138 kV Oyster Creek Project
Public MeetingPublic Meeting
Michael J. Pakeltis, P.E.Director, Transmission Operations
CenterPoint EnergyCenterPoint Energy
March 7, 2013
Overview
Tonight’s Presentationg
Facts about CenterPoint Energy Houston Electric, LLC (“CenterPoint Energy”) Project Detailsj CenterPoint Energy’s Application to the Public Utility Commission (PUC) PUC’s Transmission Line Certification Process Electric & Magnetic FieldsElectric & Magnetic Fields Land Acquisition Types of Transmission Structures Project ScheduleProject Schedule Resource Websites Q&A – submit written questions to designated CenterPoint Energy employees
2
CenterPoint Energy Houston Electric –An electric delivery company only
Company FactsCompany Facts
Does not generate or sell electricityO d i t i l t i d li Owns and maintains electric delivery system – towers, poles, and wires
5,000 square-mile electric service territoryterritory
Serves over 2 million electric customers
Regulated by the PUCegu ated by t e UC
3
Proposed ProjectPreliminary Route Segment Mapy g p
Need to establish a new route from a 138 kV transmission line
id t b t ti it i
345kVCorridor
corridor to a new substation site in Brazoria County
Cannot connect to 345 kV or 69 kV Many alternatives are proposed
138kVCorridor
Only one multi-segment transmission line route will ultimately be constructed
Many alternatives are proposed
` ultimately be constructed
Proposed138kVSubstation Site
69kVCorridor
5
Why is the Project needed?
The proposed 138 kV transmission line will provide electric transmission service to Freeport LNGservice to Freeport LNG Development’s (Freeport LNG) proposed natural gas pretreatment and generation facility located north of
New Natural Gas Pretreatment and Generation Facility generation facility located north of
State Highway (SH) 332 near the interchange of SH 332 and County Road 690.
Generation Facility
Proposed CenterPoint Energy will also build a
new substation, known as the Oyster Creek Substation, within Freeport
ProposedSubstationSite
Creek Substation, within Freeport LNG’s property to interconnect the new generator and serve the facility.
6
Project Process Overview
CenterPoint Energy will be seeking approval from the PUC to construct a 138 kV double-circuit transmission line to its proposed Oyster Creek Substation site Currently gathering information from public and governmental sources Routing segment alternatives are currently being evaluated Information gathered will be used to refine the routing alternatives
CenterPoint Energy will file an Application for a Certificate of Convenience CenterPoint Energy will file an Application for a Certificate of Convenience and Necessity (CCN) with the PUC in July 2013 The PUC will decide whether the application should be approved and the
route that the transmission line will be constructed The PUC can select any route proposed in the CCN application
7
Early Stages for Preparing a CCN Application
Identify study area boundary
Gather initial environmental and land-use data from various agencies for th d fi d t dthe defined study area
Identify preliminary transmission line routing segments Provide diverse geographic alternatives Follow compatible rights-of-way where possible
Hold a public meeting to gather input from landowners and other interested partiesparties
8
Next Steps in Preparing a CCN Application
Prepare a Routing Study and Environmental Assessment Assess, tabulate, and consider factors for each preliminary transmission line
segment from the following: Information provided at the public meeting Submitted questionnaires Governmental and agency contacts Field investigations
G f f Gather additional environmental and land-use data for the defined study area Add, modify, or delete initial preliminary transmission line routes based on
information gathered Identify a set of alternative routes proposed for construction in the CCN Identify a set of alternative routes proposed for construction in the CCN
Application
Prepare and Submit a CCN Application and Provide Notice
9
PUC Certification Process forTransmission Lines Process defined by the Public Utility Regulatory Act (PURA) and PUC
Substantive and Procedural RulesT t t th tilit b it CCN li ti t th PUC To start the process, a utility submits a CCN application to the PUC
Notice is sent to affected landowners, municipalities, and adjacent utilities Intervention and comment period
With Intervention – Administrative Hearing Technical review session Testimony filed by all partiesy y p Administrative Law Judge presides Proposed final order is issued
OR Without Intervention PUC Staff Review OR...Without Intervention – PUC Staff Review Recommends approval as submitted or with modifications
PUC Makes Decision
10
Within 12 months after CCN application is submitted Approve / Approve with modifications / Deny
Electric and Magnetic Fields
Electric and magnetic fields, sometimes referred to as “EMF”, exist wherever there is a flow of electricity
Sources of EMF include: Wiring in houses offices and schoolsWiring in houses, offices, and schools Electrical appliances and equipment (such as hairdryers, refrigerators, and
computers) Power lines Power lines
CenterPoint Energy mitigates EMF where practical
Information about EMF can be found on the project websitep j
11
Land Acquisition
If the Project receives PUC approval, CenterPoint Energy will acquire an easement, including access roads and material yards, by mutual agreement with the landownerwith the landowner
If a mutual agreement cannot be reached, CenterPoint Energy will begin a condemnation proceeding by filing a petition in court. This process is d ib d i th St t f T L d ’ Bill f Ri htdescribed in the State of Texas Landowner’s Bill of Rights A judge will appoint three landowners from the resident county to serve as special
commissioners The special commissioners will determine the land value following a hearing where The special commissioners will determine the land value following a hearing where
all interested parties are entitled to provide evidence of valuation
Once the amount determined by the commissioners has been paid to the landowner or registry of the court CenterPoint Energy may take possessionlandowner or registry of the court, CenterPoint Energy may take possession of the easement for construction of the line
Either party can object to the value of the compensation by the
12
commissioners and file an appeal with the court for a trial by judge or jury. The appeal does not change possession
What will the transmission line structureslook like? Steel towers and concrete
poles are the alternatives being consideredbeing considered
Right-of-way (ROW) width varies depending on the
dj t l dadjacent land use Towers require an 80’ wide
ROW in undeveloped areas Concrete poles require a 60’ Concrete poles require a 60
wide ROW in undeveloped areas
Concrete poles require a 25’ p qwide ROW adjacent to roadways (aerial only)
The PUC will ultimately
13
decide the types of structures to be used
Typical structure shown. Heights will vary with topology.
Steel Towers can span longer distances, requiring fewer structures
What will the transmission line structureslook like?
Typical structures shown. Heights will vary with topology.
Concrete poles are more compact, Roadways cannot accommodate
14
p prequiring less ROW but more structures per mile
ysteel towers
Project Schedule
15
Construction Phases
Transmission line construction is accomplished in several distinct phases, including: Right-of-way preparation (clearing access etc )Right of way preparation (clearing, access, etc.) Foundation installation Structure installation
Wi i t ll ti Wire installation Right-of-way clean-up
16
Resource Websites
www.centerpointenergy.com/oystercreek
www.puc.texas.gov
17
Q&A Session
18