Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | manahari-bhandari |
View: | 236 times |
Download: | 0 times |
of 37
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
1/37
MHP MHP Components
MICRO HYDRO COMPONENTS ANDSURVEYING ASPECTS
Presented by:Krishna Prasad Devkota
UCS/NMHDA
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
2/37
MHP MHP Components
Contents of the Presentation
MH Components
Site Survey
Load Survey Flow Measurement
Location & Alignment Fixing
Alignment Survey & Head Measurement
Power Equation
Reporting
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
3/37
MHP MHP Components
Civil Components
Mechanical Components
Electrical Components(Electro-mechanical Components)
Transmission/Distribution Network
Components of Micro Hydro Project
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
4/37
MHP MHP Components
N
Forbay
Tailr
ace
Penstock Pipe
Power House
WEIR
Spilw
ay
Canal
River/Khola
Spilw
ay
Anchor Block
Anchor Block
Support PierKholsa
Crossing
HeadraceCanalDe
silting
Basin
Major Civil Components Of MicroHydro Scheme
n3'hnljB't cfof]hgfsf l;len;+/rgfx?
Intake
WeirCanal
CrossingForebay
Anchor Block
Support Piers
Power House
Tailrace
Source
Spill way
Trashrack
Spillway
Civil Components of Micro Hydro
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
5/37
MHP MHP Components
Weir and Intake
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
6/37
MHP MHP Components
Desilting Basin
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
7/37
MHP MHP Components
Canal
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
8/37
MHP MHP Components
Forebay
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
9/37
MHP MHP Components
SUPPORT STRUCTURES
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
10/37
MHP MHP Components
Powerhouse and Tailrace
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
11/37
MHP MHP Components
400/11000V,15kVA
L.T.L ightningArrestor
R
Y
B
N
Forbay
AnchorBlock
ExpansionJoint
Air VentPipe
SupportPire
AnchorBlock
PenstockPipe
ELC Board
Generator
Turbine
Trasrack
Power House
Electro Mechanical Components Of Micro Hydro Scheme
H.T.LineL.T.Line
T.Plateform
MCCB
H.T.Li ghtningArrestor
Drop-outFuse
Transformer( T1)
GroundL evel
DangerPlate
Penstock pipe
TransmissionLine
Transformer
ELC
Earthing
Generator
Turbine
Electro-Mechanical Components of Micro Hydro
Expansion J oint
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
12/37
MHP MHP Components
Electro-Mechanical Arrangement
Turbine
Generator
Base Frame
Valve
Expansion J oint
Pressure Gauge
Direct Coupling
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
13/37
MHP MHP Components
Pulley & Belt
Turbine Genrator
ELC=
Balast Tank
Electro-Mechanical Arrangement
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
14/37
MHP MHP Components
IGC/ELC/Governor
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
15/37
MHP MHP Components
Transmission/Distribution Network
Powerhouse
Transmission
Line
DistributionLine
Service Line
House wiring
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
16/37
MHP MHP Components
Transmission/Distribution
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
17/37
MHP MHP Components
Site Survey
To gather the detailed information
and measurement of the site forthe suitability of the installation ofa micro hydro plant.
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
18/37
MHP MHP Components
Major Tasks of site survey
Power demand (Load Survey); Flow measurement;
Head measurement; Optimum power output (Tentative);
Water users; High flood level Social aspects
(Interest/motivation/capability/conflict of the community)
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
19/37
MHP MHP Components
Major Tasks of site survey (Contd...)
Location of the civil structures(Alignment, Geological Aspect & Space Availability)
Transmission/distribution Length(with household distribution);
Protection works;
Environmental aspects;
Economical aspects;
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
20/37
MHP MHP Components
Demand survey
This survey is mainly the preparation ofpotential consumers list with their powerdemand.
Count the number of households, shops,
lodges, offices, temples, schools,industries etc.
Calculate the power needed for each
consumer (in terms of the numbers of bulbs or tube lights,radio, TV, fans and other appliances).
Calculate total power demand
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
21/37
MHP MHP Components
Flow Measurement
To find the available discharge in
the source (river/stream) forpower generation
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
22/37
MHP MHP Components
Bucket method
Conductivity method (Salt dilution method)
Weir method
Current meter method
Float Method
Ultrasonic method
Flow Measurement Method
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
23/37
MHP MHP Components
Applicability
Bucket method : < 30 lps Conductivity meter: 30 lps to 2000 lps Weir Method:
Triangular Smaller flowRectangular- Larger flow
Current meter: > 2000 lps
Float method: Rough method (only for estimate) Ultrasonic method: for discharge in
penstock pipe/Canal
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
24/37
MHP MHP Components
Flow Estimation
Common Methods used in Nepal:
MIP method
WECS/DHM method
To estimate the available discharge for thepower generation throughout the year.
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
25/37
MHP MHP Components
Flow estimation
MIP method for catchment area less than 100km2
For catchment area larger than 100 km2 alongwith the MIP method, WECS/DHM method could
be used Lower values derived from the above two
methods should be adopted
11 month exceedance flow should be comparedwith measured flow of detailed feasibility study
M IP m e thod is m os tly adop ted in N epa l
d ( )
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
26/37
MHP MHP Components
Developed by M. Mac Donald (consulting firm) in 1990. Country divided into 7 hydrological regions. Based on wading measurements by Department of
Hydrology and Meteorology, non-dimensional regionalhydrographs were developed for each region. The
month of April was used for non-dimensionalizing. Coefficients for each month for each region have been
developed
Mean monthly flows
Low flow measurement
MIP region number
Measurement date
OUTPUTINPUT
MHP
Medium Irrigation Project (MIP)Method
http://www.gtz.de/nepal/projects/shpp.htmlmailto:[email protected]:[email protected]://www.gtz.de/nepal/projects/shpp.html7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
27/37
MHP MHP Components
MIP MethodMonth Non dimensional
flow or Region 3
Measured flow
(l/s)
Factor Estimated
mean monthlyflows (m3/s)
January 2.71
Factor = 600/1e.g.
Jan flow =600x2.71 =1626 l/s
1.626
February 1.88 1,128
March 1.38 0.828
April 1.00 600 (15 April) 0.600
May 1.88 1.128
June 3.13 1.878
July 13.54 8.124
August 25.00 15.000
September 20.83 12.498
October 10.42 6.252
November 5.00 3.000
December 3.75 2.250
Annual Avg. 4.526
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
28/37
MHP MHP Components
Discharge measurement between November &May (dry season)
No rain during the past 3 days from the day offlow measurement
flow (Qd) at river for 11 months excedence.
Consider seepage (5-10%) + environmentalflows (10-15%).
Thus, need to use at most 85% of the 11months exceedance flow.
+- 10% tolerance on Qd at commissioning.
Nepalese Guidelines & Standardsfor MHP Hydrology
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
29/37
MHP MHP Components
Location & Alignment Fixing
While selecting the location for the MH componentsfollowing considerations have to be made.
Weir and Intake
Possible to divert the flow either naturally or by constructinga simple and low height weir
Headrace Canal
Safe from high flood, landslip, tension cracks, falling rocksetc.
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
30/37
MHP MHP Components
Settling/desilting Basins
Close to the intake & possible to flush thesediments safely
Forebay
Stable, safe and suitable for penstock route.
Spillways
At forebay, settling basin and at canal (as per necessity)
Location & Alignment Fixing (Contd)
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
31/37
MHP MHP Components
Location & Alignment Fixing (Contd)
Penstock alignment
Stable, safe, straight as possible with
minimum number of bends and steeperterrain (30 -45)
Powerhouse
adequate space, safe from floods & safeto discharge the tail water back into thestream.
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
32/37
MHP MHP Components
Alignment Survey & Head Measurement
Common Methods:
Abney Level
Auto Level Theodolite
Total Station
To find the topographical feature and leveldifference between the Intake, forebay andpowerhouse.
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
33/37
MHP MHP Components
Necessary precautions need to be
made during the survey & projectimplementation period in order toreduce the environmental impacts.
Environmental Consideration
PowerOutputCalculation
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
34/37
MHP MHP Components
CIVIL COMPONENTS
Head (m)
Power Output Calculation
Village
Discharge (l/s)
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
35/37
MHP MHP Components
Power Equation
P = * g*Q*H*
Where,
P = Power (Watt)
= Density of water (kg/m3)
g = Acceleration due to gravity (m/sec2)
Q = Discharge (l/sec)H = Head (meter)
= Overall efficiency
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
36/37
MHP MHP Components
Reporting
Flow Calculation Estimation of Discharge
Design Discharge
Demand Supply Analysis End Use Application
Design & Drawings (sizes of structures/equipment) ;
Cost/financial analysis and
Conclusion and Recommendations.
7/29/2019 3 Fundamental of Site Survey Krishna Prasad Devkota
37/37
MHP MHPComponents
Thanks!!!