DVVERGIL
2815 Penn Ave
Phase_04
08-20-2018
project notes
VERGILdv.com4311 Butler St,
Pittsburgh Pa 15201 +1 412.889.9933
www.Next-Architecture.net1133 Penn Avenue
Suite 100Pittsburgh, PA 15222
412-681-1145
Exterior_01
• 30,000 SF creative and tech friendly office
• 7,000+/- SF floorplates
• Boutique style building with sleek modern finishes
• Q3 2019 delivery
• Up to 28 parking spaces available on-site
• Two private outdoor decks
• Being built on spec
• Double height first floor with open mezzanine and historic architectural details
• Pittsburgh Winery on lower level
PENN AVENUE2815
DVVERGIL
2815 Penn Ave
Phase_04
08-20-2018
project notes
VERGILdv.com4311 Butler St,
Pittsburgh Pa 15201 +1 412.889.9933
www.Next-Architecture.net1133 Penn Avenue
Suite 100Pittsburgh, PA 15222
412-681-1145
Interior_01Mezzanine Centered
DVVERGIL
2815 Penn Ave
Phase_04
08-20-2018
project notes
VERGILdv.com4311 Butler St,
Pittsburgh Pa 15201 +1 412.889.9933
www.Next-Architecture.net1133 Penn Avenue
Suite 100Pittsburgh, PA 15222
412-681-1145
Notes
Exterior_02DVVERGIL
2815 Penn Ave
Phase_04
08-20-2018
project notes
VERGILdv.com4311 Butler St,
Pittsburgh Pa 15201 +1 412.889.9933
www.Next-Architecture.net1133 Penn Avenue
Suite 100Pittsburgh, PA 15222
412-681-1145
Notes
Interior_02Mezzanine Centered
© 2020 CBRE, Inc. This information has been obtained from sources believed reliable. We have not verified it and make no guarantee, warranty or representation about it. Any projections, opinions, assumptions or estimates used are for example only and do not represent the current or future performance of the property. You and your advisors should conduct a careful, independent investigation of the property to determine to your satisfaction the suitability of the property for your needs. Photos herein are the property of their respective owners and use of these images without the express written consent of the owner is prohibited.
CONTACT US
JEREMY Z. KRONMAN, CCIM, SIOR Vice Chairman+1 412 394 [email protected]
TIMOTHY S. MCCARTHY Vice President+1 412 394 9816 [email protected]
26'-5" 22'-512" 22'-6" 21'-11"
18'-3
1 2"19
'-71 2"
24'-3
1 2"23
'-10"
D06
D10
D01
D01
D01D01D01
D01 D01
D01
D01
D01
D07
D04
D04
D04
D02
D05
D01
D03
D09
2815
PE
NN
AV
EN
UE
2815
PE
NN
AV
EN
UE
ALL
EG
HE
NY
CO
UN
TYP
ITTS
BU
RG
H,
PA
152
22
DRAWING NO.
VERSIONS/REVISIONS:
PROJECT No.
05.28.2018 SD Set
18031.01
THIS IS AN INSTRUMENT OF SERVICE NOT TO BE ALTERED, COPIED, OR USED FOR CONSTRUCTION WITHOUT WRITTEN PERMISSION FROM NEXT ARCHITECTURE, L.P. - COPYRIGHT 2018 (ALL RIGHTS RESERVED) NOT FOR CONSTRUCTION
DemolitionPlan @BASEMENT
A1.00
2815
PE
NN
AV
EN
UE
2815
PE
NN
AV
EN
UE
ALL
EG
HE
NY
CO
UN
TYP
ITTS
BU
RG
H,
PA
152
22
DRAWING NO.
VERSIONS/REVISIONS:
PROJECT No.
05.28.2018 SD Set
18031.01
THIS IS AN INSTRUMENT OF SERVICE NOT TO BE ALTERED, COPIED, OR USED FOR CONSTRUCTION WITHOUT WRITTEN PERMISSION FROM NEXT ARCHITECTURE, L.P. - COPYRIGHT 2018 (ALL RIGHTS RESERVED) NOT FOR CONSTRUCTION
1A1.00
Demolition Plan @ BASEMENTSCALE: 1/8" = 1'-0"
DEMOLITION LEGEND:
DASHED LINES INDICATE EXISTINGWALL CONSTRUCTION to beREMOVED in THEIR ENTIRETY.
DASHED LINES INDICATE EXISTINGDOOR, FRAME, HARDWARE and ALLOTHER RELATED ACCESSORIES tobe REMOVED in THEIR ENTIRETY.
EXISTING INTERIOR DOOR &FRAME to REMAIN.
EXISTING INTERIOR PARTITION orCORE WALL to REMAIN. G.C.SHALL PATCH, REPAIR, ETC. andPREPARE to RECEIVE NEWCONSTRUCTION or FINISHES.
EXISTING WINDOW to REMAIN.
DASHED LINES INDICATE EXISTINGWINDOW CONSTRUCTION to beREMOVED in ITS ENTIRETY.
DEMOLITION GENERAL NOTES:1. WHERE EXISTING SPEED TILE OR BRICK WALLS ARE REMOVED. PREP
AND PATCH EXISTING FLOOR AND CEILING TO BE LEVEL WITHADJACENT SURFACES.
2. PROVIDE SAW CUTS IN FLOOR AS REQUIRED FOR NEW PLUMBINGLINES.
3. AT FIRST FLOOR/ MEZZANINE CEILING, REMOVE LOOSE PLASTER/LATHE AND PREP & PATCH AREA WITH NEW PLASTER/ LATHE.
4. AT 2ND AND 3RD REMOVE LOOSE PLASTER, PREP for PAINT.
HATCH INDICATES WORK N.I.C.
DEMOLITION PLAN KEY NOTES:EXISTING SPEED TILE WALL.
EXISTING BRICK WALL.
DASHED LINES INDICATE REMOVAL OF EXISTING STAIR,RAILINGS AND ALL RELATED ACCESSORIES. PREP EXISTINGFLOOR OPENING FOR CONCRETE INFILL.
DASHED LINES INDICATE REMOVAL OF EXISTING RAISEDSLAB.
DASHED LINES INDICATE REMOVAL OF EXISTING PLUMBINGFIXTURES AND ALL TOILET ACCESSORIES. CAP UTILITIESBELOW FLOOR. PATCH HOLES TO BE EVEN WITH ADJACENTFLOOR.
DASHED LINES INDICATE REMOVAL OF EXISTING AREA WAYWALLS FOR INSTALLATION OF NEW EXTERIOR STAIR. PATCHEXISTING WALLS.
DASHED LINES INDICATE REMOVAL OF EXISTING CONVEYOREQUIPMENT AND ADJACENT COLUMNS, PREP EXISTINGFLOOR OPENING FOR NEW CONCRETE.
DASHED LINES INDICATE REMOVAL OF EXISTING STAIR,RAILINGS AND ALL RELATED ACCESSORIES. PREP EXISTINGFLOOR OPENING FOR CONCRETE INFILL.
DASHED LINES INDICATE REMOVAL OF EXISTING BRICK WALLFOR INSTALLATION OF NEW STAIR DOOR. PROVIDE (2) STEELCHANNELS THRU BOLTED WITH A STEEL PLATE AT THE DOORHEAD AND JAMBS. PATCH SILL WITH CONCRETE. LEVEL WITHADJACENT FLOOR.
DASHED LINES INDICATE REMOVAL OF EXISTING CHIMNEYFROM BELOW BASEMENT TO TOP OF CHIMNEY. PATCHEXISTING EXTERIOR WALL WITH BRICK AS REQUIRED TOALIGN WITH ADJACENT SURFACES.
REMOVE BASE WAINSCOAT AND RELATED TRIM FROMEXISTING FLUTED WOOD COLUMN.
REMOVE EXISTING DISPLAYS, HALF WALL AND PARTITIONSFROM ENTIRE SPACE.
DASHED LINES INDICATE REMOVAL OF EXISTING METALMEZZANINE FLOOR, COLUMNS, JOISTS, STAIRS, RAILINGS,ETC. IN THEIR ENTIRETY. PREP AND PATCH ANY HOLE LEFTBY MEZZANINE ATTACHMENT TO EXISTING CONSTRUCTION.
REMOVE EXISTING ONE STORY ADDITION IN ITS ENTIRETY.THIS INCLUDES THE REMOVAL OF THE ROOF, SUPPORTINGBAR JOIST, INTERIOR COLUMNS, CMU WALLS, 3 OVERHEADDOORS, CONCRETE SLAB, ETC. PREP SITE FOR NEWASPHALT.
REMOVE EXISTING OFFICE AREA IN ITS ENTIRETY. THISINCLUDES WOOD FRAMED MEZZANINE/ CEILING, INTERIORWALLS, COUNTERS, DOORS, PLUMBING FIXTURES, ETC. PREPAND PATCH REMAINING ELEMENTS FOR INSTALLATION OFNEW FINISHES. KEEP EXISTING MARBLE ELEMENTS FORPOSSIBLE REUSE.
REMOVE EXISTING WOOD STAIR, RAILING, STRINGER, ETC. INITS ENTIRETY. PATCH SLAB EDGES AS REQUIRED TO INSTALLNEW STAIR.
D01
D02
D03
D04
D05
D06
D07
D08
D09
D11
D12
D10
D13
EXTERIOR DEMOLITION GENERAL NOTES:1. REMOVE ALL EXISTING EXTERIOR WINDOWS, WOOD INFILLED
WINDOWS AND DOORS FROM FACADE. PREP AND PATCH FOR NEWWINDOWS AND DOORS.
2. REMOVE FULL HEIGHT EXISTING FIRE ESCAPE FROM REAR OFBUILDING IN ITS ENTIRETY. PATCH EXISTING WALLS AT TIE-IN POINTS.
3. REMOVE ALL EXISTING SIGNAGE AND BANNERS.
4. REMOVE ALL UTILITY PIPING, CONDUIT, WIRES THAT ARE NO LONGERIN USE.
5. REMOVE EXISTING METAL ANGLES AND METAL ATTACHMENTS THATARE NO LONGER IN USE.
6. REFER TO A0.50 FOR BRICK CLEANING SPECIFICATION.
D14
D15
D16
REMOVE EXISTING ROOF MEMBRANE, SHEATHING AND ALLSTRUCTURAL FRAMING. CLEAR ANY DEBRIS IN VOID SPACETO MAKE AREA READY FOR NEW FLOOR.
REMOVE EXISTING ROOF DOG HOUSE DOWN TO 3RD FLOORCEILING. REMOVE NORTH BRICK WALL DOWN TO BE EVENWITH EXISTING PARAPET.
REMOVE EXISTING PARAPET CAP AS REQUIRED TO INSTALLNEW WALLS OF 4TH FLOOR.
REMOVE EXISTING CARPET AND PREP FLOOR FOR NEWFINISH.
REMOVE BRICK PARAPET DOWN TO 42" ABOVE FINISHEDPATIO HEIGHT.
D17
D18
D19
D20
D21
7,000 SFPER FLOOR