+ All Categories
Home > Documents > 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

Date post: 18-Jul-2016
Category:
Upload: dean-roberts
View: 6 times
Download: 1 times
Share this document with a friend
Description:
Replacement of existing diesel generators with biomas fuel, utilising rice husks that are generally waste product
18
1 One Asia Group Pte Ltd Introduction Agricultural waste is traditionally discarded, but when used in biomass gasification 1.8 kilogram yields about 1 kWh of electricity. The cost of power derived from the aquired waste would be about half of what would be spent on kerosene and diesel fuel for generators and lanterns. This development plan presents the opportunity to redevelop existing diesel powered generators that currently contribute 25 MW into the local power grid, into more efficent cleaner bio fueled driven sub stations and at the same time produce household gas that is used in almost every hosuehold across the Country and is entirely imported at high cost to the consumers Contents 1. Objective 2. Project summary 3. Background project and Bio fuel data
Transcript
Page 1: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  1    

One  Asia  Group  Pte  Ltd    

 

 

Introduction  

Agricultural  waste  is  traditionally  discarded,  but  when  used  in  biomass  gasification  1.8  kilogram  yields  about  1  kWh  of  electricity.    The  cost  of  power  derived  from  the  aquired  waste  would  be  about  half  of  what  would  be  spent  on  kerosene  and  diesel  fuel  for  generators  and  lanterns.  This  

development  plan  presents  the  opportunity  to  redevelop  existing  diesel  powered  generators  that  currently  contribute  25  MW  into  the  local  power  grid,  into  more  efficent  cleaner  bio  fueled  driven  

sub  stations  and  at  the  same  time  produce  household  gas  that  is  used  in  almost  every  hosuehold  across  the  Country  and  is  entirely  imported  at  high  cost  to  the  consumers  

Contents  

1. Objective  2. Project  summary  

3. Background  project  and  Bio  fuel  data  

Page 2: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  2    

One  Asia  Group  Pte  Ltd    

4. Required  to  develop  the  project  –  Benefits  of  using  bio  fuel  and  land  useage      

5. Planning  for  funding  6. Appendix  7. Bio  of  key  team  members  

8. Site  pictures  of  one  of  the  diesel  powered  stations  to  be  converted  into  gassification  drivers  under  the  project  

 

#1  Objective    

This   business   plan   sets   out   to   outline   the   renewable   energy   situation   in   Cambodia   and   the  opprtunities  available  to  project  development.  

Our  requirements  are  to  seek  funding  for  a  total  of  three  million  five  hundred  thousand  US$  .  With  

drawdown  on  the  funding  being  phased  in,  with  four  separate  drawdowns  for  each  subsequently  Re  -­‐   developed   diesel   powered   station   into   Bio   fuelled   power   stations   that   are   existing   Diesel   fuel  powered  assets  within  the  outer  lying  provinces  of  Cambodia.    

The  redevloped  power  stations  will  in  adittion  to  the  energy  produced  also  produce  “  Gas  “  as  a  by  

product,   the   bottled   household   gas   would   once   sold   to   consumers   contribute   to   a   very   early  repayment  of  princple  and  also  offer  very  strong  project  returns.  

Financial  forecasts  are  attached  and  indicate  very  healthy  project  returns.  

 We   look   forward   to   your   response   and   ultimate   comitment   to   joinning   us   in   this   project  development.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 3: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  3    

One  Asia  Group  Pte  Ltd    

#2  Summary    Cambodia   relies  on  nearly  100%   imported  oil   fuel   from  overseas   to  generate   the  country’s  energy  needs.     If  10%  of  expected  consumption  of  oil  diesel  used  for  projected  power  generation   in  2024  was  substituted  with  biomass,  it  would  save  the  equivalent  of  30  million  USD  of  foreign  currency.        Current  imports  of  cooking  gas  from  Thailand  and  Vietnam  is  at  10,000mt  a  month.  With  a  wholesale  price  pf  $1,000  mt  or   retail   cost   t  $1,500  a  month  which  puts  a  market  value  of  $120  million  a  yr  wholesale.  Cambodia  does  not  produce  any  cooking  gas  all  is  100%  imported.    Under   guaranteed   agreement   with   Kingdom   of   Cambodia,   Prime   Asia   Group   Cambodia   will   take  mandate   to   redevelop   existing   diesel   powered   generators   into   efficient   biomass   powered   power  generating  facilities  and  produce  and  sell  locally  produced  gas  into  the  provincial  consumer  base.    Our   mandated   development   schedule   allows   us   to   redevelop   up   to   three   power   stations   in   the  Cambodian  provinces.  Collectively  the  new  plants  will  each  produce  4  MW  of  electrical  energy  that  will   be   sold   into   the   energy   grid   under   a   power   purchase   agreement   issued   to   Prime   Asia   Group  Cambodia.        Once  commissioned,  the  first  facility  will  operate  continuously  and  is  expected  to  net  over  $18,000  per  day.  Power  plants  operated  with  local  sourced  biomass  feedstock  will  lower  electricity  costs  and  improve  local  economic  activities.        In   addition   to   the   positive   economic   impacts   the   project   will   creating   lasting   environmental  improvement   by   reducing   Cambodia’s   carbon   footprint   and   job   creation   will   support   social,  educational  and  health  strategies  of  Cambodia.        This  project  will  be  an  important  national  initiative  that  can  be  replicated  in  as  many  as  25  additional  locations  throughout  Cambodia.    The   Power   Purchase   Agreement   (PPA)   carries   a   letter   of   support   from   the   state   generator,    “Electricite  du  Cambodge“,  and  incremental    commercial  and  Political  risk  coverage  will  be  secured.    Additional  insurance  will  cover:    

• Contract  frustration  • Failure  to  honour  guarantee  ,  plus  non-­‐payment,  and  • Transferability  protection  on  earnings  made  within  the  Country  • Payback   within   second   year   after   commencement   of   operation,   positive   NPV   and   IRR  

assumption  forecast  between  30-­‐35%.    Prime  Asia  Group  Cambodia  along  with  our  established  bio  mass  power  provider,  jointly  propose  an  environmentally   responsible,   energy   generation   gasification   facility   using   agricultural  waste   as   the  feedstock,   which   will   generate   excellent   financial   returns,   guaranteed   under   agreement   with   The  Kingdom  of  Cambodia  which  will  be  supplemented  with  risk  insurance  guaranteed  by  strongly  credit  rated  political  and  project  financing  providers.    

Page 4: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  4    

One  Asia  Group  Pte  Ltd    

#3  Background  of  the  proposed  project  

With   the   on-­‐going   increase   in   oil   prices,   renewable   energy   has   been   given  more   attention   in   the  world.   Within   the   alternatives,   the   bio-­‐energy   field   has   been   considered   as   one   of   the   most  promising  alternative  renewable  energy  sources.    Already  some  countries  such  as  Brazil  have  been  using  bio-­‐energy  as  a  main  energy  supply  and  more  countries  particularly  those  which  are  land  rich  have  been  adopting  bio-­‐energy  development  plans  as  of  late.      Following  the  leads  of  several  regional  governments,  the  Government  of  Cambodia  recognising  their  country’s  oil  dependency  and  indeed  risks  on  importing  nearly  100%  of  its  oil  for  energy  use  is  now  focusing   on   alternative   sources   of   energy   and   have   now   developed   their   own   Bio   Energy  Development   program   by   encouraging   the   greater   planting   of   Sugarcane,   Cassava,   Palm   oil,  Coconuts  and  Jatropha  for  feeding  various  forms  of  bio-­‐energy.    

Source Oil Products Hydro-Electric Biomass Energy Total

Domestic Supply 0 0.004 3.620 3.624 Imported Supply 1.525 0 0 1.525 Total 1.525 0.004 3.620 5.149

Table Supply of Primary Energy in Cambodia (2005, million ton COE)

 It  is  forecasted  that  the  oil  diesel  demand  in  Cambodia  in  2005  was  about  524,000  tons  as  a  whole,  and  will  become  1,237,000  tons  in  2020.      Within  this  estimated  amount,  387,000  tons  are  supposed  to  be  used  as  a  power  generation  fuel  and  it  is  assumed  that  a  portion  of  this  total  will  be  replaced  by   biodiesel   fuel   (BDF).   Consequently,   it   is   expected   that   671,000   tons   of   BDF  will   be   required   to  cover  energy  demand  of  the  entire  country  of  Cambodia  in  2020.     Bio  energy  is  defined  as  one  important  category  of  renewable  energy.  It  consists  of  various  forms  of  energy  derived   from  biomass.   Solid  biomass  covers  organic,  non-­‐fossil  material  of  biological  origin  which   may   be   used   as   fuel   for   heat   production   or   electricity   generation.   Biogas   is   composed  primarily   of   methane   and   carbon   dioxide   produced   by   anaerobic   digestion   of   biomass   and  combusted  to  produce  heat  and  power.      The  following  are  some  of  the  positive  factors  and  conditions  to  be  mobilized  to  promote  Bio  energy  in  Cambodia:    •  80%  of  the  country  is  not  considered  to  be  under  active  management      •  Low  cost  manpower  in  cultivating  the  ground  is  available,  and  •   Potential   exists   for   developing   additional   bio   fuel   crop   sources  which  will   bring   an   incremental  income  source  for  Cambodian  farming  villages.    With  this  background  knowledge  and  experience,  Prime  Asia  Group  Cambodia   is   ideally  positioned  to  develop  sustainable  bio  energy  in  the  outer  provinces  of  Cambodia.  The  first  proposed  plant  will  provide  up   to  4  Mw  per  hour   into   the   local  grid  and  will  do  so  utilising  agricultural  waste  sourced  from   local   providers  with   approved   allocation   to   develop   up   to   a   total   of   3  more   similar   stations  within  the  Cambodian  provinces.                

Page 5: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  5    

One  Asia  Group  Pte  Ltd    

#4  Developing  this  plan  –  requirements  and  responsibilities    The  operating  company  will  obtain  the  land  allocation  for  the  project  under  a  long  term  lease  at  2$  per  sq  meter,    will  also  source  the  granting  of   the  Power  Purchase  Agreement,  known  as  the  PPA.  The  by  product  produced  from  the  gassifaction  process  will  be  gas  which  the  operating  Company  will  negotiate  with   local   importers   and   arrange   for   purchases   at   gate   of   the   project.   There  will   be   no  marketing  requirements  or  distribution  (  logistics  issues  )  all  income  will  be  paid  in  US$  cash.    Once  confirmation  of  willingness  to  confirm  funding  ability  is  received  the  “  funder  “  will  be  granted  a  stake  within  the  operating  company  that  will  be  granted  the  PPA  and  also  receive  an  equal  profit  of  all  sold  by  products  from  the  project.    The  operating  company,  once  granted  the  PPA,  will  be  required  to  hold  the  land  concession  for  the  project  under  a  20  year  lease  arrangement.      

• The  operating  company  will  be  incorporated  in  Cambodia  with  its  Parent  Holding  Company  in  Singapore    

 • All  capital  returns  and  subsequent  dividends  will  be  paid  from  Cambodia  and  be  net  of  any  

local  taxes    The  on  shore  operating  company  will  install  local  management  to  both  run  the  day  to  day  operations  as  well  as   install  an  overall  manager  to  supervise  the  operation.  We  would  welcome  an  expatriate  employee  nominated  by  the  funding  partner  to  act  in  a  senior  management  role.    Cash  funding  will  then  need  to  be  transferred  by  the  funder,   into  an  appointed  company  US  dollar  denominated  bank  account  for  the  initial  purchase  and  transportation  of  capital  goods.    Once  the  project  is  “live“,    revenue  will  start  to  accrue,  the  on  shore  company  will  then  become  the  collection  agent  supplying  all  documentary  paperwork  to  substantiate  costs  and  revenue.    On   shore   earnings   and   the   actual   contract   for   the   project   will   be   protected   at   all   times   from  expropriation  /   in  ability   to  transfer  off  shore.  The   local  operating  company  will  be  responsible   for  risk  mitigation  products.    Once  the  initial  project  is  “  on  line  “  and  producing,    we  will  make  subsequent  drawdown  on  further  funds   to  build  and   initiate  development   for  subsequent     facilities   that  under   the   terms  of   the  PPA  allow  us  to  develop  and  operate.    We  trust  this  sets  out  and  defines  the  responsibilities  and  roles  of  each  party.  We   look  forward  to  working  with  you  and  assure  you  of  our  commitment  to  project  completion  and  returns  as  projected  within  the  document.    The   following  will   set  out  planning  and   the  benefits   that  we  can  contribute   into   the  economy  and  the  provincial  network.                  

Page 6: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  6    

One  Asia  Group  Pte  Ltd    

Biofuel  energy  plant  development      Practically,   the   bio-­‐energy   project   will   be   coherently   developed   and   organized   from   plantation,  collection  of   raw  materials,   processing,   transport   and  distribution,   agricultural   training,  promotion  and  legal  framework  governing  such  as  land  use,  specification  of  mixed  fuel,  tax  and  etc.      Ideally  our  raw  material  of  choice  would  be  agricultural  waste  which  can  be  readily  collected  from  the  array  of  farms  within  the  provincial  areas.      Supply  chain  management    Our  group’s  goal  is  to  deliver  maximum  value  to  the  central  power  generating  company  for  the  least  possible  total  cost.  The  supply  chain  must  therefore  be  built  on  various  players’  role,  i.e.  farmers  as  raw  material  producers,  the  process  manufacturer  and  the  supplier  of  the  bio  energy.    Transparency  and  positive  contributions  to  the  community  are  essential.  Our  team  has  developed  strategic  on  the  ground  relationships  and  are  operating  under  a  “  fair  trade  “  policy  with  future  suppliers,  ensuring  we  share  and  develop  within  the  communities  that  touch  into.    Experienced  management  with  such  projects    We  have  secured  a   strategic   relationship  with  a   renowned  Bio  engineering  company   in  China,   this  company   has   to   their   name,   with   a   broad   array   of   bio   fuel   experience   and   operating   experience  throughout  Asia  Pacific.    Combined  with  our  operating  group  knowledge  and  experience  throughout  the  region  we  have  an  operating   structure   that   is   focused   ,   transparent   and   efficient   and   perfectly   positioned   to   ensure  management   from   the   top   down   within   plantation   and     operation/retail   system   in   power  generation.    Indirect  economic  benefits    An  inferred  benefit  from  this  project,  is  to  be  found  in  maximizing  the  state’s  opportunity  cost  from  the  available  land,  which  could  ultimately  provide  a  significant  saving  of  foreign  currency  and  extra   income   to   the   local   communities.   Consequently,   the   following   are   other   economic   benefits  when  this  project  is  implemented:    

• The   ultimate   amount   of   diesel   used   can   be   reduced   by   introducing   extra   power   market  contributions  via  bio  energy  plants;  this  hopefully,  will   lead  to  the  decrease  of  the  ultimate  cost  of  power  generation  and  transportation.  

• The  reliable  and  cheap  supply  of  energy  can  surely   facilitate   the   industrial  development   in  the  state.  

• Job  opportunity   for   local  worker   is   expected   in   the  whole   supply   chain  of  BDF  production  stage.  

• The  technology  transfer  is  expected  through  the  construction,  and  it  is  possible  to  contribute  to  the  technology  improvement  of  the  state  

 Environmental  Impact  of  using  bio-­‐fuel    Bio-­‐fuels  are  by   its  nature  very  clean  because  they  contain  few  impurities  and  due  to  their  oxygen  content   they   are   expected   to   lead   to  more   complete   combustion   and   lower   pollutants   emissions.  This   is  particularly   important   in  developing   countries.   The  environmental   effects  of  bio-­‐fuel   in  use  thus  need  to  be  monitored.        

Page 7: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  7    

One  Asia  Group  Pte  Ltd    

There  are  environmental  implications  for  bio-­‐fuel  production.  Extending  the  use  of  bio-­‐fuel  can  both  reduce  net  greenhouse  gas  emissions  and  air  pollutants  such  as  SOX  and  CO,  etc.  The  cultivation  of  energy  crops  can  also  impact  on  biodiversity,  soil  and  water  resources.  Though  the  positive  effects  of  bio-­‐fuel   use   is   considered   greater   than   the   negative   aspects,   cautious   examination   is   needed   to  assess  the  environmental  impact  of  Bio  fuel  projects.    Generally   speaking,   Bio-­‐fuel   production   project   for   transport   fuel   is   applicable   as   a   clean  development   mechanism   “CDM”   project.   However,   since   good   methodology   to   be   used   for   the  project   has   not   yet   been   approved   by   “CDM”   Executive   Board,   no   bio-­‐fuel   project   has   been  approved  as  a  qualifying  “CDM”  project.            Land  useage  and  availability    In  Cambodia,  fertile  land  is  mostly  used  for  producing  rice,  and  other  non-­‐rice  field  is  used  for  maze,  mung  bean,  soybean,  cassava  and  sugar  cane.  Rubber  is  also  an  important  crop  in  eastern  Cambodia.  The  total  cultivated  area  for  rice  was  2.3  million  ha  (MAFF  statistics,  2005)  out  of  total  agricultural  area  of  approximately  3.8  million  ha.      According   to   the   international   agencies   (World   Bank,   UNDP   and   FAO),   1.25   million   ha   of   land   is  potentially  available   for   crops  other   than   rice,   and  another  2.3  million  ha  of   shrub   lands  may  also  have  potential,  which  indicates  an  enormous  amount  of  unutilized  land.        

 Fig. Harvest of Different Crops in Cambodia (2003)  As   land  usage  modifies   and  develops   ,   alternative   sources   of   income   for   rural   poupulations   arises  from   various   land   /   forest   clearance   projects   which   offers   income   sources   such   as     fire   wood,  charcoal  and  timber  as  an  important  source  of  alternative  income  other  than  agricultural  resources  for  the  rural  populations  that  these  projects  impact.    All  said  and  done,  our  requirements  for  the  “ideal”  land  parcel  are  as  follows:    

• 2  hectares  amount  of  land  allocation    • Accessible  to  road  network  (  tarmac  road  )  • Linkable  into  the  local  grid    • Ready  access  to  supply  of  Bio  fuel    (  no  more  than  100Km  )  

Page 8: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  8    

One  Asia  Group  Pte  Ltd    

• Clear  operating  process  with  the  local  supplier  source  that  we  select  as  being  most  efficient  to   our   project(s),   we   would   also   consider   placing   some   of   our   heavy   equipment   into   the  facility  to  help  their  processing  quality  and  quantity.  

• Land  will  be  leased  to  the  operating  group  ,  with  all  documentation  in  English    #5  Planning  for  Funding    We  are  looking  for  either  equity  funding  or  an  outright  loan  for  this  project.  The  following  cash  flows  will   provide   “payback   “within   the   first   year   after  operations   commence,  will   provide  positive  NPV  and  very  healthy  IRR  returns.      Please  refer  below  for  further  details:    Financial  and  Economic  Analysis  of  developing  Bio  fuel  power  generating    plant      The  following  financial  analysis  is  carried  out  based  on  the  cost  and  revenue  incurred  from  the  development  project.    The   project   cost   estimation   is   carried   out   on   the   following   premises;   the   following   costs   are   not  incurred:  

• Environmental  Impact  Assessment  (EIA)  • License  application  fee  for  project  implementation  • Compensation  for  relocation  on  any  related  project  sites  • Import  tax  of  related  consumable  materials  and  equipment  • Utility  service  fee  during  plant  construction  (electricity  and  water)  • Fuel  and  electricity  for  trial  operating  period    

Forecast  Data  

*  Investor  Data:  

-­‐  Capital  Investment:  Per  4MW  generator  plant  USD  $  2,500,000.00      

-­‐  Bio  Power  Capacity:  MW  Per  constructed  station  

-­‐  Agricultural  waste  consumption:  30,000  MT/  yr.  

-­‐  Agricultural  waste  Price:$20$/MT    

*  Local  Data:    

-­‐  PPA  Period:  20    years  

-­‐  Daily  Period:  20-­‐24  hrs  

-­‐  Electricity  Price:  $0.20/kwh  (Guaranteed  from  the  PPA  )                  

Page 9: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  9    

One  Asia  Group  Pte  Ltd    

Construction  Costs    We  have  estimated  the  construction  costs  of  the  plant:      Construction   Costs  

Purchase  of  Land  (leased)    $220,000.00    

Engineering  Cost    $200,000.00    Engineering  Service    $  60,000.00    Commercial  /  political  Insurance    $  200,000.00    Total    $680,000.00      

REVENUE:  

Assumption  1      Data  assumption  on  Biomass  $  per  Kwh   0.20      Total  Kwh   28,800.00        MWH   1      Total    $    5,760,000.00          

Calculation  2:    based  on  local  data  consumption.  

Assumption  2  Local  consumption  $  per  Kwh   0.20  Kw  total   4,000.00    days   360  hours   20  Total      $  5,760,000.00    Note  -­‐  If  18hrs/day  consumption  then  revenue:  $5.184  

EXPENSES:  

Calculation1:  20hrs/day.  

Expenses   Totals          

Waste  @  $20  per  MT   $1,040,000.00     52,000      

Manpower  $  300  per  *  10  pax       $36,000.00      P  /a  cost      

Maintenance  1.5%   $10,200.00,     of  construction  costs  

Total   $1,086,200.00            

 

 

 

 

Page 10: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  10    

One  Asia  Group  Pte  Ltd    

Calculation2  :  18hrs/day.  

Expenses   Totals    18  hour  day  

Waste  @$20  per  MT   $576,000.00      28,800  

Manpower  $  300  *  10  pax       $36,000.00      P/a  cost      

Maintenance  1.5%   $10,200.00        of  construction  costs  

Total   $622,200.00            

 

MARGIN:  

Calculation1.  

Margin        20hr  day  

Revenue   $5,760,000.00    

Expenses   $1,086,200.00  

Total   $4,673,800.00    

 

Calculation2.  

Margin       18  hr  day  

Revenue   $5,184,000.00    

Expenses   $622,200.00    

 Total     $4,561,800.00    

 

NET  MARGIN:  

Net  Margin       20  hr  day  

Revenue   $5,760,000.00    

5y  Amortised  Sunk  costs  and  expenses   $1,586,200.00    

 Total     $4,173,800.00    

*  note  –  this  ignores  any  income  from  gas  sales  which  is  conservatively  forecast  at  2million  US$  with  

no  other  added  expenses.    

Calculation  2  .  

Net  Margin        18  hr  day  Revenue   $5,184,000.00    5y  Amortised  Sunk  costs  and  expenses   $1,122,200.00      Total     $4,061,800.00  *  note  –  this  ignores  any  income  from  gas  sales  which  is  conservatively  forecast  at  2million  US$  with  

no  other  added  expenses.    

 

 

Page 11: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  11    

One  Asia  Group  Pte  Ltd    

Year  2  Forecasts:      

On  Going  Costs   Costs  Engineering  Cost    $100,000.00    Engineering  Service    $  50,000.00    Commercial  /  political  Insurance    $  200,000.00    Total    $350,000.00      

Revenue  

Assumption  1      Data  assumption  on  Biomass  $  per  Kwh   0.20      Total  Kwh   28,800.00        MWH   1      Total    $    5,760,000.00          

Calculation  2:    based  on  local  data  consumption.  

Assumption  2  Local  consumption  $  per  Kwh   0.20  Kw  total   4,000.00    days   360  hours   20  Total      $  5,760,000.00    Note  -­‐  If  18hrs/day  consumption  then  revenue:  $5.184  

EXPENSES:  

Calculation1:  20hrs/day.  

Expenses   Totals   24  hour  day      Waste  @  $22  per  MT   $1,232,000.00     56,000       +10%  to  22$  

Manpower  $  330  *  10  pax     $26,400.00     +10%  330$        

Maintenance       $10,500.00     estimate  against  previous  year  

Total   $1,268,900.00              

 

 

 

 

 

Page 12: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  12    

One  Asia  Group  Pte  Ltd    

Calculation  2:  18hr/day  

Expenses Totals 18 hour day Waste @ $22/MT $1,029,600.00 46,800 +10% Manpower $ 330 * 10 pax $39,600.00 +10% Maintenance $10,500.00 estimate against previous year Total $1,079,700.00    

MARGIN:  

Calculation1.  

Margin       20  hr  day  

Revenue   $5,760,000.00    

Expenses   $1,268,900.00  

Total   $4,491,100.00    

 

Calculation2.  

Margin        18  hr  day  

Revenue   $5,184,000.00    

Expenses   $1,079,700.00  

 Total     $4,104,300.00    

 

NET  MARGIN:  

Net  Margin       20  hr  day  

Revenue   $  5,760,000.00    

On-­‐going  costs   $350,000.00    

 Total     $  5,410,000.00    

*  note  –  this  ignores  any  income  from  gas  sales  which  is  conservatively  forecast  at  2million  US$  with  

no  other  added  expenses.    

Calculation  2  .  

Net  Margin       18  hr  day  

Revenue   $    5,184,000.00    

On-­‐going  costs   $    350,000.00    

 Total     $  4,834,000.00    

*  note  –  this  ignores  any  income  from  gas  sales  which  is  conservatively  forecast  at  2million  US$  with  

no  other  added  expenses.    

Page 13: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  13    

One  Asia  Group  Pte  Ltd    

 

After  adjustments  for  cost   increases  with  fixed  PPA  revenue  total  net  margin  under  scenario’s  one  

and  two  still  both  indicate  strong  financial  returns  we  have  assumed  initial  equity  investment  being  repaid   in   the   first  year  after  commencement  of  operations.  However,  we  will  most   likely   chose   to  depreciate  the  capital  expenditure  over  the  frst  5  years.  Please  note  the  PPA  guarantees  prices  fixed  

for  the  first  five  years  of  operation.  

Taxes    Import   Tax   for   machinery   and   equipment’s   to   be   used   for   the   construction   is   deemed   to   be  exempted.  The  VAT  shall  be  also  exempted.    Depreciation    Depreciation  period:  5  years  -­‐  Selection  of  depreciation  method:  Assume  the  salvage  value  of  the  total  initial  investment  will  become  0  (null)  in  5  years,  and  the  value  redeemed  evenly.  (  estimate  10  year  life  is  more  likely  ).                                                                      

Page 14: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  14    

One  Asia  Group  Pte  Ltd    

References    

1. All  capital  expenditure  data  has  been  sourced  from  similar  such  Bio  energy  projects  such  as  the  Pepsi  cola  sponsored  Bio  energy  development  in  the  Philippines.    

2. Forecasts  have  been  based  upon  known  power  purchase  levels  within  Cambodia.  3. Background   data   has   been   gathered   from   ADB   alternative   power   development   research  

papers.  4. Clean   Biz   Asia   has   also   been   used   as   a   reference   source   for   data   and   background  

information.    #6  Appendix        #1   <http://www.phnompenhpost.com/index.php/2012101059210/Business/renewable-­‐energy-­‐used-­‐for-­‐rice-­‐milling.html>    Wednesday,  10  October  2012  Rann  Reuy    The  Federation  of  Cambodian  Rice  Millers  Association  in  Battambang  province  will  establish  a  biomass-­‐generated  electricity  plant  in  Battambang,  an  insider  said.  The  plant  will  cost  up  to  US$10  million  and  generate  10  megatwatts  of  electricity.      Phou  Puy,  president  of  the  Federation  of  Cambodian  Rice  Millers  Association  (CRMA)  and  the  Baitong  Rice  Export  Company,  said  he  is  scheduled  to  sign  a  contract  with  a  Malaysian  firm  in  the  upcoming  days  to  set  up  the  power  plant  operated  by  biomass  from  rice  husks  for  generating  the  power.    Yesterday  Phou  Puy,  who  did  not  remember  the  name  of  the  Malaysian  firm,  confirmed  that  the  biomass  generator  was  a  project  being  completed  in  cooperation  between  his  company  and  a  Malaysian  firm.      “We  are  preparing  to  sign  a  contract  with  each  other.  The  plant  is  worth  $10  million  with  the  capacity  to  generate  10  megawatts,”  he  said.      Phou  Puy  said  the  intention  of  creating  the  plant  is  to  cut  the  cost  of  processing  milled  rice  to  enhance  the  competition  capacity  in  the  market  and  use  thousands  of  tonnes  of  rice  husks  which  are  otherwise  useless.      “It  is  important  to  reduce  the  cost  of  producing  milled  rice  for  export,  we  will  save  some  money  by  using  rice  husks  that  would  normally  be  poured  into  the  ponds  uselessly,”  he  said.  “We’re  establishing  the  biomass  plant  for  use  in  our  rice  milling  factory,  and  for  supplying  electricity  to  our  federation  members.  It  could  be  ready  in  late  2013  or  in  early  2014.”      Victor  Jona,  Deputy  Director  General  at  the  Department  of  Energy  in  the  Ministry  of  Industry,  Mines  and  Energy,  said  officials  did  not  yet  have  official  statistics  of  biomass  generators  in  Cambodia,  but  the  trends  for  establishment  of  these  machines  have  been  increasing  at  rice  milling  sites  because  the  owners  want  to  use  rice  husks  to  generate  electricity.    He  said  in  the  next  year,  a  26-­‐megawatt  power  plant  would  also  start  operating  in  a  sugar-­‐cane  production  factory  in  Kratie  province.      

He  added  that  the  government  encourages  the  establishment  of  renewable  plants  through  not  applying  import  taxes  on  materials  used  to  build  them.  

#2  <http://www.cleanbiz.asia/news/cambodia-­‐rice-­‐husk-­‐biomass-­‐energy-­‐project-­‐signs-­‐ge#>  

Page 15: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  15    

One  Asia  Group  Pte  Ltd    

US-­‐listed  GE  has  revealed  that  the  SOMA  Group  is  to  use  GE’s  Waukesha  gas  engine  technology  to  power  a  new  rural,  rice  husk  biomass-­‐energy  project.      The   project   is   Cambodia’s   first   integrated   biomass   gasification-­‐gas   engine   solution   designed   to  supply   renewable   electricity   to   the   local   grid   in   support   of   the   country’s   Cambodia   Rice   Husk  Biomass-­‐Energy  Project  rural  electrification  goals.    SOMA,  a  leading  Cambodian  industrial  conglomerate,  and  GE  signed  the  contract  during  a  US-­‐ASEAN  Business  Council  (USABC)  and  US  Chamber  of  Commerce-­‐sponsored  forum  in  the  city  of  Siem  Reap  in  northwestern  Cambodia.  Ministry  level  officials  from  the  US  and  Cambodia  were  both  present  at  the  signing.      The  Hak  Se  mill  biomass  gasification  project  is  in  the  country’s  rural  rice  milling  region  of  Kamphong  Cham   and   will   be   developed   by   Ankur   Scientific   Energy   Technologies   a     technology   company   in  renewable  energy  technologies  based  in  India.      The  rice  husk  will  be  converted  into  biogas,  which  then  will  be  used  in  two  GE  VHP  5904  Waukesha  engines  to  generate  a  total  of  a  1.5  megawatt  (MW)  of  renewable  electricity.  Part  of  the  power  will  support   the   rice  mill’s   operations   while   surplus   electricity   will   be   sold   to   the   local   grid.   The   new  power  plant  is  expected  to  begin  commercial  service  in  March  2013.    By   recycling   rice   mill   waste   into   biogas   to   support   the   local   grid,   the   SOMA   Group   project   is  supporting  Cambodia‘s  Rural  Electrification  Program  that  seeks  to  supply  electricity  to  every  village  by  2020  and  to  connect  70  percent  of  the  country’s  households  to  the  grid  by  2030.  Currently,  only  50  percent  of  rural  villages  have  access  to  electricity  with  demands  for  power  growing  at  25  percent  a  year.    The   deal   is   the   first   since   GE   and   the   Cambodian   government   signed   a   2011   alternative   energy  development   agreement   to   identify   opportunities   to   use   GE’s   technology   to   meet   the   country’s  energy challenges.  Biomass  in  the  Philippines  

 #  3  <http://www.cleanbiz.asia/news/philippines-­‐looks-­‐rice-­‐biomass-­‐source-­‐energy#>  

DP  CleanTech,  a  Chinese  biomass  and  waste-­‐to-­‐energy  business,  won  a  contract  to  build  a  facility  in  the   Philippines   that   will   use   rice   husk,   rice   straw   and   woodchips   to   produce  power,  Bloomberg  reports.   DP   CleanTech   will   build   the   12-­‐MW   power   plant   for   AseaOne   Power Corp.,   the   Beijing-­‐based   company   said   today   in   an   e-­‐mailed   statement.   The   value   of   the   contract  wasn’t  disclosed.  Construction  of  the  plant  in  the  Aklan  province  is  expected  to  start  in  October  and  it  may  begin  working  in  April  2014,  according  to  the  statement.Key  

#7  Team  Members    Bio    Data  

Our  lead  Project  Manager    

A  High-­‐Tech  enterprise  with  more  than  10  patents,  specializing  in  researching,  developing,  manufacturing,  selling  green  energy  products  and  selling  biomass  gas.  The  group  has  accumulated  considerable  experience  in  R&D  within  the  renewable  energy  sector.  Experienced  within  biomass  energy  produced  from  rice  husk  ,  palm  shell,  wheat  straw,  cotton  stalk,  bagasse,  wood  chip  and  even  sludge.    

Our  lead  engineering  partners  

Page 16: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  16    

One  Asia  Group  Pte  Ltd    

Our   lead   engineers   have   extensive   power   industry   experience   throughout   central   Asia   and  Africa.  

The   group   are   experienced  with  operational  management   in   the   growing   economies  of   the  world  and  bring  with  them  seasoned  professionals  within  the  group.  

Specialties  

• Experienced  in  development  of  power  projects,    • Renewable  energy  knowledge  and  applications  • Hard  commodity  markets  such  as  the  oil  industry.  

 Our  lead  Coordinator  

An  MBA  graduate  with  extensive  Asia  Pacific  experience  within   the  AsiaPacific   region.  He  has  held  strategic  management  positions  throughout  the  Asia  Pacific  region  and  over  this  time  has  developed  and   maintained   strong   contacts   and   references   within   the   business   community.      Specialties  

• Identification  of  strategic  business  alliances  

• Subsequent  project  management  • Identification  and  management  of  inherent  project  /  financial  risks  • Information  technology  

• Business  intelligence  

Our  combined  team  tenor  within  this  area  affords  the  project  host  as  well  as  the  financing  party  well  over  50  years  of  total  project  and  product  experience.  

Site  pictures  for  one  of  the  Diesel  powered  generators  that  will  be  taken  off  line  under  this  project:  

Page 17: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  17    

One  Asia  Group  Pte  Ltd    

Page 18: 2014 OAG Bio Power - Project Replacement of Existing Diesel Plants to Gassification April 2014

 

  18    

One  Asia  Group  Pte  Ltd    


Recommended