Tangential silo in 9 steps KIH 620, 14.04.2011
Page 1
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 1:
• Casting of the silo structure
Page 2
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 2:
• Install pre-assembled mixing chamber and bin top filter
Page 3
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 3:
• Install silo cone segments
Page 4
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 4:
•Install silo aeration system
•Install pre-assembled pressure relief vents
•Install roof structure/silo slab
Page 5
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 5:
• Install platforms, stairs, ladders etc.
• Install silo access doors, sockets for silo openings, sockets for dedusting etc.
Page 6
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 6:
• Install distribution vessel with trough conveyor, bag filter, overpressure flap, silo pilot etc. on silo roof
Page 7
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 7:
• Install outlet equipment and trough conveyor
• Install rotary blowers
Page 8
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 8:
• Install pipes inside and outside
• Install aeration system for mixing vessel
•Install main pressure pipes
Page 9
Polysius
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.
Step 9:
• Install chutes and ducts
• Install ventilation system for silo cone
• Install control system for pneumatic valves and dosing valves