Date post: | 23-May-2018 |
Category: |
Documents |
Upload: | truongkien |
View: | 217 times |
Download: | 0 times |
Bass, B.J., and Beaver, J.L. 1
Comparison of Field Measurements from Deep Burial Test Installation of Two 24 in. Diameter1
Corrugated High Density Polyethylene Pipes with 2D Soil-Structure Interaction Finite Element2
Analysis34
5
6
7
Corresponding Author: Brent J. Bass, Simpson Gumpertz & Heger Inc., 41 Seyon St., Building 1, Suite8
500, Waltham, MA 02453, phone: 781.907.9327, fax: 781.907.9009, [email protected]
10
Jesse L. Beaver, Simpson Gumpertz & Heger Inc., 41 Seyon St., Building 1, Suite 500, Waltham, MA11
02453, phone: 781.907.9272, fax: 781.907.9009, [email protected]
13
14
15
Submission Date: 1 August 201516
Word Count: 4,13217
Figure Count: 518
Table Count: 819
Total Equivalent Word Count: 7,38220
21
Bass, B.J., and Beaver, J.L. 2
ABSTRACT1
A field test program was developed and implemented to monitor two 24 in. diameter corrugated high-2
density polyethylene pipes under 20 ft of fill. The test compared performance of two corrugated pipe wall3
geometries and provided data for comparison to design calculations and finite element models. Test pipes4
were installed in compacted sand embedment overtopped by granular stone dust backfill placed in5
accordance with manufacturer requirements. Backfill densities were measured by nuclear density tests.6
The authors instrumented the pipe sections with bonded resistance strain gages and displacement sensors,7
and soil pressure cells embedded in the backfill above the pipes. Instrumentation data were recorded8
during the installation and backfilling, continuing for over 10,000 hrs. The authors modeled the9
installation using two-dimensional (2D) soil-structure interaction (SSI) finite element analysis in10
CANDE-2007 software for comparison to field-measurements. Instrumentation configuration and11
measurements were compared to AASHTO design calculations in a TRB 2015 paper. This paper12
compares measured values at the end of the test to theoretical results from finite element analysis.13
14
15
Bass, B.J., and Beaver, J.L. 3
INTRODUCTION1
Two 20 ft long parallel runs of instrumented 24 in. diameter corrugated high-density polyethylene2
(HDPE) pipes were installed under 20 ft of fill in late spring 2012. The two runs of pipe were installed in3
a single partial trench (positive projecting embankment) with 6 ft clear spacing and embankment backfill4
placed above (Figure 1). Two locations were instrumented with displacement transducers, strain gages,5
and soil pressure cells. The installation had active instrumentation for initial installation to over6
10,000 hrs after completion of embankment fill placement.7
8
9
FIGURE 1 As-built installation cross-section looking north.10
11
The instrumented pipes were installed in compacted sand embedment overtopped by granular12
stone dust backfill placed in accordance with manufacturer requirements. Backfill densities were13
measured during installation using a nuclear density gage, allowing for determination of the soil load14
above the pipe and confirmation of target embedment stiffness. Instrumentation data were recorded15
during backfill placement through the end of the test. Detailed information about instrumentation,16
including measurements and comparison to AASHTO design (1) are presented in (2).17
A two-dimensional (2D) soil-structure interaction (SSI) finite element model (FEM) of the18
installation was developed in CANDE-2007 (CANDE) (3). CANDE model inputs include pipe material19
and geometry, soil types and compaction, embankment geometry, and construction increments. The FEM20
uses a non-linear soil model to represent embedment soil stiffness. Outputs of interest from the pipe21
model include hoop thrust, bending moment, and displacement. Output for the soil includes vertical and22
lateral pressures.23
24
PIPE SAMPLES, CORRUGATION, AND MATERIAL PROPERTIES25
We instrumented four 10 ft lengths of pipe in our laboratory. We installed instrumentation 2 ft from the26
ends of each 10 ft length, then joined them to form two 20 ft lengths with the instrumented sections near27
the center joint. The 20 ft lengths were installed in two parallel runs, Runs A and B. Runs A and B had28
different corrugation geometries. Run A had an overall deeper corrugation, and Run B had a greater unit29
area, moment of inertia, and pipe stiffness (EI/0.149R3) (Table 1).30
Bass, B.J., and Beaver, J.L. 4
TABLE 1 Profile Section Properties1
2
PipeRun
Area, A(in.2/in.)
Moment ofInertia, I(in.4/in)
Distance fromCentroid to
Inner Fiber, yin
(in.)
Distance fromCentroid to
Outer Fiber, yout
(in.)
CorrugationDepth,yin + yout
(in.)
PipeStiffness,
PS(lb/in./in.)
A 0.290 0.132 0.674 1.373 2.047 36.6B 0.353 0.139 0.738 1.070 1.808 38.4
3In addition to the pipe section property inputs, CANDE requires input of pipe material properties4
(Young’s modulus). For comparison to the approximately 10,000-hr test, we used a modulus5
representative of 10,000-hr load duration from ASTM D6992 (4) tensile creep tests. These tests were6
performed at a constant stress of 500 psi, similar to the 510 psi maximum expected pipe service stress.7
From the test results, we estimated 30,000 psi as an appropriate 10,000-hr modulus for the model.8
9
TEST INSTALLATION10
11
General Description12
The test site consisted of a subtrench plus embankment installation (positive projecting embankment) to13
facilitate 20 ft of soil over the instrumented sections. The two runs were laid in the north-south direction14
with blind-end bulkheads at the north ends. 30 ft of non-instrumented pipe was added at the south end of15
each run to provide man-access from the embankment toe. The installation included trench drainage and16
ventilation pipes.17
18
Soil Materials, Placement, and Timeline19
Table 2 provides a soil materials summary including results from grain size distribution tests and20
maximum dry densities per the modified Proctor test (MPD) in accordance with ASTM D1557 (5)21
Procedure C. ASTM D6938 (6) wet unit weight tests were performed on the bedding, embedment, and22
embankment fill.23
24
TABLE 2 Soil Material Summary25
26
Material DescriptionASTM D2487 (7)
or D2488 (8)Classification
AASHTOM145 (9)
Classification
Maximum Dry Density,Modified Proctor Test
(pcf)
In Situ Firm, Stable,Well-Graded Sand
with Silt
SW-SM(D2488)
N/A N/A
Bedding andEmbedment
Well-Graded Sandwith Silt
SW-SM(D2487)
A-1-B 120.5
EmbankmentFill
Granular Stone Dust SM(D2487)
A-1-B 135.5
N/A = Data not available as test was not performed for in situ soil.27
The pipes were installed with 9 in. of well-graded sand with silt bedding, compacted by two28
passes of a Wacker WP1550 walk-behind vibrating plate compactor. Three field compaction tests were29
performed on the bedding to determine the average wet unit weight of 114 pcf, equal to 92% MPD.30
Embedment soil (well-graded sand with silt) was placed in 6 in. nominal lifts to 2 ft over the31
pipes and the soil pressure cells were installed. Each embedment layer was compacted with one pass of32
the plate compactor. Workers shovel-sliced the embedment material into the haunches. Fifty-three field33
Bass, B.J., and Beaver, J.L. 5
compaction tests were performed on the embedment resulting in a weighted-average wet unit weight of1
106 pcf or 83% MPD.2
Embankment fill (granular stone dust) was placed in 1 ft lifts. The first four lifts were compacted3
with a single pass of a roller compactor. The final fill depth of 20.6 ft at the top of embankment was4
achieved 12 days after placement of the initial embedment lift. Sixty-four field compaction tests were5
performed on the embankment fill to determine a weighted-average wet unit weight of 129 pcf, equal to6
89% MPD.7
8
Instrumentation9
Test pipe instrumentation consisted of displacement transducers, strain gages, and soil pressure cells. We10
instrumented two vertical cross-sections (Sections 1 and 2) of each pipe run. The instrumented cross-11
sections were positioned 2 ft north (Section 1) or south (Section 2) of the joint between the two 10 ft12
sections. Instrumentation details for each sensor type are provided in (4). An instrumentation cross-13
section at Section 1 with sensor naming conventions is shown in Figure 2.14
15
16
FIGURE 2 Section 1 instrumentation and sensor naming conventions.17
18
Displacement Transducers19
We measured displacements and circumferential shortening using draw wire rotational resistance20
displacement transducers (draw wires). Section 1 (Figure 3) included vertical, horizontal, and two21
diagonal diameter measurements, plus a circumferential shortening draw wire (housing near right of22
figure). Section 2 had only vertical and horizontal diameter measurements.23
24
Bass, B.J., and Beaver, J.L. 6
1
2
FIGURE 3 Instrumentation at Section 1.3
4
Strain Gages5
We installed sixteen bonded resistance strain gages, eight per pipe run, at Section 1. We installed four6
gages at each springline, two on the interior surface corrugation valley and two on the exterior surface7
crest (Figure 2).8
9
Soil Pressure Cells10
We installed three vibrating wire pressure transducer soil pressure cells within the embedment soil. We11
installed one soil pressure cell 1.15 ft above and centered over the top of each pipe profile (Figure 2), 1 ft12
north of Section 1, with the third pressure cell centered between the pipes.13
14
MEASUREMENT RESULTS15
16
Manual Measurements17
We measured inside diameter and internal circumference by man-entry approximately 10,250 hrs after18
completing embankment construction (Table 3). We measured the diameter using a tape measure with19
1/16 in. increments. We measured circumference with a π-tape, directly reading an equivalent diameter 20
for a circular shape. Deflection data is presented as a change in diameter relative to Day 0 π-tape 21
measurements (23.75 in. for Run A and 24.16 in. for Run B). Negative measurements indicate a reduction22
in diameter or circumference.23
24
25
Bass, B.J., and Beaver, J.L. 7
TABLE 3 Pipe Deflection and Circumferential Shortening from Manual Measurements at1
10,000 hrs2
3
Measurement Run A Run BSection 1 Section 2 Section 1 Section 2
Vertical Deflection (%) -3.7 -4.2 -2.8 -4.3Horizontal Deflection (%) 0.6 1.1 0.4 0.9Circumferential Shortening Strain (%) -1.0 -1.1 -0.9 -0.8
4
Electronic Measurements5
We started data collection on pipe sensors on Day 0 with unloaded pipes and on soil pressure cells when6
the fill depth allowed for their installation. Data acquisition continued for 10,000 hrs after completion of7
earthwork.8
Draw Wires9
Draw wire data at the end of the test is presented in Table 4. Negative deflection is a decrease in diameter.10
Displacement data was generally stable for the 10,000 hrs of data acquisition on all but four gages:11
• Draw Wires B-2-H and A-1-H stopped functioning on Days 390 and 419, respectively.12
• Draw Wire A-2-V had a -0.3% change in vertical deflection in a 17-hr period on Day 323 then13
remained around -3.7%. We are unsure of what caused this sudden change and omit this data from14
Table 4.15
• Draw Wire B-1-H showed a steady reduction in horizontal deflection over the last six months,16
reaching 0.0%.17
TABLE 4 Draw Wire Deflection or Circumferential Shortening Strain at 10,000 hrs1819
Location Draw Wire No. Run A(%)
Run B(%)
Section 1, Vertical A/B-1-V -3.4 -3.3Section 2, Vertical A/B-2-V -- -3.6Section 2, Horizontal A/B-2-H 0.6 --Section 1, Diagonal A/B-1-D1 -0.5 -0.7Section 2, Diagonal A/B-1-D2 -1.2 -0.7Section 1, Circumferential A/B-1-Circ -0.8 -0.9
20
Vertical deflections were -3.3% to -3.6%, similar to manual measurements. The one horizontal21
draw wire still working at the end of the test showed a value much lower than the vertical deflection22
results but similar to manual measurements. The two pipe runs had similar magnitudes of circumferential23
shortening strain from draw wires and manual measurements.24
Strain Gages25
Six of the sixteen electrical resistance strain gages failed during backfilling. All failed gages were inside26
gages, four on Run A and two on Run B. An additional inside gage failed on Run B in the first two27
weeks, leaving B-In-W-2 as the only functional inside gage. Seven strain gages remained functional28
throughout the test. Gage failure can be attributed to difficulty bonding to the highly curved, smooth29
HDPE surface in these small diameter pipes, high thrust strains, curvature changes from bending, large30
service temperature ranges, moisture, and external embedment impingement. Table 5 presents strain gage31
data at 10,000 hrs. Negative values show compression from combined thrust and bending.32
33
TABLE 5 Strain Gage Measurements at 10,000 hrs34
Bass, B.J., and Beaver, J.L. 8
1
Location Gage No. Run AStrain
(%)
Run BStrain
(%)
Inside Surface, West Springline, Section 2 A/B-In-W-2 -- -0.28Outside Surface, East Springline, Section 1 A/B -Out-E-1 -0.72 --Outside Surface, East Springline, Section 2 A/B -Out-E-2 -0.83 -0.39Outside Surface, West Springline, Section 1 A/B -Out-W-1 -0.41 --Outside Surface, West Springline, Section 2 A/B -Out-W-2 -0.06 -0.49
2
Pairs of gages at nearby locations (different by 1 or 2 in their numbering) should show a similar3
response. The two Run A west springline gages (A-Out-W-1 and A-Out-W-2) registered very different4
strains of -0.41% and -0.06%. Gage A-Out-W-2 showed a consistent reduction in strain from 2,000 hrs to5
10,000 hrs that indicates likely gage failure. We exclude the -0.06% value from further discussion.6
Soil Pressure Cells and Vertical Arching Factor7
Soil pressure cell data can be used to approximate a vertical arching factor (VAF). VAF is the ratio of the8
soil load carried in the wall of a buried structure divided by the weight of the soil prism above the pipe9
outside diameter to the ground surface. The VAF may be calculated using springline hoop thrust to10
determine the soil load in the pipe wall. The VAF can also be calculated as the ratio of the soil pressure11
directly over the pipe divided by the free field vertical pressure (unit weight times height of fill).12
For a fill height of 20.6 ft, with embedment material to 2 ft above the pipes, and the average13
moist unit weights given above, the free-field vertical pressure at the soil pressure cell locations, 1 ft14
above the pipes, is 17.4 psi. Measured vertical soil pressures at the end of the test were 11.2 psi, 13.8 psi,15
and 20.1 psi for Run A, Run B, and between the pipe runs, respectively. Using soil pressure to calculate16
VAF gives VAF = 0.64 for Run A, VAF = 0.79 for Run B, and a ratio of 1.16 times the free field pressure17
for the soil column between pipes. Some additional arching may occur in the 1 ft height between the18
pressure cells and the top of pipes.19
20
CANDE FINITE ELEMENT ANALYSIS21
22
Model Description23We created a two-dimensional plane strain FEM of the test installation using the computer program24
CANDE. The model incorporates nonlinear soil behavior using the Duncan/Selig hyperbolic model with25
soil properties developed by Selig for SIDD concrete pipe installations and later adopted by AASHTO.26
We modeled all placed soils as SW soils in CANDE, representative of the sand embedment and27
stone dust backfill used. We based soil compaction levels in the model on field density test28
measurements. Compaction levels for Duncan/Selig soil model parameters are based on maximum29
density per the standard Proctor test (11). For example, SW95 soil is representative of the sand bedding30
material compacted to 95% maximum dry density per the standard Proctor test (95% SPD). Recall that31
field density tests reported modified Proctor densities (MPD). To convert from modified to standard32
Proctor densities, we increased the reported compacted density by 5%. Thus, 90% MPD in the field33
measurements is 95% SPD for input into CANDE. Model soil properties are summarized in Table 6.34
Figure 4 shows the model finite element mesh near the pipes with soil zones depicted by different colors.35
36
37
Bass, B.J., and Beaver, J.L. 9
TABLE 6 Soil Properties used in CANDE Finite Element Model1
2
Zone MaterialColor inModel
Description Soil Model UnitWeight
(pcf)
In Situ Red Firm, stable, well-graded soil Linear Elastic, E = 3,000 psi 120Bedding Orange Well compacted sand Duncan/Selig, SW95 114Haunches Blue Sand manually worked into place Duncan/Selig, SW80 106Embedment Yellow Moderately compacted sand Duncan/Selig, SW90 106Backfill Green Compacted stone dust Duncan/Selig, SW95 129
3
4FIGURE 4 CANDE Finite Element Model Mesh near Pipes (Green Soil Continues to 20.6 ft Total5
Cover (Not Shown)).6
7
The FEM includes incremental construction of soil lifts around and above the pipe. The initial8
construction increment consisted of the red in situ soil. We then placed soil fill (including bedding) at9
6 in. to 9 in. lifts around and above the pipes until reaching 6 ft of cover. Embankment fill was placed in10
12 in. lifts to 20.6 ft. We modeled the soil as fully bonded to the pipe.11
Boundary conditions along the sides of the model restrain lateral displacement and allow free12
vertical displacement. Fixed boundary conditions along the bottom of the model restrain movement in13
both the vertical and horizontal directions. We did not include construction live loads or compaction14
forces. Soils were placed at the compacted density. The soil model allows for increased soil stiffness15
with increased confinement provided by the fill above.16
We modeled the pipes using the linear-elastic basic pipe type in CANDE with beam element17
input properties including the area and moment of inertia shown in Table 1. We included a gravity line18
load for the pipe beam elements of 0.0119 lb/in. based on a 65 pcf unit weight for HDPE. We used a19
30,000 psi elastic modulus to evaluate results that correspond to the 10,000 hr test based on tensile creep20
testing.21
Bass, B.J., and Beaver, J.L. 10
Model Results1CANDE model outputs, including thrust, moment, and deflection are presented in Table 7 along with2
computed wall strains.3
4
TABLE 7 CANDE Model Results Summary(a)56
Behavior Run A Run BCrown(b) Springline(b) Crown(b) Springline(b)
Thrust (lb/in.) -60.5 -111.1 -66.6 -121.8Moment (in.-lb/in.) 27.1 -15.8 29.2 -16.3Thrust Strain(c) (%) -0.7 -1.4 -0.7 -1.2Outer Fiber Flexural Strain (%) -0.9 0.6 -0.8 0.4Inner Fiber Flexural Strain (%) 0.5 -0.3 0.5 -0.3Outer Fiber Combined Strain(d) (%) -1.7 -0.8 -1.4 -0.8Inner Fiber Combined Strain(d) (%) -0.3 -1.7 -0.1 -1.5Deflection(e) (%) -2.8 0.8 -2.6 0.8a. Negative strain is compression, positive bending occurs at crown, positive deflection is increased diameter.b. At controlling nodes near crown and springline (moment and thrust do not peak exactly at crown or springline).c. Considers effective area based on uniform compression strain.d. Considers effective area based on combined strain at inner or outer fibers.e. Vertical deflection presented in crown column, horizontal deflection in springline column.
7
We calculated strains from CANDE force output during post-processing based on pipe cross-8
section geometry and 30,000 psi elastic modulus. Circumferential shortening strain, calculated from the9
CANDE thrust results around the entire circumference of the pipes, was -0.9% strain and -0.8% strain for10
Runs A and B, respectively.11
A contour plot of vertical soil stress is shown in Figure 5. The superimposed red line is at an12
elevation approximately 1 ft above the pipes at the location of the soil pressure cells in the field test. The13
vertical soil pressures at this elevation in the model were 12.8 psi, 13.2 psi, and 19.5 psi for Run A,14
Run B, and between the pipes. The vertical soil pressure at the springline elevation between the pipes was15
20.2 psi.16
17
Bass, B.J., and Beaver, J.L. 11
1
23
FIGURE 5 Contour Plot of Vertical Stress (psi) from CANDE Model Output.4
5
We calculated VAFs from CANDE analysis results using two methods: (1) based on vertical6
soil stress 1 ft above the pipes and the assumed free field vertical overburden pressure of 17.4 psi, and (2)7
from the beam element springline thrust and vertical soil stress between pipes at the springline elevation8
and the calculated soil prism load at the springline elevation. We calculated the soil prism load at the9
springline of the pipes to be 240 lb/in. (each springline) and the free field vertical overburden soil10
pressure to be 18.9 psi.11
VAFs calculated from CANDE vertical soil stress were 0.74, 0.76, and 1.12 at an elevation 1 ft12
above the pipes for Run A, Run B, and between the pipes, respectively. VAFs calculated from springline13
thrust and vertical soil stress at the springline elevation between pipes were 0.46, 0.51, and 1.07 for14
Run A, Run B, and between the pipes, respectively.1516
DISCUSSION OF MEASURED DATA AND COMPARISON TO CANDE OUTPUT17
18As reported in (2), for a 75-year design life installation, the maximum allowable cover height for the test19
installation conditions to meet the AASHTO 1.95 dead load factor and thermoplastic pipe resistance20
factors would be 12.5 ft and 16.5 ft for Run A and Run B, respectively.21
22
Deflection23Manual deflection and circumferential strain measurements (Table 3) showed similar order of magnitude24
but greater variability than electronic measurements (Table 4). The greater variability of manual25
measurements is likely due to the nature of taking manual measurements in the tightly confined 24 in.26
diameter space.27
FEM results showed less vertical deflection (2.8% and 2.6% for Runs A and B, respectively) than28
the instrumentation measured values (3.3% to 3.6%). FEM results gave horizontal deflections of 0.8% for29
both pipes. Manual horizontal deflection measurements ranged from 0.4% to 1.1%, enveloping the FEM30
results and instrumentation results (0.6% for Run A). Run A has 5% lower moment of inertia than Run B.31
This lower bending stiffness should result in greater deflection, which is reflected in the FEM results but32
is less apparent in the manual data. Draw wire deflection data does not show a significant difference33
between runs.34
FEM results showed -0.9% and -0.8% circumferential strain for Runs A and B, respectively. All35
circumferential shortening measurements were similar in magnitude to the FEM results, however the36
Bass, B.J., and Beaver, J.L. 12
instrumentation values showed Run A (-0.8%) to have slightly less shortening than Run B (-0.9%). The1
corrugation unit area of Run A is 82% of that of Run B, therefore greater circumferential shortening is2
expected in Run A. This is reflected in CANDE results and manual measurements but not in3
instrumentation results.4
All vertical deflections at 10,000 hrs were of an acceptable magnitude to meet pipeline5
serviceability criteria and design assumptions, with a maximum allowable deflection of 5% in (1).6
7
Strain8Measured and theoretical strains at the end of the test are summarized in Table 8.9
10
TABLE 8 Measured and Theoretical Strain(a) at End of Test11
12
Location MethodRun A
(% Strain)Run B
(% Strain)
Springline Inner FiberField Test Strain Gage -- -0.3
CANDE Combined Strain -1.7 -1.5
Springline Outer FiberField Test Strain Gage -0.4 to -0.8 -0.4 to -0.5
CANDE Combined Strain -0.8 -0.8a. Negative strain is compression.
13
Measured and computed strains were less than the approximate 2.5% compression strain limit14
(based on 5% ultimate strain and a factor of safety for dead load of 1.95) allowed in design (2). However,15
this measurement process does not adequately address the effects of local buckling on the material strains16
at stiffer regions of the corrugation cross-section and this test was only to 10,000 hrs, whereas the typical17
design life is 75 years.18
With positive horizontal deflections, we expect the springline-measured strain magnitude at the19
inside fiber (-0.3%) to be greater than the outside fiber (-0.45%) at the same springline location. This was20
not observed in the measurement results although the trend did exist in the CANDE results. Since nearly21
all inside surface strain gages failed, the last remaining measurement (-0.3%) may not be reliable. These22
measurements may have been affected by initiation of local buckling of the corrugation wall. Springline23
outer fiber strain gage measurements were close to the CANDE results. The high inside gage loss rate is24
likely from the curvature change due to bending on the HDPE substrate.25
FEM results showed greater inside fiber combined strain in Run A than Run B.26
27
Soil Pressures and Vertical Arching Factors28Measured vertical soil pressures at an elevation 1 ft above the pipes (11.2 psi, 13.8 psi, and 20.1 psi for29
Run A, Run B, and between the pipes, respectively) were similar to FEM results (12.8 psi, 13.2 psi, and30
19.5 psi, respectively). VAFs computed from these results, therefore, were also comparable. Calculated31
VAFs from FEM springline thrust and soil pressure values (0.46 for Run A, 0.51 for Run B, and 1.0732
between pipes at the springline) were significantly lower than those calculated from FEM vertical soil33
pressures (0.74, 0.76, and 1.12 for Run A, Run B, and between the pipes, respectively). This shows the34
effects of additional vertical soil arching under the pressure cells and over the top half of the pipes.35
36
CONCLUSIONS37
Deflection and circumferential strain measurements at the end of the 10,000 hr test installation were of38
comparable magnitude to FEM results although instrumentation vertical deflections were slightly higher.39
FEM deflections were consistent with expectations when comparing results from the two pipe runs with40
different cross-sections. Instrumentation results showed no conclusive difference between pipe runs.41
Bass, B.J., and Beaver, J.L. 13
Reliable strain gage installation on HDPE pipes is difficult to achieve. Springline outer fiber1
strains calculated from FEM results were comparable to measured values. FEM showed trends consistent2
with expectations for flexible pipes with positive horizontal deflections.3
Vertical arching factors computed from vertical soil pressures (measured or from FEM) showed4
consistent trends expected for flexible pipes that shed load to the adjacent soil column when installed in5
granular fill that is well compacted around the pipes.6
7
ACKNOWLEDGEMENT8The test installation, data processing, and modeling were funded by Advanced Drainage Systems Inc.9
10
Bass, B.J., and Beaver, J.L. 14
REFERENCES1
1) AASHTO LRFD Bridge Design Specifications, 2012 Edition. AASHTO, 2012.2
2) Bass, B.J., B.R. Vanhoose, and J.L. Beaver. Comparison of Field Measurements from Deep3
Burial Test Installation of Two 24 in. Diameter Corrugated Plastic Pipes with the AASHTO4
Thermoplastic Pipe Design Method. Proceedings of the Transportation Research Board5
Conference 2015, Washington, D.C., 2015.6
3) Mlynarski, M., M.G. Katona, and T.J. McGrath. Modernize and Upgrade CANDE for Analysis7
and LRFD Design of Buried Structures. NCHRP Report 619, Transportation Research Board,8
National Research Council, 2008.9
4) ASTM D6992-03(2009). Standard Test Method for Accelerated Tensile Creep and Creep-10
Rupture of Geosynthetic Materials Based on Time-Temperature Superposition Using the Stepped11
Isothermal Method. ASTM International, 2009.12
5) ASTM D1557-12. Standard Test Methods for Laboratory Compaction Characteristics of Soil13
Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3)). ASTM International, 2012.14
6) ASTM D6938-10. Standard Method of Test for In-Place Density and Water Content of Soil and15
Soil-Aggregate by Nuclear Methods (Shallow Depth). ASTM International, 2010.16
7) ASTM D2487-11. Standard Practice for Classification of Soils for Engineering Purposes17
(Unified Soil Classification System). ASTM International, 2011.18
8) ASTM D2488-09a. Standard Practice for Description and Identification of Soils (Visual-Manual19
Procedure). ASTM International, 2009.20
9) AASHTO M145-91 (2008). Standard Specification for Classification of Soils and Soil-Aggregate21
Mixtures for Highway Construction Purposes. AASHTO, 2011.22
10) ASTM D698-12s1. Standard Test Methods for Laboratory Compaction Characteristics of Soil23
Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3)). ASTM International, 2012.24
25
26