+ All Categories
Home > Documents > 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

Date post: 03-Jun-2018
Category:
Upload: juan-carlos-villagran-fante
View: 214 times
Download: 0 times
Share this document with a friend
6
INTEGRATED PROTECTION SCHEME FOR PUMP-STORAGE HYDROELECTRIC POWER PLANT Z. Gajić * , J. Menezes * , D. Trišić ¤ , M. Čitaković ¤  *ABB AB; SA Products, Sweden, [email protected] ¤  PD Drinsko-Limske HPP; Bajina Bašta, Serbia, [email protected] Keywords: Generator protection, pump-storage hydro unit. Abstract This paper describes design of an integrated numerical  protection scheme for two pump-storage generator/motor- transformer units. Regardless of the application complexity, the complete protection scheme for one unit can be integrated within a single numerical multifunctional IED. 1 Introduction The Bajina Bašta Pump-Storage Plant is located in the vicinity of town Perućac on river Drina. Its two turbines operate with a net hydraulic head of approximately 600 meters between an upper reservoir located on the top of Tara mountain and the lower lake formed by a dam on Drina river. Each generator/motor-transformer unit has rating of 315MVA, 11/242kV, 428.6rpm. In addition to these two units another four 100MVA generators are constructed within the dam and are used as stand-alone generators. Phase reversal disconnectors are located at the high-voltage side of the step-up transformer in the 220kV switchyard, as shown in Figure 1. A 220kV substation connecting these units to the national grid is located 8km away. As a consequence two circuit breakers in series are installed on the HV side of the step-up transformer in order to secure separation of the unit from the system during fault conditions. Additionally, due to transport limitations, each unit step-up transformer is  built by parallel connection of two tanks of 160MVA each. This plant was put in operation in 1982 when the original  protection scheme was designed using discrete electromechanical relays with induction discs. Due to aging of the existing equipment new protection scheme is needed. 2 Unit operating modes The two generator/motor-transform er units have the following  particular operating modes which need to be taken in consideration during design of the integrated protection scheme with numerical IED: 1. Generator operating mode of the unit 2. Pump operating mode of the unit 3. Synchronous start [5,6] of the unit into pump mode 4. Electrical braking of the synchronous machine for  both generator and pump operating modes Logical programming capability of the numerical multifunctional IED [1,3] makes it possible to automatically detect actual operating condition of the unit and accordingly adapt relay operation. In the following subsections different operating modes of the two units will be briefly described. 2.1 Generator and pump operating modes The main differences between the generator and pump operating modes are changes in direction of the synchronous machine rotation and change of direction (i.e. sign) of the active power flow. Change of the rotation direction  practically causes swapping of the positive and negative sequence quantities measured by the protection scheme. This must be taken into consideration during protection scheme design. Especially numerical generator protection relays can  be affected because operation of many protection functions can be based on current and voltage sequence components. 2.2 Synchronous start The 315MVA unit is started as a synchronous motor by a 100MVA generator located in the dam, with both units initially at standstill. The necessary switching is performed to disconnect two machines from the transmission system and to connect the 100MVA generating unit to the 315MVA  pumping unit. For this purpose 89S disconnector is used as shown in Figure 1. Note that the two machines are actually interconnected over short 220kV line. The fields of both units are energized and the generator turbine gates are opened to a  predetermined position. Both the generator and the motor will accelerate together. Once the full speed of rotation is achieved the pump unit is then synchronised with the 220kV transmission system, at which time the generating unit is disconnected, and consequently disconnector 89S is opened. Then the pump is loaded to approximately 300MW. Sometimes this start method is called back-to-back start in the literature. In this particular plant synchronous start is fully automatized and it takes altogether around five minutes to complete. However its operation shall be supervised by the  protection scheme and in case of any malfunction, the two machines shall be quickly separated. Synchronous start causes linear frequency variations of motor current and voltage signals from 0 to 50Hz as well as linear voltage magnitude increase from 0% to 100% at machine terminals. Such conditions will have effects on many  protection functions. Thus, the IED must be capable to measure and track the actual power system frequency in order to ensure proper operation of all protection functions integrated with the IED during this start condition.
Transcript
Page 1: 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

8/12/2019 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

http://slidepdf.com/reader/full/1mrg002497-en-integrated-protection-scheme-for-pump-storage-hydroelectric-power 1/5

INTEGRATED PROTECTION SCHEME FOR

PUMP-STORAGE HYDROELECTRIC POWER PLANT

Z. Gajić *, J. Menezes *, D. Trišić ¤, M. Čitaković ¤ 

*ABB AB; SA Products, Sweden, [email protected]¤ PD Drinsko-Limske HPP; Bajina Bašta, Serbia, [email protected]

Keywords: Generator protection, pump-storage hydro unit.

Abstract

This paper describes design of an integrated numerical protection scheme for two pump-storage generator/motor-

transformer units. Regardless of the application complexity,

the complete protection scheme for one unit can be integratedwithin a single numerical multifunctional IED.

1 Introduction

The Bajina Bašta Pump-Storage Plant is located in thevicinity of town Perućac on river Drina. Its two turbinesoperate with a net hydraulic head of approximately 600

meters between an upper reservoir located on the top of Taramountain and the lower lake formed by a dam on Drina river.Each generator/motor-transformer unit has rating of315MVA, 11/242kV, 428.6rpm. In addition to these two unitsanother four 100MVA generators are constructed within the

dam and are used as stand-alone generators.Phase reversal disconnectors are located at the high-voltage

side of the step-up transformer in the 220kV switchyard, asshown in Figure 1. A 220kV substation connecting these units

to the national grid is located 8km away. As a consequencetwo circuit breakers in series are installed on the HV side ofthe step-up transformer in order to secure separation of theunit from the system during fault conditions. Additionally,due to transport limitations, each unit step-up transformer is built by parallel connection of two tanks of 160MVA each.

This plant was put in operation in 1982 when the original protection scheme was designed using discrete

electromechanical relays with induction discs. Due to aging

of the existing equipment new protection scheme is needed.

2 Unit operating modes

The two generator/motor-transformer units have the following particular operating modes which need to be taken inconsideration during design of the integrated protection

scheme with numerical IED:1.  Generator operating mode of the unit

2.  Pump operating mode of the unit3.  Synchronous start [5,6] of the unit into pump mode4.  Electrical braking of the synchronous machine for

 both generator and pump operating modes

Logical programming capability of the numericalmultifunctional IED [1,3] makes it possible to automatically

detect actual operating condition of the unit and accordinglyadapt relay operation. In the following subsections different

operating modes of the two units will be briefly described.

2.1 Generator and pump operating modes

The main differences between the generator and pump

operating modes are changes in direction of the synchronousmachine rotation and change of direction (i.e. sign) of theactive power flow. Change of the rotation direction

 practically causes swapping of the positive and negativesequence quantities measured by the protection scheme. Thismust be taken into consideration during protection schemedesign. Especially numerical generator protection relays can be affected because operation of many protection functionscan be based on current and voltage sequence components.

2.2 Synchronous start

The 315MVA unit is started as a synchronous motor by a

100MVA generator located in the dam, with both unitsinitially at standstill. The necessary switching is performed to

disconnect two machines from the transmission system and toconnect the 100MVA generating unit to the 315MVA pumping unit. For this purpose 89S disconnector is used asshown in Figure 1. Note that the two machines are actuallyinterconnected over short 220kV line. The fields of both unitsare energized and the generator turbine gates are opened to a predetermined position. Both the generator and the motor willaccelerate together. Once the full speed of rotation is achieved

the pump unit is then synchronised with the 220kVtransmission system, at which time the generating unit isdisconnected, and consequently disconnector 89S is opened.

Then the pump is loaded to approximately 300MW.Sometimes this start method is called back-to-back start in theliterature. In this particular plant synchronous start is fullyautomatized and it takes altogether around five minutes to

complete. However its operation shall be supervised by the protection scheme and in case of any malfunction, the two

machines shall be quickly separated.Synchronous start causes linear frequency variations of motorcurrent and voltage signals from 0 to 50Hz as well as linearvoltage magnitude increase from 0% to 100% at machineterminals. Such conditions will have effects on many protection functions. Thus, the IED must be capable to

measure and track the actual power system frequency in order

to ensure proper operation of all protection functionsintegrated with the IED during this start condition.

Page 2: 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

8/12/2019 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

http://slidepdf.com/reader/full/1mrg002497-en-integrated-protection-scheme-for-pump-storage-hydroelectric-power 2/5

 

~

ROV2 PTOV

59N UN>

STEF PHIZ

59THD U3d/N

T2W PDIF

87O 3Id/I

REG670

CV GAPC

46 I2>

OC4 PTOC

51 3I>

TR PTTR

49 Ith

LEX PDIS

40   Φ<

GOP PDOP

32 P>

GOP PDOP32 P>

OEX PVPH

24 U/f>

UV2 PTUV27 3U<

OV2 PTOV

59 3U>

OC4 PTOC

51 3I>

CC RBRF

50BF 3I> BF

GEN PDIF

87G 3Id/I

Gen/Mot Selection

SA PTUF

81U f<

8km long 220kV OHL

 Aux Power 

Synch Start

CV GAPC

51/27 I>/U<

CV GAPC

21 Z<

CV GAPC

50AE U</I>

GOP PDOP

32 Q>

GUP PDUP

32 P>

SA PTOF

81O f>Y

Y

OC4 PTOC

87S 3Id>Σ

220kV CB #1

11.5 240kV V 

11 110

3 3

kV V 

220 100

3 3

kV V 

2*160MVA

234.74/11kV

Yd5

315MVA

11kV

428.6rpm

SDD RFUF

60FL

CV MMXU

Meter.

1)

2)

Note:

1) Overcurrent function used as generator diff during starting and el-braking (pickup from 2Hz)

2) Overcurrent function used during back-to-back starting and el-braking (pickup from 2Hz)

EF4 PTOC

51N IN>

89DB

Excitation

Equipment

89G 89P

52-D

El. Braking

Field CB

CV MMXU

Meter.

220kV CB #2 52-R

OC4 PTOC

51/67 3I>

PSP PPAM

78 Ucos

EF4 PTOC

51N IN>

PH PIOC

50 I>>

ROV2 PTOV

59N 3Uo>

SDD RFUF

60FL

GUP PDUP

37 P<

CC RPLD

52PD PD

89S

18000/5A

18000/5A

1200/1A

1200/1A

41

IEC 61850

 ANSI IEC

LEGEND:

CV GAPC

27SS 3U<

 

Figure 1: Application overview for the first generator/motor -transformer unit and new integrated protection scheme

2.3 Electrical braking

A period of time which is required to stop a synchronousmachine, without any additional braking actions, in many

cases can be longer than half an hour. Such prolonged low-speed operation can be dangerous for the machine bearings

due to low oil pressure. Thus, mechanical braking isfrequently used to bring the turbine and rotor of a hydro-generator to a standstill. Such brakes operate on a principle ofmechanical friction which slows down a rotating mass of thegenerator. In case of peak-load and pump-storage power

 plants where frequent unit starts and stops are required, themechanical braking does not offer the optimal solution due to

Page 3: 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

8/12/2019 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

http://slidepdf.com/reader/full/1mrg002497-en-integrated-protection-scheme-for-pump-storage-hydroelectric-power 3/5

high maintenance demands. In such cases electric braking isoften used. In this particular case after separation of 315MVAunit from the network its rotational speed reduces naturally to

50% quite quickly, however if no additional actions are takenit will take more than 15 minutes until rotor stops.

In order to speed-up this process electrical braking is applied.When unit speed falls to 50% of the rated speed, disconnector89DB is closed (see Figure 1). This operation effectivelymakes a three-phase short circuit at the machine terminals.Then the field current is applied which is sufficient to induce

80% of the rated current in the stator. These two currents willthen produce a braking torque which will stop the machine

rotor within approximately five minutes. Note that for quitelow speed of rotation, mechanical brakes are also applied.Electrical braking is used in both the generator and the pumpoperating mode.While electrical braking is active, voltage at the machineterminals will be practically zero. This will in effect disable

any frequency tracking features within numerical IED whichis based on voltage measurement [1]. At the same time the

stator current will have almost constant magnitude but withfrequency variation from approximately 25Hz down to 0Hz.Such condition will unquestionably have effect on many protection functions and special means are required to preventrelay unwanted operation and to provide dedicated protectionfunctionality for this particular operating condition.

3 Integrated protection scheme

Connected instrument transformers to the numerical IED are

shown in Figure 1. Statuses of all primary apparatuses, shown

in this figure, are also made available to the IED as double point indications. Finally additional binary signals such as:wicket-closed; speed larger than 80%; synchronous startmode selected and machine stop order are also wired to theIED. Logical programming capability of the IED is then used

in order to derive actual operating mode of the unit. Thisinformation is then used to adjust the operation of various

 protection functions integrated within the IED.

3.1 IED protection functionality

This section describes individual features and protectionfunctions integrated into the IED [1,3] for this particular

installation.Frequency tracking is available in the IED and will measureand track actual system frequency by utilizing voltage signalsat the machine terminals. This will enable use of almost all protection functions integrated within IED during all unitoperating modes with exception for electrical braking. During

synchronous start this feature will be fully operational alreadywhen measured voltage has frequency around 9Hz.Differential protections 87G and 87T  require no specialtreatment because phase reversal disconnectors are locatedoutside their protection zones (see Figure 1). However, 87Trestraint stage must be blocked during electrical braking andspecial treatment is required during extremely low frequency

condition (i.e. 2Hz-10Hz) when frequency tracking feature isnot fully operational, as described in the next paragraph.

Generator low-frequency differential protection 87S [7] isonly active while machine is in synchronous start or electrical braking operating mode. It is realized by using an overcurrent

function which measures sum of the currents from the twosides of the stator winding. Note that no biasing is required

 because external faults are not feasible during these twooperating modes. This function is able to operate fromapproximately 2Hz and it is set to 15% of the machine rating.Machine overcurrent protection 51 is realized by using anovercurrent function with four stages. Two stages are used as

time-delayed backup protection during normal machineoperation. Third instantaneous stage set at 50% of the

machine rating is only active during synchronous start whilethe fourth instantaneous stage set at 125% is only activeduring electrical braking. This function is able to operate fromapproximately 2Hz.Negative sequence protection 46  is realised by using twosequence functions. The first function measures the negative

sequence current and it is only active while machine isrotating as generator. The second function measures the

 positive sequence current and it is only active while machineis rotating as motor. Both functions have pickup and timedelay set in accordance with the machine capability.95% stator earth fault protection 59N  measuresfundamental frequency voltage at machine neutral point and itis active in all operating modes of the unit.100% stator earth fault protection 59THD is based on third

harmonic differential principle and it is active in all operatingmodes of the unit.80% stator earth fault protection 59N  measuresfundamental frequency, open delta voltage at machine

terminals and it is active in all operating modes of the unit.Under-impedance protection 21  has two zones and it is blocked during synchronous start and electrical braking.

Over-current protection with under-voltage seal-in 51/27 has one operating stage and it is blocked during synchronousstart and electrical braking.Loss of excitation protection 40  is based on ph-to-phimpedance measurement and it is blocked during synchronousstart and electrical braking.Fuse failure feature 60FL for 11kV VT is based on ΔI/ΔU

 principle and it is blocked while the machine is notsynchronised to the 220kV transmission system.Accidental energising protection 50AE is based on voltage

supervised overcurrent principle but it is blocked duringsynchronous start and electrical braking.Generator thermal overload protection 49 is based on truerms current measurement. It is active in all operating modes.Power functions 32 and 37  are using Arone-connectionwhich insures proper P and Q measurements including

directionality during all operating modes. One under-powerstage, set at 50%, is used for direct tripping in motoroperating mode (loss of power protection), while anotherstage, set at 105%, is used as active, over-power protection in both motor and generator operating modes. Other six stagesare used as inputs into the plant control system.Over-frequency protection 81O is always active.

Under-frequency protection 81U  is only active in pumpoperating mode.

Page 4: 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

8/12/2019 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

http://slidepdf.com/reader/full/1mrg002497-en-integrated-protection-scheme-for-pump-storage-hydroelectric-power 4/5

Over-voltage protection 59 measures three ph-to-ph voltagesand it is active in all operating modes.Under-voltage protection 27  measures three ph-to-ph

voltages and it is only active in pump operating mode.Under-voltage protection 27SS measures the maximum ph-

to-ph voltage. It is used as additional protection functionwhich is only active during synchronous start and whenmachine speed exceeds 80%. It shall detect that motorexcitation system has failed to transfer to permanentexcitation supply from the machine terminals. It is set to 50%

with 1s delay.Over-excitation protection 24  is based on ph-to-ph voltage

measurements and it is blocked during electrical braking.Step-up transformer HV side over-current protection 51 is realized by using an overcurrent function with four stages.Two stages are used as time-delayed backup protection duringunit normal operation. Third instantaneous stage set at 75% ofthe transformer rating is only active during synchronous start

with time delay of 0.2s.Step-up transformer HV side earth fault protection 51N is

realized by using a residual overcurrent function with fourstages. Only two stages are used and they are always active.Unit circuit breaker failure protection 50BF  is connectedto step-up transformer HV CTs and it can be used to sendinter-trip command to the remote substation in an unlikelyevent of the two 220kV breakers failing to trip.220kV OHL instantaneous over-current protection 50  isset to 9.6kA primary and it is used to instantly trip for anyfault in power plant 220kV switchyard.220kV OHL over-current protection 51/67  is used as backup protection for 8km long 220kV OHL.

220kV OHL earth fault protection 51N  is used as backup protection for 8km long 220kV OHL.Pole discordance protection 50PD  is used to detect failureof the primary apparatuses to open/close all three poles.

Pole slip protection 78 is connected to 220kV line CTs andVTs outside of the phase reversal disconnectors, whichenables use of positive sequence quantities for this protectionirrespective of the generator or pump operating mode of theunit. Function is based on Ucosφ principle.Fuse failure feature 60FL  for 220kV VT is based on

measurement of negative and zero sequence quantities and itis always enabled.

Tripping matrix  is designed to emulate existing tripping

arrangements used by discrete electromechanical relays.

3.2 IED metering and monitoring functionality

The IED provides P, Q, S, U, I, f and cosφ measurements at

generator terminals as well as for the 220kV line. Thesemeasurements are shown as on-line service values on thesingle line diagram which is available on the IED built-inHMI, (see Figure 2). This facilitates testing, commissioningand trouble shooting of the integrated protection scheme [4].Built in disturbance recorder and event list provide

information about IED operation during secondary and primary testing [4] as well as during different operating

modes of the unit. Internally calculated quantities such as P,Q, f and differential currents can also be recorded.

Figure 2: SLD with on-line measurements

Programmable LEDs provide quick operator overview about protection function which caused tripping of the unit. The

IED also displays the operating mode of the unit on the built-in HMI as determined by the logic programmed within therelay.

4 Field experience

The integrated protection scheme was put in trial services in

August 2009. Since then, operating experience wascompletely in accordance with expectations. During October

2009 minor modifications to the relay configuration andsettings were performed in order to optimize usage of the built-in disturbance recorder and event list during differentoperating modes of the unit. Additionally function 27SS wasintroduced into the scheme in order to ensure detection offailure within excitation system of the 315MVA motor unit

during synchronous start mode.The following figures come from recordings captured during

unit actual operation. Figure 3 and Figure 4 shows statorcurrent waveforms during electrical braking. Most surprisingwere waveforms for low rotational speeds (see Figure 4)which caused some spurious starting of 87S function.Figures 5 and 6 were captured during synchronous start, when

motor excitation failed to transfer to permanent supply. Atfull speed of rotation motor voltage is below 50% of rated

Page 5: 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

8/12/2019 1MRG002497 en Integrated Protection Scheme for Pump-Storage Hydroelectric Power Plant

http://slidepdf.com/reader/full/1mrg002497-en-integrated-protection-scheme-for-pump-storage-hydroelectric-power 5/5

(see Figure 6). As a consequence function 27SS wasintroduced to detect such condition.

0 20 40 60 80 100100

50

0

50

100

IL1

IL2

IL3

Gen NP Current Waveforms

Time [ms]

   C  u  r  r  e  n   t

   [   %   ]

Figure 3: Stator currents at the beginning of el. braking

0 500 1 103

1.5 103

100

50

0

50100

IL1

IL2

IL3

Gen NP Current Waveforms

Time [ms]

   C  u  r  r  e  n   t   [   %   ]

Figure 4: Stator currents at the end of el. braking (f<1Hz)

0 20 40 60 80 10040

20

0

20

40

IL1

IL2

IL3

Gen NP Current Waveforms

Time [ms]

   C  u  r  r  e  n   t   [   %   ]

Figure 5: Currents for synch. start with failed excitation

0 20 40 60 80 100100

50

0

50

100

UL1L2

UL2L3

Gen Voltage Waveforms

Time [ms]

   V  o   l   t  a  g  e   [   %   ]

Figure 6: Low voltages for synch. start with failed excitation

Behaviour of the 100% stator earth fault protection 59THD, based on the third harmonic differential measurement [2], isextremely good. Third harmonic voltages have almost

constant relationship irrespective of the actual operating modeof the unit. Figure 7 shows third harmonic voltages captured

on the unit one during pump operating mode.

0 20 40 6020

10

0

10

20

3Uo_TRMUN_NP

Third Harmonic Voltages

Time [ms]

   V  o   l   t   S  e  c  o  n   d  a  r  y

 

Figure 7: Third harmonic voltages in pump mode

5 Conclusion

Bajina Bašta pump-storage plant is crucial for everydayoperation of the Serbian power system. The two units are

typically operated in the generator mode during the day and inthe pump mode during the night. Thus, integrity of the protection scheme for these two units is essential.The new integrated protection scheme is still under trialoperation, which means that the new tripping matrix is

 blocked, but its performance is completely satisfactory. Thenext step would be to install the second identical IED to

obtain redundancy, enable the trip matrix and thendecommission the old electromechanical protection scheme.

References

[1] ABB. “Generator Protection IED REG670, TechnicalReference Manual”, 1MRK502013-UEN , (2007).

[2] I. Brnčić, et al. “Adaptive 100% stator earth fault protection based on third harmonic voltagemeasurement”, International Conference on Relay

Protection and Substation Automation of Modern EHV

Power Systems, Moscow – Cheboksary, Russia, (2007).[3] Z. Gajić. “REG670 Installation in RHE Bajina Bašta”,

ABB Doc. No. 1MRG000228 , (2009).[4] Z. Gajić. “Test Report for REG 670 installed on GM1

unit in RHE Bajina Bašta”, ABB Doc. No.1MRG000235, (2009).

[5] IEEE PSRC. “Protective relaying for pumped storage

hydro units rotating machinery protection subcommitteeof the IEEE power system relaying committee”,

Transaction on Power Apparatus and Systems, volume94, pp. 899-907, (1975).

[6] IEEE PSRC. “IEEE Guide for AC Generator Protection”,IEEE Std C37.102™-2006 .

[7] M. Stien. “Generator Protection Application Guide”, ASEA, A03-0211E , (1983).


Recommended