+ All Categories
Home > Documents > 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended...

2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended...

Date post: 05-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
93
BC hydro REGENERATION sm Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 [email protected] December 2, 2011 Ms. Alanna Gillis Acting Commission Secretary British Columbia Utilities Commission Sixth Floor - 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Gillis: RE: Project No. 3698622 British Columbia Utilities Commission (BCUC) British Columbia Hydro and Power Authority (BC Hydro) Amended F2012 to F2014 Revenue Requirements Application (F12-F14 RRA) Attached as Exhibit B-13 is BC Hydro's presentations from its Workshop held on December 1, 2011. For further information, please contact Fred James at 604-623-4317 or bye-mail at [email protected]. Yours sincerely, (10< et = Chief Regulatory Officer af/rna Enclosure (1) Copy to: BCUC Project No. 3698622 (Amended F12-F14 RRA) Registered Intervener Distribution List. British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3 www.bchydro.com B-13
Transcript
Page 1: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

BChydro REGENERATION s m Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 [email protected]

December 2, 2011

Ms. Alanna Gillis Acting Commission Secretary British Columbia Utilities Commission Sixth Floor - 900 Howe Street Vancouver, BC V6Z 2N3

Dear Ms. Gillis:

RE: Project No. 3698622 British Columbia Utilities Commission (BCUC) British Columbia Hydro and Power Authority (BC Hydro) Amended F2012 to F2014 Revenue Requirements Application (F12-F14 RRA)

Attached as Exhibit B-13 is BC Hydro's presentations from its Workshop held on December 1, 2011.

For further information, please contact Fred James at 604-623-4317 or bye-mail at [email protected].

Yours sincerely,

. ~~--~ (10< et = Chief Regulatory Officer

af/rna

Enclosure (1)

Copy to: BCUC Project No. 3698622 (Amended F12-F14 RRA) Registered Intervener Distribution List.

British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3 www.bchydro.com

B-13

markhuds
BCH 2012-2014 Revenue Requirements
Page 2: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

1

December 1 Workshop: • Amended F2012 to F2014 Revenue

Requirements • F12 & F13 DSM Expenditures • Generation Marginal Cost Model

Page 3: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

2

Introductions

Janet Fraser - Chief Regulatory Officer Fred James - Manager, Regulatory - Rates and Finance Wafi Kassam - Manager, Finance Bryan Hobkirk - Regulatory Advisor Wayne Taylor - Consultant John Duffy - Manager, DSM Planning Lyle McClelland - DSM Business Advisor Renata Kurschner - Director, Generation Resource. Dave Bonser - Engineer, Generation Resource

Page 4: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

3

Agenda 9:00 - Welcome and Workshop objectives 9:10 - Overview and Presentation of Amended Application 9:20 - 10:20 – Review of Amended Costs/Revenues

10:20 Coffee Break (20 minutes) 10:40 – Amended Appendix A – Financial Schedules 11:00 – New Appendix II – F12 & F13 DSM Expenditures

12:00 – Lunch (90 minutes) 1:30 – Generation Marginal Cost Model presentation 3:00 – Concluding remarks and wind-up

Page 5: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

4

Workshop Objectives

Amended F12-14 RRA Provide an overview of the Amended F2012 – F2014 Application. Describe how information is organized and presented. Highlight areas of change from March 2011 Application. Answer questions as to what information is in the Amended F2012 – F2014

Application.

DSM Provide overview of F12 & F13 DSM Expenditures New Appendix II. Generation Marginal Cost Model (MCM) Provide description of the MCM, its purpose and design.

Page 6: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Presentation of Amended Information

• Original Application material presented in the Amended Application

as filed in March 2011.

• Amended and new material presented as grey shaded text or grey shaded tables.

• New grey shaded tables (with actual F11 data) also denoted by letter designation. eg. New Table 4-A

• New appendices titled: i.e. New Appendix BB.

5

Page 7: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Presentation of Amended Information

6

Page 8: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Presentation of Amended Information

7

Page 9: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Presentation of Amended Information

The Amended Application, in Chapter 5 reflects the impact of the following changes :

DCEO Business Group reorganization, T&D Transformation- Initial Phase, Workforce reductions for Phase 1 & 2– 450 FTE reductions, Addition of 100 new front line operational FTEs, New outsourcing agreements.

The new Safety and Environment management structure and other

organizational changes have not been fully implemented and therefore are not completely reflected in the Amended Application. Section 5.2.2.4

8

Page 10: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Presentation of Amended Information

The impact of the following changes are reflected at the KBU level: DCEO reorganization – discussion of DCEO KBUs transferred to other

Business Groups is reflected in italics in new Business Group section, Sections 5.2.2.2, 5.5 and 5.7.

T&D Transformation- Initial Phase, Section 5.5.1.4.

Workforce reductions for Phase 1 - 300 FTE reductions, Section 5.2.2.1

9

Page 11: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Presentation of Amended Information

10

Page 12: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Presentation of Amended Information

The impact of the following changes are reflected at the Corporate level, and are discussed further in Section 5.7:

• Additional reduction of 150 FTEs over F13 & F14, Section 5.2.2.1,

• Addition of 100 new front line operational FTEs, Section 5.2.2.1,

• New outsourcing agreements, Section 5.2.2.1

11

Page 13: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Amended F12-F14 RRA Overview

• BC Hydro requesting rate increases of 8.0 per cent for F12, 3.91

per cent for F13 and F14. • DARR remains at 2.5 per cent for the three years of the test

period. • A net reduction in the revenue shortfall of $819 million over the

test period. • Load, revenue and cost of energy forecast updates. • Proposed PTP allocation change withdrawn in the Amended

Application. • Additional regulatory account transfers.

12

Page 14: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Amended Application – also includes

• BC Hydro’s Initial Response to Government Review

Recommendations – October 2011 – New Appendix CC

• Uniform System of Accounts – New Appendix DD

• F12/F13 DSM Expenditures – New Appendix II

• Auditor General Report on Deferral Accounts – New Appendix GG

13

Page 15: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Requested Order - Amendments

• Final average rate increases of 8 per cent for F2012 and 3.91 per cent for each of F2013 and F2014.

• Setting of the DARR at 2.5 per cent effective April 1, 2011 and continuing until at least April 1, 2014 (F2015).

• Approval of amended OATT rates effective April 1, 2011, 2012 and 2013.

• Deferral of increase in net Cost of Energy since March 2011 Application.

• Deferral of actual implementation costs of new outsourcing arrangements.

• Refunds of credit balances in regulatory accounts at the end of F11.

• Change in amortization period for past and future DSM costs to 15 years.

• Acceptance of DSM expenditure schedule for F12 and F13.

14

Page 16: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Summary of Reductions

15

$ million Total F12 – F14

Business Group Operating Cost Reductions -163

Increase in Forecast of Powerex Net Income -136

Higher PTP Allocation to Powerex -39

Impact of Lower Interest Rates -161

Reduction in Forecast taxes -14

Increase in Forecast Miscellaneous Revenues -26

Refund of Credit Balances in Regulatory Accounts -27

Other -10

Impact of Reductions in Forecast Capital Additions -54

Impact of Lower Actual F2011 Capital Additions -61

Impact of Change to DSM Amortization Period -101

Impact of Reductions in Forecast DSM Expenditures -7

Impact of Lower Actual F2011 DSM Expenditures -19

Total -819

Page 17: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Lower Operating Costs

• Reductions of net $163 million from March Application.

• Reductions from three different streams:

Workforce reductions Outsourcing Other operating cost reductions

16

Page 18: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Operating Cost Reductions

17

Page 19: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

18

Operating Cost Reductions

Page 20: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Higher Trade Revenue

• Increased Powerex net income by $136 million over three years (F12-F14).

• Increase is a reflection of average Powerex net income over last five years.

• Powerex net income also reflects withdrawal of proposed change to PTP charges (additional $39 million).

19

Page 21: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Lower Interest Rates

20

Page 22: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Other revenue adjustments

• Reduction in forecast taxes ($14 million).

• Increase in forecast miscellaneous revenues ($26 million).

• Refund of credit balances in regulatory accounts ($27 million).

21

Page 23: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Capital Additions – Presentation of IFRS Impact in Application and Amended Application

22

Application: • F12-14 Capital expenditures and additions were presented in CGAAP, • IFRS impacts on amortization, IDC, rate base, ROE were separately shown in

Schedule 18, to reflect BC Hydro’s transition to IFRS.

Amended Application : • F12-14 Capital expenditures and additions shown on Schedule 13 are

presented in IFRS. • This reduces capital expenditures by $541 M and reduces capital additions by

$393 M over test period. See sections 6.3.2, 6.3.5.

• IFRS impacts on amortization, IDC, rate base, ROE are removed in Amended Schedule 18, and recognized through Amended Schedule 13 – Capital Expenditures and Additions.

Change in presentation has no impact on the revenue requirements over test

period.

Page 24: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Capital Additions – Reductions from Application – Section 6.3.5)

23

New Table 6-C Capital Addition Reductions – Amended F12-F14 RRA

New Table 6-C presents the transition of F12-14 Capital Additions, from the original Application which was presented in CGAAP, to the Amended Application which is presented in IFRS. Also Includes:

• Changed circumstances: new information or project cost updates since Application • Risk based deferrals: project or program deferrals or re-prioritization • Managed reductions: includes cost management activities • See Section 6.3.5 for further discussion, New Table 6-D for list of projects & programs impacted.

Page 25: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Amended Appendices I and J

• Amended Appendix I - updated to reflect amended capital expenditures, with amended variance explanations.

• Amended Appendix J – updated to reflect change in project information, in service date, and total project cost forecasts.

• All updated or amended information is grey-shaded.

24

Page 26: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

25

DSM Impacts on Amended F12-14 RRA Revenue Shortfall

• Impact of change to DSM Amortization period from 10 to 15 Years -

($101) million reduction, see Appendix II, section 1.3.4

• Impact of reductions in forecast F12-14 DSM Expenditures - ($7) million reduction, see New Appendix II, section 3.3

• Impact of lower Actual F2011 DSM expenditures - ($19) million reduction, see New Appendix II,1.2

• Further discussion at DSM session on New Appendix II

Page 27: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Other Updates in Amended F12-14 RRA

• F12-14 Load Forecast, • F12-14 Revenue Forecast, • F12-14 Cost of Energy Forecast.

26

Page 28: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Amended Load Forecast - (Section 3.2.2)

•Application - Energy Sales Forecast based on August 2010 Update of 2009 Load Forecast •Amended F12-14 RRA – based on March 2011 Update of December 2010 Load Forecast •December 2010 Load Forecast included in New Appendix FF, to present forecast methodology.

27

Changes between Application and Amended Application due to: •Increase in load – primarily revised forecast for industrial customers •Decrease in DSM savings due to change in rate assumptions •Change in assumed real rate increases used in forecast (price elasticity) •See section 3.2.2 for further discussion

Amended Table 3-1 Energy Sales Forecast F2012 to F2014

Page 29: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

28

Amended Revenue Forecast F2012 – F2014 (Section 3.3)

Domestic Revenues($ million) F2012 F2013 F2014 F2012 F2013 F2014 F2012 F2013 F2014

1 2 3 4 5 6 7 = 4 - 1 8 = 5 - 2 9 = 6 - 3

1 Residential 1,382.4 1,371.9 1,353.2 1,405.6 1,407.4 1,398.3 23.1 35.5 45.12 Light Industrial and Commercial 1,192.9 1,170.5 1,148.0 1,213.3 1,195.0 1,178.7 20.4 24.5 30.73 Large Industrial 616.1 624.0 660.7 607.5 654.9 704.2 (8.6) 30.9 43.54 Other 112.0 117.7 136.3 111.2 117.5 144.0 (0.8) (0.3) 7.75 Revenue from Deferral Rider 90.2 98.4 108.4 89.2 94.3 99.4 (1.0) (4.1) (9.0)6 Total 3,393.7 3,382.5 3,406.7 3,426.8 3,469.1 3,524.6 33.1 86.6 118.0

F12-F14 RRA Amended F12-F14 RRA Difference

•Reasons for change to forecast domestic revenues are similar to change in forecast domestic energy sales •See Section 3.3.3 and Amended Schedule 14.0, Appendix A for further details

New Table 3-F F2012-F2014 Domestic Revenues

Page 30: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

29

Amended F2012-14 Cost of Energy (Section 4.1.3)

Amended Table 4-1 Cost of Energy Summary

•The increase in forecast Cost of Energy over F12-14 is due to increases in forecast load, increases in forecast IPP supply and revised outage schedules. •Amended Schedule 4.0 provides further detail on forecast energy costs and sources of supply.

($ million) F2012 F2013 F2014 F2012 F2013 F2014 F2012 F2013 F2014

1 2 3 4 5 6 7 = 4 - 1 8 = 5 - 2 9 = 6 - 3Cost of Energy

1 Heritage Energy 413.1 376.5 354.3 402.2 393.8 371.2 (10.9) 17.2 16.92 Non-Heritage Energy 705.3 728.1 838.4 801.0 954.5 1,098.4 95.8 226.4 260.03 Total 1,118.3 1,104.6 1,192.7 1,203.2 1,348.3 1,469.5 84.9 243.7 276.9

F12-F14 RRA Amended F12-F14 RRA Difference

Page 31: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

30

Amended F2012-14 Cost of Energy (Section 1.3.1.7)

New Table 1-C Cost of Energy Deferral

•BCH is proposing to defer $215.3 million related to the increase in forecast COE over test period, excluding the impact to COE of increased forecast energy sales and reclassification of 4 IPP Capital leases, •Deferred amount to be included in NHDA, See section 1.3.1.7.

($ million) F2012 F2013 F2014 F2012 F2013 F2014 F2012 F2013 F20141 2 3 4 5 6 7 = 4 - 1 8 = 5 - 2 9 = 6 - 3

1 Cost of Energy 1,118.3 1,104.6 1,192.7 1,203.2 1,348.3 1,469.5 84.9 243.7 276.9

Plus EPA Capital Lease Accounting:2 Operating Costs 20.6 30.0 37.7 22.8 17.5 17.9 2.2 (12.5) (19.8)3 Taxes 2.3 3.9 5.0 2.0 2.0 2.1 (0.3) (1.9) (2.9)4 Amortization 27.9 35.7 51.5 24.7 12.6 12.6 (3.2) (23.1) (38.9)5 Finance Charges 23.0 30.4 48.9 21.0 29.1 27.5 (2.0) (1.3) (21.4)6 Subtotal 73.8 100.0 143.1 70.5 61.2 60.1 (3.3) (38.8) (83.0)

7 Less Rate Revenue at April 1, 2011 Rates (3,289.2) (3,269.5) (3,283.1) (3,323.0) (3,360.1) (3,409.7) (33.8) (90.6) (126.6)8 Impact of Rate Increases (263.1) (399.6) (545.4) (245.0) (410.7) (566.4) 18.1 (11.1) (21.0)9 Subtotal (3,552.3) (3,669.1) (3,828.5) (3,568.1) (3,770.8) (3,976.1) (15.7) (101.7) (147.6)

10 Net (2,360.2) (2,464.5) (2,492.7) (2,294.3) (2,361.3) (2,446.5) 65.9 103.2 46.2

F12-F14 RRA Amended F12-F14 RRA Difference

Page 32: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Amended F12-F14 RRA DSM Appendix December 1, 2011

Page 33: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

2

DSM Appendix Structure

Appendix II Chapter 1: Introduction Chapter 2: The Need for DSM Chapter 3: DSM Costs and Benefits Chapter 4: DSM Performance Management Attachment 1: Glossary of Terms and Acronyms Attachment 2: Load Resource Balance Attachment 3: Codes and Standards Overlap with DSM Attachment 4: Initiative Descriptions Attachment 5: DSM Plan Tables Attachment 6: Assumptions Attachment 7: DSM Evaluation, Measurement and Verification Attachment 8: Prior DSM Performance Reports submitted to the BCUC Attachment 9: BCUC Directives related to DSM

Page 34: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

3

Overview

Orders sought Need for DSM DSM expenditures DSM benefits Government review DSM amortization DSM performance management DSM risk management Productivity and process improvements

Page 35: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

4

Orders Sought (section 1.1)

Acceptance of the 2-year DSM expenditure schedule of $360.7 million as being in the public interest

Approval of a change in the amortization period for DSM

expenditures from 10 years to 15 years

F2012 ($ Million)

F2013 ($ Million)

2-Year Total ($ Million)

Programs 138.3 150.1 288.4

Rate Structures 5.5 4.7 10.2

Supporting Initiatives 31.1 31.0 62.1

Total 174.9 185.8 360.7

Page 36: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

5

Need for DSM (Figure II-2-1)

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

Firm

Ene

rgy

Capa

bilit

y (G

Wh)

Fiscal Year (year ending March 31)

Load Forecast Uncertainty Existing and Committed Resources Planned Resources

2010 Mid Load Forecast Before DSM* 2010 Mid Load Forecast After DSM*

Operating Planning

* including 3,000 GWh/yr of insurance starting F2021

Page 37: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

6

Closing the Load Resource Gap (Figure II-2-3)

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

Firm

Ene

rgy

Capa

bilit

y (G

Wh)

Fiscal Year (year ending March 31)

Load Forecast Uncertainty Existing and Committed Resources Planned Resources

2010 Mid Load Forecast Before DSM* 2010 Mid Load Forecast After DSM*

Operating Planning

* including 3,000 GWh/yr of insurance starting F2021

Page 38: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

7

Cost-Effectiveness (section 2.6)

DSM is a cost-effective alternative to new power supply and electricity infrastructure DSM programs $32/MWh BC Hydro’s Reference Energy Price $129/MWh

Page 39: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

8

Updated DSM Plan (section 3.2)

Continuing the same suite of initiatives from the 2008 LTAP, updated to reflect new information on costs, energy savings and plan performance

3 tools and 6 supporting initiatives Codes and

Standards Lighting Residential Appliances Residential Electronics

Other Residential Equipment Building Codes Commercial/Industrial Equipment

Rate Structures

Residential Inclining Block Large General Service Medium General Service

Small General Service Transmission Service

Programs Residential (9) Commercial (4)

Industrial (4) Cross Sector (2)

Supporting Initiatives

Public Awareness & Education Community Engagement Technology Innovation

Codes and Standards Support Information Technology Indirect and Portfolio Enabling

Page 40: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

9

DSM Expenditures (Table II-3-3)

F2012 Plan

F2013 Plan

F2012-F2013 Total

Rate Structures 5.5 4.7 10.2

Programs - Residential 31.0 34.5 65.5 - Commercial 54.4 54.4 108.8 - Industrial 59.4 71.7 131.1 - Cross-Sector 8.1 6.4 14.5 Total Programs 152.9 167.2 320.1

Supporting Initiatives 31.1 31.0 62.1

Total Expenditures 189.5 202.8 392.3

Less: Exempt Industrial Projects (11.3) (14.7) (26.0) In Home Feedback (3.3) (2.3) (5.6)

Expenditure Request 174.9 185.8 360.7

Page 41: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

10

Program Expenditures (Figure II-4-4)

$0

$50

$100

$150

$200

$ m

illion

Incremental Savings - Programs (GWh/yr) 324 447 505

Incentive Costs ($ million) $51 $103 $118

Variable Non-Incentive Costs ($ million) $12 $15 $15

Fixed Non-Incentive Costs ($ million) $32 $35 $34

Total Program Costs ($ million) $95 $153 $167

F2011 Actual F2012 Plan F2013 Plan

Page 42: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

11

Energy Savings (Figure II-3-1)

Page 43: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Savings Breakdown (graph of Table II-3-4)

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

F2011 Actual F2012 Plan F2013 Plan

GW

h/ye

ar

Codes and Standards Rate Structures Residential Commercial Industrial

12

Page 44: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Benefits – Avoided Supply-Side Costs (section 3.5.1)

Reduced energy and capacity costs

Present value benefit (F2012-F2036) $16.4 billion

13

Page 45: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

14

Revenue Requirement Reduction (Figure II-3-2)

-400

-300

-200

-100

0

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

Fiscal Year

($ M

illio

n)

Page 46: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

15

Rate Impact (Figure II-3-3)

-7.00%

-6.00%

-5.00%

-4.00%

-3.00%

-2.00%

-1.00%

0.00%2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036

Fiscal Year

Perc

ent (

%)

Cumulative Rate Impact

Page 47: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

16

Other Benefits (sections 3.5.3 - 3.5.5, 3.8)

Economic Development Employment

Environmental

Avoided land and water impacts Reduced GHG emissions

Non-Energy Customer Benefits

Reduced maintenance costs

Alignment with B.C.’s Energy Objectives

Page 48: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

17

Government Review Recommendations (summary of Table II-3-6)

Recommendation BC Hydro Response

54 – Re-evaluate energy conservation programs

DSM Expenditures reduced $23 million

56 – Re-evaluate SMI in home display rebate program

The in-home display rebate program is being reviewed

Page 49: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

18

Persistence of DSM Program Savings (Figure II-3-4)

0

2

4

6

8

10

12

14

16

18

F2002

F2003

F2004

F2005

F2006

F2007

F2008

F2009

F2010

F2011

F2012

F2013

F2014

F2015

Year

s

Historical Forecast

Page 50: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

19

Amortization of DSM Costs (section 3.7)

BC Hydro is requesting approval to change the amortization period of DSM costs from 10 to 15 years

Page 51: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

20

DSM Performance Management (Figure II-4-1)

Page 52: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

21

DSM Performance Tracking (Table II-4-3 extract)

DSM Program Key Performance Indicators

Leading Lagging

Residential Lighting •Participation of key retailers •Participants •Energy savings •Costs

Commercial New Construction

•Energy study agreements •Incentive agreements •Identified potential customer projects

•Energy savings •Costs

Industrial Power Smart Partner - Transmission

•Energy studies completed •Energy savings identified in completed energy studies •Energy manager agreements •Incentive agreements •Identified potential customer projects

•Energy savings •Costs

Page 53: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

22

Electricity Savings Confirmation – Large Projects (Figure II-4-2)

Page 54: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

23

Risk Mitigation (section 4.5)

Begins with identification and assessment of risks Risks are assessed and mitigated at the program, initiative, and

portfolio levels

Examples of risk mitigation tactics Codes and Standards: encourage government to expedite

enactment of regulations Rate Structures: redesign rate structures Programs: modify program designs to increase participation Portfolio: shift effort between initiatives or customer sectors

Page 55: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

24

Productivity Improvement (Figure II-4-3)

Num

ber o

f Pro

ject

s

Page 56: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

25

Process Improvements (section 4.6)

Internal and external focus Examples:

Development of Power Smart Partner Express

Integration of Renovation Rebate Program in LiveSmart BC

program and partnership with FortisBC Energy

Page 57: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

26

Questions ?

Page 58: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 59: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 60: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 61: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 62: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 63: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 64: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 65: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 66: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 67: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 68: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 69: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 70: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 71: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 72: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 73: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 74: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 75: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 76: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 77: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 78: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 79: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 80: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 81: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 82: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 83: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 84: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 85: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 86: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 87: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 88: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 89: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 90: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 91: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 92: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and
Page 93: 2011 12 02 Exhibit B 13 BC Hydro December 1 2011 Workshop ... · Presentation of Amended Information The impact of the following changes are reflected at the Corporate level, and

Recommended