1 Successful Successful decommissioning of a decommissioning of a nuclear plant nuclear plant Evelyn Hooft Bart Thieren 20 june 2008
Transcript
Page 1: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

1

Successful Successful decommissioning of a decommissioning of a

nuclear plantnuclear plant

Evelyn HooftBart Thieren

20 june 2008

Page 2: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

2

IntroductionIntroduction

■NIRAS: public institute responsible for the safe management of radioactive waste in Belgium. Has developped a coherent and central management system

■Belgoprocess: industrial daughter of NIRAS, main activities are treatment and storage of radioactive waste and decommissioning of shut down nuclear installations

Page 3: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

3

IntroductionIntroduction

■NIRAS is charged by the belgian State with the clean up of nuclear liabilities = task of public benefit

~ 1986 : site BP 1 (Eurochemic)~ 1989 : site BP 2 (Ex waste department

of SCK.CEN)~ 1991 : installations and fission products

originated from research reactors and other installations of the SCK.CEN

Page 4: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

4

Foto site 1Foto site 1

Page 5: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

5

EurochemicEurochemic

Page 6: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

6

Eurochemic Eurochemic

■ First reprocessing plant in Europe■ Goal

~ Research and development in the field of reprocessing spent fuel originated from nuclear reactors

~ Construction of a pilot plant

Page 7: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

7

Reprocessing ?Reprocessing ?

■ Definition: Reprocessing = recycling

~ Spent fuel (nuclear fuel) can be recycled■ 97% of the material can be reused for

electricity production (U and Pu)■ 3% is waste and is vitrified, interim stored

awaiting for disposal.

Page 8: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

8

History of EurochemicHistory of Eurochemic

■ 1957 Constitution of Eurochemic■ 1960 Start construction■ 1966 Start up and active operation■ 1974 Shutdown■ 1978 Take-over by the Belgian State

with the intention to continue reprocessing

■ 1984 Constitution of Belgoprocess■ 1985 Belgoprocess takes over the

personnel

Page 9: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

9

■ 1986 Decision to end reprocessing in Belgium Transfer actions to NIRAS

■ 1987 Start decommissioning studies■ 1989 Start decommissioning pilot

project ■ 1990 Start decommissioning

Eurochemic■ 2008 Start conventional demolition

History of EurochemicHistory of Eurochemic

Page 10: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

10

Pilot projectPilot project

■ Decommissioning of two smaller buildings for endproducts originated from reprocessing ~ To demonstrate that decommissioning

is feasible~ To demonstrate that costs can be

managed~ To develop and optimise dismantling

techniques~ To train personnel

Page 11: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

11

Before and afterBefore and after

Page 12: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

12

Main lessons learnedMain lessons learned

■ Emphasis should be put on:

~ Decontamination of metal components~ Automation of concrete decontamin-

ation

Page 13: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

13

Clean-up of EurochemicClean-up of Eurochemic

Page 14: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

14

■ Main data~ Length 90 m, width 27 m,

height 27 m~ Volume: 56.000 m³~ Concrete volume: 12.500 m³~ Concrete surface: 55.000 m²~ Metal: 1.500 ton

■ 7 levels, 40 main cells■ 106 cell structures

Clean-up of EurochemicClean-up of Eurochemic

Page 15: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

15

■ Radiological status in 1981

~ Contamination level up to 200 Bq/cm² (alpha) and 125 Bq/cm² (beta)

~ Sometimes contamination in depth~ Hot spots up to several mSv/h~ No activation

Clean-up of EurochemicClean-up of Eurochemic

Page 16: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

16

Used techniquesUsed techniques

■ Removal of metal components■ Decontamination of concrete surfaces■ Removal of contamination in depth■ Removal of pipe penetrations■ Techniques for working on heights

Page 17: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

17

Removal of metal Removal of metal componentscomponents

Page 18: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

18

Removal of metal Removal of metal componentscomponents

Page 19: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

19

Decontamination of Decontamination of concrete surfacesconcrete surfaces

Page 20: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

20

Decontamination of floorDecontamination of floor

Page 21: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

21

Removal of contamina-Removal of contamina-tion in depthtion in depth

Page 22: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

22

Removal of pipe Removal of pipe penetrationspenetrations

Page 23: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

23

Working at heightWorking at height

Page 24: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

24

Working at heightWorking at height

Page 25: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

25

To decontaminateTo decontaminate

■ Main streams~ Metal~ Concrete

Page 26: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

26

To decontaminateTo decontaminate

■ Main streams~ Metal 1.494 ton~ Concrete 2.913 ton (incl. barytes blocs)

(period 1988 – 2007)

Page 27: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

27

Metal decontaminationMetal decontamination

Page 28: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

28

Before and afterBefore and after

Page 29: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

29

Concrete samplingConcrete sampling

Page 30: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

30

Clearance measuresClearance measures

■ 100 % surface measurement ■ Taking samples and analyses■ Procedure is representative and

approved by the department of fysical control

■ Control organism (Bel-V) subsidiary of FANC

Page 31: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

31

Clearance measurementClearance measurement

Page 32: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

32

SafetySafety

■ Top priority for Belgoprocess

■ Radiation dose■ Contamination risque■ Conventional safety

Page 33: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

33

SafetySafety

■ Top priority for Belgoprocess

■ Radiation dose (average < 2 mSv/year.person over 1990-2007)

■ Contamination risque (Protective clothes including full-face mask)

■ Conventional safety~ Circumstances as on a construction

warf~ Vibration stress

Page 34: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

34

Protective clothesProtective clothes

Page 35: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

35

Protective clothesProtective clothes

Page 36: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

36

Isolation of a moduleIsolation of a module

Page 37: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

37

DemolitionDemolition

■ Method

Page 38: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

38

Result:Result:

■ Production streams■ Men-hours■ Budget■ Planning

Page 39: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

39

Result: productionResult: production

CONTAMINATED MATERIAL

DECONTAMINATION OF MATERIALS

RADIOACTIVE WASTE

UNCONTAMINATED MATERIAL

RECYCLING WASTE PROCESSING

&

&

& &

&&

& &

DECOMMISSIONING

Page 40: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

40

Result: productionResult: production

CONTAMINATED MATERIAL

DECONTAMINATION OF MATERIALS

RADIOACTIVE WASTE

UNCONTAMINATED MATERIAL

RECYCLING WASTE PROCESSING

&

&

& &

&&

& &

557 t 1.530 t

2.356 t 145 t

2.913 t 1.675 t63%

DECOMMISSIONING (31/12/2007)4.588 t

2.501 t

Page 41: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

41

Result: productionResult: production

CONTAMINATED MATERIAL

DECONTAMINATION OF MATERIALS

RADIOACTIVE WASTE

UNCONTAMINATED MATERIAL

RECYCLING WASTE PROCESSING

&

&

& &

&&

& &

557 t 1.530 t

2.356 t 145 t

2.913 t 1.675 t63% -> 88%

DECOMMISSIONING (31/12/2008)+9.552 t

+9.552 t

4.588 t

2.501 t

Page 42: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

42

Result: men-hoursResult: men-hours

■ Initial estimation: 403 man-year■ Current estimation: 600 man-year■ Difference explained by:

~ Decontamination until clearance~ Differences with the initial inventory~ Labour-intensive clearance

measurements and procedures

Page 43: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

43

Result: budgetResult: budget

Initial estimation

M€1992 M€2008

1990 - 2007

M€2008

after 2007M€2008

Total

M€2008 Ratio

Decommissioning costs

54,8 73,9 115,1 30,0 145,1 1,96

Treatment (tarif 2008)

68,7 92,6 25,7 4,2 29,9 0,32

Totaal 123,5 166,5 140,8 34,2 175,0 1,05

Forced decontamination till clearance

Less treatment, interim storage and disposal

End result remains equal

Page 44: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

44

Result: planningResult: planning

■ Conventional demolition~ East part: september 2008~ Central part: einde

2010~ West part : einde 2012

~ Distribution of water, air, steam,.. for neighbouring buildings remains

Page 45: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

45

Result: planningResult: planning

20082010

2012

Page 46: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

46

AmbitionsAmbitions

■ Safety■ Environment■ Socio-economical■ Exploitation of the disposal site for

category-A waste■ International partner

Page 47: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

47

ConclusionConclusion

■ Start of the conventional demolition of Eurochemic

■ In 2012 completely demolished■ Cleaned-up historical heritage■ Know-how to recycle >90%

Belgoprocess and NIRAS decommission succesfully a nuclear plant

Page 48: 1 Successful decommissioning of a nuclear plant Evelyn Hooft Bart Thieren 20 june 2008.

48

More informationMore information

■ Websites~ Eurochemic

www.eurochemic.be~ Belgoprocess