Please insert new cover image 9cm (H) by 30.48cm (W) Working together for a safer world 2014/94/EU Directive & Port infrastructure: The Poseidon Med II, elemed & CYnergy experience Panayiotis Mitrou Technology & Innovation Manager Marine & Offshore, South Europe International Multidisciplinary Conference on Sea, Traffic and Logistics 2017 22 nd November 2017 Rijeka, Croatia
Transcript
Page 1: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

Please insert new cover image – 9cm (H) by 30.48cm (W)

Working together for a safer world

2014/94/EU Directive & Port infrastructure:

The Poseidon Med II, elemed & CYnergy experience

Panayiotis Mitrou Technology & Innovation Manager

Marine & Offshore, South Europe

International Multidisciplinary

Conference on Sea, Traffic and Logistics

2017

22nd November 2017 Rijeka, Croatia

Page 2: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Forces Driving Change

Policies Technology Societal Needs

Page 3: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Societal Challenges NOx-PM-Noise

EURO VI

90% of the Societal Impact comes from NOx and PMs (US Ports Research)

Marine Engines NOx Emission limits 30-40 times greater than EURO VI (Cars)

Page 4: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

EU Directive 2014/94 & national framework

The deployment of alternative fuels in transport

sector

• Minimum levels of infrastructure across the

EU

refuelling & charging points

natural gas, hydrogen, electricity

National policy frameworks

• EU wide standards for the infrastructure

Common & standardised equipment

Future standards (battery swaping)

• Clear consumer information to facilitate use

of alternative fuels

in Greece

National Policy Framework on

alternative fuels

Legislation

Policy measures

Infrastructure development

financing

Photo source: Safety4Sea

Page 5: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

LNG as Fuel in the Mediterranean

100

stakeholders

136

million euro

Page 6: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Countries Greece, Cyprus, Italy

Ports Venice, Igoumenitsa, Patras,

Piraeus, Heraklion, Limassol

Duration: June 2015 – Dec 2020

Budget: ~€53M

Coordinator

:

Public Gas Corporation

Technical

Coordinator

:

Hellenic Gas Transition System

Operator

EU

financing:

50% CEF

Page 7: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Partners

Page 8: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

42nd Interferry Conference

LNG bunkering

in 5 ports

design

Retrofit/ new

buildings

shipyards

assessment

Regulatory

framework

financial

assessment

Page 9: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

LR @ Poseidon Med II

AiP for new building

designs

Port Risk – HAZID

Exclusion Zones

Navigational

simulations

Quantity-Quality

verification

Shipyards

preparedness

HAZOP & AiP

vessels retrofit

Page 10: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Regulatory framework

Presidential Decree for LNG Bunkering

operations

Quantity & quality measurements across the

LNG bunkering supply and custody transfer

chain

Page 11: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

• Establishment of a Natural Gas

supply and distribution system in

Cyprus

• FSRU as Focal point

• Optimization of the upstream,

midstream and downstream NG

facilities

Page 12: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

• Countries: Greece & Cyprus

• Duration: April 2017 – March

2020

• Budget:

• Total: €7.470.000

• CEF Contribution: 60%

About

Page 13: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

42nd Interferry Conference

Pillars of action

Define NG supply, storage, trade & distribution schemes

Develop technical & operational designs & studies for FSRU

Develop implementation plan for NG in road transportation

Develop implementation plan for NG for industrial-commercial use

Develop implementation plan for NG for maritime transport

Preparing financing structures

Page 14: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

• HAZID:

jetty terminal lay out & FSRU gas export operations on site

identification of failure scenarios and risk reduction measures

• HAZOP:

assess hazard potential of mal-operation/ mal-function of items

of equipment

assess the consequential effects on the facility as a whole

• QRA:

verify/quantify potential MAH associated with design, systems,

ops at concept level

identify drawbacks, regulatory non-compliances, provide

recommendations as part of EIA

• Regulatory framework:

legal/ regulatory framework in CY, as well as rules, standards,

guidelines within EU

LR @ CYnergy

Page 15: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

3 Member States – Participating

Ports:

• Piraeus – Killini (Greece)

• Limassol (Cyprus)

• Koper (Slovenia)

Cross-european maritime network

and macro-regional strategies for

Adriatic-Ionian Seas

First Cohesion Fund project in Motorways of the Sea

Page 16: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

The Consortium

Hellenic Lloyd's SA

National Technical University of Athens

Piraeus Port Authority

Killini Port

Cyprus Ports Authority

Port of Koper

Hydrus Engineering Ltd

Spanopoulos Group

Protasis SA

Hellenic Centre for Marine Research

Page 17: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

42nd Interferry Conference

Port engineering

designs

cold-ironing

All-electric RoPax

vessel

Regulatory

framework

Financial

analysis

Engineering

designs for vessels

OPS at Killini Port

All-electric

ships 1st OPS in East

Med

Conceptual

design

Cold ironing

& shipping

electrification

Ships & ports

FEED

detailed

Page 18: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

LR @ elemed

Risk assessment

For vessels

AiP

For electric ship

Risk assessment for ports

Training

OPS & Safety

Shipyards preparedness

Techno-economic assessment

Potential vessels

Page 19: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Killini Cold Ironing Installation

• First operational On-Shore Power

connection for a Ro-Pax serving

Zakinthos & Kefallonia islands

• Supply 1 berthing position

• 500 kVA needs during port stay

• 4 Shore connections projected

• 1 electric bunkering position

projected

Page 20: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Funding - New tools EIB GSS CEF EFSI

Connecting Europe Facility (TEN – T)

‘Motorways of the Sea-Cohesion Fund ’

EFSI – European Fund for Strategic

Investment (Juncker Package)

Blending Call

350 + 270 Million

Alternative Fuels infrastructure

April 12 deadline

Page 21: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Innovation as KEY to Growth

Page 22: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

How LR can help you

Risk

Assessment

Studies

Funding options through

Environmental Societal

Due Diligence

LNG as Fuel

Advisory

Optimised Port

Operations

Shore Power

Compliance

International

Standards

Safety & Security Carbon Footprint

Page 23: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

STL 2017 Conference

Concluding Remarks

Ports as the critical link between efficient sea and shore transport

Shipping Societal impact stemming from Port and Close to Port

operations

Alternative fuels pose both opportunities and risks,…competition

Be prepared for further regulatory action

Start today , explore options, plan well ahead

Keep the time factor in mind We as LR are here to assist you towards a

sustainable Future for port operations

Page 24: 2014/94/EU Directive & Port infrastructure: The Poseidon ... LR... · jetty terminal lay out & FSRU gas export operations on site ... Conceptual design Cold ironing & shipping electrification

Panayiotis Mitrou

Technology & Innovation Manager

Marine & Offshore

South Europe

E [email protected]

Lloyd’s Register and variants of it are trading names of Lloyd’s Register Group Limited, its subsidiaries and affiliates.

Copyright © Lloyd’s Register Group Limited. 2017. A member of the Lloyd’s Register group.

www.lr.org

Thank you for your attention.