+ All Categories
Home > Documents > Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Date post: 24-Oct-2015
Category:
Upload: amritmandal0191
View: 347 times
Download: 18 times
Share this document with a friend
Description:
This report includes all required technical details, financial assessment with Net Cash Flow from 1MW Solar PV project in India. From selection of Solar PV panels, inverters to selection of Isolator, grid synchronization & grid evacuation voltage, all detail can be found in this report.
Popular Tags:
28
Queries@ [email protected] Detail Project Report 1MW p SPV Power Plant www.renewpowerzone.in Page 1 Acknowledgement This analysis based report is done for the readers of my previous report 1MW Utility Scale SPV Power Plant, mainly for the readers from South region of INDIA as they are asking repeatedly about the probability and feasibility-technical & Financial-of a SPV power plant in their region. At the same time it’s not possible for me to design a report for each and every state from South India, so I took Chennai city. Also the previous report was not so detail, was very basic and meant to the readers who want to get an overview on how a utility scale power plant works. Now, in this report, I discuss about in depth. From panel’s selection to CB sizing all are presented in very detail. Hope, this time you get a strong knowledge on designing and estimation of 1MW solar PV power plant. Unlike the previous report, the financial aspect discussed at the end of the paper. In this paper, the financial assessment has done in very detail and considering the current scenario of SPV market including the cost of solar PV modules, inverters’ cost, cable, transformer etc. prices and the funding, interest rate. And if you have any queries or need clarification, please contact at [email protected] or [email protected] . Disclaimer The presented data here are NOT TAKEN from any copyright materials and not showing under my name. The meteo data collected from NASA website and NREL database which is free over the internet. Designing of PV system is totally based on the practical experience of the author. Assumption & Consideration Shading consideration: No shading has been considered at the site during the calculation design. So it is advised that at the time of execution, please check whether there is any kind of obstacle in the site which may cause partial/full shading on PV strings and/or PV array. If the shading occurs, then the estimated power generation will not match the actual power generated. Load Factor: It is assumed that the produced power from the PV plant will be fed to the local utility grid. So, while designing the system, no unbalanced load considered in 3 phase configuration. Meteo data: The calculation based on the meteo data collected from NASA website which is very reliable. Now, based on the co-ordinates the values have been presented in this report. So, total design is based on this data. For a different location (coordinates), the system design will differ. It is advised not to copy and implement the design without consulting the author or any certified PV professional because this design estimation is valid only for a particular site.
Transcript
Page 1: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 1

Acknowledgement

This analysis based report is done for the readers of my previous report 1MW Utility Scale SPVPower Plant, mainly for the readers from South region of INDIA as they are asking repeatedlyabout the probability and feasibility-technical & Financial-of a SPV power plant in their region.At the same time it’s not possible for me to design a report for each and every state from SouthIndia, so I took Chennai city. Also the previous report was not so detail, was very basic andmeant to the readers who want to get an overview on how a utility scale power plant works.Now, in this report, I discuss about in depth. From panel’s selection to CB sizing all arepresented in very detail. Hope, this time you get a strong knowledge on designing andestimation of 1MW solar PV power plant. Unlike the previous report, the financial aspectdiscussed at the end of the paper. In this paper, the financial assessment has done in very detailand considering the current scenario of SPV market including the cost of solar PV modules,inverters’ cost, cable, transformer etc. prices and the funding, interest rate.And if you have any queries or need clarification, please contact at [email protected] [email protected] .

DisclaimerThe presented data here are NOT TAKEN from any copyright materials and not showing undermy name. The meteo data collected from NASA website and NREL database which is free overthe internet. Designing of PV system is totally based on the practical experience of the author.

Assumption & Consideration

Shading consideration: No shading has been considered at the site during the calculationdesign. So it is advised that at the time of execution, please check whether there is any kind ofobstacle in the site which may cause partial/full shading on PV strings and/or PV array. If theshading occurs, then the estimated power generation will not match the actual powergenerated.Load Factor: It is assumed that the produced power from the PV plant will be fed to the localutility grid. So, while designing the system, no unbalanced load considered in 3 phaseconfiguration.Meteo data: The calculation based on the meteo data collected from NASA website which isvery reliable. Now, based on the co-ordinates the values have been presented in this report. So,total design is based on this data. For a different location (coordinates), the system design willdiffer. It is advised not to copy and implement the design without consulting the author or anycertified PV professional because this design estimation is valid only for a particular site.

Page 2: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 2

Site consideration: this design has been done by considering the PV modules & array will beground-mounted and the site-elevation angle taken 30 .

Cost Estimation: 1MW Solar PV power plant cost estimation has done considering the currentPV market scenario (Sept-Dec 2013), so after few months the cost may vary according themarket.CAD design & layout: I have not uploaded/attached the CAD design. If anybody interested insetting up the plant then only contact at the given e-mail ids to get the design file.

Transmission & wheeling losses: Here, in this report, while doing the technical assessment, thedistance from nearest substation to the 1MW solar PV power plant taken within 1.5 KM and sothe wheeling losses considered as 3% of total power transmission. And in the financialassessment, no wheeling charges have been considered.

Design Criteria: While designing & estimating the technical components & solutions, all therequired/applicable standard design codes have been considered. Mainly the IEC (InternationalElectrotechnical Commission) Codes, IS codes from BIS have been considered thoroughly.

Page 3: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 3

Contents1) Introduction 42) Project details 53) Location metrological details 64) Determination of optimum tilt angle 75) Solar power plant overview 86) Module selection & sizing 97) Inverter selection & sizing 118) Transformer selection 129) Other protective devices including switch gear details 1310) Cable sizing & selection 1411) Civil works details 1612) Performance analysis & simulation 1713) Timeline of the project 2114) Operation & maintenance structure of the plant 2215) Financial calculation, estimation of NCF, Payback period 2316) Guide on selection of various components 2717) Conclusion 2818) About the Author 28

Page 4: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 4

IntroductionIndia is densely populated and has high solar insolation, an ideal combination for using solar power inIndia. India is already a leader in wind power generation. In the solar energy sector, some large projectshave been proposed, and a 35,000 km2 area of the Thar Desert has been set aside for solar powerprojects, sufficient to generate 700 GW to 2,100 GW. Also India's Ministry of New and RenewableEnergy has released the JNNSM Phase 2 Draft Policy, by which the Government aims to install 10GW ofSolar Power and of this 10 GW target, 4 GW would fall under the central scheme and the remaining 6GW under various State specific schemes.

The Electricity Act, 2003, paves way for an innovative approach to solve our country’s power problems.It has paved the way for a competitive environment; open access to existing transmission anddistribution network to transmit electricity across regions; de-licensing of generation, captive power anddedicated transmission lines; licensing of distribution and supply companies and the restructuring ofState Electricity Boards.

The Ministry of Power has mandated to promote cogeneration and renewable sources for Powergeneration under Nodal agencies and hence it will play a major role in mainstreaming renewable energysector. The advantage or renewable resources includes their capacity to produce energy withoutproducing carbon-based warming and polluting agents into the atmosphere. The financial cost of itsapplications is not always cheap but if the environmental costs of using fossil are accounted for,renewable energy wins hands-down. There are also indirect savings on health and its costs as there areno harmful emissions.

In the above backdrop, YOUR COMPANY NAME has decided to set up a 1/1000 MW/KW Solar PowerPlant. This Detailed Project Report (DPR) brings out all technical details and overall costs justifying theselection of the project. The total power generation is envisaged to be 1050KW from Solar PhotovoltaicCell. It is a very important document that is required for Environmental Impact Assessment (EIA) studies,fixation of tariff, finalizing Power Purchase Agreement (PPA) and also for submission to FinancialInstitutions for obtaining project funding. The total project cost is expected to be Rs ___ Crores and theaverage cost of generation is expected to be Rs. 7.5/kWh (ASSUMED).

For this project, poly-crystalline technology based 3rd generation Solar PV modules will be used. Alongwith this, highly efficient, photon-tested string inverters going to be integrated to the system. Thesetechnologies are the best in the industry. So, It’s clear that our project is not compromising with thequality of the materials and or the components which obviously led this project to success.

Page 5: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 5

Client’ details

Country India

Location CHENNAI

Contact id [email protected]

Contact Person abc

company ABCXYZ

Purpose Power generation &distribution to State utility grid

Project DetailsType of installation Ground-mounted

Estimated array peakpower

1100KWp

Shading consideration Shade-free

Grid voltage 11KVPhase connection 3-phase

Grid frequency 50HzAvailable/required area 20000 m2(apprx)

Safety level IP65

Site Location/Layout

Site & Meteo DetailsLocation coordinates 10.5, 78.5 (assumed)

AmbientTemperature(0C)

Max Average Min28.5 27.2 25.5

Relative humidity 72.5%Daily Solar irradiation-

Horizontal5.19 KWh/m2/day

Atmospheric Pressure 100.1 kPA

Wind Speed 2.7 m/sEarth temperature Max Average Min

29.6 28.8 26.4Height from sea level 10m

Page 6: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 6

0

1

2

3

4

5

6

7

KWh/

m2/

day

Solar Irradiation

Solar Irradiation

23

24

25

26

27

28

29

30

31Air & earth temperature-monthly

Air temperature

earth temperature

Page 7: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 7

Optimum Tilt Angles For Solar PV Array Adjusted by Months

Jan Feb Mar Apr May Jun34° 26° 13° 0° 11° 14°

Jul Aug Sep Oct Nov Dec12° 5° 6° 19° 29° 35°

Figures shown in degrees from vertical

Irradiation Data on different tilt angles (respect to horizontal surface, KWh/m2/day)

Months 100 250 120

January 5.04 5.35 5.41February 5.98 6.16 6.16March 6.51 6.41 6.52April 5.76 5.39 5.85May 5.78 5.65 5.78June 5.28 5.22 5.29July 4.99 4.9 4.99August 5.09 4.9 5.1September 5.33 5.14 5.34October 4.67 4.69 4.71November 4.27 4.44 4.45December 4.5 4.78 4.84Annual avg. 5.26 5.25 5.36

* Here, 120 angle at AM1.5 has been chosen as fixed south faced model for the project

Winter

56° angle

Spring/Autumn

80° angle

Summer

104° angle

On the 21st December, the sun will rise 87° east of due south and set 87° west of due south.On the 21st March/21st September, the sun will rise 91° east of due south and set 91° west of duesouth.On the 21st June, the sun will rise 95° east of due south and set 95° west of due south.

Page 8: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 8

Solar PV System Design

System OverviewSPV Array Peak Power 1082KWp

No. of SPV strings 206Connection of PV modules in each string Series

Inverter 20KW MPPT based 3 phase string InverterInverter Type/Topology MPPT & Transformer Less

Total no. of Inverters 53Strings/Inverter 4/1

Modular Components

Components Specification Quantity Make

Solar PV modules Max Peak Power=250WpVoc= 36V ;Vmp= 29V

Isc= 9.25A ; Imp= 8.65A

4326

Non-Modular ComponentsComponents Electrical Specification Quantity MakeInverters 20KW, 3Phase &MPPT;

Vmax= 800V53

Transformer 1250KVA 1SCADA/MonitoringSystem

Integrated with RemoteMonitoring system web based

1

Circuit Breaker Inverter to Busbar= 46A 3p;busbar/Panel box totransformer= 1600A 3p;

531

DC Disconnect 1000V,20Amps 206Switch Gear Rated voltage=12KV;

Rated main busbarcurrent(Max)=1250A;SC withstand capacity = 25KA/3sDynamic capacity= 50KA

1

Distribution Panel NA 1Isolator Vmax= 12KV;

Max cont. current=1250A1

Cables DC Side= 10 mm2

AC Side=LT: 16mm2 & HT:185mm2

Page 9: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 9

Solar PV Module Specification & Array Sizing Details

Required Electrical Characteristics of SPV Modules

Design criteria IEC-61853-1

Watt Peak 250Wp

VOC 37.20V

VMPP 30.10V

ISC 8.87A

IMPP 8.30A

ModuleEfficiency/module area

15%

Power Tolerance ±2%

Technology Si-Poly

No. of cells 60 cells in series

Required Temperature Co-efficient Characteristics@ STC

NOCT (oC) 45 ± 2 oC

Module Efficiency (%/oC) -0.07 ± 0.01

Temp. Co-Eff. Of Pmax (%/oC) -0.43 ± 0.05

Temp. Co-Eff. Of Voc (%/oC) -0.34 ± 0.05

Temp Co-Eff. of Isc (%/oC) 0.065± 0.05

PV Module Behavior at different irradiance levelPV Parameters @ 1000W/m2 @800 W/m2 @ 400 W/m2

PMPP 249.8.2W 200.6 W 100.00VOC 37.2V 36.8 V 35.8VVMPP 30.1V 30.2 V 30.1VISC 8.87A 6.64A 3.55AIMPP 8.31A 7.10A 3.33AModule efficiency 15.54% 15.32% 15.27%Temperature co-eff -0.43%/0C -0.43%/0C -0.44%/0C

Required Operating Condition Details:Maximum SystemVoltage (IEC)

1000V

Maximum Fuse Rating 15A

Limiting ReverseCurrent

15A

Operating TempRange

(-10 to 60)0C

Max Static Load-front(Snow+Wind)

5500PA

Max Static Load-Rear(wind)

2500PA

Model design parameters

R shunt 250 ohm

R shunt (G=0) 2100 ohm

R series model 0.29 ohm

R series max 0.37 ohm

R series apparent 0.47 ohm

Page 10: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 10

Solar PV Array Sizing & Connection Detailsconditions At STC (250C) At Avg. Ambient temp. (280C)Suggested array Size 1100 KWp 1100KWp

Actual Solar PV Array Size 1082KWp 1100KWp

Watt Peak of each SPV module 250Wp 263WpTotal nos. of SPV modulerequired

4326 4326

Total nos. of strings 206 206Nos. of SPV modules in eachstring

21 21

SPV connection in each string Series SeriesString voltage (VMPP) 609V 630VString current (ISC / IMPP) 8.87A/8.3A 9.51A/8.82AConnection of strings Parallel ParallelArray voltage (VOC / VMPP) 780V/635V 750V/620VArray current (ISC / IMPP) 1830A/1710A 1960A/1816A

Page 11: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 11

Detail Solar Inverter Specification & Design Details

Inverter Type String Inverter (MPPT)Quantity 53INPUT (DC)Max. Power 23KW

Max absolute Input Voltage 1000VStart Voltage 350VNominal MPP voltage range 490V-800V

Max Input Current per string 41.5ANos. of Independent MPP inputs/stringsper MPP inputs

1/6

OUTPUT (AC)Rated Output Power 20000WMax. Apparent AC Power 20000VAPower Threshold 20WNominal AC Voltage/range 3/N/PE;230/460VAC Power Frequency/ range 50HzMax. output current 3x29APower factor at rated power 1Feed-In phases/connection phases 3/3EfficiencyMax. Efficiency 98.7%Protection DetailsDC Disconnect AvailableDC Surge Arrester AvailableProtection Class I (as per IEC 62103)Total harmonic distortion <1.8%Operating Temperature range -25◦-60◦CNoise Emission <35dBSelf Consumption <25WCooling option Forced Air-cooledProtection type IP65 (as per En 60529)Remote Monitoring SystemUser Interference & Communication

With RS-485/Ethernet

Electrically Isolated relay output AvailableStatus Display AvailableInverter to inverter communication AvailableAnti-islanding protection AvailableInverter connection detailsTotal nos. of inverter 53Nos. of strings per inverter 4Connection of strings/inverter ParallelInter-inverter connection Parallel into Cu busbarInter-Inverter isolator Provided

Page 12: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 12

Transformer SizingDesign Criteria IS-2026 / IEC-60076Transformer type Power transformer, core type with oil-immersed ;

650C winding temp riseCooling type ONAN(Oil Natural Air Natural)Rated KVA 1250KVAHigh Voltage rating 11000VLow Voltage Rating 460VNominal impedance 4.7%Impedance tolerance 7.5%Nominal secondary amps 1250AMax SC withstand current 20KA/3sHV connection DELTALV connection WyeOperating frequency 50HzTap changer ±5% of full load capacity

Protective devices

components Specification QuantityDC Disconnects String to inverter= 1000V, 15A; 2 pole

(As per IEC-60947)206

Switch gear Rated voltage=12KV;Rated main busbar current(Max)=1250A;SC withstand capacity = 25KA/3sDynamic capacity= 50KAIP55

1

Circuit breakers (MCCB)(NOT required if Inverter has inbuiltprotection)

Inverter to Busbar= 60A 3p;busbar/Panel box to transformer= A 3p;

531

Main Isolator (HT side)Design criteria IS-9921/IEC-129

Operating frequency 50hz ±3% Rated peak withstandcurrent (KA peak/rms)

63.5KA

Nominal system voltage 11KV 1.2/50 micro sec lightingwithstand Volts (KV peak)

To earth andisolating poles

Across the isolatingdistances

170 195Max system voltage 12KV Rated 1 minute power

frequency withstandvoltage(KV r.m.s)

To earth andisolating poles

Across the isolatingdistances

75 85

Max continuous current 2500A No. of poles 3

Rated SC current for 3s 40KA Min creepage distance 320mm

Page 13: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 13

Cable Sizing

DC Side Cables (strings to inverter)Design criteria IEC-60811 & IEC-60216Cable material CopperSingle cable length per string to inverter 70 ftCross section per string 4 mm2

Voltage drop 0.18VRelative power loss reference to Max DC power 0.07%Max withstand temp. Normal condition Short-circuited

condition900C 2500C

Max withstand current capacity 42KA/1secConductor type StrandedInsulation material XLPELT Cables (Inverters to busbur/distribution panel)Design criteria IEC-60228 & IEC-60811Cable material CopperMax Single cable length per inverter to panel box 60 ftCross section 16 mm2

Voltage drop (3phase) 0.46VRelative power loss reference to Max AC nominalpower

0.23%

Max withstand temp Normal condition Short-circuitedcondition

900C 2500CMax withstand current capacity 2KA/1secConductor type StrandedInsulation PVCHT Cables (from distribution panel to feed-in point)Design criteria IEC-60502Cable material AlCable length from distribution panel to feed-in point

25 ft

Cross section 185mm2

Voltage drop (total) L1 1.37VL2 1.37VL3 1.37V

Relative power loss reference to Max ACpower

0.57%

Voltage grade 11KV(UE), heavy dutySC withstand current capacity 26KA @1sInsulation XLPE

Page 14: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 14

Line LossesDC Side AC Side Total

Total cable length 8120 ft 3070 ft 11180 ftCable cross section 4 mm2 16 mm2 +185 mm2 4 mm2 +16 mm2 +185

mm2

Power loss @ nominaloperation

35 KW 5 KW 40KW

Relative power loss @nominal operation

0.07% 0.76% 0.83%

Busbar constructional AnalysisBusbar material Main busbar Auxilury busbar

Al alloy E91 Egrade

Copper

Busbar insulation Fully insulated

Busbar length Main Aux3.5mt 0.75mt x 52

Earthing bus materials GS (IEEE std. 80/IEC-60439-1)

Earthing & Lighting ProtectionDesign Criteria IEEE Standard-80

Grounding System Earth grid resistance Less than 10 ohm

Placing of earthelectrode

Earth Pit

Earth Electrode sizing

Physical Parameters Heavy duty GI pipes, 32mm dia, 3mt long

Material Galvanized Steel(GS), flat typeMin depth of earth pit 600mmComponents grounding Min 75x10mm GS stripLightning Protection

Design criteria As per IEC-62305Placing On the highest panel of arrayDimension 40mm dia with 3m height (vertical air

termination)

Page 15: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 15

CIVIL WORKS

Live Loads estimation of control room + admin building (as per IS 875:1987)parameters details RemarksRoof load 1750 kg/ m2 As per IS-456

Ground floor load Control room 18000kg/m2 As per IS-456Office 5000kg/ m2 IS-456

Piping load 50 kg/ m2 As per IS-456Electrical + HVAC 26 kg/ m2 As per IS-456

Seismic load As per IS-456Roof drainageRoof drain heads 6Construction detailsInterwall

Cement : Sand 1:6Interwall thickness 230mmParapet walls

Cement : Sand 1:4thickness 115mm

Steel work Reinforced bars will be providedas per IS 800:2007

PV Array mounting & constructional detailsPV tilted angle (optimized) 130 (@1070 W/m2/day)

Mounting type Ground mountedOverall dimension As per design

Foundation Plain cement concrete (PCC)Foundation grade 1:5:10

Wind load 9.72 Km/hrFixing type SS 304 fasteners

Total Land required 5 acres

Page 16: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 16

System Performance Analysis & Simulation

Solar Paths at site on monthly basis Reference Incident energy in collector plane

Normalized production per installed KWp

Page 17: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 17

Performance Ratio (PR) Normalized Production & Loss factor

Daily System Output Energy SPV Array Power Distribution

Page 18: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 18

Page 19: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 19

Overall Power plant performance SummeryTotal no. of PV modules 4326 (250Wp)Total nos. of Inverters 53 (20KW)

Max DC input per Inverter 21KWNominal PV power 1082 KWp

Max. PV power output 1027 KWdcNominal AC power 1060KWac

Max operating power @ STC 962KWacMax operating power @Ambient Temp. 1027KWac

Plant production 1655 MWh/yearSpecific production 1526KWh/KWp/year

Normalized production 4.2 kWh/KWp/dayArray losses 0.87 KWh/Kp/day

Overall losses 0.22 KWh/KWp/dayPerformance ratio 0.80

Page 20: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 20

Time line of the project

Design

•Preparation of design & estimation of the plant•15 working days required.

Landacquisition

•As per design requirement, proper land selection & acquisition processed.•Time required 1 month

PPA

•Power Purchase Agreement(PPA) with private power purchaser need to be finalized at a feasible rate.•Required time is 15 working days

DPR

•Preparation of Detailed Project Report including technical feasibility of the project prepared.•Time required 6 working days.

finance

•Arrangement of finance/fund for the project from nationalized or private financing agency with significant interest rateand equity share will be finalized.

•Required time for this stage is 1 month.

procurement

•After finalizing PPA and arrangement of fund for the project, procurement work starts including preparation & finalizing ofvendor selection, BOM, BOQ, order placing, follow-ups of delivery to site/warehouse.

•Estimated time for this step is 1 month.

construction

•After the processing of procurement, first civil construction at the site starts for PV mounting structure set-up andcontrol-room, administrative building. Finishing the civil works, PV installation & all electrical construction works includingthe Grid Evacuation will be processed.

•Estimated time for this whole work is 2 months.

commissioning

•Commissioning of the plant by authorized govt. body or certified 3rd party will be done followed by Completion of projectexecution.

•required time for this step is 6 working days.

Page 21: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 21

Operation & Maintenance of Plant

Why do we need an O&M for Solar PV power plant?As every plant needs a regular maintenance work to make it functional & in well-condition, soin this case also, a PV power plant also requires a sound & efficient operation & managementteam to perform all the work after plant commissioning.A detailed structure of O&M team has been provided here in a hierarchy model to demonstratein a simpler way.

Plant manager

Maintenanceengineer(E&IE)

Technician1

skilled labour1

Technician2

skilled labour2

control roomtechnician

maintenanceEngineer(Mech)

Skilled labour1 skilled labour2

operationmanager

Supply chainexecutive

Accountsexecutive

Page 22: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 22

Financial Analysis & feasibility

Initial Investment in terms of components’ cost & service charges

Sl.No.

Components/services Total cost(in INR)

Remarks

1. Solar PV modules 45,100,000 41rs/Watt peak2. Solar inverters 11,660,000 11rs/Watt peak3. Transformer 2,940,000 From international vendor4. Protective devices 1,200,000 From international vendor5. Wires/Cables 1,000,000 Considering IEC codes & ISO

certified6. SCADA/RMS 1,000,0007. Project execution & commissioning 2,000,0008. Construction works 4,000,0009. Grid evacuation 1,000,000 (assumed) Assumed because of having

no sufficient data10. Other official works 1,000,000 Subject to change as per

rulesTotal Project investment 70,900,000 INR

Total expenses over the year for plant O&M and staffing = 2,000,000This expense is considered for regular maintenance cleaning of PV array, checking the status ofinverter, cable-fault checking, emergency maintenance & replacement of components andannual salaries of O&M team of the plant.

Loan Interest rate is @12% over 70% of total project cost which shall be completed within next7 years (the rest 30% as equity shares).

Estimated time period 7 years 10 yearsTotal Loan amount 49,630,000 49,630,000Interest rate 12% 12%EMI 876,110 712,050Monthly interest 285,270 298,460total Interest paid 23,962,830 35,815,600

*all the amounts are considered in INR currency.

Page 23: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 23

Detailed Analysis of Installment, EMI, Interest of the 70% projectfinance/fund

Sl.No.

Installments EMI Monthly principle Monthly Interest

1) 0 0 0 02) 1 876,105 379,805 496,3003) 2 876,105 383,603 492,5024) 3 876,105 387,439 488,6665) 4 876,105 391,314 484,7926) 5 876,105 395,227 480,8787) 6 876,105 399,179 476,9268) 7 876,105 403,171 472,9349) 8 876,105 407,203 468,90310) 9 876,105 411,275 464,83111) 10 876,105 415,387 460,71812) 11 876,105 419,541 456,56413) 12 876,105 423,737 452,36914) 13 876,105 427,974 448,13115) 14 876,105 432,254 443,85116) 15 876,105 436,576 439,52917) 16 876,105 440,942 435,16318) 17 876,105 445,351 430,75419) 18 876,105 449,805 426,30020) 19 876,105 454,303 421,80221) 20 876,105 458,846 417,25922) 21 876,105 463,434 412,67123) 22 876,105 468,069 408,03624) 23 876,105 472,749 403,35625) 24 876,105 477,477 398,62826) 25 876,105 482,252 393,85327) 26 876,105 487,074 389,03128) 27 876,105 491,945 384,16029) 28 876,105 496,864 379,24130) 29 876,105 501,833 374,27231) 30 876,105 506,851 369,25432) 31 876,105 511,920 364,18533) 32 876,105 517,039 359,06634) 33 876,105 522,210 353,89635) 34 876,105 527,432 348,67436) 35 876,105 532,706 343,39937) 36 876,105 538,033 338,07238) 37 876,105 543,413 332,69239) 38 876,105 548,847 327,25840) 39 876,105 554,336 321,769

Page 24: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 24

41) 40 876,105 559,879 316,22642) 41 876,105 565,478 310,62743) 42 876,105 571,133 304,97244) 43 876,105 576,844 299,26145) 44 876,105 582,613 293,49246) 45 876,105 588,439 287,66647) 46 876,105 594,323 281,78248) 47 876,105 600,266 275,83949) 48 876,105 606,269 269,83650) 49 876,105 612,332 263,77351) 50 876,105 618,455 257,65052) 51 876,105 624,640 251,46653) 52 876,105 630,886 245,21954) 53 876,105 637,195 238,91055) 54 876,105 643,567 232,53856) 55 876,105 650,002 226,10357) 56 876,105 656,502 219,60358) 57 876,105 663,068 213,03859) 58 876,105 669,698 206,40760) 59 876,105 676,395 199,71061) 60 876,105 683,159 192,94662) 61 876,105 689,991 186,11463) 62 876,105 696,891 179,21464) 63 876,105 703,860 172,24665) 64 876,105 710,898 165,20766) 65 876,105 718,007 158,09867) 66 876,105 725,187 150,91868) 67 876,105 732,439 143,66669) 68 876,105 739,763 136,34270) 69 876,105 747,161 128,94471) 70 876,105 754,633 121,47272) 71 876,105 762,179 113,92673) 72 876,105 769,801 106,30474) 73 876,105 777,499 98,60675) 74 876,105 785,274 90,83176) 75 876,105 793,127 82,97977) 76 876,105 801,058 75,04778) 77 876,105 809,068 67,03779) 78 876,105 817,159 58,94680) 79 876,105 825,331 50,77481) 80 876,105 833,584 42,52182) 81 876,105 841,920 34,18583) 82 876,105 850,339 25,76684) 83 876,105 858,842 17,26385) 84 876,105 867,431 8,674

Page 25: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 25

Net Cash Flow/year Estimation (all amounts are in INR)Initial Investment 70,900,00Expenses for O&M per year 2,000,000Total amount paid/year for loan(7 years termconsidered)

10,513,320

Tolerance factor 2%Total amount to be paid per year 12,763,600Energy generated per year 1,655MWhPPA rate for next 12 years 7.5rs/KWhREC floor price 12,000rs/MWh (approx.)Gross cash flow through PPA 12,412,500Gross cash flow through REC trading 19,860,000Net Cash Flow (NCF) per year 21,759,180

0

100000

200000

300000

400000

500000

600000

700000

800000

900000

1000000

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85

Installment

EMI

Monthly Principle

Monthly Interest

Page 26: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 26

NET CASH FLOW & PAY BACK PERIOD

Now according to Discounted Cash Flow method (considering @10% DCF)

years Present value of rs.1 @10%1 0.909 19,779,094.622 0.826 17,973,082.683 0.751 16,341,144.184 0.683 14,861,519.945 0.621 13,512,450.786 0.564 12,272,177.527 0.513 11,162,459.348 0.467 92,145,357.809 0.424 83,660,898.56

10 0.386 76,162,987.84

So, Pay Back Period= 6 years 1 month (approx.)

Page 27: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 27

Most suitable vendors/suppliers of the project componentsSolar PV modules 1. Vikram Solar

2. Waaree Energies3. Sova Power4. Canadian Solar5. Trina Solar6. First Solar

Inverter 1. Power One2. SMA3. Smart Power4. REFusol5. Delta6. Schneider Electric

Transformer 1. ABB2. Schneider Electric3. Ascott transformer4. Voltech

Switch gear 1. Schneider Electric2. Megawin

DC Disconnect 1. Schneider ElectricCircuit breaker 1. Megawin

2. ABB

SCADA/RMS 1. DrakerCables 1. Havells

2. Finolex cables3. RR Kabels4. Anchors

Isolator 1. ABB2. Schneider Electric3. Megawin

Page 28: Detail Project Report (DPR) : 1MW Utility Scale Solar PV Power Plant

Queries@ [email protected]

Detail Project Report1MWp SPV Power Plant

w w w . r e n e w p o w e r z o n e . i n Page 28

Conclusion

I’d like to thank you for reading the whole paper. Hope you have got clear view on design &estimation of 1MW utility scale Solar PV Power Plant. Though I have discussed about thetechnical part as well as the financial part in detail, I might have been forgot to add anythingmore important. So, you are most welcome to give your valuable feedback & suggestion on thisreport. At the end, I discussed about some companies for the components. I have chosen thesecompanies because their products are fulfilling my design criteria. It is not that I’m representingthese companies and their products.

About Myself: I’m a Solar PV professional currently working with a solar EPC company asProject Engineer. I’ve done B.Tech in Electrical Engineering & holding a PG certificate inAdvanced Solar Energy from delft Technical University, Netherlands.

Personally I provide technical consulting including site survey, technical design, CAD design,preparation of DPR, guide in procurement & Construction.

You can review my papers/reports at www.wbut.academia.edu/amritmandal

Connect to my professional profile in linkedIn at –http://www.linkedin.com/pub/amrit-mandal/55/667/a3

Read solar PV related articles & learn about new technologies at- www.renewpowerzone.in

Contact me or send your queries at- [email protected] , [email protected]

THANK YOU


Recommended