2015 SAE Aero East Design Team2015 SAE Aero East Design Team
2015 SAE Aero Design East Team
Status Report(April 2, 2015)
2015 SAE Aero East Design Team2015 SAE Aero East Design Team2
SAE Aero East 2015 TeamProject Advisor
Dr. Drew Landman
Team MembersAndrew Tonkovic
Chris ThurmanGreg ShivelyKevin RhamyLucas Mills
Mason HunerkochMichael Lauruska
Ryan LaporteSara Mendelsohn
William Fisher
Team LeaderJeremy Newman
2015 SAE Aero East Design Team2015 SAE Aero East Design Team3
Overview• Project Schedule• Competition Objectives• Design Summary• Competition Summary• Competition Results• Discussion• Recent Work• Future Work
2015 SAE Aero East Design Team2015 SAE Aero East Design Team4
Project Schedule
2015 SAE Aero East Design Team2015 SAE Aero East Design Team5
Competition Objectives• Overall length, height and span of the aircraft cannot
exceed 175 inches• The maximum weight cannot exceed 55 pounds• The use of fiber-reinforced plastic is prohibited• Payload bay dimensions of 10” x 4” x 4”• Unload and reload payload in one minute• 1000 watt power limiter • Take off in 200 feet, fly a 360 degree circuit, and land
in 400 feet
2015 SAE Aero East Design Team2015 SAE Aero East Design Team6
Design Summary• Utilized Modified Pratt Truss to minimize weight• Optimized cargo weight capacity • Produced high lift coefficient• Maximized ground effect
2015 SAE Aero East Design Team2015 SAE Aero East Design Team7
Competition Summary• Pre-Competition Prep– Submitted tech report– Reconstructed aircraft– Completed final test flights– Created PowerPoint for oral presentation– Created marketing flyer for presentation– Travel logistics
2015 SAE Aero East Design Team2015 SAE Aero East Design Team8
Competition Summary (cont.)
• Technical inspection– Failed 1st inspection due to non-compliant payload bay– Received penalty point deduction for failure to report
dimension changes– Constructed new payload bay– Passed 2nd inspection and cleared to fly
2015 SAE Aero East Design Team2015 SAE Aero East Design Team9
• Oral Presentation– Gave technical overview of aircraft design and construction– Payload load/unload demonstration
• Earned bonus points for completing within time limits
Competition Summary (cont.)
2015 SAE Aero East Design Team2015 SAE Aero East Design Team10
• Flight Rounds– Flight 1: Disqualified because lost nose gear on landing– Flight 2: Disqualified because of crash on landing– Flight 3: Successful flight carrying 13.5 lbs– Flight 4: Successful flight carrying 18.5 lbs
Competition Summary (cont.)
2015 SAE Aero East Design Team2015 SAE Aero East Design Team11
Competition Results• Flight Scoring:
2015 SAE Aero East Design Team2015 SAE Aero East Design Team12
Competition Results (cont.)
• Technology Report Scoring:
2015 SAE Aero East Design Team2015 SAE Aero East Design Team13
• Oral Presentation Scoring:
Competition Results (cont.)
2015 SAE Aero East Design Team2015 SAE Aero East Design Team14
• Overall Competition Scoring:
Competition Results (cont.)
2015 SAE Aero East Design Team2015 SAE Aero East Design Team15
• Overall finish of 13th out of 37 entrants• Finished 7th on the tech report• Finished 10th on the oral presentation• Aircraft carried 18.5 lbf
(improved upon 2014 max payload weight of 9.11 lbf) • Tech report and oral presentation results improved
Discussion
2015 SAE Aero East Design Team2015 SAE Aero East Design Team16
Discussion (cont.)
• Lessons Learned from Competition– Double check dimensions: match aircraft to technical
report– Weight must be homogenous mass: no loose plates– Solid wheels– Reliable front nose gear design– Implement trade studies in oral presentation– Access panels for all servos
2015 SAE Aero East Design Team2015 SAE Aero East Design Team17
Recent Work• Constructed revised front landing gear• Compiled lessons learned• Gathered media from competition• Sent Thank-You letter to sponsors• Begin editing final report and
presentation
2015 SAE Aero East Design Team2015 SAE Aero East Design Team18
Future Work• Organize all documents and media for future teams• Implement new nose gear and replace damaged
rudder servo• Continue test flights– Attain ultimate goal of more than 20 lbf payload
• Recruiting efforts for 2016 team• GROUP BARBEQUE!
2015 SAE Aero East Design Team2015 SAE Aero East Design Team
Questions?