENTAL PROTECTION AND WASTE MANAGEMENT ............... 68 

    11  OPERATION & MAINTENANCE ORGANIZATION OF THE POWER PLANT… 70 

    11.1  TRAINING  ..................................................................................................................................... 71 

    11.2 

    PLANT OPERATION ORGANIZATION CHART  .............................................................................. 72 11.3  PROJECT IMPLEMENTATION STRATEGY  ...................................................................................... 73 

    11.4  PROJECT DEVELOPMENT  ............................................................................................................. 73 11.5  FINALIZATION OF THE EQUIPMENTS AND CONTRACTS  ............................................................ 73 11.6  PROCUREMENT AND CONSTRUCTION  ......................................................................................... 74 11.7  ERECTION AND COMMISSIONING PHASE  .................................................................................. 75 

    12  PROJECT COST ESTIMATE AND FINANCIAL ANALYSIS ........................ 76 

    12.1  PLANT OPERATION  ...................................................................................................................... 77 12.2  SALABLE ELECTRICITY  ................................................................................................................ 78 12.3

     

    SALE PRICE OF ELECTRICITY...................................................................................................... 78 

    12.4  SALE PRICE OF CARBON CREDITS  .............................................................................................. 78 

    LIST OF TABLES:

    Table 1-1: Installed Capacity in MW in India at the End of 10th Plan ___________________ 17  

    Table 1-2: Installed Capacity in MW in India as of 31 Mar 2010  _______________________ 17  

    Table 1-3: Actual Power Supply Position _______________________________________________ 18 Table 1-4: Capacity Addition during 11th Plan (As Per Planning Commission) __________ 18 

    Table 1-5: Likely Power Supply Position at the End of 2010-12 ________________________ 18 

    Table 1-6: Installed capacity of all states as on 31.03.2010 (in MW)  __________________ 19 

    Table 1-7: Installed Capacity in MW in Andhra Pradesh at the End of 10th Plan ________ 19 

    Table 1-8: Installed Capacity in MW in Andhra Pradesh as of 31 Mar 2010  ____________ 20 

    Table 1-9: Actual Power Supply Position _______________________________________________ 20 

    Table 1-10: Projects planned for 11th Plan _____________________________________________ 20 

    Table 1-11: Likely Power Supply Position at the End of 2010-12  21 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    3/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table 7-7: Transformer specification for grid interfacing at 33/132 kV  _________________ 56  

    Table 7-8: Monitoring system specification  ____________________________________________ 57  

    Table 12-1: Project Cost Estimate _____________________________________________________ 76  

    Table 12-2: Assumptions supporting financial projections  _____________________________ 80 

    Table 12-3: Estimation of Depreciation ________________________________________________ 82 

    Table 12-4: Projected Profitability,Balance Sheet,CF, IRR ands WC  ____________________ 84 

    Table 12-5: Project Debt Service Coverage Ratio (DSCR) ______________________________ 88 

    List of Figures:

    Figure 1:  Location map of Anatapur district in India: ............................................................. 28 

    Figure 2:  Map showing proposed project site within Anantapur  ............ ............. ........... ..... 28 

    Figure 3: 

    Typical module mounting structure:  .......................................................................... 47  Figure 4:  Grid-Connect equipments  ............................................................................................... 48 

    Annexure

    1  Project site Photographs

    2  Land ownership details of the proposed project

    3  Contour map of the project site

    4  Schematic diagram showing 5MWp Solar PV Plant Layout

    5  Schematic of Control Room Layout

    6  Schematic of earthing layout

    7  Power Evacuation Scheme 5MWp to 33/132 kV substation

    8  Incorporation certificate of Saisudhir Energy Limited

    9  Memorandum and Articles of Association of Saisudhir Energy Limited

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    4/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    ABBREVIATIONS

    General

    AB Air Breaker

    ACB Air Circuit Breaker

    AC Alternate current

    ACSR Aluminum Conductors Steel Reinforced

    BOS Balance of the System

    CO2  Carbon Dioxide

    CIS Copper Indium Selenium

    CT Current Transformer

    DAS Data Acquisition System

    DC Direct Current

    DP Double Pole

    DPR Detailed Project Report

    APTRANSCO Andhra Pradesh Transmission Corporation

    HT High Tension

    LT Low Tension

    LV Low Voltage

    MNRE Ministry of New and Renewable Energy

    kWh Kilo Watt Hour

    NO2  Nitrous Oxide

    MCB Main Combiner Box / Miniature CircuitBreaker

    MFM Multi Function Meters

    PLF Plant Load Factor

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    5/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    SO2  Sulphur Dioxide

    SP Single Pole

    VCB Vacuum Circuit Breaker

    XLPE Cross Linked Polyethylene

    Units

    % Percentage˚C Degree Centigrade

    H Hour

    Ha Hectare

    Kg Kilogram

    kV Kilo-Volt

    kW kilo Watt

    kWe kilo Watt electrical

    kWp kilo Watt peak

    Lt Liter

    M Meter

    m2  Square meter

    m3  Cubic meter

    Mg milli gram

    Mm milli meter

    MW Mega Watt

    MWe Mega Watt electrical

    Tons Tons

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    6/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    INTRODUCTION 

    As the world broadens its portfolio of power options to meet growing energy

    demands and increasingly stringent environmental concerns, solar power is

    emerging as an attractive option. Of all the routes for conversion of solar into

    useful energy, direct conversion of sunlight to electricity through solar

    photovoltaic technology is well accepted. Solar photovoltaic has been

    recognized as an important route for generation of substantial quantities of grid

    quality power by utilizing the light energy of solar radiation.

    SAISUDHIR Energy Limited (SSEL) a group company of SAISUDHIR

    Infrastructures Limited is intent to develop solar photovoltaic power plant of

    (SPV) power project at Veerapuram village of Anatapur district, in the State of

    Andhra Pradesh.

    SSEL intend to setup grid interactive solar power project based on Copper

    Indium Selenium (CIS) modules also called as thin film modules. The project

    activity is to install grid connected 5 MW solar power project. The full power

    rating of the solar power plant shall be 5.0 +5% and -0% MW DC at standard

    test conditions (STC) of 1000 W/sq meter sunlight and 25 degree centigrade.

    The project is selected to install CIS modules which comply with IEC 61646 for

    quality and IEC 61730 safety standards.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    7/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    The project envisages an investment of approx. Rs 650 million for the

    installation of 5 MW solar power plant which would provide quantity power with

    a power purchase price signed with NTPC's Vidyut Vyapar Nigam Ltd or NVVN

    which is the designated Nodal Agency under Jawaharlal Nehru National Solar

    Mission (JNNSM) for procuring the solar power by entering into a Power

    Purchase Agreement (PPA) with Solar Power Generation Project Developers. In

    addition, the Power Project would generate direct and indirect employment

    opportunities; create of civic facilities for establishment of ancillary industries.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    8/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    EXECUTIVE SUMMARY

    1.  The average per capita consumption of energy in India is around 612 kW,

    which is much lower than that of the developed countries like USA,

    Europe, Australia, Japan etc. However, this figure is expected to rise

    sharply due to high economic growth and rapid industrialization. Energy

    is a necessity and sustainable renewable energy is a vital link in

    industrialization and development of India. A transition from conventional

    energy systems to those based on renewable resources is necessary to

    meet the ever increasing demand for energy and to address

    environmental concerns.

    2.  Thus, the present scenario needs for addition of major renewable energy

    sources of energy for overall economic development of the country.

    3.  Solar Photovoltaic Power plant operates on the principle of the

    photoelectric phenomenon - direct conversion of light to electricity. The

    solar radiation incident upon a silicon-based semiconductor photovoltaic

    cell produces direct electric current.

    4.  Photovoltaic cells are integrated into modules with a voltage of 6 - 12 V;

    the electrically interconnected modules form solar systems with an output

    voltage of 230 V.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    9/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Construction services in the field of Water, Power, Buildings

    Infrastructures, Solid Waste Management and Irrigation etc.,

    6.  SAISUDHIR builds the high-voltage electric transmission system that

    helps to keep the lights on, business running and communities strong.

    The company has played a major role in the complete preparation,

    analysis, design, construction management and inspection of energy

    structures, high voltage transmission lines and distribution systems

    across the country.

    7.  SAISUDHIR has an in-house capability for designing Transmission Line

    Towers & Switchyard Structures.

    8.  SAISUDHIR energy proposed to install a 5 MW Solar Photovoltaic (SPV)

    power plant under phase I of Jawaharlal Nehru National Solar Mission

    (JNNSM) of new grid connected projects. The generated electricity will be

    sold to NVVN with a long term Power Purchase Agreement (PPA). The

    company has already entered into a PPA agreement with NVVN.

    9.  This report highlights the details of the proposed power generation

    scheme, site facilities, solar radiation in the proposed site location and

    water, evacuation of generated power, features of main plant and

    equipment including the inverter system, electrical systems,

    environmental aspects, estimate of capital cost and the financial analysis

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    10/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    11.  The plant is designed with an availability factor of 100%. The plant will

    generate about 9.63 million units per year at the module array terminals,

    after the losses in the system about 9.32 million units will be available at

    the grid terminals which will amount to a plant load factor of about

    21.28 %. The project site was selected on the basis of:

    •  Availability of good solar insulation

    •  Availability of uninhabited land at a reasonable cost

    •  Availability of stable grid near to the project site

    •  High Power Demand in the State

    •  Availability of good infrastructural facility including road and rail

    connection

    12.  The power generated at 11kV from the power plant will be stepped-up to

    33 kV level and connected to APPCL sub-station at Raydurg, which is

    about 10 km from the project site. The total power produced is envisaged

    as 9.63 million units at the PV array. After the losses the net available

    energy for supplying to the grid is about 9.32 million units. Thus, the net

    salable electricity to the grid works out to 9.32 million units. The plant is

    envisaged to operate 365 days at a plant load factor (PLF) of 21.28%.

    The transmission line required from the SSEL 5 MW plant site to the

    substation will be laid by the project promoters.

    13 Th l t ill i f IEC 61646 d l f CIS thi fil

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    11/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    of MS galvanized steel with 8 module structure, fixed tilt type, 80 nos of

    array junction boxes, Power conditioning  unit (inverter) 10 nos of 500

    kVA, 1.25 MVA transformer 5 nos, 6.5 MVA transformer 1 no for

    interfacing with grid, LT and HT Panel and protection and metering,

    cables and earthing system set.

    14.  The net energy sales from the plant workout 9.32 million units. The

    entire energy will be sold to NVVN through APTransco grid. The financial

    analysis is made with a levelised power purchase price of Rs. 12.00 /

    kWh.

    15.  The total cost of generation includes the insurance cost, repairs and

    maintenance, cost of administration, salaries and wages, cost of utilities.

    16.  The total installed project cost including civil, mechanical and electrical,

    preoperative expenses and the contingency works out to Rs 650 million.

    17.  The solar power plant reduces contribution to atmospheric carbon-di-

    oxide vis-à-vis fossil fuel generation. The project helps solar radiation

    into useful electricity, adding to the sustainability of the project and the

    local environment. Thus, the project meets the UNFCCC norms set to

    qualify for obtaining CDM benefits. The project is envisaged to register

    with UNFCCC for availing the CDM benefits.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    12/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    moratorium period of 1 year. The equity from SSIL will be Rs 195.00

    million. The interest rate for the term loan is considered as 11.50 %.

    19.  The depreciation computed is on straight line basis.

    20.  Income tax at the rate of 32.45% % is considered in the financial

    analysis. The benefits available under Section 80 IA, for power projectshave been taken into consideration in the financial analysis while

    calculating the income tax liability. The post tax Project Internal Rate of

    Return (IRR) works out to 13.63% and Post tax Equity IRR works out to

    18.89%.

    21.  The project also generates Clean Development Mechanism (CDM)

    revenue with reduction at 1% in the subsequent years. If we consider the

    revenue from sale of carbon credits with a minimum price of € 12 per

    CER, the project generates additional revenue of about INR 7.5 million,which will add to the profitability of the project.

    22.  Minimum Project Debt Service Coverage Ratio (DSCR) will work out to

    1.35 and average DSCR will work out to 1.65.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    13/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    PROJECT AT A GLANCE

    1 Project Authority SAISUDHIR Energy Limited

    2 Project Installed Capacity5 MW +5% and –0% Solar PhotovoltaicPower Plant

    3 Selected LocationT.Veerapuram Village, AnantapurDistrict.

    4 Nearest Major Towns Anantapur

    5 Seismic Zone Zone-4 as per IS 1893-1984.

    6 Access by BusWell Connected, buses are Operated byAndhrapradesh State Road TransportCorporation (APSRTC)

    7 Nearest Airport Bangalore International Airport (BIAL)

    8 Access by Rail Anantapur Railway Station is on theBangalore-Hydrabad line.

    9 Solar module typeCopper Indium Selenium (CIS) Thin filmmodules

    10 Capacity of each module 130 Wp

    11 No. of modules 41,600 Nos

    12 PV System Mounting Structure type MS Galvanised(> 70 micron)

    13 Module mounting structure type 8 Module mounting structure

    14 No. of module mounting structures 5,200 Nos.

    15 No. of Array junction boxes 80 Nos.

    16 Power conditioning Unit (Invertor)capacity 500 kVA

    17 Power conditioning Unit specifications Input voltage range 450-900V

    18 No. of invertors 10 Nos.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    14/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    22 LT Panel with protection & metering 5 Nos.

    23 LT Panel with protection & metering 2 Nos

    24 Cables and earthing systems 1 set

    25 Gross Power Generation (kW) 5000 +5% and -0%

    27Net exportable power at 33 kV tonearest grid substation(kW)

    9.32 million units

    28 Power Purchase tariff with NVVN in`  12.00

    29 Plant Load Factor 21.28%

    30 Total Project cost (Rs. In millions) 650

    31Preliminary and pre-operativeexpenses (Rs. In millions)

    30.00

    32 Equity from Promoters(Rs. In millions) 195.00

    33Term loan from Financial Institutions(Rs in millions)

    455.00

    34 Interest on term loan 11.50%

    35 Project IRR (post tax) 13.63 %

    36 Equity IRR (post tax) 18.89 %37 Plant Commissioning Date Dec 2011

    38Land requirement

    •  Module area25 Acres51,089 m2

    39 Land DevelopmentThe entire station will be laid at auniform level.

    TECHNICAL FEATURES 

    40 Power EvacuationThrough 33/132kV Transmission linesRaydurg substation located 10km fromproject site.

    OTHER FACILITIES 

    41 Mode of ImplementationThrough EPC (Engineering, Procurementand Construction) or thru split contracts.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    15/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    1  NEED AND JUSTIFICATION FOR THE PROJECT

    1.1  Introduction

    India with 17 percent of the world population and just 0.8 per cent of the

    world’s known oil and natural gas resources is going to face serious energy

    challenges in the coming decades. Besides energy independence, the

    devastating impact of climate change has become an issue of critical

    importance. Energy production using fossil fuels is the major contributor to

    greenhouse gas emissions. Hence, transition to a low-carbon energy economy is

    the real solution for mitigating the impact of climate change.

    India has huge potential for producing electricity from renewable sources. The

    achievement so far is about 17,222 (as on 31.03.2010) MW, as against global

    installed capacity of approximately 2,00,000 MW of renewable electricity

    generation. While India’s achievement is commendable, it is necessary for us to

    keep pace with the fast growth in developed countries.

    There are three imperatives that necessitate a transition to a sustainable energy

    system in the 21st century: They are Climate change and its potentially

    disastrous consequences. Peaking of production, depletion and extinction of

    fossil fuels and Energy Autonomy and Independence.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    16/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Peaking of production of all fossil fuels (viz. oil, gas and coal) in the next two

    decades and gradual extinction of these resources is an accepted scientific fact.

    Even assuming that they would be available, India, which is already dependent

    on their import, would become more and more import dependent. The financial

    implications of large scale imports would destroy our economy and necessitate

    strategies to move towards energy autonomy or independence.

    The conversion of solar energy to electricity displaces an equivalent amount of

    grid power, which would otherwise be produced by grid connected fossil fuel

    dominated power plants. Grid power is comprised of a large share of fossil fuel

    based generation systems.

    1.2  Power Scenario in India

    As per Section73(a) of the Indian Electricity Act-2003, CEA has been carrying

    out periodic electric power survey to project state-wise and region-wise power

    plans together with assessment of peaking power and energy surpluses /

    deficits. The estimate prepared by the CEA is revised and updated from time to

    time taking into account the actual growth rates achieved. The Reports and

    National Electricity Plan prepared by CEA i.e. Report on (17th) Electric Power

    Survey of India published in August 2007, Draft National Electricity Plan-

    Transmission published in 2005 and Power Scenario at a glance published in

    April 2010 have been referred for carrying out demand analysis of the State of

    Andhra Pradesh and other regions

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    17/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    region while other regions i.e. Northern, Western and Southern will expect a

    shortage of power at the end of 11th Plan i.e. 2011-12. Actual power scenario

    of are as follows in terms of:

    •  Installed Capacity

    •  Actual Supply/Generation.

    •  Likely capacity addition.

    Table 1-: Installed Capacity in MW in India at the End of 10th Plan

    Coal Gas Diesel Total

    STATE 26,005.7 41,731.6 3,729.8 604.6 46,066 0.0 975.7 73,047.4

    PRIVATE 1,230.0 4,241.4 4,183.0 597.1 9,021.5 0.0 6,784.8 17,036.3

    CENTRAL 7,418 25,118.3 5,809.0 0.0 30,927.3 3,900.0 0.0 42,245.3

    TOTAL 34,653.7 71,091.3 13,721.8 1,201.8 86,014.8 3,900.0 7,760.5 1,32,329

    INSTALLED CAPACITY (AT THE END OF 10TH PLAN) (FIGURES IN MW)

    Sector Hydro Thermal Nuclear R.E.S.

    (MNRE)

    Total

     

    Table 1-: Installed Capacity in MW in India as of 31 Mar 2010

    Sector Hydro Nuclear R.E.S Total

    Coal Gas Diesel Total (MNRE)

    STATE 27,065.00 44,977.00 4,046.12 602.61 49,625.73 0.00 2,701.12 79,391.85PRIVATE 1,233.00 8,056.38 6,307.50 597.14 14,961.02 0.00 12,819.99 29,014.01

    CENTRAL 8,565.40 31,165.00 6,702.23 0.00 37,867.23 4,560.00 0.00 50,992.63

    TOTAL 36,863.40 84,198.38 17,055.85 1,199.75 1,02,453.98 4,560.00 15,521.11 1,59,398.49

    Thermal

    INSTALLED CAPACITY AS ON 31.03.2010 (FIGURES IN MW)

     

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    18/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table 1-: Actual Power Supply Position

    9 Period PeakDemand

    (MW)

    Peak Met(MW)

    PeakDeficit/

    Surplus

    MW

    PeakDeficit/

    Surplus

    %

    EnergyRequi-

    rment

    MU

    Energy Availability (MU)

    EnergyDeficit/

    Surplus

    MU

    EnergyDeficit/

    Surplus

     %9TH PLAN END 78,441 69,189 -9,252 -11.8 5,22,537 4,83,350 -39,187 -7.52002-03 81,492 71,547 -9,945 -12.2 5,45,983 4,97,890 -48,093 -8.82003-04 84,574 75,066 -9,508 -11.2 5,59,264 5,19,398 -39,866 -7.12004-05 87,906 77,652 -10,254 -11.7 5,91,373 5,48,115 -43,258 -7.32005-06 93,255 81,792 -11,463 -12.3 6,31,757 5,78,819 -52,938 -8.42006-07 1,00,715 86,818 -13,897 -13.8 6,90,587 6,24,495 -66,092 -9.6

    2007-08 1,08,866 90,793 -18,073 -16.6 7,39,345 6,66,007 -73,338 -9.92008-09 1,09,809 96,685 -13,124 -12 7,74,324 6,89,021 -85,303 -11APR,09 1,18,472 1,02,725 -15,748 -13.3 8,30,300 7,46,493 -83,807 -10.1MAR ,2010 1,18,472 1,02,725 -15,748 -13.3 76,493 67,513 -8,980 -11.7

    ACTUAL POWER SUPPLY POSITION

     

    NOTE :-  PEAK DEMAND - 121891 MW , ENERGY REQUIREMENT - 794561 MU FOR THE YEAR2008-2009(AS PER 17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLYPOSITION IN THE MONTH(S) - MARCH & OCTOBER

    SOURCE:- DMLF DIVISION

    Table 1-: Capacity Addition during 11th Plan (As Per Planning Commission)

    Coal Gas Diesel Total

    STATE 3,482.0 19,985.0 3,316.4 0.0 23,301.4 0.0 0.0 26,783.4

    PRIVATE 3,491.0 9,515.0 2,037.0 0.0 11,552.0 0.0 0.0 15,043.0

    TOTAL 15,627.0 52,850.0 6,843.4 0.0 59,693.4 3,380.0 0.0 78700.4*

    CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)

    Sector Hydro Thermal Nuclear Wind Total

     NOTE :- * AS PER ACTUAL ORDERS , THE CAPACITY COMES TO 78900.4 MW 

    Table 1-: Likely Power Supply Position at the End of 2010-12

    Period Peak

    Demand(MW)

    Peak

    Met(MW)

    Peak

    Deficit/Surplus(MW)

    Peak

    Deficit/Surplus( % )

    Energy Requi

    rment (MU)

    Energy

    Avail-ability(MU)

    Energy

    Deficit/Surplus(MU)

    Energy

    Deficit/Surplus( % )

    2011-12 1,52,746 1,42,765 -9,981 -6.5 9,68,659 9,48,836 -19,823 -2.0

    LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12 (DEMAND AS PER 17TH EPS)

     

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    19/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table 1-: Installed capacity of all states as on 31.03.2010 (in MW)

    S.No

    .

    STATES HYDRO NUCLEAR R.E.S TOTAL

    COAL GAS DIESEL TOTAL

    1 CHANDIGARH 46.74 27.09 15.32 0.00 42.41 8.84 0.00 97.99

    2 DELHI 581.62 2 ,602.96 808.01 0 .00 3 ,410.97 122.08 0 .00 4 ,114.67

    3 HARYANA 1,327.68 3,017.99 535.29 3.92 3,557.20 109.16 76.50 5,070.54

    4 H.P . 1 ,539.94 118.30 61.88 0 .13 180.31 34.08 275.83 2 ,030.16

    5 J&K 1 ,480.53 263.70 304.14 8 .94 576. 78 77 .00 129.33 2,263. 64

    6 PUNJAB 2,962.89 3,208.19 263.92 0.00 3,472.11 208.04 278.90 6,921.94

    7 RAJASTHAN 1,454.80 4,149.48 665.03 0.00 4,814.51 573.00 926.15 7,768.46

    8 U.P . 1 ,597.42 6 ,912.84 549.97 0 .00 7 ,462.81 335.72 587.70 9 ,983.65

    9 UTTRAKHAND 1,919.18 261.26 69.35 0.00 330.61 22.28 132.92 2,404.99

    10 CHATTISGARH 120.00 4,383.00 0.00 0.00 4,383.00 47.52 218.95 4,769.47

    11 GUJARAT 772.00 7,008.89 3,894.49 17.48 10,920.86 559.32 1,655.91 13,908.09

    12 M.P. 3 ,223.66 4 ,282.10 257.18 0 .00 4 ,539.28 273.24 287.86 8 ,324.04

    13 MAHARASHTRA 3,331.84 11,203.05 3,715.93 0.00 14,918.98 690.14 2,437.97 21,378.93

    14 GOA 0.00 277.03 48.00 0.00 325.03 25.80 30.05 380.88

    15 D&D 0.00 19.04 4.20 0.00 23.24 7.38 0.00 30.62

    16 D&N HAVAILI 0.00 22.04 27.10 0.00 49.14 8.46 0.00 57.60

    17 A.P. 3,617.53 6,259.88 2,580.40 36.80 8,877.08 214.28 700.51 13,409.40

    18 KARNATAKA 3,599.80 3,902.67 220.00 234.42 4,357.09 195.36 2,234.09 10,386.34

    19 KERALA 1,781.50 765.38 533.58 256.44 1,555.40 78.10 138.76 3,553.76

    20 T.N 2,108.20 5,519.81 1,026.30 411.66 6,957.77 478.50 4,865.51 14,409.98

    21 P .CHURY 0 .00 207 .01 32.50 0 .00 239.51 16.28 0.00 255. 79

    22 D .V .C 193.26 3 ,563.10 90.00 0 .00 3 ,653.10 0 .00 0 .00 3 ,846.36

    23 B IHAR 129.43 1 ,661.70 0 .00 0 .00 1 ,661.70 0 .00 54.60 1 ,845.73

    24 JHARKHAND 200.93 1,737.88 0.00 0.00 1,737.88 0.00 4.05 1,942.86

    25 ORISSA 2,166.93 1,828.10 0.00 0.00 1,828.10 0.00 64.30 4,059.33

    26 SIKKIM 75.27 68 .10 0.00 5.00 73.10 0 .00 47.11 195. 48

    27 W.BENGAL 1,116.30 6,756.34 100.00 12.20 6,868.54 0.00 164.70 8,149.54

    28 ARP .P. 97.57 0 .00 21.05 15 .88 36.93 0 .00 67.42 201. 92

    29 ASSAM 429.72 60.00 441.32 20.69 522.01 0 .00 27.11 978.84

    30 MANIPUR 80.98 0 .00 25.96 45.41 71.37 0 .00 5 .45 157.80

    31 MEGHALYA 230.58 0.00 25.96 2.05 28.01 0.00 31.03 289.62

    32 MIZORAM 34.31 0 .00 16.28 51.86 68.14 0 .00 28.47 130.92

    33 NAGALAND 53.32 0 .00 19.19 2 .00 21.19 0 .00 28.67 103.18

    34 TRIPURA 62.37 0 .00 160.84 4.85 165.69 0 .00 16.01 244.07

    35 A&N ISLAND 0.00 0 .00 0 .00 60.05 60.05 0 .00 5 .25 65.30

    36 LAKSHDEEP 0.00 0 .00 0 .00 9 .97 9 .97 0 .00 0 .00 9 .97

    THERMAL

     

    Table 1-: Installed Capacity in MW in Andhra Pradesh at the End of 10th Plan

    Coal Gas Diesel Total

    STATE 3,582.6 3,132.5 272.3 0.0 3,404.8 0.0 103.0 7,090.3PRIVATE 3.8 0.0 1,603.4 36.8 1,640.2 0.0 283.4 1,927.4

    CENTRAL 0.0 2,378.0 0.0 0.0 2,378.0 152.5 0.0 2,530.5

    TOTAL 3,586.3 5,510.5 1,875.7 36.8 7,423.0 152.5 386.4 11,548.2

    INSTALLED CAPACITY (AT THE END OF 10th PLAN (FIGURES IN MW)

    Sector Hydro Thermal Nuclear R.E.S.

    (MNRE)

    Total

     

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    20/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table 1-: Installed Capacity in MW in Andhra Pradesh as of 31 Mar 2010

    Coal Gas Diesel Total

    STATE 3,617.53 3,882.50 0.00 0.00 3,882.50 0.00 188.43 7,688.46

    PRIVATE 0.00 0.00 2,580.40 36.80 2,617.20 0.00 512.08 3,129.28

    CENTRAL 0.00 2,377.38 0.00 0.00 2,377.38 214.28 0.00 2,591.66

    TOTAL 3,617.53 6,259.88 2,580.40 36.80 8,877.08 214.28 700.51 13,409.40

    Sector Hydro Thermal   Nuclear R.E.S.

    (MNRE)

    Total

     Table 1-: Actual Power Supply Position

    Period

    Peak

    Demand(MW)

    Peak

    Met(MW)

    Peak

    deficit/Surplus

    (MW)

    Peak

    Deficit/Surplus (

    % )

    Energy

    Requi-rment

    (MU)

    Energy

    Avail-ability

    (MU)

    Energy

    Deficit/Surplus

    (MU)

    Energy

    Deficit/Surplus (

    % )

    9TH PLAN END 8,585 6,873 -1,712 -19.9 48,394 44,302 -4,092 -8.5

    2002-03 8,491 6,858 -1,633 -19.2 47,258 44,049 -3,209 -6.8

    2003-04 8,679 7,769 -910 -10.5 48,080 46,680 -1,400 -2.9

    2004-05 8,093 7,903 -190 -2.3 50,416 50,061 -355 -0.7

    2005-06 8,999 8,542 -457 -5.1 53,030 52,332 -698 -1.3

    2006-07 10,208 8,641 -1,567 -15.4 60,964 58,280 -2,684 -4.4

    2007-08 10,048 9,162 -886 -8.8 64,139 61,511 -2,628 -4.1

    2008-2009 10,823 9,997 -826 -7.6 71,592 66,754 -4,838 -6.8

    APR,09-MAR10 12,135 10,880 -1,255 -10.3 79,014 73,784 -5,230 -6.6

    MAR 2010 12,135 10,880 -1,255 -10.3 7,929 7,040 -889 -11.2  

    Table 1-: Projects planned for 11th Plan

    EFFORTPROJECTS

    PROJECT AGENCY STATUS TYPE

    CAPACITY

    (MW)

    LIKELY YEAR /

    DATE OFCOMMISSIONING

    1 SIMHADRI-EXT U-3,4 NTPC Under Construct ion COAL 1,000 2010-12

    2 1,000

    3 JURALA PRIYA U1,2 APGENCO Commissioned HYDRO 78 31.08.2008

    4 JURALA PRIYA U,3 APGENCO Commissioned HYDRO 39 07.06.2009

    5 JURALA PRIYA U 4-6 APGENCO Under Construction HYDRO 117 2010-11

    6  NAGARJUNA SAGAR TR APGENCO Under Construction HYDRO 50 2010-12

    7 PULICHINTALA APID Under Construction HYDRO 120 2010-12

    8 RAYALSEEMA U4 APGENCO Commissioned COAL 210 2007-08

    9 RAYALSEEMA ST III U5 APGENCO Under Construction COAL 210 2010-11

    10 VIJAYWADA TPP ST-IV,U1 APGENCO Commissioned COAL 500 8.10.2009

    11 KOTHAGUDEM ST-V APGENCO Under Construction COAL 500 2011-12

    12 KAKTIYA TPP APGENCO Under Construction COAL 500 2010-11

    13 2,324

    14 KONASEEMA OAKWELL Commissioned GAS/LNG 280 3.5.2009

    SUB TOTAL –Central sector 

    SUB TOTAL –state sector 

    PROJECTS PLANNED FOR XITH PLAN (STATE/PRIVATE/CENTRAL SECTOR) INCLUDING BEST

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    21/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table 1-: Likely Power Supply Position at the End of 2010-12

    Period Peak Peak Peak Peak Energy Energy Energy Energy

    2011- 14,721 12,357 -2,364 -16.1 89,032 80,338 -8,694 -9.8

    LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)

     

    Table 1-: Likely Capacity Addition During 11th Plan

    FOR THE STATE : - Ty St Installed Capacity Benefits 

    Commissioned Last Unit 

    *SIMHADRI ST-II T U 1,000.00 1,000.00 384.00 (2010-2012)*ENNORE JV COST T U 1,000.00 1,000.00 129.00 (20110-2012)

    KAIGA U-3 & 4 N U 440.00 440.00 123.00 COMM 220.00 11.04.2007

    *KALPAKKAM PFBR N U 500.00 500.00 142.00 (2010-2011)

    778.00

    NAGAR SAGAR TR H U 50.00 50.00 50.00 (2010-2012)

    VIJAYWADA TPP T U 500.00 500.00 500.00 COMM 500.00 ( 8.10.2009 )

    KOTHAGUDEM ST-V T U 500.00 500.00 500.00 (2011-2012)

    JURALA PRIYA H U 234.00 234.00 234.00 COMM 27.06.2009

    RAYALSEEMA 4&5 T U 420.00 420.00 420.00 COMM 210.00 20.11.2007

    PULICHINTALA H U 120.00 120.00 120.00 (2011-2012)

    KAKTIYA TPP T U 500.00 500.00 500.00 (2010-2011)1,824.00

    KONASEEMA CCGT G U 445.00 445.00 445.00 COMM 280.00 (3.5.2009)

    GAUTAMI CCGT G C 464.00 464.00 464.00 COMM 464.00 (3.5.2009)

    KONDAPALLI CCPP G U 233.00 233..00 233.00 COMM 233.00 (5.12.2009)

    KONDAPALLI CCPP T U 366.00 366.00 133.00 (2010-2011)

    1,275.00

    3,757.00GRAND-TOTAL:-

    LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS

    CENTRAL-SECTOR

    CENTRAL-SECTOR TOTAL:-

    STATE-SECTOR

    STATE - SECTOR TOTAL:-

    PRIVATE-SECTOR

    PRIVATE-SECTOR TOTAL:-

     

    Note: U-Under Construction Project;C-Commissioned* Share from Central Sectors Projects for which M.O.P. Orders areyet to be issued is tentative.

    Table 1-: Peak & Energy Table

    YEAR

    Requirment Actual Requirement

     

    Actual

    2004-05 8,168 8,093 48,928 50,416

    2005-06 8,810 8,999 54,683 53,030

    2006-07 9,597 10,208 59,311 60,964

    2007-08 10,454 10,048 64,331 64,139

    PEAK ENERGY

    PEAK AND ENERGY TABLE

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    22/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    From the above tables i.e. Actual power Supply position for the state of Andhra

    Pradesh, it clearly indicates the consistent power deficit of around 8.5 % at the

    end of 9th Plan continuing till 2009-10 up to 11.2%.

    1.3  Justification for the project

    For the state of Andhra Pradesh the projected peak load is 13,514 MW (2010-

    11). Table above shows Installed capacity as on 31 Mar 2010 for the state of

    Andhra Pradesh, actual power supply position and capacity addition during 11th

    Plan for the state of Andhra Pradesh. As per present power scenario for the

    state of Andhra Pradesh the peak deficit during 2006-07 is around 4.4 %. As

    per table above power deficit for the state of Andhra Pradesh during 2011-12

    will be around 1,255 MW (March 2010). Thus Considering projected power

    demand for the state of Andhra Pradesh, power generated from the proposed

    power plant may be utilized for the state of Andhra Pradesh.

    The proposed solar photovoltaic power plant (SPV) will contribute to bridge the

    gap between the demand and availability of power.

    As per the proposed transmission evacuation plan, the proposed power station

    shall be connected to APTransco 33/132 kV substation at Raydurng, in

    Anantapur district. Therefore it is considered that the proposed power plant will

    be able to contribute to the power requirement of the Andhra Pradesh, hence it

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    23/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    The project activity will result in an annual average reduction of about 8000

    tCO2e per year by replacing electricity generated from fossil fuel fired power

    plants. The project activity has been essentially conceived to generate GHG

    emission free electricity by making use of available Solar PV in the project area.

    The project - being a renewable energy project - leads to sustainable

    development through efficient utilization of naturally available sunlight and

    generation of additional employment for the local stakeholders.

    The Government of India in its Interim Approval Guidelines for CDM Projects

    has stipulated a set of indicators for describing the sustainable development of

    a project. According to these indicators, the sustainability of the described

    project is as follows:

    Social well being:

    The project activity is generating employment opportunities for professional,

    skilled and unskilled labour for development, engineering, procurement

    operation and maintenance of the project activity. The development of project

    specific infrastructure will result in employment and income generation activities

    for local personnel. In addition various kinds of maintenance work would

    generate employment opportunities for local contractor on regular and

    Economic well being:

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    24/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    •  The project activities will act as a nucleus for other economic activities

    such as setting up of cottage industries, shops, hotels etc. around the

    area, contributing to the economic development around the project area.

    •  Proposed power plant will use solar radiation as resource for generation

    of power helps conserve foreign exchange by reducing the need to import

    fossil fuels to meet the country’s growing energy demand.

    Environmental well being:

    Solar energy based power generation system will be a robust clean technology

    involving latest state of the art renewable energy options to be used for the

    purpose of electricity generation. The project implementation will lead to

    reduction of SOx, NOx and particulate matter (PM) emissions. It therefore

    results in an improvement in air quality and human health.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    25/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    2  DETAILS ABOUT THE PROPOSED PROJECT LOCATIONIN ANANTAPUR DISTRICT

    2.1  Introduction

    Anantapur district is situated in 13'-40'' and 15’-15'' Northern Latitude and 76'-

    50'' and 78'-30'' Eastern Longitude. It is bounded by Bellary, Kurnool District

    on the North, Cuddapah and Kolar Districts of Karnataka on South East and

    North respectively. The District is roughly oblong in shape, the longer side

    running North to South with a portion of Chitradurg District of Karnataka State

    intruding into it from west between Kundurpi and Amarapuram Mandals.The

    Distance of State capital Hyderabad from the district is of ~300 Kms. TheDistrict of Anantapur has a fairly good elevation which provides the District with

    tolerable climate throughout the year. It has a gradual fall from the South

    North towards the valley of the Pennar in Peddavadugur, Peddapappur and

    Tadipatri Mandals. There is a gradual rise in Hindupur, Parigi, Lepakshi,

    Chilamathur, Agali, Rolla and Madakasira Mandals in the South to join the

    Karnataka Plateau where the average elevation is about 2000 feet is above the

    mean sea level.

    2.2  Area and population in Anantapur District

    There are 929 inhabited villages, out of 964 total Revenue villages of the

    District. The number of villages in size group of 500 to 1999 forms 36.71% of

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    26/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    2.3  Rainfall and Climate

    Anatapur district being far from the East coast, it does not enjoy the full

    benefits of North East Monsoons and being cut off by the high western Ghats,

    the South West Monsoon are also prevented from penetrating and punching

    the thirst of these parched soils. It is therefore seen, the district is deprived of

    both the monsoons and subjected to droughts due to bad seasons. The normal

    rainfall of the district is 553.0 MMs. by which it secures least rainfall when

    compared to Rayalaseema and other parts of Andhra Pradesh. The normal

    rainfall for the South West Monsoon period is 338.0 MMs. which forms about

    61.2% of the total rainfall for the year. The failure of the rains in this South

    West monsoon period of June to September will lead the District to drought by

    failure of crops. The rainfall for North East monsoon period is 156.0 M.Ms. only,

    which forms 28.3% M.Ms. of the total rainfall for the year (October to

    December). 

    2.4  Temperature

    March, April and May are warm months when the normal daily maximum

    temperature ranges between 29.1 C to 40.3 C. November, December and

    January are cooler months when the temperature falls about 15.7 C,

    Hindupur, Parigi, Lepakshi, Chilamathur, Agali, Rolla and Madakasira Mandals

    being at High Elevation are more cooler than the rest of the Mandals in the

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    27/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    2.5  Proposed Project location

    The Proposed project site T Veerapuram is located in Raydurg Taluk of

    Anantapur district. Below figure shows the project location. The site selection

    for a Solar Power Plant is pre-dominantly determined by solar insulation

    availability & grid connectivity for exporting power. Equally important are other

    essential factors/considerations such as:

    •  Availability of adequate land for Power Plant and green belt development

    •  Soil condition like soil bearing capacity etc.

    •  Proximity to State Electricity Grid enabling economic evacuation of power

    generated

    •  Availability of water and power during construction

    •  Availability of local work force in the proximity

    •  Availability of load centres (towns) within vicinity

      Easy accessibility of the site

    The proposed project site in Veerapuram village, Anatapur district of Andhra

    Pradesh State is found favoring all the above factors to a reasonable extent.

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    28/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Figure : Location map of Anatapur district in India:

    Figure : Map showing proposed project site within Anantapur

    ProposedProject site for

    5 MW SPVPower Project

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    29/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    2.6  Land requirement and layout of the proposed Project

    The Power Plant will be located in the proposed site in Veerapuram village. The

    total land area required for the project is about 25 acres. The Power Plant

    layout can be divided into two sections as:

    1.  Module mounting area and

    2.  Control room

    The major portion of the site will be used for module mounting. As described in

    the Power Plant Scheme the module will be mounted in a steel structure which

    will be installed facing South direction for best efficiency & optimal power

    output. The steel structure will be grouted using RCC foundation. The proposed

    structure is designed to hold 8 modules per structure and which can withstand

    wind speed up to 100km/hr. The structure is designed in such a way that it will

    occupy minimum required space without sacrificing the performance.

    The interconnection cables are routed within the structure and the output cables

    from the modules are taken through proper size conduit to the smart connect

    box. The output cables from the junction boxes are routed under the ground

    through conduits or cable trenches. Man holes for regular maintenance and

    inspection will be provided at equal distances as required. Earthing for all the

    module mounting structures will be done using copper or GI conductors. The

    D t il d P j t R t 5 MW SPV b d l t t V A t di t i t A dh P d h

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    30/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    provided in this area alone for protection of modules. The proposed power plant

    layout is enclosed as annexure 5.

    2.7  Land availability and acquisition for the project

    As mentioned in the previous section, solar power plant of 5 MW capacity

    requires about 25 acres of land. The land required by the project is already

    acquired on lease basis.

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram Anantapur district Andhra Pradesh

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    31/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    RADIATION DATA AND PROJECTED POWER GENERATION FROM THE PROJECT

     ACTIVITY

    Actual site of installation is T. Veerapuram village, Raydurg taluka, located in

    Anatapur district. The latitude and longitude of this site is 14.36 0N and 76.56

    0E respectively. Solar radiation available is for Anatapur in Andhra Pradesh is

    considered for simulation of project parameters.

    Latitude : 14.70 ºN

    Longitude : 77.60 ºE

    Below is the weather data for Anatapur district. The data is taken from surface

    metrology and solar energy data NASA earth science enterprise programme and

    is based on 22 years of yield data analysis.

    The irradiation and temperature details considered for the design purpose are

    as below:

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram Anantapur district Andhra Pradesh

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    32/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table -: Temperature details considered for design:

    Average annual solar insulation at horizontal angle taken for Anantapur based

    on the above chart: 5.34 KWh/m²/day.

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    33/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    2.8  Simulation report of the power plant

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    34/88

    j

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    35/88

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    36/88

    The above simulation analysis is carried out based on the fixed structures.

    Saisudhir energy and NVVN has entered into a power purchase agreement for

    the capacity of 5 MW +5% and -0% power plant capacity. The entire generated

    energy will be sold to NVVN on a long term basis. With this arrangement to

    optimize the power generation potential, it was envisaged to install PV modules

    of 5.250 MW capacity to take care of the DC side energy losses in the system.

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    37/88

    3  SELECTION OF TECHNOLOGY

    The key components of a photovoltaic power system are the photovoltaic cells

    (sometimes also called solar cells) interconnected and encapsulated to form a

    photovoltaic module (the commercial product), the mounting structure for the

    module or array, the inverter (essential for grid-connected systems and) and

    charge controller (for off-grid systems only).

    3.1  Existing Solar Photovoltaic Technologies

    Crystalline silicon technologies currently account for most of the overall cell

    production in the IEA PVPS countries. Single crystal PV cells are manufactured

    using a single-crystal growth method and have commercial efficiencies between

    15 % and 18 %. Multicrystalline cells, usually manufactured from a melting and

    solidification process, are less expensive to produce but are marginally less

    efficient, with conversion efficiencies around 14 %.

    PV cells made from ribbons demonstrate an average efficiency around 14 %.

    Thin film cells, constructed by depositing extremely thin layers of photovoltaic

    semi-conductor materials onto a backing material such as glass, stainless steel

    or plastic, show stable efficiencies in the range of 7 % to 13 %. Thin film

    materials commercially used are amorphous silicon (a-Si), cadmium telluride

    (CdTe), and copper-indium-gallium-diselenide (CIGS) and Copper Indium

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    38/88

    S.No. Parameter Crystalline Thin Film CPV

    Types of Materials Mono/ Polycrystalline Amorphous Silicon, CdS,

    CdTe, CIGS, CIS etc.

    Triple Junction GaAs Cell &

    lens , tracker

    1 Handling Better protection against

    breakage

    Not Guaranteed Installation would be at site.

    Not Guaranteed

    2 Power Efficiency 12-16% 6-8% 20-25%

    3 Technology Well Developed Under development Under development

    4 Module Weight Light weight modules Heavier modules Heaviest System

    5 Area ut ilizat ion Higher power generated

    per unit area due to high

    efficiency

    Less power per unit area Highest power per unit area

    6 Temperature Effects Temperature variations

    affect output

    Lesser impact of Temperature

    variations

    High variation

    7 Irradiance Used particularly for

    Normal radiations

    Better performance with Diffuse

    radiations

    Works only for Normal

    radiations

    8 Module quantity Lesser nos required due

    to high efficiency

    More modules required Lowest nos. of modules

    required

    9 Output per MW

    installed

    High Varies as per sunlight condtion

    and various locations

    Very High(due to tracking)

    10 Transportation Cost Lower Transportationcost

    Higher cost High cost

    11 Mounting Structure Fewer Mounting structure

    required per KW power

    More Mounting structures

    required

    Sophisticated mounting

    required

    12 Land Requirement Lesser space required per

    MW

    Largest space requirement Lowest space required

    13 Inverter High inverter f lexibilit y Limit ed inverter f lexibilit y Limit ed inve rter f lexibilit y

    14 Cost High cost per Watt Lower cost per Watt Highest cost per Watt

    14 Environment Effects Less Sensitive Sensitive Sensitive

    15 Stabilizat ion Stable power output f rom

    at initial stages

    Stability achieved after 4-6

    months

    Unknown

    16 Availability Easily available Limited supply Limited supply

    17 Health hazards Made f rom non toxic

    material (Si)

    Toxic materials used for t hin

    films (CdS, CdTe)

    Unknown

    18 Power Degradation Less degradation Highest degradation for init ial 5-

    7 years

    High Degradation

    19 Plant Maintenance Less maintenance Highest maintenance required, High maintenance required, so

    3.2  Thin film modules

    Thin film modules are potentially cheaper to manufacture than crystalline cells

    have a wider customer appeal as design elements due to their homogeneous

    appearance present. Disadvantages, such as low-conversion efficiencies and

    requiring larger areas of PV arrays and more material (cables, support

    structures) to produce the same amount of electricity.

    3.3  Comparison between Crystalline, Thin film and CPV

    Technologies

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    39/88

    3.4  Conclusion on selection of technology

    Each of the above technologies has their own particular strengths and

    weaknesses which have played a role in our decision making. We have decided

    to use Copper Indium Selenium (CIS) Thin film modules as our

    preferred technology. These advantages and disadvantages in addition with

    their market availability and costing are the key parameters on basis of whichwe have taken our technological decision.

    In the section 4.3 we have compared various technologies, and justification of

    why we have chosen a particular technology. In the below section we have

    compared the CIS, vis a vis Crystalline, Amorphous technologies.

    Characteristic CIS Crystalline Amorphous Remarks

    Module efficiency ++ +++ - cSi still higher than CIS, but the differenceis getting narrow

    Appearance ++ - ++ CIS modules are all black, and therefore

    very compatible with roof settings

    High Temperature - - ++ CIS and cSi do not have anneal effect

    Light soaking effect ++ - - CIS has light soaking effect. Higher thannominal power output is expected.

    Degradation ++ ++ - Degradation rate is almost same asCrystalline.

    Production cost ++ + ++ Unit production cost of CIS modulesexpected to decrease by mass production

    but not in the case of crystalline module.Manufacturing process + - + Simple processes allow a smooth and

    efficient production overall

    Environmentalcontribution

    + - + Environmentally friendly - CIS modules donot include toxic or pollutant elements

    Energy payback time ++ + ++ Manufacture of CIS modules require only a

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    40/88

    4  POWER PLANT DESIGN CRITERIA

    The Power Plant is sized on the following major criteria:

    •  Solar Power (average insulation available)

    •  Power evacuation facility in the vicinity of the proposed site along with

    Grid availability on 24 Hours a day basis.

    Details of the design process and are presented in the below sections.

    4.1  Design and Simulation projections by PVSYST

    PVSYST tool is one of the most accepted design tool for the study, sizing,

    simulation and data analysis of complete PV systems. We have used this tool to

    generate the most realistic energy yield simulation results which are detailed in

    this report. Main features of PVSYST:

    1)  Detailed computation of the used components (modules, inverters, etc)

    2)  Simulation on hourly basis and detailed evaluation and consideration of

    different loss factors.

    3)  Calculation of arbitrary orientated module planes (fixed and tracking

    systems)

    4)  Most accepted and used tool to generate simulation results for big PV

    power plants, as the results are based on systematic and refined

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    41/88

    4.2  PV Power Plant Energy Production

    The system lifetime energy production is calculated by determining the first-year energy generation as expressed in kWh (AC)/kWp (AC), then degrading

    output over the system life based on an annual performance degradation rate.

    System degradation (largely a function of PV panel type and manufacturing

    quality) and its predictability are important factors in lifecycle costs since they

    determine the probable level of future cash flows. This stream of energy

    produced is then discounted to derive a present value of the energy generated

    to make a levelized cost calculation. The first year kWh/kWp is a function of

    the:

    •  The amount of sunshine the project site receives in a year.

    •  The mounting and orientation of the system (i.e., flat, fixed-tilt, tracking,

    etc.).

    •  The spacing between PV panels as expressed in terms of system ground

    coverage ratio (GCR).

    •  The energy harvest of the PV panel (i.e., performance sensitivity to high

    temperatures, sensitivity to low or diffuse light, etc.).

    •  System losses from soiling, transformers, inverters, and wiring

    inefficiencies.•  System availability largely driven by inverter downtime.

    4.3  PV power plant capacity factor

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    42/88

    A PV power plant’s capacity factor is a function of the insulation at the project

    location, the performance of the PV panel (primarily as it relates to high-

    temperature performance), and the orientation of the PV panel to the sun, the

    system electrical efficiencies, and the availability of the power plant to produce

    power.

    4.4  Selection of Inverter and Components

    For a complete reliable system and to ensure high energy yield from the plant,

    innovative components with latest technology are selected. The inverter that is

    selected is of very high efficiency over a wide range of load. The inverter

    operates in excess of 95.0% efficiency in comparison with the requested of 93%

    efficiency.

    Design lifetime of the inverter is at 35,000 hours with rated power at 40°C. This

    is approximately 4.8 hours at full load per day to estimate the lifetime of 20

    years.

    4.5  Selection of Monitoring System

    Monitoring system requirement for a large power plant like 5 MW with state of

    the art technology, monitoring and analysis of is carried out. Few features are

    of the monitoring system are presented as follows:•  Monitors the performance of the entire power plant (string wise

    monitoring, junction boxes, inverters, etc)

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    43/88

    •  Alerts in case of error (discrepancy in normal operation of components,

    like module string/ diodes/ inverter/ junction box / loose contacts/ etc,)

    to facilitate recognition and correction of the fault with minimum

    downtime.

    •  Visualizes nominal status of the connected components via Control

    Center PC Software (diagnosis on site or remote)

    •  Logs system data and error messages for further processing or storing

    •  Stores and visualizes energy yield data (for life of the plant) in the Portal

    from where the data can be accessed remotely.

    4.6  Design criteria for Cables and Junction boxes and

    The power plant will adopt the best engineering practice for complete cable

    routing in the power plant by using minimal cable length while connecting in

    series string, using optimal size cables to ensure the entire plant cable losses

    are minimum.

    The junction boxes proposed are completely pre-wired to ensure ease of

    installation, maintenance and eliminates any installation hassles. These junction

    boxes not only combine the DC power from strings but also monitor each string

    performance and feed the same data to the central monitoring system.

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    44/88

    5  DESCRIPTION OF MAJOR COMPONETS OF THE POWERPLANT

    The Solar electricity is produced when the Photons from the sun rays hit the

    electrons in the Solar PV panels, this will generate Direct Current (DC). The DC

    electricity from the panels passes through DC distribution network to a grid

    interactive inverter, which converts the DC electricity into 220V AC for single

    phase and 415V AC for 3 phase operation by using state of the art technology.

    In order to achieve a higher system voltage, modules are connected in Series,

    called a string. A higher system voltage has the advantage of less installation

    work (smaller conductor cross sections). Lower currents flow at the same

    efficiency so that cable losses are reduced. The strings are connected with the

    photovoltaic branch or the PV-distributor (Smart connect box). This distributor

    is connected with the Main Combiner Box (MCB) which acts as the main DC

    collecting unit which passes the power to be converted to the central inverters.

    Central inverters combine the various advantages of the other installation

    technologies. Thus the module fields are less sensitive towards partial

    darkening, as is the case with string inverters. This results in a very good MPP-

    matching of the inverters. Thanks to higher system voltages than is the case

    with module oriented inverters, central inverters reach a very high efficiency.

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    45/88

    The AC power from the inverter are passed to Low voltage panel and then to

    the main transformer. From the transformer, the power is routed through the

    high voltage panel and eventually to other required measuring & protection

    devices before connecting to the grid.

    Grid connected solar power plant comprises of the main equipment and

    components listed below.

    1.  Solar PV Modules

    2.  Central inverters

    3.  Module mounting system

    4.  Grid connect equipments

    5.  Monitoring system

    6.  Cables & connectors

    7.  Buildings for housing the electronics (Power-house)

    5.1  Solar PV modules

    A photovoltaic module is a packaged interconnected assembly of photovoltaic

    cells, which converts sunlight into energy. For this project, CIS Thin film PV

    technology solar module of 130 Wp is considered.

    The Tilt angle for the modules would be 15o  (all the modules will be facing

    south).

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    46/88

    expensive, yet at the same time the best quality inverters, output voltage in

    sine wave. Inverters connecting a PV system and the public grid are

    purposefully designed, allowing energy transfers to and from the public grid.

    Central inverters are used in large applications. Many times they can be

    connected according to the "master-slave" criteria, when the succeeding

    inverter switches on only when enough solar radiation is available or in case of

    main inverter malfunction. Inverters connected to module strings are used in

    wide power range applications allowing for more reliable operation.

    In the proposed project the invertors will connect 41600 modules (each 130Wp

    (+-3%)) in series. Such 5200 no of strings will be required for 5250.0 System

    The output of the strings will be connected to Central 500 kW PCU. Like this 10

    PCU’s are required. The PCU is nothing but converting the DC Power into AC

    power and feeding into the grid. It is design with a high efficiency >97% with

    IGBT technology, It is delivering the max. Power generated through solar

    modules in to grid due to its inbuilt feature of MPPT operations. The PCU ishaving internal self protection in case of any fault in the grid. Also the PCU has

    inbuilt contactors/breakers with fuses for self protections.

    The PCU is having in-built microprocessor based controls. The Inverters is

    designed in such a way that it will synchronize with the utility (grid) power with

    respect to the Voltage and frequency of Grid and it gets corrected itself

    according to the grid parameters within its settable limits. The inverter is

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    47/88

    past generation for the given period. The output voltage of the inverter is

    connected to the LT side of the grid through step-up transformer of

    0.415/11/110KV or as per the requirement.

    5.1  Module mounting system

    The module mounting structure is designed for holding suitable number of

    modules in series. The frames and leg assembles of the array structures is

    made of mild steel hot dip galvanized of suitable sections of Angle, Channel,

    Tubes or any other sections conforming to IS:2062 for steel structure to met

    the design criteria. All nuts & bolts considered for fastening modules with this

    structure are of very good quality of Stainless Steel. The array structure is

    designed in such a way that it will occupy minimum space without sacrificing

    the output from SPV panels at the same time.

    Figure : Typical module mounting structure:

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    5 1 G id d i

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    48/88

    5.1  Grid connected equipments

    A simple block diagram, related to the interconnection of various systems forgird connectivity, is shown below for reference. The Power from Modules is

    directed to the central inverters through the DC combiner boxes and from the

    inverters it is routed though the Low voltage panel to the transformer. From the

    transformer, the high voltage power is routed to the metering panel, LCB and

    eventually to grid through the High Voltage Panel.

    Figure : Grid-Connect equipments

    5.2  Monitoring System

    System proposed will maintain and provide all technical information on daily

    solar radiation availability, hours of sunshine, duration of plant operation and

    the quantum of power fed to the grid This will help in estimation of generation

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Monitors the performance of the entire power plant (string wise

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    49/88

    •  Monitors the performance of the entire power plant (string wise

    monitoring, junction boxes, inverters, etc)

    •  Evaluates (strings, inverter, nominal/actual value), quantity of DC Power

    & AC Power produced.

    •  Measures instantaneous irradiation level and temperature at site. It also

    measures the module back surface temperature.

    •  Alerts in case of error (discrepancy in normal operation of components,

    like module string/ diodes/ inverter/ junction box / loose contacts/ etc,)

    to facilitate recognition and correction of the fault with minimum

    downtime.

    •  Visualizes nominal status of the connected components via Control

    Center PC Software (diagnosis on site or remote)

    •  Logs system data and error messages for further processing or storing

    •  Stores and visualizes energy yield data (for life of the plant) in the Portal

    from where the data can be accessed remotely.

    5.3  Cables and connectors

    The size of the cables between array interconnections, array to junction boxes,

     junction boxes to PCU etc shall be so selected to keep the voltage drop and

    losses to the minimum. The bright annealed 99.97% pure bare copper

    conductors that offer low conductor resistance, they result in lower heating

    thereby increase in life and savings in power consumption. These wires are

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Cable is of high temperature resistance and excellent weatherproofing

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    50/88

    Cable is of high temperature resistance and excellent weatherproofing

    characteristics which provides a long service life to the cables used in large

    scale projects. The connectors/lugs of copper material with high current

    capacity and easy mode of assembly are proposed.

    5.4  Buildings housing for electronics (power house)

    The power house will be utilized for housing the inverters, Low Voltage Panels,

    High Tension Panels, Plant Monitoring system, Safety equipments, Office room

    etc. In order to avoid shading effect the power house is proposed to be

    constructed on the North side of the layout.

    The power house will be provided with air conditioning unit in order to maintain

    the desired temperature of the equipments like inverters for better

    performance. The office space will be provided inside the control room with

    basic amenities. The performance of the Power Plant can be monitored from the

    power house. The power house will be equipped with all necessary safety

    equipments as the safety rules. The equipments will be erected as per the

    Indian Electrical Standards. The cables will be routed through cables trenches or

    cable trays as required. Alarm system will be provided to alert the operator in

    case of emergency or plant break-down.

    The power house will also house the power evacuation system except the

    transformer. The proposed transformer will be installed in outdoor next to the

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    facilities required for the installation commissioning operation and

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    51/88

    facilities required for the installation, commissioning, operation and

    maintenance of all equipment associated with the Power Plant.

    The civil works includes the following: preliminaries, additional survey, soil

    exploration, piling if needed, ground improvement, foundations, and all

    necessary site investigation associated with the operations. Site roads, site

    leveling and grading with boundary fences, and gates. In order to avoid

    flooding, rain water drainage system is provided all around the plant layout.

    5.5  Other facilities including water

    The other important requirement for the Power Plant is Water, which will be

    used pre-dominantly for module cleaning. The water table is very good in the

    proposed site and bore-well for required depth will be erected to meet the

    requirement. An over-head tank / underground sump will be constructed as per

    the requirement for the water storage.

    A first-aid station will be located as part of the power house/office room.

    Sufficient space will be provided for vehicle parking near to the power house.

    Within the layout approach roads will be made for easy movement of man &

    machines.

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    6 SPECIFICATION OF MAIN PLANT AND EQUIPMENT

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    52/88

    6  SPECIFICATION OF MAIN PLANT AND EQUIPMENT

    Technical specification of major components and bill of materials are presented

    in this section.

    Table -: Bill of materials

    SlNo.

    System Components QTY Total Capacities

    1

    SOLAR MODULESolar Cell Type: CIS Thin film moduleSolar Module Type: Aluminum Framed ModuleModule Wattage: 130Wp eachTotal PV modules rated power: 5250 kWpCertification: IEC 61646

    41,600 Nos. 5.408 MWp

    2

    PV SYSTEM MOUNTING STRUCTURE with

    single axis trackingMaterial: MS Galvanized(>70 micron)i) Design of Solar Photovoltaic 20 moduleMounting Structure, Fixed tilt

    5200 Nos.Voc=750VoltVmax=600Volt

    3 Array Junction boxes 80 Nos. 06 Input 1output type.

    5

    POWER CONDITIONING UNIT (Inverter)500kVA, IP20MAKE: AEG or equivalentSpecifications: Input Voltage range 450 - 900V8 Modules connected in series; 5200 strings

    10 Nos.

    6 1.25 MVA Transformer 5 Nos. ONAN with OLTC

    7 6.5 MVA Transformer 1 No.8 LT panel with Protection & metering 5 Nos.

    9 HT Panel with protection Panel & metering 2 No. 11 KV & 33 KV

    10 Cables 1 Set PVC Cu Cables11 Lightning 1 Set Standard9 Earthing System 1 Set Standard10 Metering Metering panel Universal / Rema

    11 Cables 1 Set Monocab/Finolex

    12 AccessoriesAccessories forcable,interconnection

    Huber + Suhner

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table -: Technical specification of proposed solar modules at STC

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    53/88

    p p p

    Table -: Specifications of module mounting structure

    Technical Specifications for a typical Solar Photovoltaic CIS Thin film moduleat Standard Test Conditons (STC)

    Output power –Pmax (Watts) 130 Wp +/-5%

    Warranted minimum Pmax 130 Wp +/-5%

    Voltage at Pmax 77.0 V

    Current at Pmax 1.82 A

    Open-circuit voltage 109 V

    Short circuit current 2.10 A

    Maximum system voltage (Volts) DC 600 V

    Fuse rating 15 A

    Type of solar PV cell CIS Thin film

    Suitability For grid connected system

    Module output Multi contact plug

    Certification IEC 61646

    Fire rating Class C

    Power warranty10 year warranty on 90% of theminimum output

    Structure Technical Specification 

    Parameters Specifications

    Type Single axis tracking systemConfiguration Each structure will hold 20 modules.Material MS GalvanizedOveralldimension

    As per design, please refer Attachment C & D

    Coating Hot dip (galvanized) Minimum of 70 Micron sizeWi d ti 100 k /h (H i t l)

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    54/88

    Table -: Cables speficification

    Table -: Invertors specification

    Cable Technical Specification

    Parameters Specifications

    Standard IS 1554/694-1990

    Working voltage Up to 1100V

    Temperature range -15 Deg C to +70 Deg C

    Sizes Suitable sizes

    Inverter Technical Specifications

    Parameters Specifications

    Input Voltage range Vpmin=500 VDC to Voc=820 VDCRecommended solar power asinput

    500-580 kWp

    Output Voltage 510 VAC (Phase), 400 VAC (Line)

    AC outputs 5 Connectors (L1, L2, L3, N and PE)

    DC inputs 4 minimumOutput power 500 kW or above

    Output current distortion Less than 2%

    MPP range at DC rated output 500- 820 VDCMains frequency range 50 Hz +/- 0.4%Maximum Efficiency Greater than 95 %

    Operating modeMaximum Power Point Tracking (>1%accuracy)

    Power factor (Cosφ) 1Ambient temperature range 0-40 °CRelative humidity 95% non-condensing

    Protection Type IP20Automatic turn on

    When sufficient solar generator poweris available

    Resetting time after ACdeactivation

    Minimum 2 minutes

    Ground fault monitoring Reverse

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table -: Transformer specification at 33 kV side

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    55/88

    Parameters Specifications

    Transformer 1.25 MVA, 415/33 KV, 5 Nos

    No. of Phases 3

    Type Copper wounded transformer.

    Cooling type Oil cooled (ONAN)

    Installation Outdoor

    Primary voltage 415V

    HV 33000 volts

    LV 415 volts

    Vector Group Dyn 11

    Percentage impedance 5%

    Secondary voltage 33 kV at 33kV panelToppings and windings 33 kV side

    Regulation at unity power factor 1.32 %

    Regulation @ 0.8 power factor 4.68 %

    Max Efficiency @ 36% load >99%

    Efficiency (25~125% of load) @

    unity power factor 98.5~99%Efficiency (25~125% of load) @0.8 power factor

    98~98.9%

    Insulation class Class-A

    EnclosureWelded steel tank and bolted coverconstruction.

    First filling of oil Confirms to IS 335

    Applicable standards IS2026

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table -: Transformer specification for grid interfacing at 33/132 kV

  • 8/18/2019 09 - DPR for 5 MW Grid Connected PV Plant in Andhrapradesh.pdf

    56/88

    Parameters Specifications

    Transformer 6.50 MVA, 33/132 KV, 1 No.

    No. of Phases 3

    Type Copper wounded transformer.

    Cooling type Oil cooled (ONAN)

    Installation Outdoor

    Primary voltage 415V

    HV 33000 volts

    LV 11000 volts

    Vector Group Will match with the grid requirement

    Percentage impedance 5%

    System voltage 33kV at 33 kV panel

    Toppings and windings 11 kV side

    Regulation at unity power factor 1.32 %

    Regulation @ 0.8 power factor 4.68 %

    Max Efficiency @ 36% load >99%

    Efficiency (25~125% of load) @unity power factor 98.5~99%Efficiency (25~125% of load) @0.8 power factor

    98~98.9%

    Insulation class Class-A

    EnclosureWelded steel tank and bolted coverconstruction.

    First filling of oil Confirms to IS 335

    Applicable standards IS2026

    Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 

    Table -: Monitoring system specification


Recommended