Alanhurst/Cherrycrest Storm Drainage Improvement Project Andrews United Methodist Church June 2, 2015 Proposed Design Presentation and Easement Acquisition Kick-Off Meeting
Transcript
Page 1: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst/Cherrycrest Storm Drainage Improvement Project

Andrews United Methodist ChurchJune 2, 2015

Proposed Design Presentationand Easement Acquisition

Kick-Off Meeting

Page 2: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Introduction of Staff• Charlotte-Mecklenburg Storm Water Services

– Danée McGee– Project Manager Phone - 704-336-4102 E-mail - [email protected]

– Doug Lozner – Watershed Area Manager

• City of Charlotte Real Estate Services– Greg Van Hoose– Sr. Project Manager

• WK Dickson – Engineer Consultant– Scott Sigmon – Project Manager – Marc Horstman– Project Engineer

• THC Inc. – Real Estate Consultant– TBD

Page 3: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Reminders• Sign-In• Agenda, and other handouts• Customer Service Comment Cards• General question and answer

period after presentation.• Property specific questions

in small group break-out sessions.

Page 4: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Agenda• Summary of project progress and

current status• Present the designed proposed

improvements• Discuss the easement acquisition process• Respond to general questions and concerns• Provide owners property-specific

information on property impacts

Page 5: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Project PhasesPLANNING (May 2012 to December 2013)

• Existing Conditions Analysis – Finding the Problems• Alternative Analysis – Finding the Solutions

DESIGN (Started May 2014 - Typically 21 to 34 mo.)– Designing the Solutions

PERMITTING (Typically 3 to 9 months, but usually overlaps the design phase)

EASEMENT ACQUISITION (Typically 8 to 12 months)BID (Typically 4 to 5 months)CONSTRUCTION (Approximately 2 years)

Page 6: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

– Survey, Public Input & Questionnaires• Original questionnaires were sent out in September of 2011

– Existing Conditions Analysis• Public Meeting – Held on March 1, 2012

– City Design Standards Alternative– Additional Alternatives– Preliminary Alternatives Cost Estimates– Recommended Alternative

• Public Meeting – Held on October 29, 2013

Planning Phase(May 2012 to December 2013)

Page 7: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• The Design Phase Generally Consists of the Following:– Preliminary Design– Permitting– Easement Acquisition– Final Design

Design Phase

Page 8: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Preliminary Design– Drainage system layout & location– Additional field survey– Utility coordination & design– Geotechnical investigations– Traffic control plans– Erosion control plans– Public meeting

Design Phase(Completed Tasks)

Page 9: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst/Cherrycrest Proposed Storm Drainage

ImprovementsScott Sigmon, P.E.

WK Dickson

Page 10: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

Page 11: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

No endwalls

Alanhurst Place Culvert

Erosion

Page 12: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

Rusted pipe

Page 13: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

Bank erosion

Page 14: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

Channel erosion

Pipe in need of repair

System I – Braxfield Drive

3 foot drop

Page 15: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

Bank erosion

Page 16: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

System E – near stream

Flow under pipe

Pipe separation

Page 17: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

N

SO

UTH

BLV

D

I-77

System L

Pipe cracking

Pipe separation with soil infiltration

Page 18: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Closed systems A through N• Bank stabilization

Review of preferred alternatives

Page 19: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place CulvertInlets added to reduce street flooding

Page 20: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Pipe will be videoed for condition assessment

Page 21: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Culvert is in poor condition

Inlets and additional pipe systems added to reduce street flooding

Page 22: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Pipes are undersized

Adding inlets and upsizing pipes reduces overland flooding

Page 23: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Inlets added to reduce street flooding

Pipe are in poor condition

Move the alignment to City right-of-way

Page 24: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Inlets added to reduce street flooding

Adding inlets and upsizing pipes reduces overland flooding Inlets added to reduce

street flooding

Page 25: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Page 26: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Pipes are undersized

Adding inlets and upsizing pipes reduces overland flooding

Page 27: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Pipes are undersized

Adding inlets and upsizing pipes reduces overland flooding

Page 28: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Pipes are undersized

Adding inlets and upsizing pipes reduces overland flooding

Page 29: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place CulvertInlets added to reduce street flooding

Pipes are undersized

Adding inlets and upsizing pipes reduces overland flooding

Page 30: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets and additional pipe systems added to reduce street flooding

Page 31: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Inlets and additional pipe systems added to reduce street flooding

Pipe are undersized

Page 32: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Stream bank stabilization to reduce erosion

Stream bank stabilization to reduce erosion

Page 33: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Alanhurst Place Culvert

Inlets added to reduce street flooding

Inlets and additional pipe systems added to reduce street flooding

Rehabilitate three existing metal culverts

Page 34: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Next Steps

• Complete Design- Permitting - Easement Acquisition- Final Design

• Bid• Construction

Page 35: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Permitting– 401/404 permit

(NC Dept of Water Quality / Army Corps of Engineers) Channel/stream & wetland delineation

Channel impacts & limits Wetland impacts & limits

– DENR/Erosion Control

Design Phase(Ongoing Tasks)

Page 36: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Easement Acquisition– An easement is a right to use land owned by

another party for a specific purpose. – Easements provide Storm Water Services with

permission from property owners to come onto their property and repair drainage problems and perform on-going maintenance.

– Granting an easement does not reduce the size of your property, but it does create some limitations on the use of the area.

Design Phase(Ongoing Tasks)

Page 37: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

Types of easements for drainage purposes

• Storm Drainage Easement (SDE) Grants access to a specific portion of the property for the purpose of repairing and maintaining a storm drainage system including creeks.

• Temporary Construction Easement (TCE)Are not permanent easements. They give us the right to access your property to construct this project only.

Page 38: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Final Design– All permits have been obtained– All easements have been acquired– Construction plans are completed

Design Phase

Page 39: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Bid process includes:• Bid advertisement• Bid opening• Recommendation for approval and City

Council award• Pre-construction meeting

Bid Phase

Page 40: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Notification to residents• Contractor begins work• Emails or mailers with progress updates• Final walk through with contractor• Accept project• Start warranty

Construction Phase

Page 41: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• A representative from THC will contact you if we need an easement for construction and/or maintenance purposes

• Obtain Applicable Permits• Finalize the Design

We will NOT have another public meeting prior to bid and construction

Path Forward

Page 42: 2015-6-2%20A%20C%20RE%20Public%20Meeting%20#3%20[1]

• Please remember to sign-in and fill out a customer service card

• The City and our consultants will stay here to answer any specific questions you may have

• General Discussion• Small Group Discussions

Thank you for coming to the meeting!