1. Introduction....................................................................................................................21.1 Client Profile......................................................................................................21.2 Problem Statement............................................................................................2
1.2.1 Sub-Problems....................................................................................................22. Project Definition...........................................................................................................3
2.1 Mission Statement....................................................................................................32.2 Constraints...............................................................................................................3
2.2.1 Equipment.........................................................................................................32.2.2 Cost.....................................................................................................................42.2.3 Time...................................................................................................................4
3. Project Organization.....................................................................................................4Introduction....................................................................................................................43.1 Project Management Plan.......................................................................................43.1.1 Work Breakdown Structure................................................................................6
3.1.2 Meeting Schedule..............................................................................................73.1.3 Rules...................................................................................................................73.1.4 Task Assignment...............................................................................................7
3.2 Documentation.........................................................................................................83.2.1 Standards....................................................................................................8
3.3 Communication........................................................................................................84. Design Concepts.........................................................................................................9
4.1 Plumbing and Piping Hardware.......................................................................94.1.1 Plumbing and Piping Hardware on Hand...............................................94.1.2 Additional Plumbing Equipment Needed.............................................104.1.3 High Temperature Vacuum Chamber...................................................11
4.2 High Temperature Vacuum/Pressure Chamber Design..............................124.2.1 Material Selection and Design Concepts...............................................134.2.2 Sealing Vacuum Chamber......................................................................144.2.3 Testing.......................................................................................................154.2.4 Connection into the Powder Metallurgy System..................................15
4.3 Self-Sealing Container.....................................................................................164.3.1 Solder material.........................................................................................184.3.2 Testing.......................................................................................................18
4.4 Fixture Design..................................................................................................184.4.1 Material........................................................................................................184.4.2 Fixture Features...........................................................................................194.5 Nitrogen System...............................................................................................20
4.5.1 Flow meter................................................................................................204.5.2 Pressure Relief Valve...............................................................................20
4.6 Temperature and pressure monitoring.........................................................204.6.1 Thermocouple..........................................................................................204.6.2 Pressure/Vacuum transducer.................................................................21
4.7 Vacuum and Filtration System.......................................................................214.7.1 Vacuum pump..........................................................................................224.7.2 Inline Filter...............................................................................................22
4.8 Cooling considerations....................................................................................225. Appendix...................................................................................................................236. Bibliography.............................................................................................................23
0
Executive SummaryThis report discusses the current state of the powder metallurgy (P/M) project and
gives recommendations for further actions. The powder metallurgy project includes the
design of many sub-systems. There are several options for each sub-system and it is
important that the advantages and disadvantages of each option are analyzed. Choosing
the best option will require continued research and testing. The Powder Metal Militia has
analyzed the existing problem and has come up with a number of practical solutions. The
two main areas of design are the vacuum chamber and the self-sealing container.
Vacuum Chamber
The original vacuum chamber had a seal which would not meet our temperature
requirement for the sintering process. Buying a vacuum chamber that would meet the
temperature requirements was investigated. Many different vacuum supply companies
were contacted, but the vacuum chamber’s that they offered were very expensive and still
did not meet our high temperature sealing requirements. The Powder Metal Militia
recommends designing a custom vacuum chamber to meet the projects design
requirements. As a team, we have met with Darrell Andersen and have preliminary CAD
drawings for the vacuum chamber. Currently, the vacuum chamber will be sealed by a ,
however, many other sealing options are being researched. Upon finishing the seal
design, Darrell can begin fabricating the vacuum chamber.
Self-Sealing Container
The design of the self-sealing container has been extensively researched. The
self-sealing container will be made using the available aluminum tubing as required by
our client. However, the method of sealing the container is still unresolved. Our team
has been in contact with multiple solder and adhesive companies. Also a method of
testing the self-sealing container is being developed. At this point we are waiting on
getting some solder samples so we can begin testing their sealing capabilities.
Further Actions
There is a lot of work to be done on this project. Many parts of the powder
metallurgy system still need to be ordered, designed, or finalized. The Powder Metal
Militia plans on continuing to research and test alternatives in order to arrive at the best
powder metallurgy system possible within our budget, time, and design constraints.
1
1. Introduction
Powder metallurgy is the process of producing a metal part by pressing a metal
powder into a die and sintering the powder until it forms a solid with nearly the same
dimensions as the original pressed metal. The three basic steps to make aluminum P/M
parts are:
1.) Precisely mixing aluminum powder with other alloys to a desired ratio.
2.) Degassing the aluminum powder mixture in a heated vacuum chamber.
3.) Pressing the degassed aluminum and sintering it in a controlled atmosphere
until the mixture reaches the desired properties.
Aluminum P/M parts are desirable because they are lightweight, corrosion resistant, and
high in strength.
1.1 Client Profile
Powder Metal Militia is developing an aluminum P/M system under the direction
of Dr. Bill Pedersen. Dr. Pedersen is a professor at the University of Minnesota Duluth
and would like to incorporate the P/M system into the engineering department’s lab
courses. Students enrolled in the lab would be able to learn hands on about powder
metallurgy and produce their very own P/M specimens. The students could test the P/M
and develop ways to improve the existing process.
1.2 Problem Statement
Design a controlled atmospheric system for powder metallurgy applications. The
final product will be a complete powder metallurgy system with the ability to produce a
degassed powder metal specimen.
1.2.1 Sub-Problems
1.) Designing the plumbing and acquiring hardware for the vacuum system.
Additional pipe sections
Heat transfer calculations for vacuum pump inlet
Welding pipe
Monitoring temperature and pressure of system
2
Filtering system before vacuum
Nitrogen system
2.) Designing the system to be safe under all conditions.
Safely dispensing metal powder
Fire and electrical hazards
Vacuum and pressure safety considerations
Researching industry standards
3.) Designing a self-sealing degassing can.
Researching and testing different types of solder
Research lid designs
Experiment with sealing lid designs
Research the use of a localized heating element
4.) Designing or purchasing a vacuum chamber
Research vacuum chambers available in industry
Design a custom vacuum chamber
Pick best alternative based on cost, time, and performance
requirements
2. Project Definition
2.1 Mission Statement
2.2 Constraints
2.2.1 Equipment
Some of the equipment needed to complete this project has been supplied by our
client. We are expected to use this available equipment to keep the overall project cost
down. For example, there may be a better vacuum pump for the degassing application,
but we will have to make the vacuum pump we have work.
3
The extreme temperature conditions during the sintering and degassing phases
also limit the possible materials used for the design of the vacuum chamber as well as the
connections within the plumbing.
2.2.2 Cost
Although a budget has not been set, the cost of equipment will come into play
when the final design decisions are made. It is important that the equipment purchased is
high-quality in order to ensure the operation of the system for years to come.
2.2.3 Time
The Powder Metal Militia has approximately eight weeks to complete our
remaining goals. Many hours of work outside the class will be necessary to meet our
objectives. Design decisions will have to be made based on the information available at
the given time.
3. Project Organization
Introduction
3.1 Project Management Plan
Our team’s project management plan is divided into three distinct phases. Phase 1,
or the Project definition phase, consists of initially meeting with other teammates,
receiving the scope of the project, dividing the project into different sub assemblies,
assigning those sub categories to team members, and brainstorming possible solutions to
each sub category. Our team completed phase one Friday February 9, 2007. Phase 2, or
the Research and Design phase, consists of each team member doing research relevant to
their assigned sub category, building CAD models of the proposed designs, writing and
presenting our baseline report, and ordering parts for the various sub categories once the
proposed designs have been approved. By following our current timeline, phase two
should be completed no later than Tuesday March 27, 2007. Phase 3, or the tying it all
together phase, consists of building the sub assemblies, testing the systems, combining all
4
of the systems into a working prototype, producing a powder metal specimen, writing the
final report, and giving the final presentation. Phase three should be completed no later
than Friday May 11, 2007.
Figure 1: Proposed Timeline
5
Figure 2: Timeline of Project
3.1.1 Work Breakdown Structure
The work breakdown structure details all of the sub assemblies that make up the
entire project. The sub systems are the steps that need to be performed in order to
successfully complete the system. Currently our team is at step 4 in the self sealing
container sub category, step 3 in the nitrogen system sub category, step 4 in the vacuum
and filtration system sub category, step 3 in the general design sub category, step 3 in the
fixture design sub category, and step 3 in the cooling system category.
6
Figure 3: Work Breakdown Structure
3.1.2 Meeting Schedule
Team meetings are scheduled for every Monday and Thursday to report project
updates and discuss project development. Meeting times and locations are scheduled in
advance during the previous meeting. Meetings with our client are generally held after
our team meetings.
3.1.3 Rules
7
Our team has a couple general rules to ensure that each team member is
performing the work they are assigned. During meetings each team member must give a
project update and inform the team what areas of the project the member is pursuing. If a
team member misses or needs to be excused from a meeting, they must notify in advance
the rest of the team and explain why they can’t make the meeting. Unexcused absences
from team meetings or failing to perform their portion of the work will affect the team
member’s performance evaluation at the end of the term.
3.1.4 Task Assignment
Our team decided to break up the work for the project as evenly as possible
with each team member assigned to different sub projects so our team can piece
them all together to complete the project. The chart below is a breakdown of the
work assigned to each team member.
Task List Andy Jeff John Sean Due Date
Cad Drawings X 2/12/2007
Shop for possible Vacuum Containers X X
Research Cooling Canister Capabilities X
Plumbing and Collars X X
High-temp O-ring Research X
Poster for Engineering Week X X X X 2/12/2007
Gauges and Thermocouples X X X
Pressure Transducer X
Self-Sealing Degassing Can Research X X X X 3/5/2007
Baseline Report and Presentation X X X X 2/12/2007
Work-Order for Heater Rewiring X 2/192007
Particle Sizing and Filter Research X
Fixture For Degassing Can X
3.2 Documentation
The process being used for document control includes a filing bin located in the
senior design lab. Each team member is responsible for filing all relevant documentation
used for research and design of the project. This provides each team member with
complete access to all related documentation, regardless the presence of other team
members. Team members are also required to keep electronic copies of all filed
8
documents. Furthermore, each team member is responsible for recording all sources of
information.
3.2.1 Standards
The standard used to this point in the design is the B243 ASTM standard. This
standard is a glossary of powder metallurgy terms. Future standards that could be used to
produce test specimens for gathering material properties are:
B925-03, Standard Practices for Production and Preparation of Powder
Metallurgy test specimen.
B331-95, Standard Test Method for Compressibility of Metal Powders in
Uniaxial Compaction. This standard explains methods for measuring the
density of green powder specimens.
3.3 Communication
The preferred method of communication within the group is e-mail. All e-mails
sent must be carbon copied to each team member.
4. Design Concepts
9
4.1 Plumbing and Piping Hardware
The plumbing and piping hardware was supplied primarily from donated sources.
The donated equipment came without any specification sheets; this required researching
the capabilities and compatibilities of the existing equipment. All of the plumbing and
piping (with the exception of two manual valves) are MDC vacuum products. We were
able to obtain technical specification sheets from the manufacture and it was determined
that the rubber o-ring seals were only rated for use below 200 ºF, which would not meet
the temperature requirement of 1200 ºF for the sintering process. The equipment
provided included o-ring seals for all joints. High temperature seals were investigated,
but none were found that were compatible with the flanges of the existing plumbing.
These temperature constraints lead us to the consideration of other options.
4.1.1 Plumbing and Piping Hardware on Hand
The equipment listing for the existing MDC hardware is listed below. The total
estimated value of equipment donated is $2642.90. Table 1 lists the hardware on hand.
10
Table 1: Plumbing and Piping Hardware on Hand
Equipment on Hand
DescriptionMDC pg
#
Reference
Number
Part
NumberPrice
Qty. on
hand
Clamps 87 K075-C 701000 $5.50 13
Flexible Coupling 117 K150-XT-10 722022 $97.00 1
Centering Ring 87 Not Sure on O-Ring Material $1.60 9
Dual Element Filter 253 DFT-4F-AC 433059 $52.00 1
Foreline Trap (filter housing) 251 KDFT-4150-2 433015 $215.00 1
Water Cooled Trap N/A KDFT-6150-2WC N/A $800.00 1
Valve (Nor-Cal) N/A ILV 1502 NW N/A $400.00 2
90 deg. With tangent (wide bend) 123 K150-2LL 723020 $80.00 3
90 deg. (tight bend) 122 K150-2L 723002 $58.00 1
KF to Clamp Style (nipple) 114 K101-1 720002 $12.00 1
KF to Female NPT (1/4") 158 K150x1/4 FPT 731008 $28.00 2
KF to Female NPT (1/2") 158 K150x1/2 FPT 731009 $28.00 1
KF to Female NPT (3/4") 158 K150x3/4 FPT 731010 $28.00 2
KF to PVC Hose 160 K150-HPV 736003 $17.00 1
1/2" Quick Disconnect to KF 157 K150xDS-50 734025 $63.00 2
Total Value $2,642.90
4.1.2 Additional Plumbing Equipment Needed
The additional equipment needed can be purchased through MDC. The total cost
of additional equipment will be $195.00 plus shipping.
Table 2: Plumbing and Piping Hardware Needed
Plumbing and Piping Hardware Needed
Description
MDC
Catalog
pg #
Reference
Number
Part
NumberPrice
Qty.
neededAvailability
Four-Way
cross 126 K150-4 725002 $135.00 1 In stock/shipping
Vacuum Hose 262 PVC-150 728037 $10.00 6
10 days plus
shipping
Total $195.00 + shipping
11
4.1.3 High Temperature Vacuum Chamber
4.1.3.1 Purchase High Temperature Chamber
The first option explored was to purchase a vacuum chamber that could
accommodate the high temperature levels, but also have the dimensions to fit inside the
furnace provided. The Snap-Tite company makes a pressure vessel that seems to meet all
or our design criteria. We are currently waiting to hear back from them with a price
quote. Many other companies were contacted, but none of them had products that met
our high temperature requirement.
Figure 4: Snap-Tite Pressure Chamber
4.1.3.2 Design and Build High Temperature Chamber
The second option explored was to design and build a custom chamber that could
withstand the temperature levels needed and have the correct dimensions to fit the
furnace. This would also give us the flexibility to incorporate other design considerations
into the system that wouldn’t have been easily done with a pre-manufactured chamber
(ex. Thermocouple).
This option was presented to Darrel Anderson for review, and he quoted the
fabrication costs at $500. This cost would not include materials, as they would be donated
12
from the MIE department and local scrap metal facilities. Further details of the custom
vacuum chamber are discussed in a later section.
4.2 High Temperature Vacuum/Pressure Chamber Design
In order to degas and sinter the aluminum carbide specimen, the self-sealing
container must be heated in an inert atmosphere, free of oxygen, such that aluminum
oxide does not form. This system design requires a vacuum chamber capable of holding
both a vacuum of approximately 1 atmosphere for degassing as well as a nitrogen blanket
of a pressure around 3 psi for the sintering phase. The proposed chamber will be
fabricated from 304 stainless steel and will have a high temperature seal which could
withstand both the applied vacuum and pressure. The two flanges will be tightened over
the seal using stainless steel bolts. The top flange will then be welded to a portion of the
plumbing, which will lead to a quick disconnect from the system.
Figure 4: Vacuum Chamber
4.2.1 Material Selection and Design Concepts
13
(annotate about austenizing temp and melting temps, price of
titanium and viability as material)
The material chosen for the chamber is 304 series stainless steel. This material
was chosen because of its high melting temperature as well as its non-corrosive
properties. Aluminum was ruled out given its melting temperature (1220°F) is so close to
the sintering temperature (1100-1200°F). Titanium could also be a viable option for a
material subjected to the given conditions, but is very expensive and would have to be
fabricated by an outside source. 304 stainless steel is the industry standard for companies
developing high temperature vacuum systems, considering donated plumbing from MDC
to be used in our system is all fabricated from this material. The MIE department also
has the ability to weld stainless steel, such that the canister can be fabricated in-house.
The main body of the vacuum chamber will be constructed of 3 ½ inch 304
stainless steel with ¼ inch wall thickness, giving it a 3 inch inside diameter. This size
was chosen because it is available through the UMD MIE department and because of the
high price associated with ordering one single section of stainless steel. (PRICE
QUOTE) This inside diameter for the vacuum chamber allows specimens up to 2.75” to
be produced; however Dr. Pedersen advises that the school would not be capable to press
anything larger than 2.5 inch diameter. The main body extends approximately 10 inches
below the bottom flange, which is about ½” short of the maximum furnace depth.
The bottom is capped with a piece of 3 inch diameter round stock cut to a
thickness of ½ inch, which will be press fit into the bottom, welded around the chamfered
bottom ridges, then machined cleanly off.
The top and bottom flanges were designed to be 6 inch in diameter, which will
provide enough room for a sealing material as well as a 6 count bolt circle on a 5 inch
diameter to seal the chamber. The thickness of each flange is ¾”, which is purposely
over-sized given the uncertainty in the sealing method. This way, the flanges could be
machined more than once if necessary to fit the chosen seal application. The top flange
will also have holes machined into the center portion for an opening to the plumbing and
a thermocouple.
14
4.2.2 Sealing Vacuum Chamber
Given such extreme conditions, the sealing issue becomes very complex as
normal seals such as o-rings and rubber gaskets would break down under these high
temperatures. Many representatives for high temperature seal companies have responded
back stating that the sintering phase would still be too high for their products to work in
our application. After much research, and while waiting for responses from a select few
companies stating they may have a viable solution for us, we have narrowed our seal
design to the following possibilities:
Cutting gasket rings from a material offered by Slade Inc. called MRG
Gasket Sheet, which is a sheet of stainless steel mechanically bonded
between two foil sheets. This option seems the most viable, especially
considering the working temperatures this product is specified to
withstand. See Appendix for product specifications.
Machining a cup and cone set of rings on the upper and lower flanges,
then compressing a sheet of brass or copper foil between the two flanges
by tightening the bolts. This design requires more research as well as
finite element analysis into the effect on the mechanical properties of
either metal under such extreme conditions if this option is chosen.
Implementation of a ceramic, high temperature gasket. This idea is
relatively new prior to this report and requires much research to ensure its
viability for our project.
The reusability of the seal would be highly beneficial. However, the seals being
researched would be plastically deformed when the flanges are fastened together and may
not provide an effective seal after multiple uses. Therefore, the seals will most likely
have to be replaced every time the vacuum chamber is used, based upon their
performance after one run. The chosen seal application will be tested to determine its
useful life for this application.
Currently the vacuum chamber flanges will be fastened using 6 stainless steel
bolts, which will be positioned equal distance around on a 5 inch bolt circle. The bolts
will then screw into a stainless steel fabricated bolt flange, which is comprised of a 3/8
inch by 6 inch diameter slice of stainless steel round stock with 6 stainless steel nuts
15
welded concentric to machined holes matching the flange bolt holes. See Figure 5. This
will eliminate the need to hold an additional wrench on a nut while tightening each bolt
down. A torque wrench will be required to administer a uniform torque on each bolt of a
magnitude yet to be determined based upon the type of seal chosen for the application.
Figure 5: Bolt Flange
4.2.3 Testing
The vacuum canister will be tested to ensure the seal will hold up under the
vacuum and pressure states under the elevated temperatures. This testing will occur once
the entire system is assembled and is run through a couple of dry runs. The effectiveness
of the seals will be monitored using the pressure transducer, which will provide feedback
on whether the system is maintaining a constant vacuum or a constant pressure.
The reusability of the seal will also be tested in this fashion, performing multiple
runs using the same seal, which would prove highly beneficial if the same seal could be
reused over and over. However, the seals being researched would be plastically
deformed when the flanges are fastened together and may not provide an effective seal
after multiple uses. Therefore, the seals will most likely have to be replaced every time
the vacuum chamber is used, based upon their performance after one run. The chosen
seal application will be tested similarly to determine its useful life for this application.
4.2.4 Connection into the Powder Metallurgy System
The machined opening on the top flange of the canister will be welded to a 90°
elbow, which will be welded to the finned pipe used for heat dissipation. The other end
of the finned pipe will use an MDC Kwik-Flange o-ring and collar connection which we
have in stock and will serve as a quick disconnect from the system. The reasoning
behind welding these components together is to limit the number of high temperature
seals in the system to just vacuum chamber seal, especially considering the chosen seal
16
will have to be experimentally tested. This will simplify the system and reduce the
number of locations a seal failure could occur.
4.3 Self-Sealing Container
The self sealing container is comprised of a 40 mil thick thin walled 2024
aluminum tube, with a 1.5 inch inner diameter, that has been cut to a length of 6 inches.
A disk was cut and welded to the bottom of the tube to seal the bottom. Sealing the top of
the aluminum container is more complex because the container must be sealed in an inert
environment after the aluminum powder mixture has been degassed. Our team
immediately thought of a hands free application that could be used immediately after the
degassing stage inside of the pressure vessel itself. There were originally four alternatives
being researched for the lid of the aluminum container.
The first alternative is to completely encase the aluminum cylinder in a ballistics
gel that would seal the aluminum powder from the outside atmosphere after the degassing
was completed. This alternative was later determined unfeasible because the aluminum
cylinder would then have to be taken to the die and crushed for the green compact. If it
was encased in ballistics gel the exact dimensions of the outer diameter of the container
wouldn’t match the die and there would be a high risk of leaking if any of the ballistics
gel was carved away. This method was also discredited due to the fact that there is no
research available to conclude how the dispersing of ballistics gel reacts to a vacuum
environment.
The second alternative is to attach 2mm by 2mm chunks of solder around the top
lip of the aluminum cylinder and place an aluminum disk on top of the chunks to form a
type of gravity seal with the aluminum container once the solder melts. This was
determined to be extremely complex because of the 40 mil wall thickness on the
aluminum container. Also after talking with Larry Lepervow from Johnson’s
Manufacturing Company, a solder and flux manufacturer, he expressed concern that the
solder wouldn’t travel completely around the top lip of the aluminum container but would
have a tendency to flow down the side of the walls.
The third alternative is to buy a lid that already had solder dispersed around the
outer edges from Williams Advanced Materials. This was a company that was found by
doing internet research into self sealing lids. The lid that was found to be applicable was
17
a 1.60 inch diameter lid made of Kovar material. The solder on the lid is comprised of
81% aluminum, 19% Indium with a melting temperature of 909 deg. Fahrenheit. The
main drawback in this approach is there wouldn’t be any way of degassing the aluminum
container because the lid would create a cap even before it sealed. Below is a picture of
some of the lids Williams Advanced Materials manufactures with the solder dispersed
around the outside edges.
Photo Courtesy of www.williams-adv.com
The fourth alternative is to create an aluminum plug that would be press fitted into
the aluminum container. The plug was designed to be inserted with the punch of the die
and distribute uniform pressure as the powder is being compacted. The plug has 45
degree chamfers on the edges to reduce wobble when being inserted into the aluminum
cylinder and to create a space for the soldering ring to seal the aluminum plug to the
container wall. The center of the plug will have holes drilled in it to allow the moisture
and oxygen to escape during the degassing process. To seal the holes after degassing is
complete, an aluminum alloy solder will be dispersed around the holes. The solder used
to seal the holes and to seal between the plug and the container wall is comprised of 80%
aluminum, 20% zinc with a melting temperature of 890 degrees Fahrenheit. The pictures
below are the preliminary drawings of the aluminum plug.
Figure 5: Aluminum Plug
The fourth alternative was chosen to be the most feasible because it will not only
allow for degassing of the aluminum powder to occur, but it also provides a larger cross
18
sectional area of solder between the aluminum plug and container wall forming a more
secure seal.
4.3.1 Solder material
The solder and flux being used for the sealing of the aluminum container is
supplied by Johnson Manufacturing Company out of Princeton, Iowa. The name of the
flux is Zinc Tech-A, it is a paste flux with a melting temperature between 950 and 1000
degrees Fahrenheit. The cost of the Zinc Tech-A flux is 20$ per ounce.
The solder is a “hard solder” that is a super plastic material comprised of 80%
aluminum, 20% zinc with a melting temperature of 890 degrees Fahrenheit. Multiple test
strips of wire solder with different diameters will be donated by Johnson Manufacturing
Company.
4.3.2 Testing
Before making a sample, the self sealing container needs to be tested to make sure
the solder seals are airtight. The method of testing is to seal the aluminum container as
described in alternative four in section 4.3 and then submerge the aluminum container in
tinted water for 48 hours. The water will be tinted with a red color to make it easier to see
if there are any leaks. After 48 hours the sample will be collected, dried off, and cut open
to inspect for any visible red water. This process will be repeated 3 times to ensure no
variability. Additional research is currently being performed into alternative testing
methods.
4.4 Fixture Design
This project will also require the design of a fixture to support the system as a whole.
4.4.1 Material
The proposed frame material for the fixture will be aluminum extrusion T-slotted
framing. The reason for this choice is modularity, such that the frame design can be
easily adjusted for any future modifications to the system as a whole. A welded steel
frame would not allow this type of simple modification.
19
The aluminum extrusion material, commonly referred to as 80/20, is also
lightweight, which will reduce the overall weight of the system greatly compared to a
welded steel frame.
Many companies offering this type of framing offer a large variety of cross
sections in their extrusions. This can be utilized when determining the structural
requirements of the frame, based upon the stresses put on structure from the weight of
system and its associated components.
4.4.2 Fixture Features
The primary purpose of the fixture is to hold the powder metallurgy plumbing and
canister. However, there are various other features that will be built into the design to
make it ergonomically friendly and to make the specimen production much easier.
The fixture will be designed with a set of wheels at the base, such that the
operator can maneuver the entire system around with ease. This allows the
system to be stored when not in use, freeing up valuable lab space. To ensure
stability and limit movement during degassing and sintering, the wheels will have
the ability to be disengaged and the fixture will then sit on the floor on its base.
While the fixture will be designed to hold the plumbing, it will also have
mechanical lift equipment incorporated into its design. This will allow the
operator to mechanically lower the canister and plumbing into the furnace for
sintering and degassing. The operator will then be able to lift the entire apparatus
out of the furnace when the process is complete, which is much safer than
removing the hot components by hand.
The fixture will also have sections dedicated to housing the vacuum pump and a
laptop. All necessary equipment will be integrated into one user-friendly fixture.
4.5 Nitrogen System
Nitrogen was chosen to blanket the part during the controlled atmosphere
sintering operation because it is relatively inexpensive and produces a part with desired
20
mechanical properties. The vacuum canister will be pressurized to approximately 3 PSI
while the part is being sintered in order to keep aluminum oxide from forming.
4.5.1 Flow meter
The team has met John Petrovic, who works at Airgas in Duluth, and discussed
equipment needed to ensure safe operation of the nitrogen system. A single stage
regulator and flow meter combination for use with nitrogen was quoted at nearly $300.
More research needs to be done in this area before final decisions are made.
4.5.2 Pressure Relief Valve
A pressure relief valve may be used in the system in order to provide protection
from over-pressurization. The pressure relief valve would be self-operating and would
let gas escape the system when safe pressures exceeded. Many companies supply these
valves. To order a valve the gas (nitrogen), set pressure, and size of thread piping must
be specified.
4.6 Temperature and pressure monitoring
4.6.1 Thermocouple
The monitoring of temperature for the degassing and sintering phases is a crucial
element. The temperature for the degassing process must be maintained at 400°F and the
temperature of the sintering process must be maintained at a minimum of 1000°F. The
temperature will be monitored by mounting a thermocouple directly into the top of the
vacuum chamber. The thermocouple provided has a male threaded end and can be
directly threaded into the top flange of the canister. By threading the thermocouple into
the system, it will minimize the possibility of a vacuum leak in the system. This will also
provide a fixed location for temperature measurements, minimizing the variation in
measurements. Another option for the placement of the thermocouple is to have the end
dangling in the middle of the canister. This would require a compression fitting where the
wire goes through the top flange. The compression fitting could pose a higher risk for
vacuum leaks and the end placement of the thermocouple would not be in a fixed
location. This option would not be recommended.
21
Further research will be done into monitoring and recording the temperature using
software such as Labview or similar products. This will provide a method of recording
temperatures that could be of value for further research purposes.
4.6.2 Pressure/Vacuum transducer
The system will require a pressure and vacuum monitoring device to ensure
proper conditions during the sintering and degassing phases. The degassing phase will
require the system to be at .1 Tor. During the sintering process the system will be
required to be under a nitrogen blanket of 2 to 3 psi. The purposed transducer is a
compound unit which measures both pressure and vacuum. The range selected for this
application is -14.7 psi to 15 psi. It can be supplied by Omega for $195. The transducer is
in stock and has immediate availability. The part number is PX209-30V15G5V. The
pressure port can be threaded directly into an adapter that goes from a Kwik Flange to a
¼” Female NPT. The adapter is listed in the table of equipment we have on hand. The
transducer can also be integrated into the lab view software for monitoring and data
recording.
4.7 Vacuum and Filtration System
The vacuum system consists of a Savant vacuum pump and a MDC inline filter.
The vacuum pump was also a donated piece of equipment and came with no
documentation. The user and maintenance manuals were eventually acquired from the
pump manufacture BOC Edwards. Complete user and maintenance manuals are available
electronically.
An option to control the vacuum pump through a vacuum control switch is
available through Omega. This would start and stop the vacuum pump at preset
conditions, eliminating the task of manually monitoring and controlling the vacuum
pressure. The model number is PSW-626. The price is $85.00.
4.7.1 Vacuum pump
The vacuum pump is a BOC Edwards Model RV12 rotary vane pump. The RV12
is a two stage, oil seal, sliding-vane vacuum pump. The pump is driven by a single phase
electric motor. Some additional specifications are listed below:
22
Maximum displacement is 17 Calculate time required to
evacuate the system
Maximum inlet temperature of 180ºF
Equipped with a thermal overload device
4.7.2 Inline Filter
The inline filter was provided with the other donated equipment. It is a 4” dual
element filter that has activated carbon and fiberglass as its filtering agents. This filter is
primarily a vapor filter, but it will also trap some particulates that may reach this point in
the system. Because of the low velocity of gases in the system (4.55 ), particle
movement is expected to be minimal. The model reference from MDC is: DFT-6F-DE, it
is also listed in the table for equipment on hand.
4.8 Cooling considerations
The cooling of the gases before they reach the vacuum pump is a concern. The
maximum temperature of the inlet gases must be below 180ºF. Therefore we must take
into account a method for cooling the gases. Two pieces of equipment that were on hand
can be utilized to accomplish this. They are discussed in the next sections.
Finned Pipe
The finned pipe is actually designed to be a flexible coupling from MDC, but for
our purposes will provide an excellent finned surface to dissipate heat. The purposed
design will have welded piping from the vacuum chamber up to the finned pipe. At the
vacuum pump side of the finned pipe is where the Kwik Flanges will begin. We
anticipate that the finned pipe will reduce the temperature at this point to a value less than
the o-ring limits (200ºF). Calculations and an experiment to test the heat transfer are still
to be done. Below is a picture of an MDC flexible coupling.
23
.
Cooling Canister
The cooling canister is another piece of equipment that was donated. The canister has
stainless steel coil that lines the inside of the canister. We would run cool water through
the coil to provide additional cooling to the gases before entering the vacuum pump. The
cooling canister is yet to be determined if it is needed. If the finned pipe provides
adequate heat transfer, the cooling canister will not be used.
5. Appendix
6. Bibliography
http://www.snap-tite.com/index.asp?loc=/Autoclave_Engineers/High_Temperature_
Vessels/index.html&title=High%20Temperature%20Vessels
24