Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 1 December 2014
6.0 CONSTRUCTION PROGRAMME
Introduction
6.1 This chapter of the ES describes the anticipated construction works programme and the
key activities that will be undertaken. Consideration of potential effects during the
construction process and any necessary mitigation measures are provided in each
relevant chapter of the ES.
Anticipated Programme
6.2 Construction of the Proposed Development will commence in 2016, subject to gaining
planning permission, and is expected to be completed within 12 years in 2028.
6.3 The housing trajectory for Cambourne West, upon which the ES has been based is
summarised in Table 6.1 below.
Table 6.1: Housing Trajectory
Year (Start - Finish)
Quantum of Housing delivered
2016-17 70 residential units
2017-18 150 residential units
2018-19 220 residential units
2019-20 220 residential units
2020-21 220 residential units
2021-22 220 residential units
2022-23 220 residential units
2023-24 220 residential units
2024-25 220 residential units
2025-26 220 residential units
2026-27 220 residential units
2027-28 150 residential units
Phasing
6.4 The phasing for the construction of the Proposed Development is illustrated on
Figure 6.1 and summarised in Table 6.2 below:
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 2 December 2014
Table 6.2: Summary of Phasing
Phase Quantum of Development delivered
Infrastructure Delivered
Enabling works
Existing access route via Sheepfold Lane upgraded and remodelled. Construction of a new permanent access incorporating a roundabout at the junction of the A1198/Caxton Bypass and construction of internal haul roads. Installation of a proportion of the SUDs drainage system to facilitate the drainage of the impermeable road surfaces in this phase. Realignment of the watercourses as appropriate to install the permanent road.
1
Approximately 385 dwellings
completed in Phase 1 on 15.97ha of land (development parcels A2 and C). The employment area (1.18ha) immediately to the north and south of Sheepfold Lane will also be established in this phase.
Approximately 18.8ha of green
infrastructure provided, including woodland planting along the northern, western and southern boundaries. In addition new planting established at the main entrances to the Site; the A1198/Caxton Bypass and Sheepfold Lane. Secondary School complete to shell and core (EIA assumption that this would be completed for occupancy by the appropriate body during this period). Ongoing construction in part of the internal access roads and SUDs drainage system, including installation of the attenuation ponds and associated discharge channels to facilitate the drainage of the roads and development surfaces in this phase. Finally, installation and connection of the development to the utilities network, these works to include any off-site reinforcement works.
2
Approximately 480 dwellings completed in Phase 2 on 12.75ha of land (development parcels A1, A2 & C).
Approximately 11.7ha of proposed green infrastructure located within the central part of the Site including playing fields either side of the main spine road. Construction of the local centre, in part, to include retail and community buildings. Close to this main community hub, construction of the first primary school to shell and core.
Ongoing construction of internal access roads and installation of SUDs drainage system.
3
Approximately 385 dwellings completed in Phase 3 on 11.2ha of land (development parcels A2, B & D).
Approximately 11.2ha of proposed green infrastructure including woodland planting along the western and northern boundaries and the main playing fields adjacent to the northern boundary. Construction of the second primary
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 3 December 2014
Phase Quantum of Development delivered
Infrastructure Delivered
school and sports pavilion in the south western part of Site, between developments cells D & E. Completion of the local centre, including construction of additional units for a range of A1-A5 uses, including shops, restaurants and cafes. A smaller retail component will also be established in the southern part of the site, close to the second primary school and children’s play area. Ongoing construction of internal access roads, including completion of the main spine road and installation of SUDs drainage system.
4
Approximately 240 dwellings completed in Phase 4 on 7.86ha of land (development parcels B & G).
Approximately 6ha of green infrastructure to be provided including woodland planting and allotments to the south of the secondary school. Ongoing construction of internal access roads, installation of SUDs drainage system and connection to the utilities network.
5
Approximately 365 dwellings completed in Phase 5 on 9.8ha of land (development parcels B & E).
Completion in part of internal access roads and areas of open space (3.4ha in total). Ongoing construction of internal access roads and installation of source control methods to serve the development to the SUDs system.
6
Approximately 270 dwellings completed in Phase 6 on 7.3ha of land (development parcel F & H). Designated Employment Area established in the north western corner of the site including the construction of the associated access off the A1198.
Woodland planting to be provided in the north west area of the Site and to the north of Swansley Wood Farm. Ongoing construction of internal access roads and installation in part of SUDs drainage system associated with the relevant attenuation pond for the proposed employment area.
7
Approximately 225 dwellings completed in Phase 7 on 7.4ha of land (development parcels F & G).
Installation of source control methods to serve the development to the SUDs system.
Description of Works
6.5 Construction will include the following activities:
Enabling works;
Site Preparation (including excavation and grading);
Provision of infrastructure;
Construction of substructure;
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 4 December 2014
Construction of superstructure;
Fit out of buildings; and
Structural Landscaping.
Enabling Works
6.6 Enabling works will involve the creation of routes into the Site along with:
Arboricultural works – including the protection of trees/vegetation to be retained
and removal of trees/vegetation to be lost;
Any required archaeological investigations;
Diversion of public rights of way as required; and
Ecological works – including the application for protected spec ies licences from
Natural England.
Site Preparation
6.7 Site preparation will involve the establishment of the construction and haul routes, on -
site parking provision and any construction worker facilities (including site compound
area with offices and welfare facilities for management and construction workers) in
addition to:
Installation of site hoarding, which will be provided to separate construction
areas from off-site publicly accessible areas;
Ground modelling works will be carried out, including topsoil stripping and
stockpiling for later use;
General vegetation clearance; and
Installation of temporary surface water management measures .
Infrastructure
6.8 Appropriate infrastructure to serve the Proposed Development will be installed:
The existing access route into the Proposed Development via Sheepfold Lane will
be upgraded and remodelled;
Construction of a new permanent access incorporating a roundabout at the
junction of the A1198/Caxton Bypass and construction of secondary internal
roads;
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 5 December 2014
Construction of a third vehicular access point off the A1198, south of the Caxton
Gibbet roundabout, to serve the commercial elements of the Proposed
Development; and
Installation and connection of the Proposed Development to the utilities network ,
including any off-site reinforcement works.
6.9 It is anticipated that the base of internal roads will be constructed and used for
construction traffic routes as the Proposed Development is built.
Construction of Substructure
6.10 This will involve foundation excavation, the installation of below ground services and
construction of new foundations. Substructure works may involve:
Localised re-grading within the Site to create level development platforms for the
structures;
Excavation for foundations and to allow installation of any below ground
services; and
Installation of ground slabs (ground bearing or suspended block) and supporting
beams.
Construction of Superstructure
6.11 This stage will involve the construction of the main building envelope of buildings and
will include the installation of timber frames, load bearing brick walls, planks, reinforced
masonry and masonry and tiling.
Fit Out
6.12 Fit out of the Proposed Development will involve the installation of block work party
walls, dry lining to internal walls, internal walls, domestic , mechanical and electrical
installations with fitted kitchens and bathrooms.
Landscaping
6.13 Landscaping works will involve some ground modelling works and the establishment of
green spaces within the Site including soil preparation, creation of waterbodies, tree
and vegetation planting, seeding, construction of footpaths/cycle routes, sports pitches
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 6 December 2014
and play areas. The ground modelling works will be undertaken concurrently with the
site preparation and substructure works outlined above. The creation of green spaces
will be undertaken simultaneously with adjacent development areas, with the majority
of the woodland planting along the northern, western and southern boundaries being
included within the first phase, so that it would have time to mature during the twelve
year construction period and provide more effective visual screening.
Material and Resource Use
6.14 The primary construction materials to be used will include concrete, brick, steel post
and beams and timber. Where possible materials and resources used during the
construction of the Proposed Development will be sourced from the local area.
Furthermore a proportion of timber will be purchased from responsible forest sources.
In terms of material selection, ‘A’ rated materials from the Building Research
Establishment’s Green Guide to Specification will be preferred.
Plant and Equipment
6.15 Consideration has been given to the types of plant likely to be used during the
construction works. The plant and equipment associated with each key element of the
construction process is set out below in Table 6.3.
Table 6.3: Construction Plant
Plant
Stage
Enabling Works Infrastructure and
substructures Construction &
landscaping
Tracked/wheeled 360 degree Excavators
Excavator mounted hydraulic breakers
X X
Excavator mounted hydraulic crushers
X X
Dumpers
Concrete Crushing Plant X X X
Mobile Craneage/Tower Cranes
X
Eight-wheeler trucks
Air Compressors
Diamond cutting tools / saws
Hand Held Tools including breakers (pneumatic and hydraulic)
Power Tools including percussion drills, cutting disks, pipe-threaders
Hand /power tools
Wheel Washing Plant
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 7 December 2014
Plant
Stage
Enabling Works Infrastructure and
substructures Construction &
landscaping
Piling Rigs X X X
Scaffold X X
Mobile access platforms X X
Delivery trucks
Skips & Skip trucks
Forklift trucks
Hours of Work
6.16 SCDC will want to regulate the hours of work by imposition of an appropriate condition
prior to the commencement of the works. It is anticipated that these will be 08:00 to
18:00 Monday to Friday and 08:00 to 13:00 on Saturdays. All work outside these hours
will be subject to prior agreement, and/or reasonable notice, by SCDC, who may impose
certain restrictions. Night time working will be with the agreement of SCDC and
restricted to exceptional circumstances.
Environmental Management
6.17 It is expected that the developer will operate an Environmental Policy which will cover a
number of key areas during the construction process. The policy, which is likely to be
required by an appropriate condition attached to the grant of planning permission, will
ensure that the developer and its contractors operate in a responsible manner during
the construction of the Proposed Development.
6.18 A Construction Environmental Management Plan (CEMP) will be provided to SCDC prior
to commencement of the works. It will include the following:
The broad plan of the phasing of the works and its context within the whole
project;
Baseline levels for noise, vibration and dust and details of any monitoring
protocols that may be necessary during the works;
Housekeeping procedures and environmental control measures;
Any requirement for monitoring and record keeping;
Contact details during normal working hours and emergency details outside
working hours;
Provision for reporting, public liaison, prior notification etc.;
The mechanism for the public to register complaints and the procedures for
responding to complaints;
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 8 December 2014
Prohibited or restricted operations (location, hours etc.);
Details of construction operations highlighting any operations likely to result in
disturbance and/or working hours outside the core working period, with an
indication of the expected duration of key phases and dates;
The details of proposed routes for heavy goods vehicles travel ling to and from
the Site;
Details of all works involving interference with a public highway, including
temporary carriageway/footpath closures, realignment and diversions where
applicable;
Construction waste (as set out at paragraph 6.25);
Construction Traffic Management (as set out at paragraph 6.21); and
Construction Impacts on Ecology (as set out at paragraph 6.32).
Construction Traffic
Construction Traffic Movements
6.19 As discussed in Chapter 9 ‘Transport and Access’, the construction of the Proposed
Development would generate approximately 675 one-way construction vehicle
movements per week, or on average 135 one-way trips per day (i.e. 270 two-way trips
per day). Approximately 63 percent of trips are made by cars or light goods vehicles,
with 37 percent HGV traffic. This equates to approximately 170 two-way car or light
goods vehicle trips and 100 two-way HGV trips per day.
Construction Traffic Routing
6.20 The construction vehicular access route to the Proposed Development is anticipated t o
be via the private road leading to Swansely Farm, off the A1198. HGVs would be
required to avoid inappropriate routes through residential streets and villages. Precise
construction routing arrangements will be contained within a CEMP which will be
approved in liaison with SCDC and other relevant statutory organisations prior to the
start of construction.
Construction Traffic Management
6.21 Whilst no long-term road closures are envisaged, short term closures may be required in
order to establish and remove large items of building plant. If this is to be required then
consent will be obtained from SCDC, the Highways Agency and the Highways Authority.
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 9 December 2014
6.22 It will be the responsibility of the developer and Contractor or Construction Liaison
Officer to finalise consultations with SCDC. Notice regarding planned closures and
diversions of roads and footpaths forming part of the Site will be given by the
Contractor/Construction Liaison Officer to SCDC, the Police, the Fire Brigade and other
emergency services sufficiently in advance of the required closure or diversion dates.
6.23 In order to minimise the amount of construction vehicles using the public highway, the
following factors will be considered:
Re-use and recycling of construction materials;
Control of wastage;
Description of permitted routes for transit of materials, avoiding sensitive areas;
Shared materials delivery opportunities;
On demand ordering;
Phased delivery times throughout the working day; and
Car sharing for operatives.
6.24 All construction traffic entering and leaving the Site will be closely controlled. Site
operatives will be encouraged to car share, if transport is not provided by the employer.
It is also envisaged that car parking arrangements for site operatives within or adjacent
to work compound areas will be enforced in order to avoid uncontrolled parking on
public highways.
Waste Management, Recycling and Disposal
6.25 Waste will be generated as a consequence of the proposed excavation and construction
works. No demolition works are proposed. All relevant contractors will be required to
investigate opportunities to minimise waste arisings at source and, where such waste
generation is unavoidable, to maximise the recycling and re -use potential of
construction materials. Excavated topsoil will be reinstated as part of the site
landscaping arrangements and will be re-used wherever possible in site re-grading and
as backfill as part of the site cut and fill balance to reduce the amount of material that
is requires to be sent off-site for recycling or disposal. Wherever feasible, such arisings
will be dealt with in a manner that reduces environmental impact and maximises
potential re-use of materials. Recycling of other materials (for example metals and
wood) will largely take place off-site where noise and dust are less likely to result in
effects to the occupants of surrounding properties.
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 10 December 2014
Drainage
6.26 Surface water drainage will be controlled by appropriate Sustainable Drainage Systems
(SUDS) and discharge arrangements will be agreed with the Environment Agency or, in
the case of discharges to sewer, Anglian Water. Construction vehicle parking areas may
need to be paved.
6.27 The Construction Liaison Officer will ensure that any water which may have come into
contact with any contaminated materials during construction will be disposed of in
accordance with the Water Resources Act (1991) and other legislation, and to the
satisfaction of the Environment Agency or Southern Water. In addition, any risk will be
reduced by adopting good management practices and relevant measures described in
the Environment Agency’s Pollution Prevention Guidelines, including: PPG01 – General
guide to the prevention of water pollution; and PPG06 – Working at construction and
demolition sites.
6.28 All liquids and solids of a potentially hazardous nature (for example diesel fuel, oils,
solvents) will be stored on surfaced areas, within secure compounds with bunding, to
the satisfaction of the Environment Agency.
Protection of Trees and Vegetation
6.29 All trees to be retained (and new trees planted in the early stages of construction) will
be protected from any unnecessary damage. Tree protections are likely to be secured by
a condition and referenced to a plan. Existing trees have been assessed according to
the guidance set out in BS5837: 2012 (Trees in Relation to Design, Demolition and
Construction - Recommendations). This assessment involved qualitative differentiations
of the existing tree stock which was used to inform the Parameter Plans. The majority
of the trees on the Assessment Site will be retained including the woodland with the
exception of some tree removal to allow for highway visibility and the ground modeling
works. The trees will be managed and protected in accordance with relevant British
Standards (BS3998:2010 ‘Recommendations for tree work’; and BS5837: 2012).
6.30 All temporary material storage will be located wherever practical at adequate distances
from vegetation and tree cover to avoid any physical damage. Where tree roots may be
subject to potential vehicle compaction, additional temporary protection of the ground
surface will be introduced in accordance with any relevant planning condition.
6.31 Similarly, other areas of vegetation to be retained as part of the Proposed Development
Cambourne West Construction Programme
19102/A5/ES2014 Chapter 6 – Page 11 December 2014
will be protected from adverse effects during construction through the installation of
temporary fencing as appropriate. Construction traffic and storage of materials will not
be permitted in these areas, ensuring that they are safeguarded throughout
construction.
Protection of Ecological Habitats and Species
6.32 Construction effects on ecology within and around the Assessment Site will be
controlled by the CEMP. Key ecological features to be retained will be buffered from
construction effects from the Proposed Development.
6.33 Habitats to be retained will be fenced off to reduce disturbance effects, for example
from increased noise and lighting. All temporary lighting will, wherever possible, be
located away from these areas and positioned as close to the ground as possible.
6.34 To limit the potential for interference with any wild bird or damaging or destroying its
nest, all vegetation removal will be timed to avoid the bird-breeding season (March to
July inclusive).
Drawn by: MW
Date: 21.08.14
Checked by: JF
Canada House3 Chepstow StreetManchester M1 5FWTel: 0161 228 7721
Phasing Plans
Scale: NTS @ A3
Residential Development
Development Land
Educational Land
Haul Roads
Constructed Roads
Application boundary
Key North
CAMBOURNE WEST
Commercial Land
Sports Buildings
Non-Development Land
Non Development Area
Drwg No: 85S - 71j
OS reference: © Crown copyright, All rights reserved. 2014 Licence number 100018033
Enabling Works
Phase 2
Phase 1
Figure 6.1
Phase 3
Drawn by: MW
Date: 21.08.14
Checked by: JF
Canada House3 Chepstow StreetManchester M1 5FWTel: 0161 228 7721
Phasing Plans
Scale: NTS @ A3
Residential Development
Development Land
Educational Land
Commercial Land
Haul Roads
Constructed Roads
Application boundary
Key North
CAMBOURNE WEST
Non Development Area
Non-Development Land
Drwg No: 85S - 72j
OS reference: © Crown copyright, All rights reserved. 2014 Licence number 100018033
Phase 4
Phase 6 Phase 7
Phase 5
Figure 6.1
Sports Buildings