+ All Categories
Home > Documents > 1 Introduction to LIFE CYCLE COSTING (LCC) Based on ASTM Building Economics Standards May 24, 2006...

1 Introduction to LIFE CYCLE COSTING (LCC) Based on ASTM Building Economics Standards May 24, 2006...

Date post: 22-Dec-2015
Category:
Upload: avis-oneal
View: 214 times
Download: 2 times
Share this document with a friend
28
1 Introduction to LIFE CYCLE COSTING (LCC) Based on ASTM Building Economics Standards May 24, 2006 Presented by: Robert Charette Hosted by: Harvard Green Campus Initiative
Transcript

1

Introductionto

LIFE CYCLE COSTING (LCC)

Based on ASTM Building Economics Standards

May 24, 2006

Presented by: Robert Charette

Hosted by: Harvard Green Campus Initiative

2

Outline

1. The Notion of Life Cycle Costing

2. Data Requirements

3. Present Value Factors

4. Calculating Life Cycle Costs - Examples

5. Supplementary Evaluation Measures - Examples

6. Integrating LCC in the Design Process

3

1. The Notion of Life Cycle

Costing

4

Life-Cycle Cost Analysis (LCCA)

A method of economic analysis that sums up, over a given study period, all relevant costs of a building, building system, or building component, in present value (PV) dollars, today’s dollar.

5Source: Means Life Cycle Costing For Facilities

Initial Cost – Office Building - $100 / SF

Uniformat Categories:

01 Foundation02 Substructure03 Superstructure04 Exterior Closure05 Roofing06 Interior Construc.07 Conveying System08 Mechanical: Plumbing HVAC Fire Protection09 Electrical11 Equipment12 Sitework 4%

16%3%

12%4%

1%15%

5%

5%

3%3%

17%12%

5% 10% 15% 20%

% of Total Building Cost

6Source: Means Life Cycle Costing For Facilities

Uniformat Categories:

01 Foundation02 Substructure03 Superstructure04 Exterior Closure05 Roofing06 Interior Construc.07 Conveying System08 Mechanical: Plumbing HVAC Fire Protection09 Electrical11 Equipment12 Sitework

$10$8$4$2 $12 $14 $16 $18 $20$6

Life Cycle Cost – Office Building - $200 / SF

Life Cycle Cost – Present Value $ / ft2

Initial Cost Operational Cost

7

ASTM Standards

Present Value Factors (4) – E917

SPV SPV*UPV UPV*

Evaluation Measures (4)

NS – E1074 AIRR – E1057SIR – E964 DPB – E1121

8

2. Data Requirements for LCC

9

Data Requirements for LCC

A. Investment costs

B. OM&R costs

C. Cyclical renewal costs

D. Financial criteria d – discount rate % e – escalation rate % n – study period years

10

3.Present Value Factors

11

Four Present Value FactorsFrom Financial Tables

1. SPV - Single Present Value (w/o escalation)

2. UPV - Uniform Present Value (w/o escalation)

3. SPV* - Modified Single Present Value (with escalation)

4. UPV*- Modified Uniform Present Value Value (with escalation))

12

4.Calculating Life Cycle Costs

13

Example – LCC of Competing

Heating / Cooling Systems• System A: Electric baseboard and

window air conditioner

• System B: Heat Pump

Financial Criteria:

Discount Rate d = 8% Energy Escalation ee = 6%

Maintenance Escalation em = 5% Study Period N = 15 years

14

Investment Related Costs

Initial Cost – Io $1,500

Replacement Cost Year 8 (Base Yr $) $400

Residual Value (Year 15 $) $150

Operation Related Costs

Base Year Electric Energy Cost $1,200

Base Year OM&R Cost$50

System A: Electric Baseboard and Window Air Conditioner

15

LCC System A

PVInvestment

Costs

PVOperational

Costs

+

= $1,772 + $16,156 = $17,927

16

LCC System B

PVInvestment

Costs

PVOperational

Costs

+

=$3,384 + $12,798 = $16,182

LCC System B $1,745 less or 10% less

17

5. Supplementary Evaluation Measures

18

Four Supplementary Evaluation Measures From Financial

Tables

1. Net Savings - (NS) E1074

2. Savings-to-Investment Ratio - (SIR) E964

3. Adjusted Internal Rate of Return - (AIRR) E1057

4. Discounted Payback - (DPB) E1121

19

Example - NS, SIR, AIRR, DPB

Attic Roof Insulation – R11 to R19

Additional Investment Cost – I $1500

Annual Energy Savings – A0 $260

Financial Criteria: d = 8% ee = 6% N = 30 yrs

20

Suplementary Evaluation MeasuresSuplementary Evaluation MeasuresAdditional Investment of $1,500 for InsulationAdditional Investment of $1,500 for Insulation

1. Net Savings (NS) $4,420

2. Savings-to-Investment Ratio (SIR) 3.9

3. Adjusted Internal Rate of Return (AIRR) 13%

4. Discounted Payback (DPB) 6.2 years

21

6. Integrating LCC in the Design Process

22

Integrating LCC into the Design Process

23

Part of the Solution

An Integrated Design Process with all stakeholders that includes at the Schematic Phase:----------------------------------------------------------------------------

• A Baseline Preliminary Project Description (PPD) in accordance with CSI/CSC Practice FF/180

• An Elemental Cost Estimate With Analytic Parametrs

• An Energy Analysis Simulation Model

24

© The Construction Specifications Institute Manual of Practice FF/180

Chart 3.4 Preliminary Project Description (PPD)

25

Table 4.3 UNIFORMAT II Elemental Cost Summary for Buildings

Project Example - 8 Story Office BuildingLEVEL 2 GROUP ELEMENTS . Level 3 Elements Quantity Unit Rate Cost

Cost per Unit GFA %

A10 FOUNDATION - - - 69,726.50 1.29 1.60%A1010 Standard Foundations 6,000.00 SF 7.67 46,025.50 0.85A1020 Special Foundations - - -A1030 Slab on Grade 6,000.00 SF 3.95 23,700.00 0.44A20 BASEMENT CONSTRCUTION - - 75,467.20 1.40 1.70%A2010 Basement Excavation 2,700.00 CY 5.91 15,960.00 0.30A2020 Basement Walls 3,840.00 SF 15.50 1.10B10 SUPERSTRUCTURE - - 688,569.96 12.75 15.80%B1010 Floor Construction 48,000.00 SF 13.37 641,632.56 11.88B1020 Roof Construction 6,000.00 SF 7.82 46,937.40 0.87B20 EXTERIOR ENCLOSURE - - 794,141.00 14.71 18.20%B2010 Exterior Walls 25,500.00 SF 18.43 469,900.00 8.70B2020 Exterior Windows 6,600.00 SF 47.58 314,041.00 5.82B2030 Exterior Doors 5.00 LVS 2,040.00 10,200.00 0.19. . . . . . . .. . . . . . . .. . . . . . . .

GFA = 54,000.00 SF

26

• kWh / SF vs targeted energy budget

• Identify energy drivers

• Identify alternatives to be evaluated

Baseline Energy Simulation

27

Summary

1. The Notion of Life Cycle Costing

2. Data Requirements

3. Present Value Factors

4. Calculating Life Cycle Costs - Examples

5. Supplementary Evaluation Measures - Examples

6. Integrating LCC in the Design Process


Recommended