Third Quarter CY 2012 RPMES REPORT Republic of the Philippines Cordillera Administrative Region Regional Project Monitoring Committee Prepared by the National Economic and Development Authority Cordillera Administrative Region RPMC Secretariat
Transcript

Third Quarter

CY 2012

RPMES REPORT

Republic of the Philippines

Cordillera Administrative Region

Regional Project Monitoring Committee

Prepared by the National Economic and Development Authority

Cordillera Administrative Region RPMC Secretariat

CY 2012 Major Programs and Projects --------- 1

Project Implementation Status --------- 2

CY 2012 Priority Sectoral Programs/ Projects --------- 4

RPMC Project Site Inspections --------- 5

Annexes:

A List of Major Programs/Projects --------- A-1 B Eight Priority Sectoral Programs/Projects

Second Cordillera Highland Agricultural Resource Management Program (CHARMP 2)

--------- B-1

4 Pantawid Pamilyang Pilipino Program (4Ps) --------- B-5

Agrarian Reform Infrastructure Support Program (ARISP)

--------- B-10

Kabugao, Apayao – Solsona, Ilocos Norte Road --------- B-13

Kabugao-Pudtol-Luna-Cagayan Boundary --------- B-17

Cordillera-wide Strengthening of Local Systems for Effective and Efficient Delivery of Maternal and Child Health Services

--------- B-20

National Greening Program (NGP) --------- B-21

Red and Black School Building Program --------- B-24

C Inspection Reports

Kabugao-Pudtol-Luna- Cagayan Boundary Road --------- C-1

Kabugao, Apayao – Solsona, Ilocos Norte Road --------- C-4

1 Third Quarter CY 2012 RPMES Report

Third Quarter CY 2012 RPMES Report

The Regional Project Monitoring and Evaluation System (RPMES) report is prepared on a quarterly basis to provide an overall view on the status of major program/project (P/Ps) implementation in the region. The report is based on the submission of eleven regional line agencies (RLAs).

I. CY 2012 Major Programs/Projects For CY 2012, there are 46 major P/Ps with an aggregate cost of Php 10.633 Billion of which about Php 5.9 billion or 55.52 percent are new P/Ps, Php 3.9 billion or 37.52 percent are multi-year projects, and Php 0.740 billion or 6.96 percent are carryover projects. In terms of cost, the economic development sector has the highest at 51.21 percent or Php 5,445 billion, followed by the infrastructure sector at 27 percent or Php 2,794 billion, and the social sector having the least at 18.68 percent or Php 1,985.883 billion. Also included are rehabilitation and reconstruction projects under the Strategic Action Plan (SAP) on areas affected by typhoons “Pedring” and “Quiel” in 2011 amounting to 4 percent or Php 407 million.

2 Third Quarter CY 2012 RPMES Report

In terms of funding source, 67 percent is locally funded while 32 percent is foreign assisted. The foreign- assisted projects are: (a) Second Cordillera Highland Agriculture Resource Management Program (CHARMP II), Php 3.2 Billion, (b) Agrarian Reform Infrastructure Support Program (ARISP), Php 903 Million; and (c) Rural Micro-Enterprises Promotion Program (RuMEPP), Php 1.8 Million.

II. Project Implementation Status For the third quarter, the overall status of project implementation is 43 percent, a 10 percent increase from the second quarter. The SAP projects posted the highest accomplishment followed the social sector, then the infrastructure sector. The economic sector’s low performance is the due to the delayed implementation of its banner project, the CHARMP 2. (Please refer to Annex A for the detailed status of the 46 projects) Projects identified under the SAP of areas affected by typhoons Pedring, Quiel and Juan posted an accomplishment of 96.41 percent, most of which are roads and school building projects. The Social Sector obtained an overall accomplishment of 52.82 percent. The projects reported under the sector are DSWD’s Pantawid Pamilyang Pilipino Program (4Ps), DepEd’s Red and Black Schoolbuilding Program, Rehabilitation of School Building including Water Sanitation Facilites and Philippines’ Response to Indigenous and Muslim Education (PRIME), DOH’s Health Facilities and Water System Projects and foreign-assisted Cordillera-wide Strengthening of Local

3 Third Quarter CY 2012 RPMES Report

Health System for Effective and Efficient Delivery of Maternal and child Health Service. The Infrastructure Sector had an overall accomplishment of 47.09 percent, composed of DPWH’s priority roads and bridge projects. These priority roads are mainly laterals that link CAR to Regions I and II. The Economic Sector posted an overall accomplishment of 45.57 percent. The sector’s accomplishment is relatively the lowest due to the negative slippages incurred by two of its major projects, these are: DA’s foreign-assisted project Second Phase of Cordillera Highland Agricultural Resource Management Project or CHARMP 2 costing about Php 3 Billion, and DENR’s National Government Priority, National Greening Program (NGP) costing about Php 124 Million. The other projects under the sector are DAR’s Agrarian Reform Infrastructure Support Project (ARISP III), DA’s Farm-to-Market Roads, NIA’s Irrigation Projects, DTI’s One Town One Product Program (OTOP) and Shared Service Facilities SSF, and DOST’s completed Small Enterprises Technology Program (SETUP), and Packaging and Labeling Project.

0.00%

20.00%

40.00%

60.00%

80.00%

100.00%

Implementation Status (as Sept. 2012)

52.82%

45.57% 47.09%

96.41%

49.27 %

4 Third Quarter CY 2012 RPMES Report

The overall performance during the quarter translates to four (4) P/P completed – the SETUP of DOST, two (2) sections of the Abra-Kalinga Road, and Gurel-Bokod-Kabayan-Buguias-Abatan Road, eight (8) P/P are ahead of schedule, 20 are on track, and 14 behind schedule. Of the 14 projects reported behind schedule, 11 projects incurred negative slippages less than negative 15 percent. The common reason reported was due to inclement weather/typhoons in the project area. Agencies have adopted catch-up plans to put the projects on track. The DA implemented CHARMP 2 had a negative 26 percent slippage because it underwent another NEDA ICC process for project reconfiguration to address the issue on LGU counterpart. CHARMP will have to retarget its work schedule once reconfiguration has been in effect. The National Greening Program (NGP) also experienced a big slippage of negative 19.63 percent due to change in procurement process. The NGP also adopted a catch-up plan to put the project on track. The Philippine Response to Indigenous and Muslim Education (PRIME) of DepEd, is the most problematic project that has a negative 51 percent slippage. DepEd acknowledges the delay and has undertaken actions to put the project on track.

III. CY 2012 Priority Sectoral Programs/ Projects From the 46 programs/projects, eight (8) were identified as priority sectoral programs/projects by the sectoral committees and tagged as their banner projects. These programs/projects with an aggregate cost of Php 5.3 billion are being closely monitored by the RPMC. These were selected based on the criteria set during the RPMES national forum: (a) foreign- assisted projects (FAP/ODA), (b) interprovincial, (c) large scale cost, (d) national priority, critical projects by the Office of the President (OP), and (e) regional priority. These programs/projects are as follows:

1. Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2) 2. Pantawid Pamilyang Pilipino Program (4Ps) 3. Agrarian Reform Infrastructure Support Project, Phase III 4. Kabugao-Solsona, Apayao-Ilocos Norte Road 5. Kabugao-Pudtol- Luna- Cagayan Boundary Road 6. Cordillera-wide Strengthening of Local health System for Effective and Efficient Delivery of

Maternal and Child Health Services 7. National Greening Program 8. Red and Black School Building Program

Of the eight (8) priority P/Ps, five (5) have been inspected/validated, while the remaining three (3) are scheduled for inspection by the RPMC before the year ends, these are CHARMP, 4Ps and the Cordillera-wide Strengthening of Local Health Systems for Effective and Efficient Delivery of Maternal and Child Health Services. The JICA-assisted Cordillera-wide Strengthening of Local Health Systems launched in the first quarter has accordingly procured medical equipment for the provinces of Abra and Apayao. (Please refer to Annex B for the details of the eight priority sectoral programs/projects)

5 Third Quarter CY 2012 RPMES Report

IV. RPMC Project Site Inspections

An inspection/validation of the Kabugao-Pudtol-Luna-Cagayan Boundary Road and the Road Opening of Kabugao, Apayao-Solsona, Ilocos Norte Road (Apayao Side) was conducted by the RPMC Inspectorate Team on October 9 - 10, 2012. These are regional priority projects and major components of the Cordillera Roads Improvement Project (CRIP). The roads are among Apayao national roads upgraded from secondary to arterial classification through DPWH Memorandum dated November 2, 2011 by DPWH Secretary Rogelio Singson. This memorandum was a result of an RDC-CAR dialogue with the DPWH Secretary held August 5, 2011 in Baguio City. During the site inspection, the Kabugao-Pudtol-Luna-Cagayan Boundary Road is proceeding smoothly having a status of 64.79 percent. The other project, the Kabugao, Apayao – Solsona, Ilocos Norte Road, 0.50 percent status, was recently issued a resume order after a suspension due to recent typhoons. It has been observed that the construction of several bridges in both projects have to be programmed to make them passable. (Please refer to Annex C for Inspection Reports)

Annex A LIST OF MAJOR PROGRAMS/PROJECTS

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-1

SOCIAL SECTOR

1. Pantawid Pamilyang Pilipino Program (4Ps)

DSWD 888.889 Loan 63.06%

Slippage: -3.62%

2. Red and Black School Building Program

DepEd CY 2011: 166.944

CY 2012: 115.200

GOP CY 2011 95.94%

209 Classrooms

CY 2012 34.16%

143 Classrooms

3. Cordillera-wide Strengthening of Local Health System for Effective and Efficient Delivery of Maternal and Child Health Services

DOH & LGUs Abra Apayao

Benguet

43.00

JICA 5%

4. National Household Targeting System for Poverty Reduction Program

DSWD 41.025 GOP, Loan

59.41%

5. Rehabilitation of School Building including Water Sanitation Facilities

DepEd School Building CY 2011: 15.468

WATSAN CY 2011: 15.861

School Building

CY 2012: 28.633

WATSAN CY 2012: 29.340

GOP CY 2011 Fund:

88.92%

CY 2011 Fund:

96.48%

CY 2012 Fund: Waiting for

SARO

6. Philippine Response to Indigenous People’s (IP) and Muslim Education (PRIME)

DepEd 3.978 AusAid 31%

Slippage: -51%

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-2

7. Construction of Various Health Facility

DOH CY 2011: 117.867

CY 2012: 335.179

GOP CY 2011 fund: 58.55%

CY 2012 fund:

6.49%

8. Water Supply System DOH 184.500 GOP 76.64%

Sub-Total 1,985.883 52.82%

ECONOMIC SECTOR

9. Second Cordillera Highland Agricultural Resource Management Project (CHARMP2)

DA 3,081.862 IFAD, ADB. OFID

34.25%

Slippage: -26.61%

10. Agrarian Reform Infrastructure Support Project Phase III

(Abra, Apayao, Benguet, Ifugao, Kalinga and Mt. Province)

DAR Total Project Cost:

903.863

CY 2011: (2 projects)

16.718

CY 2012: (12 projects)

176.027

Loan GOP

72.26%

Slippage: +22.25%

11. National Greening Program (NGP) DENR 124.339 GOP 73.44%

Slippage: -19.63%

12. Farm-to-Market Roads (CY 2011 Fund: Abra, Kalinga and Mt. Province) (CY 2012 Fund: Abra, Baguio City, Benguet, Ifugao, Kalinga and Mt. Province)

DA CY 2011: 53.00

CY 2012: 161.803

Grant CY 2011: 85.66%

CY 2012: 18.58%

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-3

13. Irrigation Projects NIA 1,078.046 (432 projects)

GOP 53.13%

14. One Town One Product Program (OTOP)

DTI 2.747 GOP 84.68%

15. Rural Micro Enterprise Promotion Programme (RuMEPP)

DTI 1.800 IFAD with GOP

Counter Part

90%

16. Shared Service Facilities Project (SSF)

DTI 8.388 NEDAC Fund

(National Export

Develop-ment and Competi- tiveness)

Awarding of bidding

suppliers

17. Small Enterprise Technology Upgrading Program (SETUP) Core and Non-Core Funded Projects

DOST 28.673 GOP 100%

18. Packaging and Labeling DOST 0.688 GOP 76%

Sub-Total 5,445.208 45.57%

INFRASTRUCTURE SECTOR

Abra

19. Abra-Ilocos Sur Road DPWH 106.195 GOP 55.25%

Slippage: -8.68%

20. Abra-Kalinga Road, K0467+000- K0474+305

DPWH 147.691 GOP 14%

Slippage: +2.67%

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-4

21. Abra-Ilocos Norte, K0436+700- K0439+395

DPWH 62.00 GOP 13.83%

Slippage: -11.17%

22. Road Upgrading along Abra-Cervantes Road (Realigned from Sto. Tomas-Manabo Bridge)

DPWH 60.00 GOP 24.77%

Slippage: +3.60%

23. Sto. Tomas-Manabo Bridge (P160.0 M)

DPWH 160.00 GOP 76.81%

Slippage: -9.03%

24. Abra-Kalinga Road K0410+000- K0413+810

DPWH 50.45 GOP 100%

25. Abra-Kalinga Road K0437+490- K0455+890, K0432+000 K0450+800

DPWH 143.67 GOP 100%

Apayao

26. Kabugao-Pudtol-Luna Cagayan Boundary Road

K0661+000 - K0661+321, K0643+646 - K0645+825 Gravel to Concrete

DPWH 58.827 GOP 62.51%

Slippage: -4.90%

27. Kabugao, Apayao-Solsona, Ilocos Norte Road

DPWH 100.00 GOP 0.05%

Slippage: -1.98%

Benguet

28. Rehab./Reconst’n/Upgrading of Kennon Road

DPWH 54.433 GOP 31.31%

Slippage: -9.49%

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-5

29. Baguio-Bontoc Road (Pico-Lamtang Rd., Baguio Itogon & Baguio-Bontoc)

DPWH 98.674 GOP 28.77%

Slippage: +14.27%

30. Baguio-Bontoc Road, K0269+000- K0275+000 (v.s.)& K0299+000-K0300+900 (v.s.) & K0305+000-K0308+500 (v.s.) & K0309+000- K0311+000 (v.s.), K0317+415-K0318+500 (v.s.), & K0323+000 – K0328+000 (v.s.)

DPWH 109.332 GOP 17%

Slippage: +1.60%

31. Gurel-Bokod-Kabayan-Buguias-Abatan Road

DPWH 98.50 GOP 91.10%

Slippage: +2.20%

32. Gurel-Bokod-Kabayan-Buguias-Abatan Road K0303+600-K03012+000

DPWH 116.50 GOP 100%

33. Rehab./Impv’t. of Gurel-Bokod-Kabayan-Buguias Road including RROW

DPWH 148.00 GOP 41.30%

Slippage: +19.70%

34. Gurel-Bokod-Kabayan-Buguias-Abatan Road, K0345+513-K0359+300 (vs.)

DPWH 68.921 GOP 46%

Slippage: -12.39%

Ifugao

35. Banaue-Mayoyao-A Lista-Isabela Bdry. Road

DPWH 58.064 GOP 17.35%

Slippage: -13.96%

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-6

36. Nueva Vizcaya-Ifugao-Mt. Province Road

DPWH 54.163 GOP 65%

Slippage: -6.64%

Kalinga

37. Kalinga-Abra Road, K0470+000-K0472+267

DPWH 53.057 GOP 39.98%

Slippage: -4.95%

38. Kalinga-Abra Road, K0476+000-K0480+1000, K0480+1000-K0482+700 (with exceptions)

DPWH 135.27 GOP 8.75%

Slippage: +1.44%

39. Balbalan-Pinukpuk Road K0485+000-K0489+000

DPWH 100.00 GOP 87% Slippage: -9.40%

40. Balbalan-Pinukpuk Road K0560+1061-K0520+449

DPWH 245.00 GOP 62% Slippage:

-10%

41. Mt. Province Bdry. –Calanan-Pinukpuk –Abbut Road (Pinukpuk) (P209.0 M) K0499+674-K0509+294 (I.S.)

DPWH 209.00 GOP 49.37%

Slippage: -50.63%

42. Balbalan-Pinukpuk Road, Abut A of Baay Bridge+(-18502) to Abut A of Baay Bridge+0

DPWH 183.239 GOP Notice of award issued September 6,

2012. Contract papers on process.

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-7

Mountain Province

43. Mt. Province –Ilocos Sur via Tue Road

DPWH 81.815 GOP 31.17%

Slippage: -6.28%

44. Mt. Province-Ilocos Sur via Kayan DPWH 92.00 GOP 54.40%

Slippage: -4.66%

Sub-Total 2,794.801 47.09%

STRATEGIC ACTION PLAN (SAP) (Rehabilitation and Recovery of Areas Affected by Disasters)

45. Disaster Related Rehabilitation Project (DRRP)

DPWH DRRP Calamity Fund CY 2011

a. Apayao 1st District Engineering Office (16 projects)

74,550.0 87.73%

b. Apayao 2nd District Engineering Office (5 projects)

14,000.0 100%

c. Benguet 1st District Engineering Office (15 projects)

45,469.0 100%

d. Benguet 2nd District Engineering Office (6 projects)

39,279.1 100%

e. Baguio City District Engineering Office (1 project)

600.0 100%

f. Ifugao 1st District Engineering Office (2 projects)

8,580.0 100%

g. Ifugao 2nd District Engineering Office (4 projects)

25,850.0 100%

h. Kalinga District Engineering Office (9 projects)

85,910.5 95.93%

i. Mt. Province District Office (28 projects)

102,459.4 100%

Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS

Cordillera Administrative Region As of September 2012

PROGRAM/PROJECT IMPLEMENTING

AGENCY PROJECT COST

(PhP M) FUNDING SOURCE

STATUS/ REMARKS

A-8

Sub-Total 396.697 96.81%

46. Quick Response Fund (QRF) DepEd GOP

a. Cabaroan ES Dolores, Abra (Construction of 1 unit-2 classroom in Bldg.1)

1.202 56%

b. Cabaroan ES Dolores, Abra (Construction of 1 unit-2 classroom in Bldg.2)

1.202 100%

c. Cabaroan ES Dolores, Abra (Construction of 3 Seater Toilet – type III with handwashing)

318.0 79%

d. Cabaroan ES Dolores, Abra (1 classroom repair)

219.0 71%

e. Tonglo Carino PS, Buguias, Benguet

1.202 15%

f. Talubin NHS, Bontoc Mt. Province (Construction of 2cl / Replacement of Burned Bldg.)

1.143 85%

g. Tumog Es, Luna, Apayao (Construction of 1stry 3 Classroom 7x9 type I)

1.942 95%

h. Lagawe CS, Lagawe, Ifugao (Construction of 2cl / Replacement of Burned Bldg.)

1.200 100%

i. Bañacao ES, Bangued West, Abra (Repair of Classrooms / Construction of Slope Protection /Water System)

1.600 100%

Sub-Total 10.027 80.56%

SAP Sub-Total 406.724 96.41%

CAR Total 10,632.616 49.27% Sources: RLAs RPMES PMC Form I-1 and RPMES PMC Form I-2 as of September 2012.

Annex B EIGHT (8) PRIORITY PROGRAMS/PROJECTS

B-1 Third Quarter CY 2012 RPMES Report

PROJECT PROFILE

Implementing Agency: Department of Agriculture-CAR

Fund Sources: GOP: Department of Agriculture Loan: IFAD, OFID, ADB Grant: IFAD

Total Project Cost: Php 3,081,862,000

Location/Area Coverage: 6 provinces, 37 municipalities, 170 barangays Abra: Lacub, Licuan-baay, Malibcong, Luba, Tubo, Sallapadan, Bucloc, Boliney Apayao: Calanasan, Kabugao, Conner Benguet: Bokod, Kabayan, Bakun, Kibungan,Buguias,Kapangan, Atok, Sablan, Mountain Province: Barlig, Besao, Sadanga, Sagada, Bontoc, Tadian, Bauko, Sabangan Kalinga: Balbalan, Pasil, Lubuagan, Tanudan, Tinglayan Ifugao: Hingyon, Hungduan, Tinoc, Asipulo, Mayoyao

Description:

The project goal is to reduce the poverty and improve the livelihood of poor rural women and men in indigenous communities in the upland areas of the Cordillera Administrative Region. The objectives are to (1) increase the household income of poor farmers through sustainable agricultural development; and (2) enhance the quality of life of targeted communities by improving land tenure security, food security and watershed conservation.

The project has five components: (1) community mobilization, participatory planning of investments, and land titling; (2) community watershed conservation (including forest management and agro forestry development); (3) agricultural and agribusiness development, and promotion of income-generating activities; (4) rural infrastructure development; and (5) project management and coordination. Farm to market access

Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2)

Agro-forestry plots

B-2 Third Quarter CY 2012 RPMES Report

Second Cordillera Highland Agricultural Resource Management Project

PROJECT PROGRESS REPORT As of September 2012

Project Duration: CY2009- CY2015

Start: January 1, 2009 End: December 31, 2015

For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter

Target 49.72% 53.43% 57.15% 60.86%

Actual 18.45% 20.65% 34.25%

Slippage -31.27% -32.78% -22.90%

Cumulative Status: (Since start of project)

Status Physical Financial

Target 60.86% FOA+ Grant: Php 2,417.48

Actual

34.25% * Php 870.93 (36% of FOA+Grant)

* (57.03% of the total allotment released)

Php 1,527.073 from CY 2009-CY2012

Slippage -26.61%

Meeting with the beneficiaries& Project field assessment

B-3 Third Quarter CY 2012 RPMES Report

Current Implementation Issues and/or Problems Encountered (if any):

1. Delayed implementation of infra subprojects due to difficulty of LGUs in providing cash counterpart required as indicated in the NG-LGU cost sharing policy.

2. Approval of the proposed rural finance scheme/Livelihood Assistance Finance (LAF) in place of the credit subcomponent.

3. Extension of OFID Loan Agreement which will close in July 2013

Actions Taken/ Recommendations:

1. The project is waiting for the approval of the proposed NG-LGU cost sharing mix of 60%-40% for 1st-2nd class LGUs, 70%-30% for 3rd-6th class LGUs from the NEDA Board. While waiting for its approval, the Project recommended LGUs regardless of their classification to opt for the cost-sharing arrangement included in the Project Financing Agreement, where the CHARMP2 will shoulder 60% and LGUs will provide 40% equity in order to proceed with the implementation of proposed subprojects. However, only a few LGUs were able to provide counterpart based on this scheme.

To initiate implementation of 25 submitted infra subproject proposals from LGUs that could not afford said NG-LGU cost sharing scheme, fund assistance from the DA-OSEC was sought to cover 30% of the total cost of subprojects. The Project and the concerned LGUs are now waiting for the release of CFA in the amount of Php 50 million from the DA-OSEC.

As of June 2012, another batch of 71 subproject proposals was submitted to DA-OSEC for fund support in the amount of Php 89 million.

2. Since the credit scheme as a subcomponent of the original Project Design is not feasible for poor target beneficiaries in CAR, the Project proposed for the Livelihood Fund Assistance (LAF) that would assist livelihood and income generating activities of target groups. This proposal is part of the revised Project Design which is now for approval by the ICC/Government.

3. The Project requested for an extension of the loan validity to coincide with the loan closing of the IFAD loan (June 2016). Request was reiterated to DA-CO for submission to Department of Finance mid of October 2012.

Remarks: The project is waiting for the final approval of the Revised Project Design by NEDA ICC Board/ National Government.

B-4 Third Quarter CY 2012 RPMES Report

Agency Contact Person:

DIR. MARILYN V. STA. CATALINA, CESO IV Regional Executive Director, DA-RFU-CAR & Project Director, CHARMP2

CAMERON P. ODSEY Project Manager, CHARMP2

Address: PROJECT SUPPORT OFFICE Baguio Stock Farm Compound, Marcos Highway corner Sto. Tomas Road, 2600 Baguio City

Telefax: Email:

+63.74.444.8329/ Tel No. +63. 74. 444.7991 [email protected]

B-10 Third Quarter CY 2012 RPMES Report

PROJECT PROFILE

Implementing Agency: DAR-CAR / DPWH-CAR / NIA-CAR / LGUs

Fund Sources: GOP: Loan: JICA

Total Project Cost: Php 903,863,055.00 Project Cost (2011): Php 16.718 M Loan/Grant Proceeds: Php 677,897,291.25 Peso Counterpart: Php 225,965,763.75

Project Cost (2012): Php 176.027 M

Location/Area Coverage: Abra: Daguioman, Lacub and Luba ARCs Apayao: Sta. Marcela, Flora and Pudtol ARCs Benguet: Bakun, Kapangan and Kibungan ARCs Ifugao: Asipulo, Hingyon and Tinoc ARCs Kalinga: Tinglayan, Rizal and Pasil ARCs Mt. Province: Sadanga, Bauko and Bontoc ARCs

Description:

The Agrarian Reform Infrastructure Support Project (ARISP) Phase III is a foreign-assisted project of DAR, designed to provide basic support services to help develop Agrarian Reform Communities (ARCs). It is funded from a concessional loan from the Government of Japan with counterpart financing from the DAR, Local Government Units and the beneficiaries. The project timetable is from CY 2008 to CY 2014.

The project espouses the concept of integrated area development in the ARCs wherein basic infrastructure, organization / institutional, agricultural and enterprise development support are combined to produce incremental growth in productivity and income among farmers. Specifically, the project considers the provision of farm-to-market roads (FMR) and bridges, irrigation projects, post-harvest facilities, and potable water supply system under its infrastructure component.

For institutional development component, this entails the organizing and strengthening of various organizations in the ARCs to build their capabilities to operate and manage the infrastructure facilities and agri-business in a sustainable basis. The project also supports the

Agrarian Reform Infrastructure Support (ARISP III)

B-11 Third Quarter CY 2012 RPMES Report

development of viable agribusiness in the ARCs to harness the agricultural potentials, add value to agricultural products, and make them more competitive in the market.

In CAR, actual project implementation commenced in CY 2011. From CY 2008 to 2010, the pre-implementation activities conducted are indicative development planning, site validation, project prioritization and individual project designs. There are 61 projects confirmed with an aggregate cost of Php 903.86 M.

For CY 2011, two (2) projects (irrigation project and water system) were implemented and recently completed with an aggregate cost of Php 16.72 M. These are located in the provinces of Abra and Benguet.

DAR and NIA ARISP III Project Management Office representatives conducted Final Project Inspection and Test Run of the newly rehabilitated Daguioman Communal Irrigation System , Daguioman, Abra with a service area of 89 hectares.

Completed Dalingoan Potable Water Supply System, Kapangan, Benguet. The project costing P 2,094,916.00 will benefit around 89 Agrarian Reform Beneficiary Households.

B-12 Third Quarter CY 2012 RPMES Report

For CY 2012, 12 projects (10 irrigation projects and 2 FMRs) are programmed for implementation with a total cost of Php 167.44 M. These are located in the provinces of Apayao, Benguet, Ifugao, Kalinga and Mountain Province.

PROJECT PROGRESS REPORT

As of September 2012

Project Duration: Start: April 2008 End: April 2014

For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter

Target 29.16 % 48.87 % 45.26%

Actual 23.88 % 36.87 % 69.62%

Slippage (5.28%) (12.00 %) (24.36%)

Cumulative Status:

(Since start of project)

Status Physical Financial

Target 50.01%

Actual 72.26%

Slippage 22.25%

Current Implementation Issues and/or Problems Encountered (if any):

1. Undue project delay due to lack of equipment and manpower

2. Absence of DPWH QAU representative during inspection.

3. Inclement weather

Actions Taken/ Recommendations:

1. Conducted Strategy Planning and monthly Area Implementation Team (AIT) meetings participated by representatives from DAR Provincial / Municipal Office, DPWH, LGU and the Contractor to draw catch-up plan.

Remarks:

Agency Contact Person:

DIR. FRANKLIN E. COCOY OIC-Regional Director, DAR-CAR #39 m. Roxas St., Brgy. Tabora, Baguio City ENGR. WILLIE GARCIA 445-4497

B-13 Third Quarter CY 2012 RPMES Report

PROJECT PROFILE Implementing Agency: Department of Public Works and Highways – CAR

Fund Source: GOP Total Project Cost: Php 100 M. Contract Cost: Php 89.089 M.

Location/Area Coverage: Barangay Madatag, Kabugao, Apayao Description: The road is a major component of the Cordillera Roads Improvement Project (CRIP) as lateral road; it connects Ilocos Region and the Northern Cordilleras. It traverses the municipalities of Kabugao and Calanasan in Apayao and turns west to Solsona in Ilocos Norte. The 76.48 km road stretch is a segment of the San Nicolas-Solsona-Kabugao-Conner-Abbut Lateral Road as Apayao’s direct access to Laoag International Airport. The road starts at PoblacionKabugao and ends in Solsona. At the Ilocos Norte side, concrete paving is being completed up to the regional boundary. Approximately 10 km. is for opening at the Kabugao side. Likewise, seven (7) major bridges are to be constructed with a total length of 445 lm. crossing several tributaries of the Apayao River. However, the whole stretch remains a gap (unpaved) even after the project. The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011. The specific project output is road opening and gravelling of 9.56 kms.

Kabugao (Apayao)-Solsona (Ilocos Norte) Road

Kabugao-Apayao- Solsona-Ilocos

Norte Rd

PROJECT LOCATION

B-14 Third Quarter CY 2012 RPMES Report

PROJECT PROGRESS REPORT As of September 2012

Project Duration: Start: June 27, 2012 End: July 21, 2013

For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter

Target 0.50% 1.53%

Actual 0.50% 0.7%

Slippage -0.83%

Cumulative Status: (Since start of project)

Status Physical Financial

Target 2.03%

Actual 0.05% 8.88%

Slippage -1.98%

Current Implementation Issues and/or Problems Encountered (if any):

Project Suspension was issued on July 1, 2012 since the contractor cannot mobilize due to series of slides and road cut along the 21 km road leading to the project site.

Actions Taken/ Recommendations:

To address this, the DPWH-CAR requested DPWH-CO to utilize savings for the removal of slides and restoration of road cuts costing Php 2.38 M. This was eventually approved and the contractor was advised to resume effective September 30, 2012.

Remarks:

Agency Contact Person:

DIR. EDILBERTO P. CARABBACAN Regional Director, DPWH– CAR Engineer’s Hill 2600 Baguio City Tel. 444-8838

B-15 Third Quarter CY 2012 RPMES Report

Kabugao Section

B-16 Third Quarter CY 2012 RPMES Report

LANDMARKS

Kabugao (Apayao) Municipal Hall

Solsona Welcome Arch

Junction San Nicolas, Ilocos Norte

B-17 Third Quarter CY 2012 RPMES Report

PROJECT PROFILE

Implementing Agency: Department of Public Works and Highways – CAR

Fund Source: GOP Total Project Cost: Php58.827 M. Contract Cost : Php 49.574 M.

Location/Area Coverage: Barangays Swan and Mataguisi, Pudtol, Apayao Description:

The road is a major component of the Cordillera Roads Improvement Project (CRIP) as the northern tip of the regional backbone. The 95.7 km. road stretch directly links the capital town Kabugao to Lower Apayao, the seat of provincial government and business growth center in the Municipality of Luna.

The road starts at junction Lenneng along the Kabugao-Conner-Abbut Road and going north-east traverses municipalities of Kabugao, Pudtol and Luna and ends at Junction Luna in Abulug, Cagayan along the Pan-Philippine Highway. The Pan-Philippine Highway connects Laoag, Ilocos Norte and Tuguegarao, Cagayan. The gap at the Kabugao side (19.359 km.), traverses a rugged mountainous terrain, then slowly goes down to the Paco Valley, which was then proposed as government center. The road will also traverse the Mataguisi Valley in Pudtol. The valleys have vast potential for agricultural production.

The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011.

Kabugao-Pudtol-Luna Cagayan Boundary Road

Kabugao-Pudtol-Luna Cagayan

Bdry Road

PROJECT LOCATION

B-18 Third Quarter CY 2012 RPMES Report

The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers have been completed. However, two (2) more major bridges across Malilibag River (60 lm) and Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of this, there are six (6) temporary bridges to be replaced with permanent bridge structures with a total length of 90 lm.

The specific project output is road construction of 2.4 km. After the project, the road has still a gap (unpaved) of 16.959 km.

PROJECT PROGRESS REPORT

As of September 2012

Project Duration: Start: February 20, 2012 End: December 12, 2012

For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter

Target 5 % 50% 17.41%

Actual 5 % 35.7% 26.81%

Slippage

Cumulative Status: (Since start of project)

Status Physical Financial

Target 67.41%

Actual 62.51% 69.49%

Slippage (4.90%)

Current Implementation Issues and/or Problems Encountered (if any):

The 4.9 % negative slippage is attributed to the work interruption during the past months due to inclement weather caused by Typhoons Gener, Helen, and Igme.

Actions Taken/ Recommendations:

To address this, the DPWH advised the contractor to provide additional manpower and equipment to fast track implementation.

Remarks:

Agency Contact Person:

DIR. EDILBERTO P. CARABBACAN Regional Director, DPWH– CAR Engineer’s Hill 2600 Baguio City Tel. 444-8838

B-19 Third Quarter CY 2012 RPMES Report

Babulayan Bridge across Apayao River

Paco Valley

Mataguisi Valley

Junction Lenneng (Kabugao)

B-21 Third Quarter CY 2012 RPMES Report

PROJECT PROFILE

Implementing Agency: DENR–CAR Fund Source: GOP Total Project Cost: P124,339,000.00

Location/Area Coverage: Region wide

The locations are spread out all over the six provinces of CAR including Baguio City with a total area of 15,258 hectares to be planted through social mobilization.

Description:

An administration priority program (Executive Order No. 26) that seeks to attain asustainable Human development, economic and ecological security through the planting of 1.5 billion trees in around 1.5 million hectares of public land within six years from year 2011 to 2016.

The NGP also aims to ensure food security, biodiversity conservation and address climate change.

In the Cordillera, the target for CY 2012 is 7.5 million trees covering 15,000 hectares with a project cost of Php 103.663 M. The project components are: (a) seedling production, Php 62.382 M; plantation site preparation; Php 17.469 M; and maintenance and protection, Php 23,812 M.

National Greening Program (NGP)

Seedling production (gmelina) of one of the People’s Organization (PO) – Baroña Family Association (BFA) in Poblacion, Lacub, Abra.

Seedling production (mahogany) of one of the POs in Conner, Apayao

B-22 Third Quarter CY 2012 RPMES Report

Seedling production (Benguet pine) of one of the POs in Benguet

Seedling production (mahogany) of one of the POs – Federation of Responsive Association for Magat Ecology Inc. in Ifugao

Seedling production (gmelina) of one of the POs in Tabuk, Kalinga

Seedling production (mahogany, narra&gmelina) of one of the POs in Natonin, Mountain Province

Benguet Pine

B-23 Third Quarter CY 2012 RPMES Report

PROJECT PROGRESS REPORT As of September 2012

Project Duration: Start: January 2012 End: December 2012

For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter

Target 11.16% 60.50% 21.41% 6.92%

Actual 14.49% 34.49% 24.46%

Slippage (3.33%) (26.01%) (3.05%)

Cumulative Status:

(Since start of project)

Status Physical Financial

Target 93.07% 95.71%

Actual 73.44% 95.71%

Slippage (19.62%) (0%)

Current Implementation Issues and/or Problems Encountered (if any):

1. For the second year, project was delayed due the difficulty of following the prescribed procurement procedure. Seedlings should be produced by the beneficiaries themselves, unlike during the first year that these may be acquired from outside of the project area.

2. Critical areas for tree planting due to climatic condition are: Abra, Benguet and western Mountain Province. In these areas, tree planting should be done only during rainy season.

Actions Taken/ Recommendations:

1. Procurement guideline was issued by DENR-CO to facilitate implementation.

2. Adopted catch-up plan

Remarks:

Agency Contact Person:

DIR. CLARENCE L. BAGUILAT Regional Executive Director, DENR-CAR No. 80 Diego Silang St., 2600 Baguio City, (442-4531, RD/F) Mr. JOSEPH MAUTING PMD, DENR-CAR (443-94-06)

B-24 Third Quarter CY 2012 RPMES Report

PROJECT PROFILE

Implementing Agency: Department of Education-CAR Fund Source: GOP

Total Project Cost: (CY 2011) P166.944 M (CY 2012) P115.200M

Location/Area Coverage: Region wide Description: The Regular School Building Program specifically targets schools which are categorized under the Red Zone or those which have a ratio of 56 or more students to one classroom: and the Black Zone, or schools which make use of makeshift classrooms and facilities. The standard DepEd design is 7m x 9m classroom for rural areas with a classroom-student ratio of 1:45. This standard also applies to all public secondary schools, regardless of location and class size. In CAR, the carry-over CY 2011projectshas a total project cost of Php166.944 M. covering 147 school sites for new 209 classrooms. The table below shows the details per province/city:

Province/City No. of

sites(CY 2011) No. of

Classrooms Project Cost

Status (AO Sept. 2012)

Abra 18 16 18,427,000 90.43%

Apayao 21 26 15,812,000 96.57%

Benguet 18 28 25,793,000 100%

Ifugao 13 21 28,493,000 98.69%

Kalinga 41 65 44,636,000 95.12%

Mt. Province 30 34 20,042,000 90.45%

Baguio 6 10 13,740,000 100%

CAR 147 209 166,943,500 95.94%

Red and Black School Building Program

B-25 Third Quarter CY 2012 RPMES Report

Mankayan Central School – On going construction (May 28, 2012)

Bulalacao National High School

Bangao National High School

B-26 Third Quarter CY 2012 RPMES Report

For CY 2012 projects, construction started during the second quarter. There are 147 school sites to have 207 new classrooms with a total project cost of Php 115.2 M. The next table shows the details per province/city:

PROJECT PROGRESS REPORT

As of September 2012

Project Duration: Start: January End: December

For CY 2012 AO 1st Quarter AO 2ndQuarter AO 3rd Quarter AO 4th Quarter

Target

Actual (CY 2011) (CY 2012)

8.44%

0.78% 7.69%

6.72% 26.47%

Slippage

Cumulative Status: (Since start of project)

Status Physical Financial

Target

Actual (CY 2011) (CY 2012)

95.94% 34.16%

Current Implementation Issues and/or Problems Encountered (if any):

Actions Taken/ Recommendations:

Remarks: Implementation of CY 2012 projects comments during this quarter.

Agency Contact Person:

DIR. ELLEN B. DONATO Regional Director Wangal, La Trinidad, 2601 Benguet

Province/City No. of sites (CY 2012)

No. of Classrooms Project Cost

Status

(AO Sept. 2012)

Abra 18 26 7,920,000 89.49%

Apayao 21 26 10,080,000 0%

Benguet 18 28 15,840,000 90.57%

Ifugao 13 21 10,800,000 27.24%

Kalinga 41 65 29,520,000 18.53%

Mt. Province 30 31 23,760,000 27.69%

Baguio 6 10 17,280,000 16.91%

CAR 147 207 115,200,000 34.16%

Annex C INSPECTION REPORTS

C-1

RPMC-CAR Inspection Report on the Road Upgrading (Gravel to Concrete) along

Kabugao-Pudtol-Luna-Cagayan Boundary Road conducted on 09 October 2012

1. The RPMC Inspectorate Team

The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on 09 October 2012 a project-site inspection on the Kabugao- Pudtol-Luna- Cagayan Boundary Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional office.

The RPMC member-agency representatives were the following:

Rene V. Valera, DILG-CAR Jerome B. Agaloos, NEDA-CAR James M. Degsi, DBM-CAR Manilyn S. Dulay, NEDA-CAR

The Team was assisted by the following DPWH Apayao 2nd Engineering District and Contractor’s representative: ADE Rustom Martinez, DPWH Apayao II Galo Aplod, OCDC Jerry Ragojos, DPWH Apayao II

Before the field inspection, the group paid courtesy to the Apayao Provincial Government officials at the Provincial Capitol in Luna, Apayao. The Team met with the Provincial Administrator Vincent Talattad and Chief Executive Atty. Xandred Claveria.

2. Project Profile

The road is a major component of the Cordillera Roads Improvement Project (CRIP) as the northern tip of the regional backbone. It traverses the municipalities of Kabugao, Pudtol and Luna in Apayao and turns east to Abulog in Cagayan. The 95.7 km. road stretch directly links the capital town Kabugao to Lower Apayao, the seat of provincial government and business growth center. The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011. The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers have been completed. However, two (2) more major bridges across Malilibag River (60 lm)

C-2

and Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of this, there are six (6) temporary bridges to be replaced with permanent bridge structures with a total length of 90 lm.

3. Project Basic Information

Specific Location Barangays Swan & Mataguisi, Pudtol, Apayao

Station Limits KO 661+000 – KO 661+321 & KO 643+520- KO646+080 Length of Road Project 2.4 km Project Cost Php 58.827 M. Contract Cost Php 49.574 M. Source of Fund CY 2012 DPWH Regular Infra Program Project Schedule Feb. 20, 2012 to Dec. 12, 2012 Contractor OCDC Major Work Items PCCP (2.4 km), RCPC, stone masonry,

concrete curb & gutter and road signs Project Status 64.79 %, slippage (2.62 %)

4. Findings The road construction is smoothly on progress. The mere 2.62 % negative slippage is attributed to the work interruption during the past months due to inclement weather caused by Typhoons Gener, Helen, and Igme. To address this, the DPWH advised the contractor to provide additional manpower and equipment to fast track implementation.

5. Comment(s)/ Recommendation(s) The work progress is commendable. It is however recommended that the DPWH should also prioritize the programming for the construction of the bridges across Paco River (District I) and Malilibag River (District 2) to finally open the road up to Kabugao.

C-3

PHOTO DOCUMENTATION

EXIT CONFERENCE

The RPMC Inspectorate Team meets ADE Rustom Martinez,

DPWH Apayao II (L)

On-going concreting of Kabugao-Pudtol-Luna-Cagayan Boundary Road (2.4 km along Barangays Swan & Mataguisi section)

Completed Babulayan Bridge across

Apayao River

Concrete approach of Babulayan Bridge

Recently completed road concreting project

Courtesy call on Apayao Provincial Administrator Vincent Talattad and Chief of Staff Atty. Xandred Claveria

C-4

RPMC-CAR Inspection Report on the Road Opening of Kabugao, Apayao- Solsona-Ilocos Norte Road (Apayao Side)

conducted on 10 October 2012

1. The RPMC Inspectorate Team

The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on 10 October 2012 a project-site inspection on the Kabugao, Apayao- Solsona-Ilocos Norte Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional office.

The RPMC member-agency representatives were the following:

Rene V. Valera, DILG-CAR Jerome B. Agaloos, NEDA-CAR James M. Degsi, DBM-CAR Manilyn S. Dulay, NEDA-CAR

The Team was assisted by the following DPWH Apayao 1st Engineering District and LGU Kabugao staff: Antonio Baguec (PE), DPWH Apayao I Arne Paul Ligwang, LGU Kabugao Domingo Enciso, DPWH Apayao I Harold Aboran, LGU Kabugao

The group paid courtesy and held separate exit conferences with DPWH Apayao 1st District ADE Edward P. Magno and LGU Kabugao Municipal Administrator Romeo B. Tamot.

2. Project Profile

The road is a major component of the Cordillera Roads Improvement Project (CRIP) as a lateral road. It directly connects Apayao Province to Ilocos Region. It traverses the municipalities of Kabugao and Calanasan in Apayao and turns west to Solsona in Ilocos Norte. The 76.48 km road stretch is a segment of the San Nicolas-Solsona-Kabugao- Conner-Abbut Lateral Road as Apayao’s direct access to Laoag International Airport. At the Ilocos Norte side, concrete paving is being completed up to the regional boundary. The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011. It was noted that even after the project, the whole stretch remains a gap until concreted. Likewise, seven (7) major bridges are to be constructed with a total length of 445 lm. crossing several tributaries of the Apayao River.

C-5

3. Project Basic Information

Specific Location Barangays Madatag, Kabugao, Apayao Station Limits KO 627+840 – KO 637+400 Length of Road Project 9.56 km Project Cost Php 100 M. Contract Cost Php 89.089 M. Source of Fund CY 2012 DPWH Infra Program Original Project Schedule June 27, 2012 to April 22, 2013 Suspension Order No.1 July 1, 2012 Resume Order No 1 September 30, 2012 Expected Completion July 21, 2013 Contractor PBO Construction Major Work Items Roadway & drainage excavation, gravelling, stone

masonry & installation of cross drainages, catch basins, common earth & solid rock excavation

Project Status 0.50 %

4. Findings

Project Suspension was issued on July 1, 2012 since the contractor cannot mobilize due to series of slides and road cut along the 21 km section leading to the project site. To address this, the DPWH-CAR requested DPWH-CO to utilize savings for the removal of slides and restoration of road cuts costing Php 2.38 M. This was eventually approved and the contractor was advised to resume effective September 30, 2012. Due to the slides and road cuts, the group had to cruise Apayao River for two (2) hours using a motor-banca and hike for an hour to reach the project site.

It was found out that the road alignment follows an old logging road of which some portions were later widened by the AFP Engineering Brigade. Accordingly, the AFP had a military camp at Barangay Madatag. The area has a vast potential for agriculture, water recreation and Philippine eagle watching. The forest area along the river and within the Apayao-Ilocos Norte boundary is a perfect eagle’s habitat.

5. Comment(s)/ Recommendation(s)

The leadership of Apayao Province and MLGU Kabugao in cooperation with the DPWH Apayao I are commended for the swift conduct of a parcellary survey on August 2011 along the road line to delineate private properties from road right-of-way (RROW). This was among the conditions set by Secretary Singson prior to the issuance of the memorandum and funding release.

For FY 2013-2016, the DPWH should program the construction of the seven (7) major bridges with a total length of 445 lm. crossing several tributaries of the Apayao River. Meanwhile, the contractor should immediately resume construction work.

C-6

PROJECT PHOTO-DOCUMENTATION

Actual Project Site at Barangay Madatag

Location: KO627+840-KO637+400

On July 1, 2012 the suspension order was issued since the contractor cannot mobilize due to series of massive slides and road cuts along the 21 km section leading to the project site.

C-7

Location: KO627+840-KO637+400

The DPWH-CO recently approved to utilized savings for the removal of slides and restoration of road cuts costing Php 2.38 M. Consequently, the contractor was advised to resume effective Sept. 30, 2012

The area has a vast potential for agriculture,

water recreation and Philippine eagle

watching

C-8

Kabugao section Junction Kabugao, Apayao

Junction San Nicolas, Ilocos Norte

Solsona Welcome Arch

C-9

COURTESY CALL and EXIT CONFERENCE

Ongoing concreting work, near regional boundary

With Engr. Domingo Enciso (R) and Kabugao Local Officials

Exit conference with Kabugao Municipal Administrator Romeo Tamot (2nd R)

Exit conference with DPWH Apayao I ADE Edward P. Magno (R) and Engr. Domigo Enciso

(L) and PE Antonio Banguec (2nd L)